Transparent railway ballast layer model manufacturing method and device and method for carrying out ballast railway roadbed frost boiling and mud pumping test by using transparent railway ballast layer model

Through the transparent ballast layer model and specially designed test equipment, the problem of difficulty in real ballast layer deformation and observation of traditional tests is solved, and efficient simulation of the slurry and mud in railway subgrade under small axial force is realized to monitor soil moisture content and Particle migration overcomes the difficulties of traditional experiments.

CN118937031APending Publication Date: 2024-11-12CENT SOUTH UNIV
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411263208.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-10
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In railway engineering, traditional indoor experiments for slurry-floating mud are difficult to achieve real meticulous study of the deformation and mud migration of the ballast layer, and huge axial pressure is required, and the inside of the ballast gravel cannot be directly observed.

Method used

The transparent ballast layer model is used to generate a ball particle model through blue light scanning, voxelization algorithm and water filling algorithm. The transparent ballast layer model is manufactured in combination with 3D printing technology, and a type of axial loading device and seepage box are designed. The test device of the head control box uses small axial force to achieve 30-60mm compression deformation of the ballast layer, and monitors soil sample moisture content and particle migration.

Benefits of technology

It realizes the real simulation of the slurry and mud-burning test of the basin railway subgrade without huge axial pressure, which is convenient for observing and monitoring mud migration, and overcomes the difficulty of real deformation and observation defects in traditional experiments.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118937031A_ABST
    Figure CN118937031A_ABST
Patent Text Reader

Abstract

The invention discloses a manufacturing method of a transparent railway ballast layer model and a device and method for carrying out ballast railway roadbed frost boiling and mud pumping test by using the model, and the manufacturing method of the transparent railway ballast layer model comprises the following steps: scanning a plurality of roadbed ballasts one by one by using a blue light scanner to obtain a three-dimensional triangular mesh model of a plurality of railway ballast particles, and storing a file; the triangular mesh data of the railway ballast particles are converted into an expression form of a tiny three-dimensional cube through a voxelization algorithm, and a shell of a railway ballast particle model is obtained; filling the shell of each particle model with spherical particles through a flooding filling algorithm; replacing the voxel grids with the ball particles to obtain a real model of the railway ballast particles; stacking a plurality of railway ballast particle models in a self-weight state and simulating a compaction process to form a railway ballast layer model; the change of the rotation angle and the gravity center of each ballast particle after accumulation is obtained, and the three-dimensional network model file corresponding to each single ballast particle is correspondingly changed and combined into an accumulated three-dimensional network model; and inputting the three-dimensional grid model data into a 3D printer, and printing a transparent ballast layer model by adopting a PVC (Polyvinyl Chloride) material.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the research field of mud bubbling mechanism of roadbed, and specifically relates to a method for making a transparent ballast layer model and a device and method for conducting mud bubbling test of ballasted railway roadbed by using the model. Background Art

[0002] In railway engineering, mud and slurry is a prominent disease that affects the structure of transportation infrastructure and driving safety. The mud and water that come out pollute the ballast, block the pores between the ballast particles, and after hardening, form a hard core inside the ballast, causing the ballast layer to lose its elasticity and endangering driving safety.

[0003] In the traditional indoor test of mud slurry, if the deformation of the ballast layer in the model box is to be equivalent to the deformation of the ballast layer caused by the passage of a real train (30-60mm), a huge axial pressure needs to be applied, which is difficult to achieve in indoor tests. In addition, the interior of ordinary ballast gravel cannot be directly observed, which is very inconvenient for studying the microscopic mechanism of mud migration during the mud slurry process. Summary of the invention

[0004] The invention aims to provide a device and method for simulating the mud bubbling test of ballasted railway subgrade realistically and intuitively without applying huge axial pressure.

