Hydraulic lifting system and lifting method thereof
By combining hydraulic lifting equipment and buffer devices, the impact problem caused by horizontal displacement during off-site assembly was solved, achieving safe and reliable structural lifting.
Patent Information
- Application Number
- CN202411078668.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-07
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2044-08-07
AI Technical Summary
When the structure to be lifted is not assembled in its original position, the horizontal impact caused by horizontal displacement during the hydraulic lifting process affects the safety and reliability of the structure to be lifted and the hydraulic lifting equipment.
The system employs hydraulic lifting equipment and a buffer device. By combining lifting ropes and traction structures, and utilizing the coordinated control of lifting and traction motors, it counteracts horizontal impact forces and ensures that the structure to be lifted returns to its installation position.
It effectively prevents the impact caused by horizontal displacement of the structure to be lifted during the lifting process, avoids damage to the hydraulic lifting equipment and structure, and achieves safe and reliable off-site lifting.
Smart Images

Figure CN118954340A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of lifting technology, in particular to a hydraulic lifting system and a lifting method thereof. Background Art
[0002] Hydraulic integral lifting is a construction process in which the structure to be lifted is first assembled as a whole on the ground or on an elevated platform, and then the structure to be lifted is lifted in situ through the hydraulic lifting facilities and equipment installed on the top of the completed concrete frame or a special lifting frame (which is usually located 1-2 meters above the installation elevation of the structure to be lifted), thereby reducing the impact on civil construction. Computer control can be used during lifting to achieve refined control of the lifting process and enhance the reliability of the lifting facilities.
[0003] This process requires that the structure to be lifted must be located below the orthographic projection of the installation location for in-situ assembly during the overall assembly, and then lifted in-situ after the assembly is completed. Due to the differences between the building structures of different floors and the different on-site construction conditions, it is often the case that the structure to be lifted cannot be assembled in-situ. When the in-situ lifting conditions are not met, a support frame combined with high-altitude assembly is usually used. This installation method requires the use of a support frame, which requires additional installation, which results in low overall installation efficiency. In addition, due to the high-altitude assembly, the risk level is high. However, if the assembly is carried out non-in-situ, the hydraulic lifting facilities and equipment cannot perform vertical lifting when lifting the structure to be lifted that is assembled non-in-situ; and because there is a distance between the horizontal positions of the hydraulic lifting facilities and equipment and the structure to be lifted, the structure to be lifted will be offset horizontally toward the hydraulic lifting facilities and equipment at the moment the hydraulic lifting facilities and equipment are started. This offset will bring horizontal pulling force to the hydraulic lifting facilities and equipment, which may easily cause damage to the hydraulic lifting facilities and equipment and failure of the connection between the hydraulic lifting facilities and equipment and the structure to be lifted, which may lead to serious consequences such as the falling of the structure to be lifted. Summary of the invention
[0004] The purpose of the present invention is to provide a hydraulic lifting system and a lifting method thereof, so as to solve the problem that when the structure to be lifted is not assembled in situ, due to the horizontal distance between the structure to be lifted and the installation position, horizontal offset occurs during the lifting process, thereby causing horizontal impact, and affecting the structure to be lifted itself and the hydraulic lifting facilities and equipment.
[0005] In order to achieve the above object, the present invention provides a hydraulic lifting system, which includes a hydraulic lifting device and a buffer device;
[0006] The hydraulic lifting device comprises two sets of lifting components arranged at intervals, and the lifting components comprise: a lifting motor, a lifting rope and a lifting point; the two lifting points are arranged at the same vertical height at intervals, the lifting rope is slidably inserted into the lifting points, the top end of the lifting rope is connected to the power output end of the lifting motor, the bottom end of the lifting rope is used to connect to the structure to be lifted, and the lifting motor can drive the bottom end of the lifting rope to move toward the direction close to the lifting point;
[0007] The buffer device comprises at least two groups of buffer components, each group of buffer components is located on the same side below the hanging point, and the buffer device comprises a fixing member and
[0008] A pulling structure; the pulling structure includes a puller, which includes a shell, a pulling motor and a pulling part, the pulling motor is arranged in the shell, one end of the pulling part is connected to the power output end of the pulling motor, the other end of the pulling part is a pulling end, and the pulling end is used to be connected to the structure to be lifted, and the pulling motor can drive the pulling end to be close to or away from the shell.
