First critical method for large sodium-cooled fast reactor

Through batch-by-batch fuel assembly loading and control rod extrapolation, the safety and reliability problems of the first criticality of large sodium-cooled fast reactors are solved, and the first criticality of large sodium-cooled fast reactors and the improvement of core utilization rate are achieved.

CN118942742APending Publication Date: 2024-11-12CNNC LONGYUAN TECH CO LTD +1
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411011859.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-26
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The prior art cannot be applied to the first criticality of large sodium-cooled fast reactors, making it difficult to guarantee safety and reliability.

Method used

Using the method of loading fuel components batch by batch and gradually extrapolation of control rods, ensure the core by gradually lifting safety rods, non-moving rods, compensation rods and adjustment rods to the top of the core, and adjusting them according to the neutron counting rate and reactor cycle. Reaching the first critical state.

Benefits of technology

The first criticality of large sodium-cooled fast reactors is achieved, the fuel loading batches are reduced, and the core utilization rate and reactor control accuracy are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118942742A_ABST
    Figure CN118942742A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of sodium-cooled fast reactor reactors, and particularly relates to a first critical method for a large sodium-cooled fast reactor. When the fuel assembly is loaded to the critical capacity, starting to lift the control rods, and executing critical operation: lifting the safety rod, the passive rod and the compensation rod to the top of a reactor core one by one in sequence; gradually lifting the No.2 adjusting rod, and paying attention to the neutron counting rate of the reactor core and the periodic change of the reactor at any time; after the second adjusting rod is lifted to the top of the reactor core, starting to lift the first adjusting rod, carrying out rod position extrapolation, gradually lifting the first adjusting rod until the reactor period of the reactor core is 200s, and stopping the lifting operation; and calculating a critical rod position according to the reactivity value obtained from the reactivity meter and the micro-integral value of the No.1 adjusting rod, and inserting the No.1 adjusting rod to the critical rod position, so that the reactor core reaches the first critical value. According to the invention, the first critical of the large-scale sodium-cooled fast reactor can be safely and smoothly realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of sodium-cooled fast reactors, and in particular relates to a method for first criticality of a large sodium-cooled fast reactor. Background Art

[0002] With the continuous development of the nuclear energy industry, in order to further improve the safety, economy and reliability of nuclear reactors, countries around the world proposed the development of the fourth generation of advanced reactors in the early 21st century, including three types of fast reactors. my country's basic research on fast reactor technology began in 1960. As one of the fast reactor types, the sodium-cooled fast reactor is the only practical breeder reactor in the world today. Different from the low utilization rate of uranium resources of 1% in pressurized water reactors, the sodium-cooled fast reactor can increase the utilization rate of uranium resources to 60-70% by relying on its unique core neutron physical characteristics, thus achieving the goal of fully utilizing uranium resources.

[0003] The China Experimental Fast Reactor (CEFR) is the first fast reactor in my country. It successfully achieved first criticality on July 21, 2010. In the construction process of the reactor, first criticality is of great significance, indicating that the reactor has been basically completed and has the conditions for increasing power and operating applications. The first criticality of CEFR means that when the core sodium temperature is (250±5)℃, all control rods are raised from the core and located at the top position, and the simulated components of the core are replaced with fuel assemblies in batches, eventually making the reactor reach criticality. During the first criticality of CEFR, the control rod extrapolation process is mainly achieved through compensating rods and regulating rods. The control rod extrapolation method of CEFR is: lift all safety rods to the top, all regulating rods to the mid-plane position, and gradually lift the compensating rod assembly to perform rod position extrapolation. The supercritical extrapolation process of CEFR is: lower all regulating rods to the bottom and lift the compensating rods to the critical rod position. Then, the regulating rod position with a certain power multiple period of the core is estimated according to the regulating rod value, the regulating rod is lifted to this position and the period fitting is performed, and finally the critical rod position of the regulating rod is obtained by interpolation and confirmed to be critical.

