Inter-column air conditioner rapid piping method and device
Through simulation layout model and environmental information processing, the welding parameters and valve opening of the branch pipeline are adjusted, and the problems of large quantities and difficult to control the quality of the air conditioner pipes in the inter-column are solved, and efficient and scientific construction decisions and quality improvement are achieved.
Patent Information
- Application Number
- CN202411084663.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-08
- Publication Date
- 2024-11-12
AI Technical Summary
The piping project of the air conditioner in the inter-column system is huge, resulting in large labor consumption and difficult to control the quality of pipeline installation. Traditional design methods cannot scientifically decide on pipeline layout and welding quality.
By establishing a simulation layout model, obtaining the operating environment information of the computer room, adjusting the welding parameters and valve opening of the branch pipeline, ensuring that the gas flow rate meets the application conditions, and using the simulation model to perform secondary judgment and parameter adjustment, improving welding quality and efficiency.
It reduces the on-site welding workload, improves construction efficiency and quality, realizes scientific decision-making on the use effect of air conditioners in the columns, and saves labor and construction costs.
Smart Images

Figure CN118940536A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of inter-row air conditioning testing, and in particular to a method and device for rapid piping of inter-row air conditioning. Background Art
[0002] Due to the large number of inter-row air conditioners, the unit piping project is huge, which requires a lot of manpower to carry out the piping work. At the same time, due to the large amount of construction work, the quality of pipeline installation is also difficult to control.
[0003] The traditional computer room air conditioning design method is to design in accordance with the relevant regulations of the specifications. However, whether the layout of the inter-row air conditioning pipelines is reasonable and whether the welding between the pipelines meets the requirements can only be tested after construction based on the experience of the staff, and the use effect of the inter-row air conditioning cannot be scientifically decided. Summary of the invention
[0004] The purpose of the embodiments of the present application is to provide a method and device for rapid piping of inter-row air conditioners, so as to solve the above-mentioned problems existing in the prior art and make scientific decisions on the use effect of the inter-row air conditioners.
[0005] In a first aspect, a method for rapid piping of an inter-row air conditioner is provided, and the method may include:
[0006] According to the on-site structure of the machine room to be processed, determine the simulation arrangement model consisting of a virtual main pipeline, multiple branch pipelines, multiple flanges and multiple valves;
[0007] Obtain the operating environment information of the computer room to be processed;
[0008] The operating environment information is processed using the simulation arrangement model to obtain an average gas flow rate in each branch pipeline in the current cycle;
[0009] If the average gas flow rate of any branch pipeline in the current cycle meets the inter-row air-conditioning application conditions, the welding parameters of the welding points between the corresponding branch pipeline and the main pipeline and the opening of the corresponding valve of the branch pipeline are adjusted so that the average gas flow rate of the branch pipeline meets the inter-row air-conditioning application conditions.
[0010] In a possible implementation, if the average gas flow rate of any branch pipeline in the current cycle meets the inter-row air conditioning application conditions, it includes:
[0011] If there is any branch pipeline whose average gas flow rate in the current cycle is greater than the first preset flow rate and not greater than the second preset flow rate, a secondary determination is made on the average gas flow rate in the current cycle;
[0012] If there is any branch pipeline whose average gas flow rate in the current cycle is not greater than the first preset flow rate, it is determined that the gas flow rate of the corresponding branch pipeline is unqualified.
[0013] In a possible implementation, performing a secondary determination on the average gas flow rate of the current period includes:
[0014] Establishing a curve of average gas flow rate and time during the current period;
[0015] If the slope of the change curve is greater than 0, it is determined that the average gas flow rate of the corresponding branch pipeline is qualified;
[0016] If the slope of the change curve is less than 0 and greater than a preset slope, the opening of the valve corresponding to the branch pipeline is adjusted according to the difference between the slope and the preset slope, and it is determined whether the average gas flow rate of the branch pipeline in the next cycle meets the application conditions of the inter-row air conditioning; the preset slope is less than 0;
[0017] If the slope of the variation curve is less than 0 and not greater than a preset slope, it is determined that the average gas flow rate of the corresponding branch pipeline is unqualified.
