Construction method for safely cleaning sudden inrush body of highway tunnel

Through early warning system and spray concrete, the safety risks and stability problems in the cleaning process of the rush during highway tunnel construction are solved, ensuring the safety and efficiency of the construction process, and preventing the rush from causing the rush again.

CN118934055APending Publication Date: 2024-11-12CHINA RAILWAY TUNNEL GROUP CO LTD +3
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411147284.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-21
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

During the construction of highway tunnels, gustings caused by complex geological conditions and changing groundwater environment are difficult to clean up quickly during the construction process, which poses safety risks and stability problems. In particular, gustings trapped in the cave may cause gustings again. Increase the difficulty of disposal.

Method used

Use an early warning system to detect the displacement of the surge body and early warning. The surge body is retained in the closed hole of spray concrete, and a drainage steel pipe and grouting steel pipe are arranged, combining concrete sealing walls and drainage holes to ensure drainage pressure reduction and stability, and gradually recover. Cleaning process.

Benefits of technology

It realizes timely early warning and safe evacuation during the construction process, prevents the surge body from slipping, ensures the safety and stability of the cleaning process, reduces the risk of surge again, and improves construction efficiency and safety guarantees.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118934055A_ABST
    Figure CN118934055A_ABST
Patent Text Reader

Abstract

A construction method for safely cleaning a sudden inrush body of a highway tunnel relates to the field of tunnel construction, and specifically comprises the steps of early warning system linkage, closing of a sudden inrush body retained in the tunnel, recovery and cleaning, and drainage and pressure reduction. A monitoring camera, a noise alarm, a displacement induction alarm and a video monitoring duty room are arranged at the position close to a tunnel face, so that a far-end combined early warning mechanism in the cleaning process is achieved, concrete spraying sealing is conducted on a loose and saturated water-containing inrush body retained in a tunnel, safety storage is provided, then a water drainage steel pipe A is arranged, and the water drainage steel pipe B is arranged in the tunnel. The open drainage and the drainage steel pipe A are used for drainage and pressure relief, and finally grouting reinforcement and cleaning are carried out, so that drainage and pressure relief are considered, and the displacement hidden danger of residual inrush bodies in the hole is prevented; the concrete blocking wall is adopted to block the end of the uncleaned part of the retained inrush body in the hole, meanwhile, the water drainage holes are pre-buried in the concrete blocking wall, the front portion of the whole blocking wall is in a water drainage and pressure reduction state, and safety guarantee is provided for implementation of a follow-up treatment scheme.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of tunnel construction, in particular to a construction method for safely clearing a sudden burst body in a highway tunnel. Background Art

[0002] It is well known that for highway tunnels with complex geological conditions and changeable groundwater environment, unfavorable geological conditions such as rock contact zones, karst, and beaded karst caves may be encountered during the construction process. When a continuous magnitude burst occurs, it will cause serious consequences. In particular, when the length of the tunnel construction exceeds a certain distance, once a sudden mud and water surge occurs, a large amount of groundwater carrying mud and rocks will surge out, forming a surf in the tunnel. When the sudden surge ends, the mud and rocks carried out by the groundwater will be retained in the tunnel. If construction needs to be resumed, the large amount of sudden surge bodies retained in the tunnel must be cleared, but there are the following problems in the cleaning process: (1) Due to the volume of the retained surge and the length of the operation, the cleaning work cannot reach the tunnel face in a short time. During the cleaning process, it is very likely that another surge will occur. However, the personnel cannot observe in real time at a position close to the tunnel face, and the safety risk of the cleaning process is high; (2) When a large amount of groundwater is exposed, the surge body retained in the cave cannot be naturally hardened in a short period of time. During the cleaning process of the surge body retained in the cave, the end of the surge body being cleaned may slip, which will pull the entire surge body behind to move, thereby causing surges to occur again in the parts around the face that have not surged into the cave, increasing the difficulty of handling; (3) When cleaning to the appropriate location, the stability protection and drainage and pressure reduction considerations of the uncleaned parts play an important role in whether there will be another sudden surge. Summary of the invention

[0003] In order to overcome the deficiencies in the background technology, the present invention discloses a construction method for safely clearing a sudden burst body in a highway tunnel.

