Drilling liner hanger, pipe string and construction technology

By using the runner switch in the tail tube suspension, opening the channel between the wellbore and the annular chamber, combining the driving mechanism of the air piston and the tile, the inaccurate operation of the tail tube suspension in the existing technology under high temperature and high pressure environments and inaccurate operation and The problem of spike leakage in the ball seat achieves reliable downward and long-term sealing of the tail tube suspension.

CN118933658APending Publication Date: 2024-11-12SHELFOIL PETROLEUM EQUIP & SERVICES CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411182901.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-27
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The existing tailpipe suspension is difficult to accurately judge the tool movement under high temperature, high pressure and narrow gap environments, and the hydraulic suspension has the risk of spike leakage, so it cannot effectively sit on the wellbore, resulting in the size, material and function that cannot meet the exploration of oil and gas wells. Development requirements.

Method used

The runner transformer is used as the information carrier for sitting and hanging action. The high-temperature melting runner transformer opens the channel between the wellbore and the annular chamber, and combines the driving mechanism of the air piston and the tile to realize the seating of the tail pipe suspension to avoid The use of ball mount and pressure transfer holes.

Benefits of technology

实现了尾管悬挂器的可靠准确下入和长效密封,避免了球座憋通引起的瞬间激荡压力和液压控制失效的问题,确保了尾管井筒的完整性和管串下入的可靠性。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933658A_ABST
    Figure CN118933658A_ABST
Patent Text Reader

Abstract

The invention provides a drilling liner hanger which comprises a body and a sitting hanging mechanism, the sitting hanging mechanism comprises a supporting sleeve fixed to the body through a shear pin, a slip and a driving mechanism, and the slip and the driving mechanism are arranged above the supporting sleeve. The driving mechanism comprises a connecting sleeve arranged below the supporting sleeve, an air piston arranged between the supporting sleeve and the connecting sleeve and an annular cavity formed among the body, the air piston and the connecting sleeve, a guide groove used for receiving annular mud is formed in the connecting sleeve, and the annular cavity is communicated with the air piston. The guide groove is filled with a flow channel conversion piece, and after the flow channel conversion piece is melted into a liquid state from a solid state in a well, the annular cement paste can push the flow channel conversion piece to enter the annular cavity to cut off the pin and promote the air piston to move upwards till the slip is hung on a casing pipe in a sitting mode.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of oil and gas well cementing and completion, and in particular to a tail pipe hanger, a pipe string and a construction process. Background Art

[0002] In recent years, with the continuous improvement of information and intelligent technology, the demand for efficient, reliable and intelligent technology in the field of oil and gas wells, especially cementing and completion tools, has gradually increased. In particular, facing many challenges such as high temperature, high pressure, and narrow gaps, liner cementing tools are limited by traditional mechanical and hydraulic mechanisms, resulting in the size, material and function being unable to meet the needs of exploration and development, which has brought new challenges to the overall pressure resistance of the liner hanger.

[0003] At present, there are two main control modes for existing liner hangers in China: mechanical and hydraulic. Mechanical liner hangers are limited by their own control methods and cannot accurately judge tool movements in horizontal wells and large-reach wells; while hydraulic liner hangers have the risk of ball seat leakage, resulting in the inability to generate pressure and achieve the sitting and hanging action.

[0004] Therefore, it is desired in the art to provide a liner hanger to solve the above technical problems. Summary of the invention

[0005] The purpose of the present invention is to provide a tail pipe hanger, which can use the flow channel transition piece as the information carrier of the hanging action, that is, the channel between the wellbore and the annulus chamber can be opened by melting the flow channel transition piece at high temperature, further promoting the tail pipe hanger to hang in the wellbore.

[0006] According to a first aspect of the present invention, there is provided a liner hanger, comprising a body,

[0007] A sitting and hanging mechanism, the sitting and hanging mechanism comprising a support sleeve sleeved outside the body, and a slip arranged above the support sleeve,

[0008] A driving mechanism, the driving mechanism comprising a connecting sleeve arranged below the supporting sleeve, an air piston arranged between the supporting sleeve and the connecting sleeve, and an annular cavity formed between the body, the air piston and the connecting sleeve,

[0009] Wherein, a guide groove for receiving annular space mud is provided on the connecting sleeve, and a flow channel transition piece is filled in the guide groove.