[0018] In a possible implementation, adjusting the opening of the valve corresponding to the branch pipeline according to the difference between the slope and the preset slope includes:
[0019] Obtaining an absolute value of a difference between the slope and the preset slope;
[0020] Determining an opening adjustment coefficient according to the absolute value range to which the absolute value belongs;
[0021] The adjustment coefficient is used to adjust the opening of the valve corresponding to the branch pipeline to obtain the target opening.
[0022] In a possible implementation, after obtaining the target opening, the method further includes:
[0023] If the target opening reaches the opening critical value of the valve corresponding to the branch pipeline and the average gas flow rate of the branch pipeline in the next cycle is not greater than the second preset flow rate, the average gas flow rate of the corresponding branch pipeline is determined to be unqualified.
[0024] In a possible implementation, after determining that the average gas flow rate of the corresponding branch pipeline is unqualified, the method further includes:
[0025] Determining a difference between the first preset flow rate and an average gas flow rate of the corresponding branch pipeline;
[0026] If the difference is not greater than the first preset flow rate difference, it is determined that there is leakage in the corresponding branch pipe, and prompt information indicating that there is leakage in the corresponding branch pipe is generated;
[0027] If the difference is greater than the first preset flow rate difference and not greater than the second preset flow rate difference, then according to the first ratio of the average gas flow rate of the corresponding branch pipeline to the flow rate of the main pipeline, if the first ratio is greater than the preset ratio, the preload force of each bolt in the flange corresponding to the corresponding branch pipeline is adjusted; if the first ratio is not greater than the preset ratio, the thickness of the welding point between the corresponding branch pipeline and the main pipeline is increased; wherein the first preset flow rate difference is less than the second preset flow rate difference;
[0028] If the difference is greater than the second preset flow rate difference, the preload force of each bolt in the flange corresponding to the corresponding branch pipeline is adjusted according to a second ratio of the difference to the second preset flow rate difference.
[0029] In a possible implementation, after adjusting the pre-tightening force of each bolt in the flange corresponding to the corresponding branch pipeline, the method further includes:
[0030] If the preload force reaches the critical value, increase the weld thickness between the main pipe and the corresponding flange.
[0031] In a second aspect, a device for quick piping of inter-row air conditioners is provided, which may include:
[0032] A determination unit, used to determine a simulation arrangement model including a virtual main pipeline, multiple branch pipelines, multiple flanges and multiple valves according to the on-site structure of the machine room to be processed;
[0033] An acquisition unit, used to acquire the operating environment information of the computer room to be processed;
[0034] A processing unit, used to process the operating environment information using the simulation arrangement model to obtain an average gas flow rate in each branch pipeline in the current cycle;
[0035] If the average gas flow rate of any branch pipeline in the current cycle meets the inter-row air-conditioning application conditions, the welding parameters of the welding points between the corresponding branch pipeline and the main pipeline and the opening of the corresponding valve of the branch pipeline are adjusted so that the average gas flow rate of the branch pipeline meets the inter-row air-conditioning application conditions.
[0036] In a third aspect, an electronic device is provided, the electronic device comprising a processor, a communication interface, a memory and a communication bus, wherein the processor, the communication interface and the memory communicate with each other via the communication bus;
[0037] Memory, used to store computer programs;
[0038] The processor is used to implement any method step described in the first aspect when executing the program stored in the memory.
[0039] In a fourth aspect, a computer-readable storage medium is provided, wherein a computer program is stored in the computer-readable storage medium, and when the computer program is executed by a processor, any method step described in the first aspect is implemented.
[0040] The present application provides a method for rapid piping of inter-row air conditioners, the method comprising: determining a simulation arrangement model consisting of a virtual main pipeline, multiple branch pipelines, multiple flanges and multiple valves according to the on-site structure of the machine room to be processed; obtaining the operating environment information of the machine room to be processed; using the simulation arrangement model to process the operating environment information to obtain the average gas flow rate in each branch pipeline in the current cycle; if there is any branch pipeline whose average gas flow rate in the current cycle meets the inter-row air conditioning application conditions, then adjusting the welding parameters of the welding point between the corresponding branch pipeline and the main pipeline and the opening of the corresponding valve of the branch pipeline so that the gas flow rate of the branch pipeline meets the inter-row air conditioning application conditions. This method can process the operating information of the machine room to be processed before the inter-row air conditioning is constructed, so as to simulate the use effect of the inter-row air conditioning, thereby adjusting the relevant parameters of the branch pipeline that does not meet the inter-row air conditioning application conditions, so that the average gas flow rate of any branch pipeline meets the inter-row air conditioning application conditions. BRIEF DESCRIPTION OF THE DRAWINGS
[0041] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments of the present application will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.