[0009] Furthermore, the buffer device includes two groups of buffer components, and the two groups of buffer components are respectively connected to two ends of the structure to be lifted.
[0010] Furthermore, the buffer device also includes a switch controller, which is electrically connected to each of the pulling motors, and is used to simultaneously control the forward or reverse rotation of each of the pulling motors.
[0011] Furthermore, the pulling structure further comprises a first connecting assembly, wherein the first connecting assembly comprises a detachably connected first connecting member and a first hanging ring;
[0012] The shell is connected to the first connecting member, and the first hanging ring is connected to the fixing member.
[0013] Furthermore, the pulling structure further comprises a second connecting assembly, wherein the second connecting assembly comprises a detachably connected second connecting member and a second hanging ring;
[0014] The pulling end is connected to the second connecting member, and the second hanging ring is used to connect the second connecting member to the structure to be lifted.
[0015] Further, the first connecting member includes a first connecting buckle and a first connecting pin;
[0016] The first connecting buckle is U-shaped, and both ends of the first connecting buckle are provided with first connecting holes penetrating the two side surfaces, and the two first connecting holes are coaxially arranged, and the first connecting pin passes through the first connecting hole at one end, the first hanging ring and the first connecting hole at the other end in sequence, and locks and fixes the first hanging ring and the first connecting buckle;
[0017] The second connecting member includes a second connecting buckle and a second connecting pin;
[0018] The second connecting buckle is U-shaped, and both ends of the second connecting buckle are provided with second connecting holes penetrating the two side surfaces, and the two second connecting holes are coaxially arranged. The second connecting pin passes through the second connecting hole at one end, the second hanging ring and the second connecting hole at the other end in sequence, and locks and fixes the second hanging ring and the second connecting buckle.
[0019] The present invention also provides a lifting method for the above hydraulic lifting system, which comprises the following steps:
[0020] S1. Arrange the suspension point above the installation position of the structure to be lifted, so that the center of the installation position falls on the line connecting the two suspension points under the vertical projection;
[0021] S2. Arrange the fixing member so that, in the vertical orthographic projection, the connecting lines of the fixing member and the two lifting points are located on different sides of the center of the structure to be lifted;
[0022] S3, calculating the horizontal impact force generated by the structure to be lifted during lifting, and setting the pulling force applied by the retractors to the connecting ropes so that in the horizontal direction, the total pulling force generated by the multiple retractors is the same in magnitude and opposite in direction to the impact force of the structure to be lifted;
[0023] S4, starting the lifting motor and the pulling motor at the same time, and controlling the lifting motor and the pulling motor to rotate forward;
[0024] S5, after the lifting structure is lifted to a predetermined height, controlling the pulling motor to reverse and move the pulling end away from the housing;
[0025] S6. When the structure to be lifted returns to below the positive projection of the installation position, the retractor is turned off;
[0026] S7. Lift the structure to be lifted to the installation position and shut down the lifting motor.
[0027] Further, in step S2, under the orthographic projection in the vertical direction, the horizontal distance between each of the fixing members and the structure to be lifted is defined as a first distance, and the horizontal distance between each of the hanging points and the structure to be lifted is defined as a second distance, and the first distance is greater than the second distance.