[0004] Although CEFR has successfully achieved first criticality and has some criticality experience, the CEFR experimental fast reactor is a small sodium-cooled fast reactor, and the core design is significantly different from that of a large sodium-cooled fast reactor. The unique criticality mode of CEFR is not applicable to large sodium-cooled fast reactors. For the above reasons, a safe and reliable experimental method needs to be established to enable large sodium-cooled fast reactors to achieve first criticality smoothly. Summary of the invention

[0005] The purpose of the present invention is to provide a method for the first criticality of a large sodium-cooled fast reactor, so that the large sodium-cooled fast reactor can achieve the first criticality safely and smoothly.

[0006] In order to achieve the above object, the technical solution adopted by the present invention is:

[0007] A method for the first criticality of a large sodium-cooled fast reactor comprises the following steps: first, loading the fuel assembly to a near-critical loading amount; and second, lifting the control rods to perform criticality extrapolation to enable the reactor unit to achieve first criticality.

[0008] Fuel assembly loading principles: 1) Except for the first and last batches of loading, each loading follows the 1 / 2 principle, that is, the amount of fuel loaded each time must be less than 1 / 2 of the extrapolated critical loading increment, and the first batch of loading shall not exceed 0.9βeff; 2) When the core keff≈0.997 or is only 0.3βeff away from the critical reactivity of the core, the last two boxes of fuel assemblies are loaded and the reactor begins to transition to supercriticality; 3) Fuel assemblies are loaded from the inside to the outside, with priority given to fuel assemblies close to the detector.

[0009] The core is loaded and reaches its first criticality by replacing the fuel simulation assemblies batch by batch. The loading quantities of the first and second batches of fuel assemblies are based on theoretically calculated values, and the loading quantities of subsequent batches are based on actual extrapolated values ​​from the test until the fuel assemblies are loaded to the critical loading amount.

[0010] Critical extrapolation scheme: When the fuel assembly has been loaded to the critical amount, start lifting the control rods and perform criticality operations: first lift the safety rods, passive rods, and compensating rods one by one to the top of the core; then gradually lift the No. 2 regulating rod, and keep an eye on the core neutron count rate and reactor cycle changes; after the No. 2 regulating rod is lifted to the top of the core, start lifting the No. 1 regulating rod, and perform rod position extrapolation, gradually lift the No. 1 regulating rod until the core reactor cycle is 200s, then stop the lifting operation; based on the current reactivity value obtained from the reactivity instrument and the differential and integral values ​​of the No. 1 regulating rod, calculate the critical rod position, insert the No. 1 regulating rod down to the critical rod position, and the core can reach the first criticality.

[0011] The following conditions must be verified before the test: 1) The control rod drive mechanism is disconnected from the control rods, and all control rods in the reactor are at the bottom position; the control rod drive mechanism and the control rod drive mechanism guide tube are at the upper position; 2) The average sodium temperature at the core outlet is 220℃~250℃; 3) The blockage gauge temperature is less than 180℃; 4) The core covering gas pressure is 2kPa-6kPa and remains stable, and the tin-bismuth alloy sealed by the plug is in a molten state; 5) The primary circuit main pump runs at 25%±4rpm and remains stable; 6) The measurement system inside and outside the reactor ensures that there are more than two sets of detection signals; confirm that the reactivity instrument is available, and the nuclear detection detectors inside and outside the reactor are working normally.