[0005] The method for making a transparent ballast layer model provided by the present invention comprises the following steps:

[0006] (1) Scanning multiple roadbed ballasts one by one using a blue light scanner to obtain three-dimensional triangular mesh models of multiple ballast particles and save the files;

[0007] (2) The triangular mesh data of the ballast particles is converted into a representation of tiny three-dimensional cubes through a voxelization algorithm, thereby obtaining the shell of the ballast particle model;

[0008] (3) Filling the shell of each particle model with spherical particles using a flood filling algorithm;

[0009] (4) Using spherical particles instead of voxel grids to obtain a realistic model of ballast particles;

[0010] (5) stacking multiple ballast particle models under their own weight and simulating the compaction process to form a ballast layer model;

[0011] (6) By obtaining the changes in the rotation angle and center of gravity of each ballast particle after stacking, the three-dimensional network model files corresponding to each single ballast particle are also changed accordingly and merged into the three-dimensional grid model after stacking;

[0012] (7) The three-dimensional mesh model data is input into a 3D printer, and a transparent ballast layer model is printed using PVC material.

[0013] When the above method is implemented, the file format saved in step (1) is obj.

[0014] When the above method is implemented, in step (2), the two parameters (x, y) in the voxel coordinates (x, y, z) need to be regarded as pixel coordinates, and z is regarded as other parameters. After calculating (x, y), the z coordinate is calculated through the normal direction of the triangle and the geometric formula.

[0015] When the above method is implemented, the operation process of step (3) is as follows:

[0016] Select the voxel outside the particle shell as the starting point;

[0017] The outside of the particle shell, the outer contour of the particle shell, and the inside of the particle shell are marked as voxels of blue, red, and white, respectively;

[0018] The voxel space is stored as a three-dimensional matrix, with white, red, and blue corresponding to the numbers 0, 1, and 2 respectively. Starting from the selected starting point, the colors of the adjacent voxels above, below, left, and right of the blue voxel are determined in turn. If they are white, the adjacent voxels are changed to blue and pushed into the stack, which stores the voxels to be looped.

[0019] The above operations are performed on the voxels in the stack in sequence until there are no more voxels left in the stack;

[0020] After the calculation is completed, the blue voxels are the outside of the particles, the red voxels are the boundaries of the particles, and the white voxels are the inside of the particles. The ballast particle voxel model is the part of the white voxels and the red voxels.

[0021] When the above method is implemented, the operation process of step (4) is as follows:

[0022] Assume that the coordinates of a voxel in the voxel space are (Rn, Cn, Ln), and the data of the spherical unit are obtained according to the following formulas (1), (2), (3) and (4);

[0023] Xs = X0 + dvox × (R-0.5) (1)

[0024] Ys = Y0 + dvox × (C-0.5) (2)

[0025] Zs = Z0 + dvox × (L-0.5) (3)

[0026] Rs = dvox / 2 (4)

[0027] (Rn, Cn, Ln) indicates that the voxel is in the Rnth row, Cnth column, and Lnth layer, dvox indicates the size of the voxel unit, and Xs, Ys, Zs, and Rs indicate the three-dimensional coordinates and radius of the spherical unit, respectively.

[0028] The ballasted railway subgrade mud and bubbling test device provided by the present invention comprises a base, a loading frame, an axial loading device, a seepage box, a pore water pressure gauge, a TDR water probe and a water head control box; the loading frame is detachably connected to the base, and the axial loading device is installed on the loading frame; the pore water pressure gauge and the TDR water probe have the same multiple rows, and the side wall of the seepage box is provided with corresponding mounting holes; the seepage box is placed on the base and has a common axial center line with the loading rod of the axial loading device; the water outlet pipe of the height-adjustable water head control box is connected to the bottom of the seepage box; and the lower end of the loading rod is detachably connected to the transparent ballast layer model.

[0029] When the device is implemented, the base is a rectangular base, and the loading frame includes support columns symmetrically connected to the four corners of the base, and a support plate connected to the top of the support column, and a guide sleeve of the loading rod is arranged at the center of the support plate.