[0028] Compared with the prior art, the hydraulic lifting system and lifting method provided by the present invention have the following beneficial effects:
[0029] The present invention provides a hydraulic lifting system, which includes a hydraulic lifting device and a buffer device, wherein the lifting motor drives the bottom end of the lifting rope to move toward the direction close to the hanging point, thereby lifting the structure to be lifted connected to the bottom end of the lifting rope, and can lift the structure to be lifted to below the hanging point; and through the fixing part and the pulling structure in the buffer device, the pulling end is driven close to the shell by the pulling motor, so that a horizontal pulling force directed to the fixing part can be applied to the structure to be lifted connected to the pulling end, which can offset the horizontal impact force generated by the horizontal deviation of the structure to be lifted during the lifting process, thereby avoiding the deviation of the structure to be lifted at the moment of lifting, so as to avoid horizontal impact on the hydraulic lifting device; and the pulling end is driven away from the shell by the pulling motor, so that the horizontal pulling force applied by the puller to the structure to be lifted can be reduced to zero, thereby returning the structure to be lifted to the position directly below the hanging point, and pulling the structure to be lifted to the installation position through the lifting rope.
[0030] The present invention also provides a lifting method, wherein a lifting point is arranged above the installation position of the structure to be lifted, and the center of the installation position falls on the connecting line of the two lifting points under the orthographic projection in the vertical direction, so that after the structure to be lifted is returned to the position directly below the lifting point, the lifting rope directly lifts the structure to be lifted to the installation position; by arranging the buffer device and the two lifting points on opposite sides of the structure to be lifted, the horizontal pulling force of the puller on the structure to be lifted and the horizontal impact force caused by the horizontal offset of the structure to be lifted are offset, and during the lifting process, the pulling motor is controlled to reverse to gradually reduce the pulling force of the puller so that the structure to be lifted slowly returns to the position below the orthographic projection of the installation position, and the structure to be lifted is finally lifted to the installation position through continued lifting of the hydraulic lifting equipment, thereby realizing non-in-situ lifting of the structure to be lifted and preventing the horizontal impact of the structure to be lifted at the moment of lifting from causing damage to the structure to be lifted and then the hydraulic lifting device. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 is a side view schematic diagram of a hydraulic lifting system and a structure to be lifted according to an embodiment of the present invention;
[0032] Figure 2 is a schematic top view of a hydraulic lifting system and a structure to be lifted according to an embodiment of the present invention;
[0033] Figure 3 yes Figure 1 A magnified schematic diagram of the middle A area;
[0034] Figure 4 yes Figure 1 A magnified schematic diagram of the middle B area;
[0035] Figure 5is a schematic top view of a first connecting member according to an embodiment of the present invention;
[0036] Figure 6 It is a side view schematic diagram of the first connecting buckle according to an embodiment of the present invention.
[0037] In the figure, 100, hydraulic lifting system; 200, structure to be lifted; 300, installation position; 1, hydraulic lifting equipment; 10, lifting component; 11, lifting rope; 12, hanging point; 2, buffer device; 20, pulling component; 21, fixing piece; 22, pulling structure; 221, puller; 2211, shell; 2212, pulling part; 22121, pulling end; 222, first connecting component; 2221, first connecting piece; 22211, first connecting buckle; 22210, first connecting hole; 22212, first connecting pin; 2222, first hanging ring; 223, second connecting component; 2231, second connecting piece; 2232, second hanging ring; 22311, first connecting buckle; 22312, first connecting pin; 224, connecting rope. DETAILED DESCRIPTION
[0038] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0039] like Figure 1 and Figure 2 As shown, a hydraulic lifting system 100 according to an embodiment of the present invention comprises a hydraulic lifting device 1 and a buffer device 2;
[0040] The hydraulic lifting device 1 includes two groups of lifting components 10 arranged at intervals, and the lifting components 10 include: a lifting motor (not shown in the figure), a lifting rope 11 and a hanging point 12; the two hanging points 12 are arranged at the same vertical height at intervals, and the lifting rope 11 is slidably inserted into the hanging point 12, the top of the lifting rope 11 is connected to the power output end of the lifting motor, and the bottom end of the lifting rope 11 is used to connect with the structure to be lifted 200, and the lifting motor can drive the bottom end of the lifting rope 11 to move in a direction close to the hanging point 12; the buffer device 2 includes at least two groups of buffer components 20, and each group of the buffer components 20 is located On the same side below the lifting point 12, the buffer device 20 includes a fixing part 21 and a pulling structure 22; the pulling structure 22 includes a puller 221, the puller 221 includes a shell 2211, a pulling motor (not shown in the figure) and a pulling part 2212, the pulling motor is arranged in the shell 2211, one end of the pulling part 2212 is connected to the power output end of the pulling motor, the other end of the pulling part 2212 is a pulling end 22121, and the pulling end 22121 is used to connect to the structure to be lifted 200, and the pulling motor can drive the pulling end 2121 to move closer to or away from the shell 2211.