[0042] Figure 1 A system architecture diagram of a method for rapid piping of inter-row air conditioners provided in an embodiment of the present application;
[0043] Figure 2 A schematic flow chart of a method for rapid piping of inter-row air conditioners provided in an embodiment of the present application;
[0044] Figure 3 A schematic diagram of the structure of a device for rapid piping of inter-row air conditioners provided in an embodiment of the present application;
[0045] Figure 4 A schematic diagram of the structure of an electronic device provided in an embodiment of the present application. DETAILED DESCRIPTION
[0046] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments of the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0047] The method for rapid piping of inter-row air conditioners provided in the embodiment of the present application can be applied to Figure 1 In the system architecture shown in Figure 1 As shown, the system may include: a server and a terminal. The server may be a physical server, or a server cluster or distributed system composed of multiple physical servers, or a cloud server that provides cloud services, cloud databases, cloud computing, cloud functions, cloud storage, network services, cloud communications, middleware services, domain name services, security services, content delivery networks (Content Delivery Network, CDN), and basic cloud computing services such as big data and artificial intelligence platforms. The terminal may be a user equipment (User Equipment, UE) such as a mobile phone, smart phone, laptop, digital broadcast receiver, personal digital assistant (PDA), tablet computer (PAD), handheld device, vehicle-mounted device, wearable device, computing device or other processing device connected to a wireless modem, mobile station (Mobile Station, MS), mobile terminal (Mobile Terminal), etc. The terminal and the server may be directly or indirectly connected by wired or wireless communication, which is not limited in this application.
[0048] The terminal is used to obtain the on-site structure of the computer room to be processed and send the on-site structure of the computer room to be processed to the server. It can be understood that the on-site structure includes the size of the computer room, the number of data cabinets, and the location of the data cabinets.
[0049] The server is used to receive the on-site structure of the processing room to execute a method for rapid piping of inter-row air conditioners provided in the present application.
[0050] Due to the large number of inter-row air conditioners, the unit piping project is huge, which requires a lot of manpower to carry out the piping work. At the same time, due to the large amount of construction work, the quality of pipeline installation is also difficult to control.
[0051] The traditional computer room air conditioning design method is to design in accordance with the relevant regulations of the specifications. However, whether the layout of the inter-row air conditioning pipelines is reasonable and whether the welding between the pipelines meets the requirements can only be tested after construction based on the experience of the staff, and the use effect of the inter-row air conditioning cannot be scientifically decided.
[0052] Therefore, the present application provides a method for rapid piping of inter-row air conditioners, which is used to solve the above-mentioned problems existing in the prior art and can make scientific decisions on the use effect of the inter-row air conditioners.
[0053] The preferred embodiments of the present application are described below in conjunction with the drawings in the specification. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present application, and are not used to limit the present application. In addition, the embodiments and features in the embodiments of the present application may be combined with each other if there is no conflict.
[0054] Figure 2 A schematic diagram of a method for rapid piping of inter-row air conditioners provided in an embodiment of the present application. Figure 2 As shown, the method may include:
[0055] Step S210: According to the on-site structure of the machine room to be processed, a simulation arrangement model including a virtual main pipeline, multiple branch pipelines, multiple flanges and multiple valves is determined.
[0056] Specifically, according to the actual size of the computer room, the number of data cabinets in the computer room, and the location of the data cabinets, the location of the inter-row air conditioners is determined, and the pipes (main pipes and branch pipes) of the inter-row air conditioners are arranged side by side. The characteristics of the inter-row air conditioner pipes are large repetition rates, and the sizes of the branch pipes of each row of inter-row air conditioners are basically the same. The arranged main pipes and branch pipes are prefabricated and divided, and numbered and identified according to the computer room name and unit location.