[0010] After the flow channel conversion component is melted from solid to liquid in the well, the annular cement slurry can push the flow channel conversion component into the annular chamber to cut off the pin and promote the upward movement of the air piston until the slip is seated on the casing.

[0011] In one embodiment, the flow channel transition member is made of a memory alloy or a polymer material.

[0012] In one embodiment, a plurality of the slips are provided along the circumference of the body and are arranged at intervals.

[0013] In one embodiment, the seating mechanism further includes a cone sleeve disposed above the cava, and an end ring sleeved outside the body and used to limit the cone sleeve, wherein the cone sleeve is provided with a guide slope for causing the cava to open radially outward.

[0014] In one embodiment, the support sleeve is fixed to the body by shear nails, and the air piston is fixed to the support sleeve by bolts.

[0015] In one embodiment, the liner hanger further comprises a straightening ring sleeved outside the body and used for limiting the position of the connecting sleeve, and a lifting joint sleeved outside the body and abutting against the end ring.

[0016] In one embodiment, the liner hanger further includes a first seal disposed between the connection sleeve and the air piston and the body, and a second seal filled in an annulus between the air piston and the body.

[0017] According to a second aspect of the present invention, a pipe string is provided, comprising a running tool, a sealing shell and a liner hanger as described above, which are connected in sequence, wherein a sealing core is provided in the sealing shell.

[0018] In one embodiment, the running tool and the integrated sealing housing of the tie-back tube are connected by a screw thread.

[0019] According to a third aspect of the present invention, there is provided a construction process, which uses the pipe string as described above, comprising the following steps:

[0020] S1, sending the liner hanger into a predetermined position in the wellbore by the sending tool, and the flow channel conversion component melts from a solid state to a liquid state in the well;

[0021] S2, the annular cement slurry pushes the flow channel conversion member into the annular chamber until the shear pins are cut off, thereby pushing the air piston upward; the slips are opened outwards under the action of the cone sleeve until they are seated on the casing;

[0022] S3, by rotating forward, the running tool is released and the tail pipe cementing work is started.

[0023] Compared with the prior art, the advantages of the present invention are:

[0024] First, the present invention uses the flow channel transition piece as the information carrier of the sitting action, that is, by melting the flow channel transition piece at high temperature, the channel between the wellbore and the annulus chamber can be opened, further promoting the liner hanger to sit in the wellbore. In addition, the device does not require a ball-throwing pressure-holding operation, and the closed-loop design of the control system can realize an infinite displacement cycle during the liner string lowering process, thereby ensuring the reliability of the string lowering.

[0025] Second, compared with the prior art, this device does not require a ball seat, so it can effectively avoid the problem of instantaneous turbulent pressure when the ball seat is blocked and damage to the bottom layer of the open hole. In addition, since there is no pressure transmission hole on this device, it can effectively avoid many problems caused by hydraulic control failure, thereby eliminating the weak links of the prior art and further ensuring the long-term sealing of the liner hanger and the integrity of the liner wellbore. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] The present invention will be described in detail below in conjunction with the accompanying drawings, in which:

[0027] Figure 1 The structure of the liner hanger according to the present invention is schematically shown;

[0028] Figure 2 for Figure 1 A partial enlarged view of

[0029] Figure 3 The first part of the structure of the pipe string according to the present invention is schematically shown;

[0030] Figure 4 The second part of the structure of the pipe string according to the present invention is schematically shown.

[0031] In the drawings, the same reference numerals are used for the same components. The drawings are not drawn to scale. DETAILED DESCRIPTION

[0032] In order to make the technical solutions and advantages of the present invention more clearly understood, the exemplary embodiments of the present invention are further described in detail below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than an exhaustive list of all the embodiments. In addition, the embodiments of the present invention and the features in the embodiments can be combined with each other without conflict.

[0033] In the description of the present invention, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features.

[0034] In the present invention, unless otherwise clearly stipulated and limited, terms such as "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be the internal connection of two elements.