[0041] Based on the above technical solution, through two sets of spaced-apart lifting components 10, driven by the lifting motor, the bottom end of the lifting rope 11 will move toward the direction close to the hanging point 12, so that the structure to be lifted connected to the bottom end of the lifting rope 11 is lifted, and it can be lifted to just below the hanging point 12; and through the fixing part 21 and the retractor 221 in the buffer device 2, driven by the retractor motor, the retractor end 22121 is close to the shell 2211, so that the retractor 221 pulls the structure to be lifted connected to the retractor end 22121 The structure applies a horizontal pulling force directed to the housing 2211, and since the retractors 221 are connected to the fixing member 21, the fixing members 21 are all on the same side of the line connecting the two suspension points 12, that is, the multiple retractors 221 can jointly apply a horizontal pulling force in the same direction to the structure to be lifted 200, so as to offset the horizontal impact of the structure to be lifted 200 during lifting, thereby preventing the structure to be lifted 200 from colliding with the side of its horizontal offset under the action of the horizontal impact, and bringing unnecessary horizontal force to the hydraulic lifting device 1, so as to avoid the horizontal impact causing damage to the structure to be lifted 200 and the hydraulic lifting device 1. In addition, during the lifting process of the structure to be lifted 200, the pulling end 22121 is driven away from the housing 2211 by the pulling motor to reduce the pulling force applied by the retractors 221 to the structure to be lifted 200 to zero, so that the structure to be lifted 200 is only subjected to the upward pulling force of the lifting rope 11, and returns to the position directly below the suspension point 12, so as to be lifted to the installation position 300.
[0042] Preferably, the hydraulic lifting system 100 in this embodiment uses an electric hoist as a pulling device. The electric hoist is a common electric device that can be used to pull heavy objects. Its sprocket serves as the pulling part 2212, and the hook fixed at the end of the sprocket serves as the pulling end 22121. Its motor serves as the pulling motor. The motor of the electric hoist can drive the hook close to or away from the shell. Its driving structure is a prior art means and will not be described here.
[0043] Furthermore, if Figure 1 and Figure 2 As shown, since the hydraulic lifting equipment 1 includes two groups of lifting components 10 arranged at intervals, in actual use, in order to reduce the shaking problem of the structure to be lifted during hydraulic lifting, each lifting rope 11 is usually connected to the two ends of the structure to be lifted 200 respectively; to correspond to the setting of the hydraulic lifting equipment 1, the buffer device 2 includes two groups of buffer components 20, and the two groups of buffer components 20 are respectively connected to the two ends of the structure to be lifted, so that the force of the structure to be lifted 200 is balanced during the lifting and return process.
[0044] Preferably, in this embodiment, the line connecting the centers of the two fixing members 21 is parallel to the line connecting the centers of the two suspension points 12, thereby facilitating the overall force balance of the structure 200 to be lifted during the lifting process and facilitating the accurate calculation of the pulling force that each puller 221 should apply.