[0012] Before loading the fuel assemblies, measure the active reference count rate and record it; according to the theoretical loading plan, load a certain number of fuel assemblies into the corresponding positions of the core. After each box of fuel assemblies is loaded into the core, measure the neutron count rate once, and calculate the 1 / M countdown rate as a function of the number of fuel assemblies entering the core; after the first batch of fuel assemblies are loaded, move the neutron source position from the outer periphery of the core to the inner circle of the core to facilitate the subsequent extrapolation of the number of assemblies. After the neutron count rate stabilizes, record the data as the reference count for critical safety supervision after each box of fuel assemblies is loaded into the core during the second batch of loading; lift the control rod assembly to the top of the core, and record the data after the neutron count rate stabilizes; The second batch of fuel assemblies in the loading scheme are loaded into the corresponding position of the core. After each box of fuel assemblies is loaded into the core, the neutron count rate is measured once, and the 1 / M countdown rate as a function of the number of fuel assemblies entering the core is calculated once; the control rod assembly is lifted to the top of the core. After the neutron count rate is stable, the number of fuel assemblies is extrapolated for the first time to obtain the loading amount of the third batch of fuel assemblies; according to the result of the first extrapolation, a certain number of fuel assemblies are loaded into the core. After the assembly loading is completed, the number of fuel assemblies is extrapolated for the second time to obtain the loading amount of the fourth batch of fuel assemblies; the above fuel assembly loading and extrapolation process is repeated. When the core Keff≈0.997 or the reactivity difference is only 0.3β effWhen the criticality is reached, two boxes of fuel assemblies are loaded into the core at one time; the transition to supercriticality is started: the safety rods are lifted to the top of the core in sequence, and the data are recorded after the neutron count rate is stable; the passive rods are lifted to the top of the core in sequence, and the data are recorded after the neutron count rate is stable; the compensation rods are lifted to the top of the core in sequence, and the data are recorded after the neutron count rate is stable; the No. 2 regulating rod is gradually lifted, 100 mm each time; during the lifting period, the neutron count rate and the reactor cycle are closely monitored. If the cycle is less than 30s, the rod lifting operation is stopped and the cycle is stopped. Continue to lift the rod after the period is greater than 300s; lift the No. 2 regulating rod to the top of the core, and record the data after the neutron count rate stabilizes; start to lift the No. 1 regulating rod by 100mm. During the lifting process, pay close attention to the neutron count rate and the reactor cycle changes. If the cycle is less than 30s, stop the rod lifting operation, and continue to lift the rod after the cycle is greater than 300s. After the lifting is completed, record the data and perform rod position extrapolation after the neutron count rate stabilizes; when the critical rod position obtained by extrapolation is greater than 200mm of the current rod position, continue to perform the regulating rod lifting operation according to the previous step When the extrapolated critical rod position is less than 200mm of the current rod position, the No. 1 regulating rod is lifted to a height of 50mm. During the lifting process, the neutron count rate and the reactor cycle change should be closely monitored. If the cycle is less than 30s, the rod lifting operation is stopped. When the cycle is greater than 300s, the rod lifting operation is continued. After the lifting is completed and the neutron count rate is stable, the data is recorded and the rod position is extrapolated. When the extrapolated critical rod position is greater than 100mm of the current rod position, the regulating rod lifting operation is continued in the above manner. When the extrapolated critical rod position is less than 100mm of the current rod position, the regulating rod lifting operation is continued in the above manner. After the control rod is 100mm in position, start to lift the No. 1 regulating rod in a jog manner, lifting it 2mm each time, and pay close attention to the neutron count rate and reactor cycle changes. Lift the No. 1 regulating rod in a jog manner until the reactor cycle is 200s, and judge that the reactor has reached the supercritical state; when the reactor cycle is 200s, read the reactivity instrument data to obtain the current reactivity value, and calculate the critical rod position of the control rod based on the current reactivity value and the calculus value data of the No. 1 regulating rod, insert the No. 1 regulating rod to the critical rod position, and make the reactor reach the first criticality.

[0013] The beneficial effects achieved by the present invention are:

[0014] By adopting a fuel loading scheme unique to large sodium-cooled fast reactors and combining it with the one-half loading principle, the technical effect of effectively reducing fuel loading batches is achieved while ensuring core safety.

[0015] By using a large sodium-cooled fast reactor to raise the regulating rod to a supercritical state, the core power doubling period can be accurately obtained, achieving the technical effect of reactor criticality more accurately.

[0016] After the first batch of fuel assemblies are loaded, the neutron source assembly is moved from the outer periphery of the core to the inner ring of the core. In the early stage, it is ensured that the in-core detector has a sufficient neutron counting rate to avoid the existence of detection blind spots; in the later stage, it is moved to the inner ring of the core to achieve the technical effect of safety and accuracy of extrapolation. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a diagram of loading batches and loading quantity of each batch;

[0018] Figure 2 This is a flow chart of the first criticality method for a large sodium-cooled fast reactor. DETAILED DESCRIPTION

[0019] The present invention is described in detail below with reference to the accompanying drawings and specific embodiments.