[0057] It can be understood that there are two types of pipelines for inter-row air conditioners, one is the main pipeline and the other is the branch pipeline. The main pipeline and the branch pipeline are simulated and prefabricated. According to the design plan, the elbows connecting the branch pipeline and the main pipeline and the flanges used for connection are simulated and welded together, and the valves and the pipelines behind the valves are simulated and installed.
[0058] In order to avoid the situation where the design scheme is not suitable for the machine room to be processed by directly applying it to the actual process, a simulation layout model consisting of a virtual main line, multiple branch lines, multiple flanges and multiple valves is determined according to the design scheme.
[0059] Step S220: Obtain the operating environment information of the computer room to be processed.
[0060] Specifically, the operating environment information may include the temperature and humidity of the environment; the acquisition process may be real-time acquisition, or the historical temperature and humidity of the computer room to be processed may be acquired according to time division (seasonal division, monthly division).
[0061] Step S230: Use the simulation arrangement model to process the operating environment information to obtain the average gas flow rate in each branch pipeline in the current cycle, and process the average gas flow rate to obtain a processing result.
[0062] It should be noted that the current period is the period corresponding to the collection of operating environment information.
[0063] If the average gas flow rate of each branch pipeline in the current cycle meets the application conditions of inter-row air conditioning, the average gas flow rate of each branch pipeline is qualified; after that, the operating environment information of other cycles can be processed to further determine whether the average gas flow rate of each branch pipeline is qualified. If the average gas flow rate meets the application conditions of inter-row air conditioning, it means that the current actual plan can enter the actual pipeline processing stage, and the prefabrication of the main pipeline uses a fully automatic pipe cutting machine to cut the pipeline according to the processing drawings, and the pipeline is processed in sections according to the pipe sections divided by the drawings, and the holes are opened. The prefabrication of branch pipelines also uses a fully automatic pipe cutting machine to cut the pipelines. The cut pipelines are welded by fully automatic welding. The elbows connecting the branch pipelines to the main pipelines and the flanges used for connection are welded together. At the same time, the valves and the pipelines behind the valves are installed, and then the generated QR code is affixed to determine the installation location on the construction site.
[0064] After prefabrication, the pipes and openings are sealed and protected, and then transported to the construction site for assembly and installation according to the position marked by the QR code. The branch pipes are welded to the main pipes according to the position of the inter-row air conditioning units on site. Each inter-row air conditioner only has one welding point to be welded, which greatly reduces the amount of welding work on site and improves the construction progress. Since a large amount of pipe cutting and welding work is completed in the factory and fully automatic equipment is used to the greatest extent, it greatly saves labor, reduces construction costs, improves construction efficiency, and saves construction time. After the branch pipes and the main pipes are installed, they are finally connected to the unit with a metal hose to eliminate errors in construction. The length of the metal hose is connected according to the actual situation on site.
[0065] If the average gas flow rate of any branch pipeline in the current cycle does not meet the application conditions of inter-row air conditioning, the welding parameters of the welding points between the corresponding branch pipeline and the main pipeline and the opening of the corresponding valve of the branch pipeline are adjusted to make the average gas flow rate of the branch pipeline meet the application conditions of inter-row air conditioning.
[0066] Specifically, first, according to the historical average gas flow rate and the empirical average gas flow rate of the branch pipeline similar to the machine room to be processed in history, the first preset flow rate and the second preset flow rate are determined;
[0067] For any branch pipeline, it is determined that the average gas flow rate of the branch pipeline does not meet the inter-row air conditioning application conditions in the current cycle, which may specifically include:
[0068] If the average gas flow rate of the branch pipeline in the current cycle is greater than the first preset flow rate and not greater than the second preset flow rate, a secondary determination is performed on the average gas flow rate in the current cycle;
[0069] If the average gas flow rate of the branch pipeline in the current cycle is not greater than the first preset flow rate, the average gas flow rate of the corresponding branch pipeline is determined to be unqualified.