[0045] Preferably, if Figure 2 As shown, the center horizontal spacing of the two fixing members 21 is defined as D1, and the center horizontal spacing of the two hanging points 12 is defined as D2, 0.75*D1≤D2≤1.5*D1. When D1 is large, the fixing members 21 will be dispersed at both ends of the structure to be lifted 200 and have a certain distance from the structure to be lifted 200. The larger D1 is, the farther the distance is, so that only a part of the pulling force applied by the puller 221 to the structure to be lifted 200 can be opposite to the horizontal impact force, while the other part is perpendicular to the horizontal impact force and cannot offset the horizontal impact force. This will require the puller 221 to provide a larger pulling force, which will reduce the pulling efficiency of the puller 221; when D1 is small, the fixing members 21 will be concentrated on one side of one point of the structure to be lifted 200, so that the pulling force applied by the puller 221 is concentrated at one point, causing uneven force on the structure to be lifted.
[0046] Furthermore, the buffer device 2 also includes a switch controller, which is electrically connected to each of the pulling motors. The switch controller is used to simultaneously control the forward rotation or reverse rotation of each of the pulling motors to achieve synchronous forward rotation and reverse rotation of each of the pulling motors, thereby avoiding the problem of uneven tension at both ends of the structure 200 to be lifted due to delays caused by manually controlling the switches of each pulling motor individually.
[0047] Preferably, the buffer device 2 in this embodiment includes two groups of buffer components 20, that is, there are two pulling motors; in order to specifically realize the control of the two pulling motors by the switch controller, the switch controller includes a main switch, a stop button, a forward contactor, a reverse contactor, a forward button and a reverse button; the stop button is used to control the on and off of the circuit in the switch controller; the forward button is electrically connected to the two pulling motors through the forward contactor, and the reverse button is electrically connected to the two pulling motors through the reverse contactor. When the switch controller controls the two pulling motors, the forward button is pressed, and the forward button controls the forward contactor to be attracted, thereby starting the two pulling motors and making them rotate forward; when the stop button is pressed, the circuit is disconnected, and both pulling motors stop running; when the reverse button is pressed, the reverse button controls the reverse contactor to be attracted, thereby restarting the two pulling motors and making them reverse; thereby realizing the synchronous forward and reverse rotation of the two pulling motors, avoiding uneven force caused by manually controlling the forward and reverse rotation of the pulling motors.
[0048] Furthermore, if Figure 1 to Figure 4 As shown, in actual use, in order to reduce construction costs and ensure the stability of the fixing member 21, existing concrete columns or other building structures in the building are usually selected as the fixing member 21; in order to facilitate the connection between the puller 221 and the fixing member 21, the pulling structure 22 also includes a first connecting component 222, and the first connecting component 222 includes a detachable first connecting member 2221 and a first hanging ring 2222; the shell 2211 is connected to the first connecting member 2221, and the first hanging ring 2222 is connected to the fixing member 21, so as to realize the connection between the puller 221 and the fixing member 21; in addition, since the first connecting member 2221 needs to be selected and replaced according to the structure 200 to be lifted to ensure the reliability of the connection; therefore, the first connecting member 2221 and the first hanging ring 2222 are set to be detachably connected for replacement.
[0049] Furthermore, if Figure 1 to Figure 4As shown, similar to the connection between the puller 221 and the fixing member 21, in order to ensure the reliability of the connection between the pulling end 22121 and the structure to be lifted 200, thereby avoiding various consequences caused by connection failure during the pulling process, the pulling structure 22 also includes a second connecting component 223, and the second connecting component 223 includes a detachable second connecting member 2231 and a second hanging ring 2232; the pulling end 22121 is connected to the second connecting member 2231, and the second hanging ring 2232 is used to connect the second connecting member 2231 to the structure to be lifted 200; similarly, since the second connecting member 2231 needs to be selected and replaced according to the structure to be lifted 200, the second connecting member 2231 and the second hanging ring 2232 are set to be detachably connected for replacement.
[0050] Preferably, if Figure 1 to Figure 4 As shown, since the horizontal distance between the fixing member 21 and the structure to be lifted 200 is greater than the distance that the pulling end 22121 can move, the pulling structure 22 further includes a connecting rope 224 , and the pulling end 22121 is connected to the second connecting member 223 via the connecting rope 224 .