[0020] The technical solution of the present invention is divided into two steps: the first step is to load the fuel assembly to a near-critical loading amount; the second step is to lift the control rods to perform critical extrapolation so that the reactor unit achieves the first criticality.

[0021] (1) Fuel assembly loading scheme

[0022] Fuel assembly loading principles: 1) Except for the first and last batches of loading, each loading follows the 1 / 2 principle, that is, the amount of fuel loaded each time must be less than 1 / 2 of the extrapolated critical loading increment, and the first batch of loading should not exceed 0.9β eff ; 2) When the core k eff ≈0.997 or only 0.3β away from the critical reactivity of the core eff 1) When the last two boxes of fuel assemblies are loaded, the reactor begins to transition to supercriticality; 2) Fuel assemblies are loaded from the inside to the outside, with priority given to fuel assemblies close to the detector.

[0023] Fuel loading plan Figure 1 As shown, the core is loaded and first critical by replacing the fuel simulation assemblies batch by batch. The loading quantity of the first and second batches of fuel assemblies is based on the theoretical calculation value for core loading, and the loading quantity of subsequent batches is based on the actual extrapolated value of the test until the fuel assemblies are loaded to the critical loading quantity.

[0024] (2) Critical extrapolation scheme

[0025] When the fuel assembly has been loaded to the critical amount, the control rods are lifted and the criticality operation is performed. The overall plan is: first, the safety rods, passive rods, and compensation rods are lifted one by one to the top of the core; then the No. 2 regulating rod is gradually lifted, and the core neutron count rate and reactor cycle changes are always paid attention to; after the No. 2 regulating rod is lifted to the top of the core, the No. 1 regulating rod is lifted, and the rod position is extrapolated, and the No. 1 regulating rod is gradually lifted until the core reactor cycle is about 200s, and the lifting operation is stopped; according to the current reactivity value obtained from the reactivity instrument and the differential and integral values ​​of the No. 1 regulating rod, the critical rod position is calculated, and the No. 1 regulating rod is inserted down to the critical rod position, so that the core can reach the first criticality.

[0026] The following is combined with Figure 2 The technical solution provided by the present invention is further described as follows:

[0027] Confirm that the reactivity instrument is available and the in-pile and out-pile nuclear detection detectors are working properly;

[0028] The following conditions must be verified before the test: 1) The control rod drive mechanism is disconnected from the control rods, and all control rods in the reactor are located at the bottom position; the control rod drive mechanism and the control rod drive mechanism guide tube are located at the upper position. 2) The average sodium temperature at the core outlet is 220℃~250℃. 3) The blockage gauge temperature is less than 180℃. 4) The core covering gas pressure is about 2kPa-6kPa and remains stable, and the tin-bismuth alloy sealed by the plug is in a molten state. 5) The main pump of the primary circuit runs at 25%±4rpm and remains stable. 6) The measurement system inside and outside the reactor ensures that there are more than two sets of detection signals.

[0029] Before loading the fuel assembly, measure the active reference count rate and record it.

[0030] According to the theoretical loading plan, a certain number of fuel assemblies are loaded into the corresponding positions of the core. After each box of fuel assemblies is loaded into the core, the neutron count rate is measured once, and the 1 / M countdown rate is calculated as a function of the number of fuel assemblies loaded into the core.

[0031] After the first batch of fuel assemblies are loaded, the neutron source position is moved from the outer core to the inner core to facilitate the subsequent extrapolation of the number of assemblies. After the neutron count rate stabilizes, the data is recorded as the benchmark count for criticality safety monitoring after each box of fuel assemblies is loaded into the reactor during the second batch of loading.

[0032] The control rod assembly is raised to the top of the core and the data is recorded when the neutron count rate stabilizes.