[0070] Furthermore, when the average gas flow rate of the current cycle needs to be determined again:
[0071] Establish the curve of average gas flow rate and time of the current cycle;
[0072] If the slope of the change curve is greater than 0, the average gas flow rate of the corresponding branch pipeline is determined to be qualified;
[0073] If the slope of the change curve is less than 0 and greater than the preset slope, the opening of the valve corresponding to the branch pipeline is adjusted according to the difference between the slope and the preset slope, and it is determined whether the average gas flow rate of the branch pipeline in the next cycle meets the application conditions of the inter-row air conditioning; the preset slope is less than 0;
[0074] If the slope of the variation curve is less than 0 and not greater than a preset slope, the average gas flow rate of the corresponding branch pipeline is determined to be unqualified.
[0075] In some embodiments, adjusting the opening of the valve corresponding to the branch pipeline according to the difference between the slope and the preset slope includes:
[0076] Obtaining the absolute value of the difference between the slope and the preset slope;
[0077] Determine the opening adjustment coefficient according to the absolute value range to which the absolute value belongs;
[0078] The adjustment coefficient is used to adjust the opening of the corresponding valve of the branch pipeline to obtain the target opening.
[0079] The smaller the absolute value of the difference, the smaller the increase in the opening. The configured absolute value range is determined based on historical experience.
[0080] After obtaining the target opening, determining whether the target opening reaches the opening critical value of the corresponding valve;
[0081] If it is not reached and the average gas flow rate of the branch pipeline in the next cycle is greater than the second preset flow rate, the average gas flow rate of the corresponding branch pipeline is determined to be qualified.
[0082] If the average gas flow rate of the branch pipeline in the next cycle is reached and is greater than the first preset flow rate and not greater than the second preset flow rate or not greater than the first preset flow rate, the average gas flow rate of the corresponding branch pipeline is determined to be unqualified.
[0083] After determining that the average gas flow rate of the corresponding branch pipeline is unqualified, the method may further include:
[0084] Determining a difference between a first preset flow rate and an average gas flow rate of the corresponding branch pipeline;
[0085] If the difference is not greater than the first preset flow rate difference, it is determined that the corresponding branch pipeline has a leak, and a prompt message indicating the leak is generated, and the welding parameters between the branch pipeline and the main pipeline are adjusted. In other words, the current welding between the branch pipeline and the main pipeline is not tight enough, and the welding parameters between the branch pipeline and the main pipeline need to be adjusted to improve the sealing between the branch pipeline and the main pipeline. Specifically, during the welding process, the initial movement speed can be reduced according to the movement speed adjustment coefficient of the configured welding robot to ensure that the welding robot improves the welding accuracy during the movement process. The movement speed adjustment coefficient is generally 0.9.
[0086] If the difference is greater than the first preset flow rate difference and not greater than the second preset flow rate difference, it is necessary to determine the reason for the failure based on a first ratio of the average gas flow rate of the corresponding branch pipeline to the average gas flow rate of the main pipeline;
[0087] When the first ratio is greater than the preset ratio, it indicates that the flange connection between the main pipeline and the branch pipeline is not tight, and the pre-tightening force of each bolt in the flange corresponding to the corresponding branch pipeline is adjusted;
[0088] When the first ratio is not greater than the preset ratio, the thickness of the welding point between the corresponding branch pipeline and the main pipeline is increased; wherein the first preset flow rate difference is less than the second preset flow rate difference; specifically, the initial thickness can be adjusted according to the configured thickness adjustment coefficient (generally set to 1.15) to determine the target thickness.
[0089] If the difference is greater than the second preset flow rate difference, the preload force of each bolt in the flange corresponding to the corresponding branch pipe is adjusted according to the second ratio of the difference to the second preset flow rate difference. It should be noted that the adjustment coefficient of the preload force is determined according to the magnitude relationship between the second ratio and the second preset ratio; the larger the second ratio, the greater the increase in the preload force.
[0090] In some embodiments, if the pre-tightening force of each bolt reaches a critical pre-tightening force value, the thickness of the weld between the main pipe and the flange is increased.
[0091] Under the above-mentioned adjustment method, if the average gas flow rate of the corresponding branch pipeline is still unqualified, a prompt message indicating that it cannot be adjusted is issued and sent to the corresponding person in charge.