[0004] In order to achieve the above-mentioned object of the invention, the present invention adopts the following technical scheme: A construction method for safely clearing a sudden burst body in a highway tunnel comprises the following steps: (1) Early warning system linkage An early warning system is set up in the tunnel to detect and warn of the displacement of the surge body. When an abnormality occurs, personnel entering the tunnel who have cleared the normal surge body will evacuate. (2) Seal the retained surge body in the cave Desilt inward from the tunnel entrance. When the water content of the retained surge body in the tunnel increases, the accumulation height exceeds half of the clearance of the cross section, and it is judged that the risk of landslide is high, desiltation is stopped, and concrete is sprayed from the inside to the outside on the surface of the uncleaned part of the retained surge body in the tunnel. During the implementation of sprayed concrete, ensure that the open water on the face is drained smoothly; drive a drainage steel pipe A with a length of not less than 15m forward along the surface of the retained surge body in the tunnel where the sprayed concrete operation has been implemented. The body of the drainage steel pipe A has evenly arranged through holes, and the number of holes driven in is set according to the water flow conditions on the surface of the surge body; Multiple grouting steel pipes are driven obliquely from the inside to the outside along the surface of the retained surge body in the tunnel where the shotcrete operation has been carried out. The horizontal and vertical spacing between two adjacent grouting steel pipes is controlled to be no more than 1.5m. The length of the grouting steel pipe should ensure that it is driven below the bottom plate by no less than 50cm. After the grouting steel pipes are laid out, cement slurry or cement double liquid slurry is used to grout and consolidate the remaining surge body in the tunnel. (3) Recovery and cleanup Following the previous step, after the consolidation of the retained surge body in the tunnel is completed, the cleaning is resumed and gradually advanced to the tunnel face. During the advancement process, the water discharge capacity in front is maintained normal, and a reinforcement stability zone of no less than 5 m is left. If the above conditions are not met, the construction is continued according to step (2) until it is close to the tunnel face or the height of the retained surge body in the tunnel is basically close to the arch crown; (4) Discharge water to reduce pressure Following the previous step, near the face or the position where the height of the retained surge body in the tunnel is close to the top of the arch, drive in joint steel bars with a length of not less than 60 cm along the four sides, insert one end of the joint steel bars into the surrounding wall, and install a formwork near the direction of the tunnel entrance to pour concrete layer by layer. During the concrete pouring process, a steel support is used to embed a drainage steel pipe B inside it, one end of the drainage steel pipe B is connected to the end of the residual surge body in the tunnel, and the other end is exposed on the surface of the concrete blocking wall. The drainage steel pipe B embedded in the concrete blocking wall is used as a drainage hole. After the concrete blocking wall is implemented, check the buried drainage steel pipe B. If the drainage capacity of the drainage steel pipe B is insufficient, use a drilling rig to drill forward in the drainage steel pipe B to clear the drainage channel.

[0005] The construction method for safely clearing a sudden burst body in a highway tunnel is characterized in that the early warning system includes a monitoring camera, a noise alarm, an early warning speaker and a displacement sensing touch device. Lighting equipment, a displacement sensing touch device, a monitoring camera and a noise alarm are respectively installed near the face. A computer monitor is connected to the video monitoring duty room set at the tunnel entrance. A temporary generator is set outside the tunnel entrance. The temporary generator is connected to the computer monitor, the monitoring camera, the noise alarm and the early warning speaker through lines. The displacement sensing touch device is connected to the noise alarm and the early warning speaker in turn.

[0006] The construction method for safely clearing a sudden surge in a highway tunnel is characterized in that the displacement sensing touch device includes a metal rod, a metal sensing wire, a magnet, an expansion bolt and an early warning alarm system. The metal rod is vertically inserted into the sudden surge near the face position, and corresponding expansion bolts are fixed on the left and right walls along the cross-sectional direction of the tunnel body. The magnet is adsorbed on the expansion bolt on the left wall, and a metal sensing wire is connected between the magnet and the alarm device. One end of the metal sensing wire is connected to the magnet, and the other end is passed around the expansion bolt on the right wall in turn and is connected to the noise alarm and the alarm device in turn.