[0033] The second batch of fuel assemblies in the theoretical loading plan are loaded into the corresponding positions of the core. After each box of fuel assemblies is loaded into the core, the neutron count rate is measured once, and the 1 / M countdown rate is calculated as a function of the number of fuel assemblies loaded into the core.

[0034] The control rod assembly is lifted to the top of the core. When the neutron count rate stabilizes, the first fuel assembly quantity extrapolation is performed to obtain the third batch of fuel assembly loading.

[0035] According to the first extrapolation result, a certain number of fuel assemblies are loaded into the core. After the assembly loading is completed, the second fuel assembly quantity extrapolation is performed to obtain the fourth batch of fuel assembly loading.

[0036] Repeat the above fuel assembly loading and extrapolation process. When the core Keff≈0.997 or the reactivity difference is only 0.3β eff When criticality is reached, two fuel assemblies are loaded into the core at one time.

[0037] Start the transition to supercriticality:

[0038] Lift the safety rods to the top of the core one by one, and record the data after the neutron counting rate stabilizes.

[0039] The passive rods are raised to the top of the core one by one, and the data are recorded after the neutron counting rate stabilizes.

[0040] Lift the compensating rods to the top of the core one by one, and record the data after the neutron counting rate stabilizes.

[0041] Gradually lift the No. 2 regulating rod, about 100mm each time. During the lifting period, pay close attention to the neutron count rate and reactor cycle. If the cycle is less than 30s, stop lifting the rod, and continue lifting the rod after the cycle is greater than 300s. Lift the No. 2 regulating rod to the top of the core, and record the data after the neutron count rate stabilizes.

[0042] Start lifting the No. 1 regulating rod by 100mm. During the lifting process, pay close attention to the neutron count rate and the reactor cycle changes. If the cycle is less than 30s, stop lifting the rod and continue lifting the rod after the cycle is greater than 300s. After the lifting is completed and the neutron count rate is stable, record the data and perform rod position extrapolation.

[0043] When the critical rod position obtained by extrapolation is greater than the current rod position by 200 mm, continue to perform the adjustment rod lifting operation according to the previous step.

[0044] When the extrapolated critical rod position is less than 200mm of the current rod position, the No. 1 regulating rod is lifted to a height of 50mm. During the lifting process, the neutron count rate and the reactor cycle change should be closely monitored. If the cycle is less than 30s, the rod lifting operation is stopped and the rod lifting is continued after the cycle is greater than 300s. After the lifting is completed and the neutron count rate is stable, the data is recorded and the rod position is extrapolated.

[0045] When the critical rod position obtained by extrapolation is greater than the current rod position by 100 mm, continue to perform the adjustment rod lifting operation according to the previous step.

[0046] When the extrapolated critical rod position is 100mm less than the current rod position, start to lift the No. 1 regulating rod in increments of 2mm each time, and pay close attention to the changes in the neutron count rate and reactor cycle. Lift the No. 1 regulating rod in increments until the reactor cycle is 200s, and it is judged that the reactor has reached a supercritical state.

[0047] When the reactor cycle is 200s, read the reactivity instrument data to obtain the current reactivity value, and calculate the critical rod position of the control rod based on the current reactivity value and the calculus value data of the No. 1 regulating rod. Insert the No. 1 regulating rod to the critical rod position to make the reactor reach the first criticality.

[0048] The key points and protection points of the present invention are: the present invention is the first method for the first criticality of a large-scale sodium-cooled fast reactor in China. The present invention has been debugged and verified, and through a specific fuel loading scheme and a control rod lifting method to reach criticality, a large-scale sodium-cooled fast reactor has been safely and smoothly reached the first criticality. A method is provided for a large-scale sodium-cooled fast reactor to move the neutron source assembly from the outer core to the inner core after the first batch of fuel assemblies are loaded. A fuel loading scheme for a large-scale sodium-cooled fast reactor is provided: the first two batches are loaded according to theoretical values, and the subsequent batches are loaded according to actual extrapolated values. The last batch is loaded with two boxes of assemblies at one time when keff≈0.997 or the reactivity is only 0.3βeff different from criticality, and the core is then transitioned to supercriticality. A method for extrapolating the control rods of a large-scale sodium-cooled fast reactor to reach criticality is provided: first lift the safety rod, the passive rod, the compensation rod, and the No. 2 regulating rod to the top of the reactor, lift the No. 1 regulating rod until the reactor has a stable power cycle, calculate the critical rod position of the regulating rod according to the value of the regulating rod and the existing reactivity of the core, and insert the regulating rod to the critical rod position to make the reactor critical for the first time.