[0092] The present application provides a method for rapid piping of inter-row air conditioners, the method comprising: determining a simulation arrangement model consisting of a virtual main pipeline, multiple branch pipelines, multiple flanges and multiple valves according to the on-site structure of the machine room to be processed; obtaining the operating environment information of the machine room to be processed; using the simulation arrangement model to process the operating environment information to obtain the gas flow rate in each branch pipeline in the current cycle; if there is any branch pipeline whose average gas flow rate in the current cycle meets the inter-row air conditioning application conditions, then adjusting the welding parameters of the welding point between the corresponding branch pipeline and the main pipeline and the opening of the corresponding valve of the branch pipeline so that the gas flow rate of the branch pipeline meets the inter-row air conditioning application conditions. This method can process the operating information of the machine room to be processed before the inter-row air conditioning is constructed, so as to simulate the use effect of the inter-row air conditioning, thereby adjusting the relevant parameters of the branch pipeline that does not meet the inter-row air conditioning application conditions, so that the average gas flow rate of any branch pipeline meets the inter-row air conditioning application conditions.
[0093] Corresponding to the above method, the embodiment of the present application also provides a device for rapid piping of inter-row air conditioners, such as Figure 3 As shown, the device comprises:
[0094] The determination unit 310 is used to determine a simulation arrangement model including a virtual main pipeline, multiple branch pipelines, multiple flanges and multiple valves according to the on-site structure of the machine room to be processed;
[0095] The acquisition unit 320 is used to acquire the operating environment information of the computer room to be processed;
[0096] The processing unit 330 is used to process the operating environment information using the simulation arrangement model to obtain an average gas flow rate in each branch pipeline in the current cycle;
[0097] If the average gas flow rate of any branch pipeline in the current cycle meets the inter-row air-conditioning application conditions, the welding parameters of the welding points between the corresponding branch pipeline and the main pipeline and the opening of the corresponding valve of the branch pipeline are adjusted so that the average gas flow rate of the branch pipeline meets the inter-row air-conditioning application conditions.
[0098] The functions of each functional unit of a device for quick piping of inter-row air conditioners provided in the above-mentioned embodiment of the present application can be achieved through the above-mentioned method steps. Therefore, the specific working process and beneficial effects of each unit in a device for quick piping of inter-row air conditioners provided in the embodiment of the present application will not be repeated here.
[0099] The present application also provides an electronic device, such as Figure 4As shown, it includes a processor 410 , a communication interface 420 , a memory 430 and a communication bus 440 , wherein the processor 410 , the communication interface 420 , and the memory 430 communicate with each other via the communication bus 440 .
[0100] Memory 430, for storing computer programs;
[0101] The processor 410 is used to execute the program stored in the memory 430 to implement the following steps:
[0102] According to the on-site structure of the machine room to be processed, determine the simulation arrangement model consisting of a virtual main pipeline, multiple branch pipelines, multiple flanges and multiple valves;
[0103] Obtain the operating environment information of the computer room to be processed;
[0104] The operating environment information is processed using the simulation arrangement model to obtain the gas flow rate in each branch pipeline in the current cycle;
[0105] If the average gas flow rate of any branch pipeline in the current cycle meets the inter-row air-conditioning application conditions, the welding parameters of the welding points between the corresponding branch pipeline and the main pipeline and the opening of the corresponding valve of the branch pipeline are adjusted so that the average gas flow rate of the branch pipeline meets the inter-row air-conditioning application conditions.
[0106] The communication bus mentioned above can be a Peripheral Component Interconnect (PCI) bus or an Extended Industry Standard Architecture (EISA) bus, etc. The communication bus can be divided into an address bus, a data bus, a control bus, etc. For ease of representation, only one thick line is used in the figure, but it does not mean that there is only one bus or one type of bus.
[0107] The communication interface is used for communication between the above electronic device and other devices.
[0108] The memory may include a random access memory (RAM) or a non-volatile memory (NVM), such as at least one disk memory. Optionally, the memory may also be at least one storage device located away from the aforementioned processor.