[0051] Furthermore, if Figure 3 to Figure 6 As shown, in order to facilitate the connection between the first hanging ring 2222 and the first connecting member 2221 and ensure the reliability of their connection, thereby preventing the problem of connection failure during the pulling process; the first connecting member 2221 includes a first connecting buckle 22211 and a first connecting pin 22212; the first connecting buckle 22211 is U-shaped, and both ends of it are provided with first connecting holes 22210 that pass through the two side surfaces, and the two first connecting holes 22210 are coaxially arranged, and the first connecting pin 22212 passes through the first connecting hole 22210 at one end, the first hanging ring 2222 and the first connecting hole 22210 at the other end in turn, and locks and fixes the first hanging ring 2222 and the first connecting buckle 22211.
[0052] Similar to the configuration of the first connecting member 2221, the second connecting member 2231 includes a second connecting buckle 22311 and a second connecting pin 22312; the second connecting buckle 22311 is U-shaped, and both ends thereof are provided with second connecting holes penetrating the two side surfaces, and the two second connecting holes are coaxially arranged, and the second connecting pin 22312 passes through the second connecting hole at one end, the second hanging ring 2232 and the second connecting hole at the other end in sequence, and locks and fixes the second hanging ring 2232 and the second connecting buckle 22311.
[0053] A lifting method for the hydraulic lifting system according to an embodiment of the present invention comprises the following steps:
[0054] S1. Arrange the suspension point 12 above the installation position 300 of the structure 200 to be lifted, so that the center of the installation position 300 falls on the line connecting the two suspension points 12 under the vertical projection;
[0055] S2, the buffer device 2 and the two suspension points 12 are respectively located on opposite sides of the structure to be lifted 200, a pulling structure 22 is connected between each of the fixing members 21 and the structure to be lifted 200, and the pulling end 22121 is connected to the structure to be lifted 200;
[0056] S3, calculating the horizontal impact force generated by the structure to be lifted 200 during lifting, and setting the total pulling force generated by the retractor 221 according to the horizontal impact force;
[0057] S4, starting the lifting motor and the pulling motor at the same time, and controlling the lifting motor and the pulling motor to rotate forward;
[0058] S5, after the structure to be lifted 200 is lifted to a predetermined height, controlling the pulling motor to reverse so that the pulling end 22121 is away from the housing 2211;
[0059] S6. When the structure to be lifted 200 returns to the position directly below the projection of the installation position 300, the pulling motor is turned off;
[0060] S7, lifting the structure to be lifted 200 to the installation position 300, and shutting down the lifting motor.
[0061] Based on the above technical solution, the hydraulic lifting device 1 is arranged with the installation position 300 of the structure to be lifted as a reference, so that under the orthographic projection of the vertical direction X, the center of the installation position 300 falls on the connecting line of the two suspension points 12; and then the fixing member 21 and the pulling structure 22 are arranged so that the pulling force of the puller 221 can be applied to the structure to be lifted 200; the total pulling force generated by the puller 221 is set according to the horizontal impact force generated when the structure to be lifted 200 is lifted, and the component force of the pulling force in the horizontal direction can be the same as the horizontal impact force but opposite in direction, and the lifting motor and the pulling motor are started at the same time to avoid the structure to be lifted. 200 is horizontally offset at the moment of lifting, causing horizontal impact; after the structure to be lifted 200 is lifted to a predetermined height, in order to avoid obstacles below the projection of the installation position 300, the pulling motor is reversed to gradually reduce the pulling force applied by the puller 221 to zero, and the structure to be lifted is only subjected to the upward pulling force of the lifting rope 11, and returns to the position below the projection of the installation position 300. The pulling motor is turned off, and the lifting motor continues to drive the lifting rope 11 to lift the structure to be lifted 200 to the installation position 300, and finally the lifting motor is turned off; thereby, the non-in-situ lifting of the structure to be lifted 200 is achieved, and horizontal impact of the structure to be lifted 200 is avoided during the lifting process.