[0007] The construction method for safely clearing a sudden surge in a highway tunnel comprises arranging an early warning button in a video monitoring duty room, and the early warning button is connected to an early warning speaker through a signal line.

[0008] In the construction method for safely clearing a sudden burst body in a highway tunnel, in step (2), the thickness of the concrete sprayed from the inside to the outside is not less than 40 cm near the tunnel face, and the thickness of the sudden burst body retained in the tunnel behind the tunnel face is not less than 20 cm. The length of the drainage steel pipe A should always be greater than the length of the reinforced area by at least 5 m.

[0009] The construction method for safely cleaning the surging body of a highway tunnel is as follows: in step (2), after the surface of the uncleaned part of the surging body retained in the tunnel is sealed by spraying concrete, if it still cannot withstand the operation of personnel and drilling rigs, dry tunnel slag is transported from outside the tunnel and evenly spread on the surface of the surging body retained in the tunnel by small mechanical equipment. During the spreading process, the direct drainage on the surface is guided to the side wall for discharge. After the paving is completed, the surface is sealed by spraying concrete, or the surface of the surging body retained in the tunnel where the spraying concrete operation has been carried out is sprayed again to seal it until it can withstand the operation of personnel and drilling rigs. After the spraying concrete is reinforced on the surface of the surging body remaining in the tunnel, it cannot affect the direct discharge of surface water.

[0010] In the construction method for safely clearing a sudden burst body in a highway tunnel, in step (2), the grouting method used is low-pressure slow grouting, and the grouting pressure is controlled within 1.5 MPa.

[0011] Due to the adoption of the above technical solution, the present invention has the following beneficial effects: 1. The construction method for safe cleaning of a sudden burst body in a highway tunnel described in the present invention realizes a remote joint early warning mechanism during the cleaning process by arranging a monitoring camera, a noise alarm, a displacement sensing alarm, and a video monitoring duty room near the face. If an abnormal situation occurs in the tunnel, timely early warning and evacuation are carried out, providing safety guarantee for the operation.

[0012] 2. The construction method for safely cleaning the surge body in the highway tunnel described in the present invention is to first seal the loose and saturated surge body retained in the tunnel with sprayed concrete to provide a safety reserve, then lay out the drainage steel pipe A, use open drainage and the drainage steel pipe A to drain water and relieve pressure, and finally implement grouting reinforcement to clean up. The process takes into account both drainage and pressure relief and prevents the hidden danger of displacement of the residual surge body in the tunnel; the ends of the uncleaned parts of the retained surge body in the tunnel are blocked by using a concrete blocking wall, and drainage holes are pre-buried on the concrete blocking wall. The front of the entire blocking wall is in a drainage and pressure reduction state, providing safety guarantee for the implementation of subsequent disposal plans. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is a plan view of the early warning system for clearing the sudden surge body retained in the cave according to the present invention.

[0014] Figure 2 It is a schematic diagram of the horizontal installation of the displacement sensing touch device of the present invention.

[0015] Figure 3 It is a schematic diagram of the reinforcement of the surge body retained in the cave according to the present invention.

[0016] Figure 4 It is a longitudinal schematic diagram of the implementation of the concrete blocking wall of the present invention.

[0017] Figure 5 It is a layout diagram of the grouting steel pipe and the drainage steel pipe A of the present invention.

[0018] In the figure: 1. Tunnel entrance; 2. Surge body in the tunnel; 3. Metal induction line; 4. Metal rod; 5. Monitoring camera; 6. Face; 7. Noise alarm; 8. Displacement sensing alarm; 9. Early warning horn; 10. Video monitoring duty room; 11. Video monitoring; 12. Alarm device; 13. Expansion bolt; 14. Magnet; 15. Formwork; 16. Uncleaned part of the surge body retained in the tunnel; 17. Shotcrete; 18. Drainage steel pipe A; 19. Bottom plate; 20. Grouting steel pipe; 21. Concrete sealing wall; 22. Cleaned part; 23. Drainage steel pipe B; 24. Joint steel bars. DETAILED DESCRIPTION

[0019] The present invention can be explained in detail by the following examples, and the purpose of disclosing the present invention is to protect all technical improvements within the scope of the present invention.