[0109] The above-mentioned processor can be a general-purpose processor, including a central processing unit (CPU), a network processor (NP), etc.; it can also be a digital signal processor (DSP), an application specific integrated circuit (ASIC), a field programmable gate array (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components.
[0110] The implementation methods and beneficial effects of the components of the electronic device in the above embodiments to solve the problems can be found in Figure 2 The various steps in the illustrated embodiment are implemented, therefore, the specific working process and beneficial effects of the electronic device provided by the embodiment of the present application are not repeated here.
[0111] In another embodiment provided in the present application, a computer-readable storage medium is provided, in which instructions are stored. When the computer-readable storage medium is executed on a computer, the computer executes a method for rapid piping of inter-row air conditioners as described in any of the above embodiments.
[0112] In another embodiment provided in the present application, a computer program product including instructions is also provided, which, when executed on a computer, enables the computer to execute a method for rapid piping of inter-row air conditioners as described in any one of the above embodiments.
[0113] Those skilled in the art will appreciate that the embodiments in the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt a complete hardware embodiment, a complete software embodiment, or a form of an embodiment combining software and hardware. Moreover, the present application may adopt a form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.
[0114] The embodiments of the present application are described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0115] These computer program instructions may also be stored in a computer readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer readable memory produce an article of manufacture including an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0116] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0117] Unless otherwise defined, the technical terms or scientific terms used in this application should be understood by people with ordinary skills in the field to which the present invention belongs. "First", "second" and similar words used in this application do not indicate any order, quantity or importance, but are only used to distinguish different components. "Include" or "comprise" and similar words mean that the elements or objects appearing before the word cover the elements or objects listed after the word and their equivalents, without excluding other elements or objects. "Connect", "couple" or "connected" and similar words are not limited to physical or mechanical connections, but may include electrical connections, whether direct or indirect. "Up", "down", "left", "right" and the like are only used to indicate relative positional relationships. When the absolute position of the described object changes, the relative positional relationship may also change accordingly.
[0118] Although the preferred embodiments of the present application have been described, those skilled in the art may make additional changes and modifications to these embodiments once they are aware of the basic creative concepts. Therefore, the present application embodiments are intended to be interpreted as including the preferred embodiments and all changes and modifications that fall within the scope of the present application embodiments.
[0119] Obviously, those skilled in the art can make various changes and modifications to the embodiments in the present application without departing from the spirit and scope of the embodiments in the present application. Thus, if these modifications and variations of the embodiments in the present application are within the scope of the embodiments in the present application and their equivalents, the embodiments in the present application are also intended to include these modifications and variations.
Claims
1. A method for rapid piping of inter-row air conditioners, characterized in that: The method comprises: According to the on-site structure of the machine room to be processed, determine the simulation arrangement model consisting of a virtual main pipeline, multiple branch pipelines, multiple flanges and multiple valves; Obtain the operating environment information of the computer room to be processed; The operating environment information is processed using the simulation arrangement model to obtain an average gas flow rate in each branch pipeline in the current cycle; If the average gas flow rate of any branch pipeline in the current cycle does not meet the inter-row air-conditioning application conditions, the welding parameters of the welding points between the corresponding branch pipeline and the main pipeline and the opening of the corresponding valve of the branch pipeline are adjusted so that the average gas flow rate of the branch pipeline meets the inter-row air-conditioning application conditions.
2. The method according to claim 1, characterized in that If the average gas flow rate of any branch pipeline in the current cycle does not meet the application conditions of inter-row air conditioning, including: If there is any branch pipeline whose average gas flow rate in the current cycle is greater than the first preset flow rate and not greater than the second preset flow rate, a secondary determination is made on the average gas flow rate in the current cycle; If there is any branch pipeline whose average gas flow rate in the current cycle is not greater than the first preset flow rate, it is determined that the average gas flow rate of the corresponding branch pipeline is unqualified.