[0035] For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0036] The present invention will be further described below in conjunction with the accompanying drawings.

[0037] Figure 1 The structure of the liner hanger according to the present invention is schematically shown;

[0038] Figure 2 for Figure 1 A partial enlarged view of .

[0039] like Figure 1 and 2 As shown, according to a first aspect of the present invention, a liner hanger 100 is provided, which mainly includes a body 10 and a sitting mechanism disposed on the upper part of the body 10. The sitting mechanism includes a support sleeve 21 sleeved outside the body 10 and a slip 22 disposed above the support sleeve 21. Preferably, the support sleeve 21 is fixed to the body 10 by shear nails 211, so that under the action of the shear nails 211, it can be ensured that the slip 22 will not be opened prematurely during the lowering process, so as to further improve the reliability and accuracy of the liner hanger 100.

[0040] In one embodiment, Figure 1 and 2 As shown, the liner hanger 100 further includes a driving mechanism disposed at the lower portion of the body 10. Preferably, the driving mechanism includes a connecting sleeve 31 and an air piston 32, wherein the connecting sleeve 31 is disposed below the support sleeve 31, and the air piston 32 is disposed between the support sleeve 31 and the connecting sleeve 31. Preferably, the air piston 32 is fixed to the support sleeve 21 by bolts. Therefore, the slips 22, the support sleeve 21 and the air piston 32 will achieve synchronous movement in the subsequent hanging work, further improving the reliability of the liner hanger 100.

[0041] In the present invention, the upper and lower end faces of the air piston 32 have the same sealing dimensions, so the air piston 32 is balanced in axial force, and thus will not move axially during lowering into the wellbore, further ensuring that the slips 22 will not be opened prematurely during lowering.

[0042] In one implementation, Figure 1 and2 As shown, an annular cavity 33 is formed between the body 10, the air piston 32 and the connecting sleeve 31. Preferably, a guide groove 34 for receiving annular slurry is provided on the connecting sleeve 31, and a flow channel transition member 35 is filled in the guide groove 34. Preferably, the flow channel transition member 35 is made of memory alloy or polymer material, so that after the flow channel transition member 35 melts (changes from solid to liquid), the annular cement slurry can be allowed to enter the annular cavity 33 through the guide groove 34.

[0043] As is known to all, as the depth of the well increases, the downhole temperature will also increase accordingly. Therefore, the present application can select the material of the flow channel transition piece 35 according to the temperature at the predetermined position, so that when the tail pipe hanger is lowered to the predetermined position in the wellbore, the flow channel transition piece 35 is melted by the high temperature in the well to allow the annular cement slurry to enter the annular chamber 33 through the guide groove 34, thereby facilitating the subsequent hanging work.

[0044] In the present invention, the annulus between the support sleeve 21, the air piston 32 and the body 10 forms an upper chamber. Therefore, after the flow channel transition member 35 melts, the annular mud will push the liquid flow channel transition member 35 into the annular chamber 33, and the force balance between the upper chamber and the annular chamber 33 will be broken. As a result, the air piston 32 cuts off the shear pins 211 under the driving effect of the annular liquid column pressure and continues to move upward until the slips 22 are hung on the casing.

[0045] In the present invention, the memory alloy is preferably a bismuth alloy, which can achieve the effect of controlling the melting point by adjusting the proportion of the alloy, so that different downhole requirements can be more easily met. Preferably, the melting point of the bismuth alloy is generally 75°C, 92°C, 125°C, 138°C and 180°C. It is worth noting that if the flow channel transition member 35 is made of a memory alloy, then if the tail pipe hanger needs to be raised later, the flow channel transition member 35 will be restored from liquid to solid and re-sealed in the guide groove 34 to effectively limit the flow path of the annular mud, further preventing the slip 22 from opening again.

[0046] In the present invention, polymer materials include but are not limited to polystyrene (melting point 120°C), polyester resin (140-150°C) and low-density polyethylene (melting point 90-125°C), so different downhole requirements can be more easily met by selecting different materials.