[0062] Further, in step S2, under the orthographic projection of the vertical direction X, the horizontal distance between each of the fixing parts 21 and the structure to be lifted 200 is defined as a first distance L1, and the horizontal distance between each of the hanging points 12 and the structure to be lifted 200 is defined as a second distance L2, and the first distance L1 is greater than the second distance L2; so as to prevent the pulling force applied by the puller 221 to the structure to be lifted 200 during the hydraulic lifting process from pulling the structure to be lifted 200 toward one side of the fixing part 21, and causing a collision due to the small horizontal distance between the fixing part 21 and the structure to be lifted 200.
[0063] The working process of the present invention is as follows: a hanging point 12 is set just above the installation position 300, and the two ends of the structure to be lifted 200 are respectively connected to the lifting rope 11; the fixing member 21 is set on the same side of the structure to be lifted 200, and the pulling end of the puller 221 is connected to the structure to be lifted 200, and the first hanging ring 2222 and the second hanging ring 2232 are located at the same horizontal height; and the buffer device 2 and the hanging point 12 are located on the horizontally opposite sides of the structure to be lifted 200.
[0064] The lifting motor and the pulling motor are started at the same time to lift the structure 200 to be lifted. After the structure 200 to be lifted is lifted to avoid the obstacles below the direct projection of the installation position 300, the pulling motor is reversed so that the pulling force applied by the puller to the structure 200 to be lifted is gradually reduced to zero, so that the structure 200 to be lifted slowly returns to the underside of the direct projection of the installation position 300, and the pulling motor is turned off; after the structure 200 to be lifted is lifted to the installation position 300, the lifting motor is turned off.
[0065] In summary, the embodiment of the present invention provides a hydraulic lifting system 100 and a lifting method thereof, wherein the hydraulic lifting system 100 comprises a hydraulic lifting device 1 and a buffer device 2. To facilitate lifting the structure 200 to be lifted to the installation position 300, the lifting point 12 in the hydraulic lifting device 1 is arranged directly above the installation position 300. However, this arrangement will cause the structure 200 to be lifted, which is not assembled in situ, to automatically shift horizontally to the side of the installation position 300 at the moment of lifting due to the horizontal spacing between the structure 200 and the installation position 300. To this end, the buffer device 2 and the lifting point 12 are arranged on opposite sides with the structure 200 to be lifted as the center, and a horizontal pulling force is applied to the structure 200 to be lifted by a puller 221. The horizontal pulling force applied by the puller 221 to the structure 200 to be lifted is set to be equal to the horizontal pulling force of the structure 200 to be lifted. The horizontal impact forces on the structure 200 are equal in magnitude and opposite in direction, thereby offsetting the horizontal impact forces, avoiding horizontal deviation of the structure 200 to be lifted at the lifting moment, thereby causing horizontal impact to the hydraulic lifting device 1, and thus avoiding damage to the hydraulic lifting device 1 and the structure 200 to be lifted. After the structure 200 to be lifted is lifted to a certain height to avoid obstacles that affect its in-situ assembly, the structure 200 to be lifted is slowly returned to the bottom of the installation position 300 by reversing the pulling motor, and then the structure 200 to be lifted is directly lifted to the installation position by the hydraulic lifting device 1, thereby realizing the non-in-situ lifting of the structure 200 to be lifted, and avoiding the horizontal impact of the structure 200 to be lifted during the hydraulic lifting process. Damage to the hydraulic lifting device 1 and the structure 200 to be lifted itself.
[0066] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present invention. These improvements and substitutions should also be regarded as the scope of protection of the present invention.