3. The method according to claim 2, characterized in that A secondary determination is performed on the average gas flow rate of the current cycle, including: Establishing a curve of average gas flow rate and time during the current period; If the slope of the change curve is greater than 0, it is determined that the average gas flow rate of the corresponding branch pipeline is qualified; If the slope of the change curve is less than 0 and greater than a preset slope, the opening of the valve corresponding to the branch pipeline is adjusted according to the difference between the slope and the preset slope, and it is determined whether the average gas flow rate of the branch pipeline in the next cycle meets the application conditions of the inter-row air conditioning; the preset slope is less than 0; If the slope of the variation curve is less than 0 and not greater than a preset slope, it is determined that the average gas flow rate of the corresponding branch pipeline is unqualified.
4. The method according to claim 3, characterized in that According to the difference between the slope and the preset slope, adjusting the opening of the valve corresponding to the branch pipeline includes: Obtaining an absolute value of a difference between the slope and the preset slope; Determining an opening adjustment coefficient according to the absolute value range to which the absolute value belongs; The adjustment coefficient is used to adjust the opening of the valve corresponding to the branch pipeline to obtain the target opening.
5. The method according to claim 4, characterized in that After obtaining the target opening, the method further includes: If the target opening reaches the opening critical value of the valve corresponding to the branch pipeline and the average gas flow rate of the branch pipeline in the next cycle is not greater than the second preset flow rate, the average gas flow rate of the corresponding branch pipeline is determined to be unqualified.
6. The method according to claim 5, characterized in that After determining that the average gas flow rate of the corresponding branch pipeline is unqualified, the method further includes: Determining a difference between the first preset flow rate and an average gas flow rate of the corresponding branch pipeline; If the difference is not greater than the first preset flow rate difference, it is determined that there is leakage in the corresponding branch pipe, and prompt information indicating that there is leakage in the corresponding branch pipe is generated; If the difference is greater than the first preset flow rate difference and not greater than the second preset flow rate difference, then according to the first ratio of the average gas flow rate of the corresponding branch pipeline to the flow rate of the main pipeline, if the first ratio is greater than the preset ratio, the preload force of each bolt in the flange corresponding to the corresponding branch pipeline is adjusted; if the first ratio is not greater than the preset ratio, the thickness of the welding point between the corresponding branch pipeline and the main pipeline is increased; wherein the first preset flow rate difference is less than the second preset flow rate difference; If the difference is greater than the second preset flow rate difference, the preload force of each bolt in the flange corresponding to the corresponding branch pipeline is adjusted according to a second ratio of the difference to the second preset flow rate difference.
7. The method according to claim 1, characterized in that After adjusting the pre-tightening force of each bolt in the flange corresponding to the corresponding branch pipeline, the method further includes: If the preload force reaches the critical value, increase the weld thickness between the main pipe and the corresponding flange.
8. A device for rapid piping of inter-row air conditioners, characterized in that: The device comprises: A determination unit, used to determine a simulation arrangement model including a virtual main pipeline, multiple branch pipelines, multiple flanges and multiple valves according to the on-site structure of the machine room to be processed; An acquisition unit, used to acquire the operating environment information of the computer room to be processed; A processing unit, used to process the operating environment information using the simulation arrangement model to obtain an average gas flow rate in each branch pipeline in the current cycle; If the average gas flow rate of any branch pipeline in the current cycle meets the inter-row air-conditioning application conditions, the welding parameters of the welding points between the corresponding branch pipeline and the main pipeline and the opening of the corresponding valve of the branch pipeline are adjusted so that the average gas flow rate of the branch pipeline meets the inter-row air-conditioning application conditions.
9. An electronic device, characterized in that: The electronic device comprises a processor, a communication interface, a memory and a communication bus, wherein the processor, the communication interface and the memory communicate with each other via the communication bus; Memory, used to store computer programs; A processor, for implementing the method steps described in any one of claims 1 to 7 when executing a program stored in a memory.
10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the method steps described in any one of claims 1 to 7 are implemented.
Citation Information
Patent Citations
Micromodule temperature field simulation method and device, computer equipment and storage medium
CN109948297A
Pipeline butt joint sealing process
CN117967869A
Feedback simulation method applicable to air-conditioning system
US20070233446A1
Cooling system and method for inverter, and air conditioning apparatus
WO2021063088A1
Control method and apparatus for opening degree of valve, and non-volatile storage medium and processor
WO2023024510A1