[0049] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that modifying the technical solutions described in the aforementioned embodiments, or replacing part or all of the technical features therein by equivalents, does not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. A method for achieving first criticality of a large sodium-cooled fast reactor, characterized in that: The first step is to load the fuel assemblies to a level close to the critical load; the second step is to lift the control rods and perform critical extrapolation to enable the reactor unit to achieve first criticality.

2. The method for first criticality of a large sodium-cooled fast reactor according to claim 1, characterized in that: Fuel assembly loading principles: 1) Except for the first and last batches of loading, each loading follows the 1 / 2 principle, that is, the amount of fuel loaded each time must be less than 1 / 2 of the extrapolated critical loading increment, and the first batch of loading shall not exceed 0.9βeff; 2) When the core keff≈0.997 or is only 0.3βeff away from the critical reactivity of the core, the last two boxes of fuel assemblies are loaded and the reactor begins to transition to supercriticality; 3) Fuel assemblies are loaded from the inside to the outside, with priority given to fuel assemblies close to the detector.

3. The method for first criticality of a large sodium-cooled fast reactor according to claim 2, characterized in that: The core is loaded and reaches its first criticality by replacing the fuel simulation assemblies batch by batch. The loading quantities of the first and second batches of fuel assemblies are based on theoretically calculated values, and the loading quantities of subsequent batches are based on actual extrapolated values ​​from the test until the fuel assemblies are loaded to the critical loading amount.

4. The method for first criticality of a large sodium-cooled fast reactor according to claim 1, characterized in that: Critical extrapolation scheme: When the fuel assembly has been loaded to the critical amount, start lifting the control rods and perform criticality operations: first lift the safety rods, passive rods, and compensating rods one by one to the top of the core; then gradually lift the No. 2 regulating rod, and keep an eye on the core neutron count rate and reactor cycle changes; after the No. 2 regulating rod is lifted to the top of the core, start lifting the No. 1 regulating rod, and perform rod position extrapolation, gradually lift the No. 1 regulating rod until the core reactor cycle is 200s, then stop the lifting operation; based on the current reactivity value obtained from the reactivity instrument and the differential and integral values ​​of the No. 1 regulating rod, calculate the critical rod position, insert the No. 1 regulating rod down to the critical rod position, and the core can reach the first criticality.

5. The method for first criticality of a large sodium-cooled fast reactor according to claim 1, characterized in that: The following conditions must be verified before the test: 1) The control rod drive mechanism is disconnected from the control rods, and all control rods in the reactor are at the bottom position; the control rod drive mechanism and the control rod drive mechanism guide tube are at the upper position; 2) The average sodium temperature at the core outlet is 220℃~250℃; 3) The blockage gauge temperature is less than 180℃; 4) The core covering gas pressure is 2kPa-6kPa and remains stable, and the tin-bismuth alloy sealed by the plug is in a molten state; 5) The primary circuit main pump runs at 25%±4rpm and remains stable; 6) The measurement system inside and outside the reactor ensures that there are more than two sets of detection signals; confirm that the reactivity instrument is available, and the nuclear detection detectors inside and outside the reactor are working normally.