[0030] When the device is implemented, the axial loading device also includes a servo motor, an eccentric wheel and a connecting rod mechanism. The servo motor is fixed on the vertical plate with its output shaft horizontally arranged. The lower end of the vertical plate is fixed on the support plate. The output shaft of the servo motor is connected to the wheel axle of the eccentric wheel through a coupling. One end of the connecting rod structure is hinged to the eccentric wheel, and the other end is hinged to the loading rod.

[0031] When the device is implemented, a horizontal pressing plate is connected to the bottom of the loading rod, and the loading rod extends out of the pressing plate and is threadedly connected to the central hole of the transparent ballast layer model.

[0032] The method provided by the present invention for conducting a ballasted railway subgrade mud bubbling test using the above-mentioned device and a transparent ballast layer model comprises the following steps:

[0033] (1) Remove the loading frame with the axial loading device installed from the base;

[0034] (2) Place the seepage box in the center on the base;

[0035] (3) Add the roadbed soil into the seepage box, compact it layer by layer, bury the pore water pressure gauge and TDR moisture probe as required, and connect them to the data acquisition system respectively;

[0036] (4) Use a plug to plug the circular hole that is higher than the roadbed soil.

[0037] (5) Reconnect and fix the loading frame to the base, making sure that the transparent ballast layer model enters the seepage box from top to bottom and contacts the surface of the subgrade soil;

[0038] (6) The water head control box adds water to the seepage box until the soil is fully saturated, and reads the data fed back by each pore water pressure gauge and TDR moisture probe;

[0039] (7) The servo motor operates to make the loading rod descend to the lowest position and then rise to the highest position, and repeat this cycle. The data acquisition system monitors the changes in the moisture content of the soil sample in real time during the entire process, and the high-speed camera records the migration of subgrade soil particles in the ballast layer model.

[0040] In order to conduct a mud bubbling test on a ballasted railway subgrade, the present invention adopts a three-step method: first, a transparent ballast layer model is made, then a test device is designed, and finally the transparent ballast layer model is used in the test device for testing. With regard to obtaining the transparent ballast layer model, the outer shell of the ballast particle model is first obtained by scanning, and then the inner shell is filled with spherical particles through a flood filling algorithm to obtain a real model of the ballast particles, and the ballast particle cluster model is obtained by stacking the real model of the ballast particles and simulating compaction, and by obtaining the changes in the rotation angle and center of gravity of each ballast particle after stacking, the three-dimensional grid model file corresponding to each single ballast particle is also changed accordingly and merged into a three-dimensional grid model after stacking. With regard to the test device and the test, since the transparent ballast layer model has the characteristic of being easily compressible, a test device with a simple structure can meet the use requirements: the axial loading device drives the eccentric wheel to rotate through a servo motor, and a connecting rod mechanism is connected between the eccentric wheel and the loading shaft, so that the rotation of the eccentric wheel realizes the cyclic lifting and lowering of the loading shaft. By connecting the transparent ballast layer model to the lower end of the loading shaft, the transparent ballast layer model can be raised and lowered cyclically. When the loading rod descends to squeeze the transparent ballast layer model against the subgrade soil sample, the transparent ballast layer model itself is compressed. That is, by applying a small axial force to the loading rod, the transparent ballast layer model can be compressed and deformed by 30-60 mm. The deformation of the transparent ballast layer model will produce a certain "suction" effect on the test soil sample, causing the soil sample to produce a pore water pressure gradient in the vertical direction, thereby inducing the pore water to carry fine particles and continuously migrate and flow, eventually forming slurry and mud. Therefore, the test device uses the transparent ballast layer model to conduct experiments, which is suitable for the real simulation of ballast layer deformation in the slurry and mud indoor test in the field of civil engineering, as well as the real-time monitoring of the movement of mud in the ballast layer. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] Figure 1 It is a schematic diagram of the manufacturing process of the transparent ballast layer model in the present invention.