[0047] Preferably, the flow channel transition member 35 is configured in a cone shape, and the guide groove 34 is configured to have a corresponding shape that can abut against the flow channel transition member 35. During the process of lowering the liner hanger 100 into the wellbore, the flow channel transition member 35 will be firmly limited in the guide groove 34, and on the one hand, the flow channel transition member 35 needs to be melted before the guide groove 34 can be opened, and on the other hand, the shear pin 211 needs to be cut off before the slip 22 can be hung on the casing. Therefore, under the condition of double limiting measures, it can be ensured that the slip 22 will not be opened prematurely during the lowering process, so as to further improve the reliability and accuracy of the liner hanger 100.

[0048] In one embodiment, Figure 1 and 2 As shown, the hanging mechanism further includes a cone sleeve 23 disposed above the slip 22. Preferably, a guide slope 231 is provided on one side of the cone sleeve 23 close to the slip 22. Specifically, the outer diameter of the guide slope 231 is from Figure 1 In the process of ascending, the slip 22 will move radially outward under the action of the guide slope 231, and the teeth arranged on the outer wall of the slip 22 will fully bite the inner wall surface of the wellbore to complete the sitting action, further improving the firmness and stability of the sitting wellbore.

[0049] In one embodiment, Figure 1 and 2 As shown, the sitting mechanism also includes an end ring 24 sleeved on the outside of the body 10. Preferably, the end ring 24 is fixedly mounted on the body 10, and the end ring 24 is arranged above the cone sleeve 23 and connected thereto by screws or threads, so as to provide favorable support for the sitting action of the slip 22. As a result, the axial position of the cone sleeve 23 will be effectively limited under the action of the end ring 24, further ensuring that the slip 22 can smoothly complete the sitting action. Preferably, a sealing ring is provided between the end ring 24 and the body 10.

[0050] In the present invention, if Figure 1 and 2 As shown, a plurality of spaced-apart slips 22 are provided along the circumference of the body 10. In other words, the slips 22 can move in multiple radial directions simultaneously under the action of the cone sleeve 23, thereby increasing the actual contact area between the slips 22 and the inner wall of the wellbore, thereby ensuring that the slips 22 can smoothly complete the hanging action, and further improving the reliability and firmness of the liner hanger 100 after hanging.

[0051] Preferably, a guiding slope matching the guiding slope 231 of the cone sleeve 23 is provided on the upper part of the slip 22. Therefore, after the slip 22 moves upward and the guiding slope contacts the guiding slope 231 of the cone sleeve 23, the slip 22 can more easily complete the radial outward movement, thereby being smoothly hung on the inner wall of the wellbore, further improving the firmness of the liner hanger 100 after being hung.

[0052] The present invention can open up the passage between the wellbore and the annulus chamber 33 by melting the flow channel transition piece 35, thereby facilitating the subsequent work of hanging the wellbore. Compared with the prior art, the present device does not need to set up a ball seat, so it can effectively avoid the problem of instantaneous turbulent pressure when the ball seat is blocked and damage to the open hole bottom layer. In addition, the tie-back tube and the sealing shell in the present invention are an integrated structure (i.e., the tie-back tube integrated sealing shell 202 hereinafter), which can effectively eliminate the weak links of the prior art and thus ensure the long-term sealing of the tail pipe hanger 100 and the integrity of the tail pipe wellbore.

[0053] In one embodiment, Figure 1 and 2 As shown, the liner hanger 100 also includes a straightening ring 11 sleeved on the outside of the body 10. The straightening ring 11 is fixedly mounted on the body 10 and axially abuts against the lower end surface of the connecting sleeve 31, so the straightening ring 11 can effectively limit the connecting sleeve 31 to ensure that the axial position of the connecting sleeve 31 does not change after the liquid column pressure is formed in the annular cavity 33. In the present invention, the straightening ring 11 not only fixes the body 10 and the connecting sleeve 31, but also plays a good straightening role for the entire liner hanger 100 during the process of being lowered into the wellbore.