[0020] Combined with Figure 1-5 The construction method for safely clearing the sudden outburst in a highway tunnel specifically comprises the following steps: (1) Early warning system linkage An early warning system is set up in the tunnel body to detect and warn the displacement of the surge body. The early warning system includes a monitoring camera 5, a noise alarm 7, an early warning speaker 9 and a displacement sensing touch device. Lighting equipment, a displacement sensing touch device, a monitoring camera 5 and a noise alarm 7 are installed near the face 6. A computer monitor is connected to the video monitoring duty room 10 set at the tunnel entrance 1. A temporary generator is set up outside the tunnel entrance 1. The temporary generator is connected to the computer monitor, the monitoring camera 5, the noise alarm 7 and the early warning speaker 9 through lines. The displacement sensing touch device is connected to the noise alarm 7 and the early warning speaker 9 in turn. An early warning button is set up in the video monitoring duty room 10, and the early warning button is connected to the early warning speaker 9 through a signal line. The displacement sensing touch device includes a metal rod 4, a metal sensing wire 3, a magnet 14, an expansion bolt 13 and an early warning alarm system. The metal rod 4 is vertically inserted into the surge body near the tunnel face 6. Corresponding expansion bolts 13 are fixed on the left and right walls along the cross-sectional direction of the tunnel body. The magnet 14 is adsorbed on the expansion bolt 13 on the left wall. A metal sensing wire 3 is connected between the magnet 14 and the alarm device 12. One end of the metal sensing wire 3 is connected to the magnet 14, and the other end is sequentially bypassed around the expansion bolt 13 on the right wall, and sequentially connected to the noise alarm 7 and the alarm device 12. When the displacement sensing touch device is in use, the insertion depth of the metal rod 4 is sufficient to ensure that it does not shake. When the surge body in the cave is displaced, the metal rod 4 falls over and touches the metal sensing wire 3, the magnet is disconnected from the expansion bolt 13, the metal sensing wire 3 triggers the noise alarm 7 and the alarm device 12, the early warning horn 9 sounds, and the personnel entering the cave who clean the normal surge body evacuate. When the cleaning height of the surge body retained in the cave exceeds 2m or the residue is mostly loose and saturated with water, it is no longer directly cleaned; (2) Seal the retained surge body in the cave At the stop construction position, concrete 17 is sprayed from the inside to the outside on the surface of the uncleaned part 16 of the surge body retained in the hole, as shown in the attached Figure 3 As shown, the thickness of the concrete 17 sprayed from the inside to the outside is not less than 40cm at the part close to the face, and not less than 20cm on the surface of the retained surge body in the tunnel behind the face. During the implementation of the concrete spraying 17, ensure that the open water of the face 6 is unobstructed; after the surface of the uncleaned part 16 of the retained surge body in the tunnel is sprayed with concrete 17 to seal it, if it still cannot withstand the operation of personnel and drilling rigs, transport dry tunnel slag from outside the tunnel, and use small mechanical equipment to evenly spread it on the surface of the retained surge body in the tunnel. During the spreading process, the direct drainage of the surface is dredged to the side wall for discharge. After the paving is completed, the surface is sprayed with concrete to seal it, or the surface of the retained surge body in the tunnel where the sprayed concrete operation has been implemented is sprayed with concrete again to seal it until it can withstand the operation of personnel and drilling rigs. After the sprayed concrete reinforces the surface layer of the residual surge body in the tunnel, it cannot affect the direct discharge of open water. Drive a drainage steel pipe A18 with a length of not less than 15m forward along the surface of the retained surge body in the hole where the shotcrete 17 operation has been carried out. The length of the drainage steel pipe A18 should be at least 5m longer than the length of the reinforced area at any time. The body of the drainage steel pipe A18 is evenly arranged with through holes, and the number of holes driven in is set according to the water flow conditions on the surface of the surge body; A plurality of grouting steel pipes 20 are driven obliquely from the inside to the outside along the surface of the retained surge body in the tunnel where the shotcrete 17 operation has been implemented. The lateral and longitudinal spacings between two adjacent grouting steel pipes 20 are controlled to be no more than 1.5 m. The length of the grouting steel pipe 20 should ensure that it is driven below the bottom plate 19 by no less than 50 cm, so as to play the role of anti-slip anchoring. After the grouting steel pipe 20 is laid out, cement slurry or cement double liquid slurry is used to grout and consolidate the surge body remaining in the tunnel. This process is mainly to consolidate the surge body remaining in the tunnel. The grouting method is low-pressure slow grouting to ensure that the slurry has sufficient contact with the residual surge body in the tunnel. (3) Recovery and cleanup Following the previous step, after the reinforcement of the retained surge body in the tunnel is completed, the cleaning is resumed and the work is gradually advanced toward the tunnel face 6. During the advancement process, the water discharge capacity in front is maintained normal, and a reinforcement stable zone of not less than 5 m is left. If the above conditions are not met, the construction is continued according to step (2) until it approaches the tunnel face 6 or the height of the retained surge body in the tunnel is basically close to the arch top. (4) Discharge water to reduce pressure Continue with the previous step, as shown in the attached Figure 4 As shown, near the face 6 or the position where the height of the retained surge body in the tunnel is close to the top of the arch, joint steel bars 24 with a length of not less than 60 cm are driven in along the four sides, one end of the joint steel bars 24 is inserted into the surrounding wall, and a template 15 is installed on the side near the tunnel opening 1 to pour concrete layer by layer. During the concrete pouring process, a steel bar bracket is used to embed a drainage steel pipe B23 inside it, one end of the drainage steel pipe B23 is connected to the end of the residual surge body in the tunnel, and the other end is exposed from the surface of the concrete blocking wall 21, facing the cleaned part 22. The drainage steel pipe B23 embedded in the concrete blocking wall 21 is used as a drainage hole. After the concrete blocking wall 21 is implemented, the buried drainage steel pipe B23 is checked. If the drainage capacity of the drainage steel pipe B23 is insufficient, a drilling rig is used to drill holes forward in the drainage steel pipe B23 to clear the drainage channel.