[0042] Figure 2 It is a schematic diagram of the overall assembly of the test device in the present invention.

[0043] Figure 3 for Figure 2 A magnified schematic diagram of part A in FIG.

[0044] Figure 4 Schematic diagram of the transparent ballast layer model and its connection with the loading rod. DETAILED DESCRIPTION

[0045] The general idea of ​​the present invention is to first make a transparent ballast layer model, then make a test device, and finally use the transparent ballast layer model in the device to carry out a ballasted railway roadbed mud bubbling test, which can overcome the defects of the current roadbed mud bubbling test.

[0046] Specifically, the production of the transparent ballast layer model includes the following steps (combined with Figure 1 ):

[0047] (1) Scan multiple roadbed ballasts one by one using a blue light scanner to obtain three-dimensional triangular mesh models of multiple ballast particles and save the files.

[0048] Start the blue light scanner, warm it up for 15 minutes, turn the camera lens to face the ballast particles on the rotating table, and in the corresponding scanning software, reasonably set the scanning area, resolution, light source intensity and other parameters according to the size and characteristics of the scanned object. After ensuring that the ballast particles are placed stably on the rotating table, click the "Start Scanning" button in the software. After the scan is completed, process the triangulated network model and save the file in the obj. format;

[0049] (2) The triangular mesh data of the ballast particles is converted into a representation of tiny three-dimensional cubes through a voxelization algorithm, thereby obtaining the outer shell of the ballast particle model.

[0050] The obj. file needs to be converted into a particle cluster. The voxelization algorithm is used to convert the triangulated mesh format into a representation of a tiny three-dimensional cube. The two parameters (x, y) in the voxel coordinates (x, y, z) need to be regarded as pixel coordinates, and z as other parameters. After calculating (x, y), the z coordinate is calculated through the normal direction of the triangle and the geometric formula. Thus, the shell of the ballast particle model can be obtained.

[0051] (3) Fill the shell of each particle model with spherical particles using the flood filling algorithm.

[0052] The result of voxelization can only get the shell of the ballast particle model. The flood filling algorithm is needed to fill the inside of the particle model shell. Generally, the voxels outside the particle shell are selected as the starting point. The outside of the particle shell, the outer contour of the particle shell and the inside of the particle shell are marked as blue, red and white voxels respectively. In the flood filling algorithm, the voxel space is stored as a three-dimensional matrix, and white, red and blue correspond to the numbers 0, 1 and 2 respectively. Starting from the selected starting point, the colors of the adjacent voxels above, below, left and right of the blue voxel (the six adjacent voxels in the three-dimensional case) are judged in turn. If it is white, the adjacent voxel is changed to blue and pushed into the stack, which stores the voxels to be looped; if it is red or blue, nothing is done.

[0053] After the above operation is completed for the initial voxel, the same operation is performed on the voxels in the stack in sequence until there are no more voxels left in the stack.

[0054] After the calculation is completed, the blue voxels are the outside of the particle shell, the red voxels are the boundary of the particle shell, and the white voxels are the inside of the particle shell. The ballast particle voxel model is the part of the white voxels and the red voxels. After the flood filling algorithm is used, the voxelized model is filled with particles.

[0055] (4) A realistic model of ballast particles is obtained by replacing voxel grids with spherical particles.

[0056] Suppose the coordinates of a voxel in the voxel space are (R n ,C n ,L n ), indicating that the voxel is in the Rth n Row, C n Column, L n Layer; using X s =X0+d vox ×(R-0.5),Y s =Y0+d vox ×(C-0.5), Z s =Z0+d vox ×(L-0.5), R s =d vox / 2, find the data of the ball unit, d vox Indicates the size of the voxel unit; X s , Y s , Z s , R s They represent the three-dimensional coordinates and radius of the spherical unit respectively.