[0054] In one embodiment, Figure 1 and 2 As shown, the liner hanger 100 further includes a lifting joint 12 disposed above the end ring 24 and axially abutting against the end ring 24. Preferably, the upper end of the lifting joint 12 is a casing buckle, which is connected to the integrated sealing housing 202 of the tie-back tube through the casing buckle; the lower end of the lifting joint 12 is fixedly sleeved at the top of the body 10.

[0055] In one embodiment, Figure 1 and 2As shown, the liner hanger 100 also includes a first seal 101 disposed between the connecting sleeve 31, the air piston 32 and the body 10, and a second seal 102 filled in the annulus between the air piston 32 and the body 10. Preferably, the upper chamber is sealed by the first seal 101; the annulus chamber 33 is sealed by the second seal 102. In this way, the pressure of the upper chamber and the annulus chamber 33 is not affected by the outside world, so as to ensure that after the flow channel transition member 35 melts, the annulus liquid column pressure formed in the annulus chamber 33 can smoothly push the air piston 32 upward, which is conducive to completing the hanging work.

[0056] Preferably, the first sealing element 101 is configured as a sealing ring.

[0057] Figure 3 The first part of the structure of the pipe string according to the present invention is schematically shown;

[0058] Figure 4 The second part of the structure of the pipe string according to the present invention is schematically shown.

[0059] like Figure 3 and 4 According to the second aspect of the present invention, a pipe string is provided, which mainly comprises a running tool 201, a tieback integrated sealing shell 202 and a liner hanger 100 connected in sequence from top to bottom. Preferably, a sealing core 203 is provided in the tieback integrated sealing shell 202.

[0060] In the present invention, the running tool 201 is connected to the integrated sealing housing 202 of the tie-back tube by a screw thread. Preferably, the tightening direction of the screw thread is opposite to the rotation direction of the drilling tool, so that after the setting is completed, the running tool 201 can be released by rotating forward, and then the conventional liner cementing operation process can be entered.

[0061] The working principle of the present invention is briefly described below:

[0062] First, the bottom of the liner hanger 100 is connected to the liner string, the top of the liner hanger 100 is connected to the integrated sealing shell 202 of the tie-back tube and the running tool 201, and the entire device is run into the predetermined position of the wellbore (unlimited displacement circulation can be achieved during the running process to ensure that the liner hanger 100 is safely and smoothly lowered into place); then, after the flow channel transition member 35 melts from solid to liquid, the annular mud will push the liquid flow channel transition member 35 into the annular chamber 33, and the force balance between the upper chamber and the annular chamber 33 will be broken. At the same time, the shear pin 211 will be cut off under the action of the annular liquid column pressure, so that the air piston 32 continues to move upward; finally, the slip 22 will move outward in multiple radial directions under the action of the guide slope 231, and fully bite the inner wall surface of the wellbore through the teeth set on the outer wall of the slip 22 to complete the sitting and hanging action.

[0063] It is worth noting that if the channel transition piece 35 is not fully melted when the liner hanger 100 is lowered to the predetermined position, a heater can be lowered by wire operation to ensure that the channel transition piece 35 is completely melted into a liquid state, thereby further improving the success rate of setting the liner hanger.

[0064] According to a third aspect of the present invention, there is provided a construction process, which uses the pipe string as described above, comprising the following steps:

[0065] First, the liner hanger 100 is sent to a predetermined position in the wellbore by the sending tool 201, and the flow channel conversion component 35 is melted from a solid state to a liquid state under the action of the high temperature in the well.

[0066] Then, the annular cement slurry pushes the liquid flow channel conversion member 35 into the annular chamber 33 and gradually increases the liquid column pressure until the shear pin 211 is sheared off. The air piston 32 continues to move upward under the push of the liquid column pressure. At the same time, the cava 22 opens radially outward under the action of the cone sleeve 23 so as to be smoothly hung on the inner wall of the casing.

[0067] Finally, the running tool 201 is released by forward rotation, and then the normal liner cementing work is resumed.

[0068] Compared with the prior art, the advantages of the present invention are:

[0069] First, the present invention uses the flow channel transition member 35 as the information carrier of the sitting action, that is, the passage between the wellbore and the annulus chamber 33 can be opened by melting the flow channel transition member 35 at high temperature, further promoting the liner hanger 100 to sit in the wellbore. In addition, the device does not require a ball-dropping pressure-holding operation, and the closed-loop design of the control system can realize an infinite displacement cycle during the liner string running process, thereby ensuring the reliability of the string running.