[0021] Parts of the present invention not described in detail are prior art.

[0022] The embodiments selected herein for the purpose of disclosing the invention are currently considered to be suitable, but it should be understood that the invention is intended to include all changes and modifications of the embodiments that fall within the scope of the concept and invention.

Claims

1. A construction method for safely clearing a sudden burst body in a highway tunnel, characterized by: The specific steps include: (1) Early warning system linkage An early warning system is set up in the tunnel to detect and warn of the displacement of the surge body. When an abnormality occurs, personnel entering the tunnel who have cleared the normal surge body will evacuate. (2) Seal the retained surge body in the cave Desilt inward from the tunnel entrance. When the water content of the retained surge body in the tunnel increases, the accumulation height exceeds half of the clearance of the cross section, and it is judged that the risk of landslide is high, desiltation is stopped, and concrete is sprayed from the inside to the outside on the surface of the uncleaned part of the retained surge body in the tunnel. During the implementation of sprayed concrete, ensure that the open water on the face is drained smoothly; drive a drainage steel pipe A with a length of not less than 15m forward along the surface of the retained surge body in the tunnel where the sprayed concrete operation has been implemented. The body of the drainage steel pipe A has evenly arranged through holes, and the number of holes driven in is set according to the water flow conditions on the surface of the surge body; Multiple grouting steel pipes are driven obliquely from the inside to the outside along the surface of the retained surge body in the tunnel where the shotcrete operation has been carried out. The horizontal and vertical spacing between two adjacent grouting steel pipes is controlled to be no more than 1.5m. The length of the grouting steel pipe should ensure that it is driven below the bottom plate by no less than 50cm. After the grouting steel pipes are laid out, cement slurry or cement double liquid slurry is used to grout and consolidate the remaining surge body in the tunnel. (3) Recovery and cleanup Following the previous step, after the consolidation of the retained surge body in the tunnel is completed, the cleaning is resumed and gradually advanced to the tunnel face. During the advancement process, the water discharge capacity in front is maintained normal, and a reinforcement stability zone of no less than 5 m is left. If the above conditions are not met, the construction is continued according to step (2) until it is close to the tunnel face or the height of the retained surge body in the tunnel is basically close to the arch crown; (4) Discharge water to reduce pressure Following the previous step, near the face or the position where the height of the retained surge body in the tunnel is close to the top of the arch, drive in joint steel bars with a length of not less than 60 cm along the four sides, insert one end of the joint steel bars into the surrounding wall, and install a formwork near the direction of the tunnel entrance to pour concrete layer by layer. During the concrete pouring process, a steel support is used to embed a drainage steel pipe B inside it, one end of the drainage steel pipe B is connected to the end of the residual surge body in the tunnel, and the other end is exposed on the surface of the concrete blocking wall. The drainage steel pipe B embedded in the concrete blocking wall is used as a drainage hole. After the concrete blocking wall is implemented, check the buried drainage steel pipe B. If the drainage capacity of the drainage steel pipe B is insufficient, use a drilling rig to drill forward in the drainage steel pipe B to clear the drainage channel.