[0057] (5) Multiple ballast particle models are stacked under their own weight and the compaction process is simulated to form a ballast layer model.

[0058] (6) By obtaining the changes in the rotation angle and center of gravity of each ballast particle after stacking, the three-dimensional network model files corresponding to each single ballast particle are also changed accordingly and merged into the three-dimensional grid model after stacking.

[0059] (7) Input the three-dimensional mesh data into the 3D printer and use PVC material to print out the overall transparent ballast layer model. Alternatively, a single ballast particle model is printed with a hollow silicone shell using 3D printing and then filled with soft glue, and then demolded after the soft glue is fixed. Multiple ballast particles are placed in a seepage box and stacked by self-weight, and then glued together for indoor testing.

[0060] like Figure 2-4 As shown, the structure of the test device is as follows:

[0061] It includes a base 1, a loading frame 2, an axial loading device 3, a seepage box 4, and a water head control box 5.

[0062] The base 1 is a rectangular base.

[0063] The loading frame 2 includes support columns symmetrically connected to the four corners of the base 1, and a support plate connected to the top of the support columns. The support plate is provided with a center hole, and a guide sleeve DXT is provided at the center hole.

[0064] The axial loading device 3 includes a servo motor 31 , an eccentric wheel 32 , a connecting rod mechanism 33 , a loading rod 34 , and a pressure plate 35 .

[0065] The servo motor 31 is installed on the vertical plate 36 with its output shaft arranged horizontally, and the lower end of the vertical plate is fixed to the support plate of the loading frame 2.

[0066] The output shaft of the servo motor 31 is connected to the wheel shaft of the eccentric wheel 32 through a coupling.

[0067] The connecting rod mechanism 33 is a two-connecting rod mechanism, including an inverted U-shaped body and a vertical rod vertically connected to the center of the top surface of the inverted U-shaped body, and a horizontal rod hinged at the top of the vertical rod.

[0068] When the connecting rod mechanism 33 is assembled, the two side arms of the inverted U-shaped body are hinged to the top of the loading rod 34 through a pin, and the outer end of the horizontal rod is hinged to the eccentric wheel 32, and the hinge is located on one side of the vertical center plane of the eccentric wheel shaft.

[0069] The bottom of the loading rod 34 is vertically connected to the pressing plate 37. The loading rod passes through the pressing plate, and the protruding section is a threaded section.

[0070] The transparent ballast layer model 6 is provided with a central threaded hole, which is connected to the extended section of the loading rod 34, and the pressing plate is located on the top surface of the transparent ballast layer model.

[0071] The seepage box 4 is a cylindrical acrylic box, and its side wall is provided with multiple circles of circular holes for installing circular hole pore water pressure gauges along the height direction, and a corresponding circular hole row is provided on one side of each row of circular holes for installing TDR water probes. That is, the number of pore water pressure gauges and TDR water probes is the same.

[0072] The height dimension of the seepage box 4 is tested to meet the thickest thickness of the common roadbed. The intervals between adjacent circles of circular holes and the number of each circle of circular holes are determined according to the different thicknesses of the roadbed.

[0073] The water head control box 5 is fixed to the column of the bracket 8 by the pipe clamp 7, and the outlet pipe of the water head control box is connected to the bottom center of the seepage box 4. The height of the water head control box 5 can be changed by moving the pipe clamp along the column to change the size of the water head.

[0074] The specific test process is as follows:

[0075] 1. Remove the loading frame with the axial loading device installed from the base;

[0076] 2. Center the seepage box on the base;

[0077] 3. Add the roadbed soil into the seepage box, compact it layer by layer, bury the pore water pressure gauge and TDR moisture probe as required, and connect them to the data acquisition system respectively;

[0078] 4. Use a plug to plug the circular hole that is higher than the roadbed soil;

[0079] 5. Reconnect and fix the loading frame to the base, making sure that the transparent ballast layer model enters the seepage box from top to bottom and contacts the surface of the subgrade soil;

[0080] 6. The water head control box adds water to the seepage box for a specified time and reads the initial data fed back by each pore water pressure gauge and TDR moisture probe;

[0081] 7. The servo motor works to make the loading rod drop to the lowest position, then rise to the highest position, and repeat this cycle. The data acquisition system monitors the changes in the moisture content of the soil sample in real time during the whole process, and the high-speed camera records the migration of subgrade soil particles in the ballast layer model.