6. The method for first criticality of a large sodium-cooled fast reactor according to claims 3 and 4, characterized in that: Before loading the fuel assemblies, measure the active reference count rate and record it; according to the theoretical loading plan, load a certain number of fuel assemblies into the corresponding positions of the core. After each box of fuel assemblies is loaded into the core, measure the neutron count rate once, and calculate the 1 / M countdown rate as a function of the number of fuel assemblies entering the core; after the first batch of fuel assemblies are loaded, move the neutron source position from the outer periphery of the core to the inner circle of the core to facilitate the subsequent extrapolation of the number of assemblies. After the neutron count rate stabilizes, record the data as the reference count for critical safety supervision after each box of fuel assemblies is loaded into the core during the second batch of loading; lift the control rod assembly to the top of the core, and record the data after the neutron count rate stabilizes; The second batch of fuel assemblies in the loading scheme are loaded into the corresponding position of the core. After each box of fuel assemblies is loaded into the core, the neutron count rate is measured once, and the 1 / M countdown rate as a function of the number of fuel assemblies entering the core is calculated once; the control rod assembly is lifted to the top of the core. After the neutron count rate is stable, the number of fuel assemblies is extrapolated for the first time to obtain the loading amount of the third batch of fuel assemblies; according to the result of the first extrapolation, a certain number of fuel assemblies are loaded into the core. After the assembly loading is completed, the number of fuel assemblies is extrapolated for the second time to obtain the loading amount of the fourth batch of fuel assemblies; the above fuel assembly loading and extrapolation process is repeated. When the core Keff≈0.997 or the reactivity difference is only 0.3β eff When the criticality is reached, two boxes of fuel assemblies are loaded into the core at one time; the transition to supercriticality is started: the safety rods are lifted to the top of the core in sequence, and the data are recorded after the neutron count rate is stable; the passive rods are lifted to the top of the core in sequence, and the data are recorded after the neutron count rate is stable; the compensation rods are lifted to the top of the core in sequence, and the data are recorded after the neutron count rate is stable; the No. 2 regulating rod is gradually lifted, 100 mm each time; during the lifting period, the neutron count rate and the reactor cycle are closely monitored. If the cycle is less than 30s, the rod lifting operation is stopped and the cycle is stopped. Continue to lift the rod after the period is greater than 300s; lift the No. 2 regulating rod to the top of the core, and record the data after the neutron count rate stabilizes; start to lift the No. 1 regulating rod by 100mm. During the lifting process, pay close attention to the neutron count rate and the reactor cycle changes. If the cycle is less than 30s, stop the rod lifting operation, and continue to lift the rod after the cycle is greater than 300s. After the lifting is completed, record the data and perform rod position extrapolation after the neutron count rate stabilizes; when the critical rod position obtained by extrapolation is greater than 200mm of the current rod position, continue to perform the regulating rod lifting operation according to the previous step When the extrapolated critical rod position is less than 200mm of the current rod position, the No. 1 regulating rod is lifted to a height of 50mm. During the lifting process, the neutron count rate and the reactor cycle change should be closely monitored. If the cycle is less than 30s, the rod lifting operation is stopped. When the cycle is greater than 300s, the rod lifting operation is continued. After the lifting is completed and the neutron count rate is stable, the data is recorded and the rod position is extrapolated. When the extrapolated critical rod position is greater than 100mm of the current rod position, the regulating rod lifting operation is continued in the above manner. When the extrapolated critical rod position is less than 100mm of the current rod position, the regulating rod lifting operation is continued in the above manner. After the control rod is 100mm in position, start to lift the No. 1 regulating rod in a jog manner, lifting it 2mm each time, and pay close attention to the neutron count rate and reactor cycle changes. Lift the No. 1 regulating rod in a jog manner until the reactor cycle is 200s, and judge that the reactor has reached the supercritical state; when the reactor cycle is 200s, read the reactivity instrument data to obtain the current reactivity value, and calculate the critical rod position of the control rod based on the current reactivity value and the calculus value data of the No. 1 regulating rod, insert the No. 1 regulating rod to the critical rod position, and make the reactor reach the first criticality.

Citation Information

Cited By

  • Method for loading reactor fuel assemblies and method for loading lead-bismuth stacks

    CN119694617A

  • Operation control method for preventing accidental short-period protection shutdown of reactor in power rising and falling process of sodium-cooled fast reactor

    CN119786084A