[0070] Secondly, compared with the prior art, the device does not need to be provided with a ball seat, so it can effectively avoid the problem of instantaneous turbulent pressure when the ball seat is blocked and damage to the bottom layer of the open hole. In addition, since there is no pressure transmission hole on the device, it can effectively avoid many problems caused by hydraulic control failure, thereby eliminating the weak links of the prior art and further ensuring the long-term sealing of the liner hanger 100 and the integrity of the liner wellbore.

[0071] The above are only preferred embodiments of the present invention, but the protection scope of the present invention is not limited thereto. Those skilled in the art can easily make changes or modifications within the disclosure scope of the present invention, and such changes or modifications should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. A liner hanger, comprising: Ontology(10), A sitting and hanging mechanism, comprising a support sleeve (21) fixed to the body (10) by shear nails (211), and a slip (22) arranged above the support sleeve (21). A driving mechanism, comprising a connecting sleeve (31) disposed below the supporting sleeve (21), an air piston (32) disposed between the supporting sleeve (21) and the connecting sleeve (31), and an annular cavity (33) formed between the body (10), the air piston (32) and the connecting sleeve (31). Wherein, a guide groove (34) for receiving annular space mud is provided on the connecting sleeve (31), and a flow channel transition piece (35) is filled in the guide groove (34). After the flow channel conversion component (35) melts from a solid state to a liquid state in the well, the annular cement slurry can push the flow channel conversion component (35) into the annular chamber (33) to cut the pin (211) and promote the upward movement of the air piston (32) until the slip (22) is seated on the casing.

2. The liner hanger according to claim 1, wherein: The flow channel transition piece (35) is made of memory alloy or polymer material.

3. The liner hanger according to claim 2, wherein: A plurality of slips (22) are arranged at intervals along the circumference of the body (10).

4. The liner hanger according to claim 3, wherein: The flow path transition piece (35) is configured to have a cone shape, and the guide groove (34) is configured to have a corresponding shape capable of abutting against the flow path transition piece (35).

5. The liner hanger according to claim 4, wherein: The hanging mechanism further includes a cone sleeve (23) arranged above the slip (22), and an end ring (24) sleeved outside the body (10) and used to limit the cone sleeve (23), wherein a guide inclined surface (231) is provided on the cone sleeve (23) for prompting the slip (22) to open radially outward.

6. The liner hanger according to claim 5, characterized in that: The air piston (32) is fixed to the support sleeve (21) by means of bolts.

7. The liner hanger according to claim 6, wherein: The tail pipe hanger further comprises a straightening ring (11) sleeved outside the body (10) and used to limit the connecting sleeve (31), and a lifting joint (12) sleeved outside the body (10) and abutting against the end ring (24).

8. The liner hanger according to claim 7, wherein: The liner hanger further comprises a first seal (101) arranged between the connecting sleeve (31), the air piston (32) and the body (10), and a second seal (102) filled in the annulus between the air piston (32) and the body (10).

9. A pipe string comprising a running tool (201), a tieback integrated sealing housing (202), and a liner hanger according to any one of claims 1 to 8, which are connected in sequence. A sealing core (203) is provided in the integrated sealing shell (202) of the tie-back cylinder.

10. The pipe string according to claim 9, characterized in that: The running tool (201) and the integrated sealing shell (202) of the tie-back cylinder are connected by screw threads.

11. A construction process using the pipe string according to claim 10, comprising the following steps: S1, the liner hanger is sent into a predetermined position in the wellbore by the sending tool (201), and the flow channel conversion component (35) is melted from a solid state to a liquid state in the well; S2, the annular cement slurry pushes the flow channel conversion member (35) into the annular chamber (33) until the shear pin (211) is cut, thereby pushing the air piston (32) upward; the slips (22) are opened outward under the action of the cone sleeve (23) until they are seated on the casing; S3, releasing the running tool (201) by forward rotation, and switching to the tail pipe cementing operation.