[0082] The test principle is as follows:

[0083] The transparent ballast layer model printed out of PVC material has the characteristic of easy compression. During the test, it is connected to the lower end of the loading rod and rises and falls with the cyclic rise and fall of the loading rod. The servo motor of the axial loading device drives the eccentric wheel to rotate, and the rotation of the eccentric wheel realizes the cyclic rise and fall of the loading rod through the connecting rod mechanism. As the transparent ballast layer model descends and squeezes the subgrade soil, the transparent ballast layer model itself is squeezed to produce axial compression. Only a small load needs to be applied to the loading rod to achieve a 30-60mm compression of the transparent ballast layer model. Through the deformation of the transparent ballast layer model, a certain "suction" effect will be produced on the subgrade soil, causing the soil to produce a pore water pressure gradient in the vertical direction, thereby inducing the pore water to carry fine particles and continuously migrate and flow, eventually forming slurry and mud.

[0084] In addition, the ballast layer is a transparent material. During the test, a high-speed camera can be used to record the migration of fine particles in the ballast layer model, which is convenient for better revealing the mechanism of soil particle migration.

[0085] The structure of the axial loading device is simple but effective. The eccentric position of the eccentric wheel and the size of the wheel disc can be changed to adjust the cyclic lifting height of the loading rod. The frequency of the cyclic lifting can be achieved by adjusting the speed of the servo motor. The amplitude and frequency of the loading rod can be accurately and conveniently controlled. The amplitude of the loading lever directly determines the deformation of the transparent ballast layer model.

Claims

1. A method for making a transparent ballast layer model, comprising the following steps: (1) Scanning multiple roadbed ballasts one by one using a blue light scanner to obtain three-dimensional triangular mesh models of multiple ballast particles and save the files; (2) The triangular mesh data of the ballast particles is converted into a representation of tiny three-dimensional cubes through a voxelization algorithm, thereby obtaining the shell of the ballast particle model; (3) Filling the shell of each particle model with spherical particles using a flood filling algorithm; (4) Using spherical particles instead of voxel grids to obtain a realistic model of ballast particles; (5) stacking multiple ballast particle models under their own weight and simulating the compaction process to form a ballast layer model; (6) By obtaining the changes in the rotation angle and center of gravity of each ballast particle after stacking, the three-dimensional network model files corresponding to each single ballast particle are also changed accordingly and merged into the three-dimensional grid model after stacking; (7) The three-dimensional mesh model data is input into a 3D printer, and a transparent ballast layer model is printed using PVC material.

2. The method for making a transparent ballast layer model according to claim 1, characterized in that: The file format saved in step (1) is obj.

3. The method for making a transparent ballast layer model according to claim 1, characterized in that: In step (2), the two parameters (x, y) in the voxel coordinates (x, y, z) need to be regarded as pixel coordinates, and z as other parameters. After calculating (x, y), the z coordinate is calculated through the normal direction of the triangle and the geometric formula.

4. The method for making a transparent ballast layer model according to claim 1, characterized in that The operation process of step (3) is as follows: Select the voxel outside the particle shell as the starting point; The outside of the particle shell, the outer contour of the particle shell, and the inside of the particle shell are marked as voxels of blue, red, and white, respectively; The voxel space is stored as a three-dimensional matrix, with white, red, and blue corresponding to the numbers 0, 1, and 2 respectively. Starting from the selected starting point, the colors of the adjacent voxels above, below, left, and right of the blue voxel are determined in turn. If they are white, the adjacent voxels are changed to blue and pushed into the stack, which stores the voxels to be looped. The above operations are performed on the voxels in the stack in sequence until there are no more voxels left in the stack; The calculation is completed. The blue voxels are the outside of the particle shell, the red voxels are the boundary of the particle shell, and the white voxels are the inside of the particle shell. The ballast particle voxel model is the part of the white voxels and the red voxels.