Claims
1. A hydraulic lifting system, characterized in that: Includes hydraulic lifting equipment and buffer devices; The hydraulic lifting device comprises two sets of lifting components arranged at intervals, and the lifting components comprise: a lifting motor, a lifting rope and a lifting point; the two lifting points are arranged at the same vertical height at intervals, the lifting rope is slidably inserted into the lifting points, the top end of the lifting rope is connected to the power output end of the lifting motor, the bottom end of the lifting rope is used to connect to the structure to be lifted, and the lifting motor can drive the bottom end of the lifting rope to move toward the direction close to the lifting point; The buffer device comprises at least two groups of buffer components, each group of buffer components is located on the same side below the hanging point, and the buffer device comprises a fixing member and A pulling structure; the pulling structure includes a puller, which includes a shell, a pulling motor and a pulling part, the pulling motor is arranged in the shell, one end of the pulling part is connected to the power output end of the pulling motor, the other end of the pulling part is a pulling end, and the pulling end is used to be connected to the structure to be lifted, and the pulling motor can drive the pulling end to be close to or away from the shell.
2. The hydraulic lifting system according to claim 1, characterized in that: The buffer device comprises two groups of buffer components, and the two groups of buffer components are respectively connected to two ends of the structure to be lifted.
3. The hydraulic lifting system according to claim 1, characterized in that: The buffer device further comprises a switch controller, which is electrically connected to each of the pulling motors and is used for simultaneously controlling each of the pulling motors to rotate forward or reversely.
4. The hydraulic lifting system according to claim 1, characterized in that: The pulling structure further includes a first connecting assembly, which includes a detachably connected first connecting member and a first hanging ring; The shell is connected to the first connecting member, and the first hanging ring is connected to the fixing member.
5. The hydraulic lifting system according to claim 4, characterized in that: The pulling structure further includes a second connecting assembly, which includes a detachably connected second connecting member and a second hanging ring; The pulling end is connected to the second connecting member, and the second hanging ring is used to connect the second connecting member to the structure to be lifted.
6. The hydraulic lifting system according to claim 5, characterized in that: The first connecting member includes a first connecting buckle and a first connecting pin; The first connecting buckle is U-shaped, and both ends of the first connecting buckle are provided with first connecting holes penetrating the two side surfaces, and the two first connecting holes are coaxially arranged, and the first connecting pin passes through the first connecting hole at one end, the first hanging ring and the first connecting hole at the other end in sequence, and locks and fixes the first hanging ring and the first connecting buckle; The second connecting member includes a second connecting buckle and a second connecting pin; The second connecting buckle is U-shaped, and both ends of the second connecting buckle are provided with second connecting holes penetrating the two side surfaces, and the two second connecting holes are coaxially arranged. The second connecting pin passes through the second connecting hole at one end, the second hanging ring and the second connecting hole at the other end in sequence, and locks and fixes the second hanging ring and the second connecting buckle.
7. A lifting method for the hydraulic lifting system according to any one of claims 1 to 6, characterized in that: The following steps are involved: S1. Arrange the suspension point above the installation position of the structure to be lifted, so that the center of the installation position falls on the line connecting the two suspension points under the vertical projection; S2, arranging the buffer device and the two lifting points to be located at opposite sides of the structure to be lifted, respectively, the pulling structure is connected between each of the fixing members and the structure to be lifted, and the pulling end is connected to the structure to be lifted; S3, calculating the horizontal impact force generated by the structure to be lifted during lifting, and setting the total pulling force generated by the retractor according to the horizontal impact force; S4, starting the lifting motor and the pulling motor at the same time, and controlling the lifting motor and the pulling motor to rotate forward; S5, after the lifting structure is lifted to a predetermined height, controlling the pulling motor to reverse and move the pulling end away from the housing; S6. When the structure to be lifted returns to below the projection of the installation position, the pulling motor is turned off; S7. Lift the structure to be lifted to the installation position and shut down the lifting motor.
8. The lifting method according to claim 7, characterized in that: In step S2, under the orthographic projection in the vertical direction, the horizontal distance between each of the fixing members and the structure to be lifted is defined as a first distance, and the horizontal distance between each of the hanging points and the structure to be lifted is defined as a second distance, and the first distance is greater than the second distance.
Citation Information
Patent Citations
Pulley assembly
CA1307783C
Indoor horizontal pipeline hoist and mount installation device
CN206580481U
Apparatus, system, and method to control torque or lateral thrust applied to a load suspended on a suspension cable
US11992444B1