2. The construction method for safe cleaning of a sudden burst body in a highway tunnel according to claim 1 is characterized by: The early warning system includes surveillance cameras, noise alarms, early warning speakers and displacement sensing touch devices. Lighting equipment, displacement sensing touch devices, surveillance cameras and noise alarms are installed near the face. A computer monitor is connected to the video surveillance duty room at the cave entrance. A temporary generator is set up outside the cave entrance. The temporary generator is connected to the computer monitor, surveillance camera, noise alarm and early warning speaker through lines. The displacement sensing touch device is connected to the noise alarm and early warning speaker in turn.

3. The construction method for safe cleaning of a sudden burst body in a highway tunnel according to claim 1 is characterized by: The displacement sensing touch device includes a metal rod, a metal sensing wire, a magnet, an expansion bolt and an early warning alarm system. The metal rod is vertically inserted into the surge body near the face position. Corresponding expansion bolts are fixed on the left and right walls along the cross-sectional direction of the tunnel body. The magnet is adsorbed on the expansion bolt on the left wall. A metal sensing wire is connected between the magnet and the alarm device. One end of the metal sensing wire is connected to the magnet, and the other end bypasses the expansion bolt on the right wall and is connected to the noise alarm and the alarm device in turn.

4. The construction method for safe cleaning of a sudden burst body in a highway tunnel according to claim 1 is characterized by: An early warning button is provided in the video surveillance duty room, and the early warning button is connected to the early warning speaker through a signal line.

5. The construction method for safe cleaning of a sudden burst body in a highway tunnel according to claim 1 is characterized by: In step (2), the thickness of the concrete sprayed from the inside to the outside shall not be less than 40 cm near the tunnel face, and the thickness of the surface of the retained surge body in the tunnel behind the tunnel face shall not be less than 20 cm. The length of the drainage steel pipe A shall always be greater than the length of the reinforced area by at least 5 m.

6. The construction method for safe cleaning of a sudden burst body in a highway tunnel according to claim 1 is characterized by: In step (2), after the surface of the uncleaned part of the retained surge body in the tunnel is sealed by spraying concrete, if it still cannot withstand the operation of personnel and drilling rigs, dry tunnel slag is transported from outside the tunnel and evenly spread on the surface of the retained surge body in the tunnel using small mechanical equipment. During the spreading process, the direct drainage on the surface is diverted to the side wall for discharge. After the spreading is completed, the surface is sealed by spraying concrete, or the surface of the retained surge body in the tunnel where the spraying concrete operation has been carried out is directly sprayed with concrete again to seal it until it can withstand the operation of personnel and drilling rigs. After the spraying concrete is used to reinforce the surface of the residual surge body in the tunnel, it cannot affect the direct discharge of surface water.

7. The construction method for safe cleaning of a sudden burst body in a highway tunnel according to claim 1 is characterized by: In step (2), the grouting method adopted is low-pressure slow grouting, and the grouting pressure is controlled within 1.5 MPa.