5. The method for making a transparent ballast layer model according to claim 1, characterized in that: The operation process of step (4) is as follows: Assume that the coordinates of a voxel in the voxel space are (Rn, Cn, Ln), and the data of the spherical unit are obtained according to the following formulas (1), (2), (3) and (4); Xs = X0 + dvox × (R-0.5) (1) Ys = Y0 + dvox × (C-0.5) (2) Zs = Z0 + dvox × (L-0.5) (3) Rs = dvox / 2 (4) (Rn, Cn, Ln) indicates that the voxel is in the Rnth row, Cnth column, and Lnth layer, dvox indicates the size of the voxel unit, and Xs, Ys, Zs, and Rs indicate the three-dimensional coordinates and radius of the spherical unit, respectively.

6. A ballasted railway subgrade mud and mud test device, characterized in that: The device includes a base, a loading frame, an axial loading device, a seepage box, a pore water pressure gauge, a TDR water probe and a water head control box; The loading frame is detachable and connected to the base, and the axial loading device is installed on the loading frame; The pore water pressure gauge and TDR water probe have the same multiple columns, and the side wall of the seepage box is provided with corresponding mounting holes; The seepage box is placed on the base, coaxially with the loading rod of the axial loading device; The outlet pipe of the height-adjustable water head control box is connected to the bottom of the seepage box; The lower end of the loading rod is detachable and connected to the transparent ballast layer model.

7. The device according to claim 6, characterized in that: The base is a rectangular base, and the loading frame includes support columns symmetrically connected to the four corners of the base, and a support plate connected to the top of the support columns, and a guide sleeve of the loading rod is arranged at the center of the support plate.

8. The device according to claim 6, characterized in that: The axial loading device also includes a servo motor, an eccentric wheel and a connecting rod mechanism. The servo motor is fixed on the vertical plate with its output shaft horizontally arranged. The lower end of the vertical plate is fixed on the support plate. The output shaft of the servo motor is connected to the wheel shaft of the eccentric wheel through a coupling. One end of the connecting rod structure is hinged to the eccentric wheel, and the other end is hinged to the loading rod.

9. The device according to claim 6, characterized in that: The bottom of the loading rod is connected with a horizontal pressing plate, and the loading rod extends out of the pressing plate and is threadedly connected with the central hole of the transparent ballast layer model.

10. A method for conducting a ballasted railway subgrade mud boiling test using the device of claim 6 and the transparent ballast layer model made according to claim 1, comprising the following steps: (1) Remove the loading frame with the axial loading device installed from the base; (2) Place the seepage box in the center on the base; (3) Add the roadbed soil into the seepage box, compact it layer by layer, bury the pore water pressure gauge and TDR moisture probe as required, and connect them to the data acquisition system respectively; (4) Use a plug to plug the circular hole that is higher than the roadbed soil. (5) Reconnect and fix the loading frame to the base, making sure that the transparent ballast layer model enters the seepage box from top to bottom and contacts the surface of the subgrade soil; (6) The water head control box adds water to the seepage box until the soil is fully saturated. After the soil is saturated, the water inlet valve below the seepage box is closed and the data fed back by each pore water pressure gauge and TDR moisture probe are read; (7) The servo motor operates to make the loading rod descend to the lowest position and then rise to the highest position, and repeat this cycle. The data acquisition system monitors the changes in the moisture content of the soil sample in real time during the entire process, and the high-speed camera records the migration of subgrade soil particles in the ballast layer model.