Installation method of land wind power equipment

By assembling wind power equipment at a position below the ground and raising it to the installation height using fluid or solid buoyancy, the safety problem of high altitude operations during the installation of onshore wind power equipment is solved, and a safer installation process is achieved.

CN118959231APending Publication Date: 2024-11-15DENGFENG POWER SUPPLY CO OF STATE GRID HENAN ELECTRIC POWER CO +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410872172.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-01
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The safety risks caused by high altitude operations during the installation of onshore wind power equipment are high, and the existing technology is difficult to effectively reduce the dangers of lifting equipment and workers.

Method used

Assembled using a mounting height below the ground, lifting the wind power equipment to the installation height and fixing it through fluid buoyancy or solid expansion force. The specific steps include assembling in the formation of well pits on the ground, using water or airbags to provide buoyancy or support, and through The lifting equipment is lifted to the installation position, and then the installation and fixation, pumping, deflation, backfilling concrete and other operations are carried out.

Benefits of technology

It effectively reduces the safety risks of high-altitude operations, improves the safety and stability of the installation process of wind power equipment, and reduces the dangers of lifting equipment and workers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118959231A_ABST
    Figure CN118959231A_ABST
Patent Text Reader

Abstract

The invention belongs to the field of wind power, and particularly relates to an onshore wind power equipment installation method which comprises the steps that wind power equipment is assembled at the position lower than the installation height of the ground, and the wind power equipment is lifted to the installation height and is installed and fixed in a force application mode comprising at least one of fluid buoyancy and solid expansive force. Assembly is carried out at the position lower than the installation height of the ground, and the safety problem that high-altitude operation must be carried out is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the field of wind power, and belongs to the catalogue of strategic emerging industries, 6 new energy industries, 6.2 wind energy industry, 6.2.5 wind power generation technical services, specifically wind farm design and construction services, and specifically involves a method for installing onshore wind power equipment. Background Art

[0002] When assembling an onshore wind turbine tower, the foundation is designed first, and then the foundation ring, multi-section tower body, and subsequent nacelle and blades are hoisted in sequence by lifting equipment. As the multi-section tower body is hoisted and fixed, the hoisting height gradually increases. Due to the inertia generated under the lifting conditions and the harsh environmental conditions at high altitudes, the shaking and instability of the high-altitude construction is more serious, and therefore, accidents of breaking and collapse of lifting equipment during the lifting process often occur.

[0003] In the prior art, for wind turbine hoisting construction in harsh environments, the wind turbine tower itself is generally equipped with stabilizers, or the stability of the lifting equipment is improved, or the construction is carried out through the coordination of multiple lifting equipment. However, in essence, it is still high-altitude work, and the danger of hoisting and the danger to the workers performing installation work on the tower are relatively high. Summary of the invention

[0004] In order to solve the problem that high-altitude operations are relatively dangerous when installing onshore wind power equipment, the present invention provides an onshore wind power equipment installation method.

[0005] The objective of the present invention is achieved in the following manner: a method for installing an onshore wind power device, wherein the wind power device is assembled at an installation height below the ground, and the wind power device is lifted to the installation height and installed and fixed by a force application method including at least one of fluid buoyancy or solid expansion force.

[0006] Furthermore, the assembling at a position below the installation height on the ground refers to forming a pit 1 from the ground downwards, and the components of the wind power equipment are assembled in the pit 1 .

[0007] Furthermore, the wind power equipment includes a tower body 2, a nacelle 21, and blades 22. The difference between the depth of the pit 1 and the height of the tower body 2 is equal to the length of the blade 22 plus L, and L≥3000mm.

[0008] Furthermore, the fluid buoyancy refers to the provision of water in the well pit 1 to provide a force for the wind power equipment to rise through the water buoyancy.

[0009] Furthermore, the solid expansion force refers to providing at least one layer of airbags 3 at the bottom of the pit 1, and providing a force to support the wind power equipment to rise by inflating the airbags 3.

[0010] Furthermore, the installation method comprises the following steps: S1, forming a well pit 1 based on digging under the ground; S2, lowering a support member 11 that matches the well pit 1 into the well pit 1; S3, a hard structure 4 is arranged on the ground around the top of the support member 11; S4. An uninflated airbag 3 is arranged at the bottom of the pit 1, the airbag 3 is connected to one end of an air pipe, and the other end of the air pipe extends out of the pit 1 and is connected to an air supply mechanism; S5, hoisting a foundation ring 23 for forming the bottom of the tower body 2 into the well pit 1, and placing the foundation ring 23 above the air bag 3; S6, hoisting the tower 24 used to form the tower body 2 into the pit 1, installing and fixing the tower 24 and the foundation ring 23, and further hoisting other towers 24, the nacelle 21, and the blades 22 and installing them to form a complete wind power equipment; S7, pouring water into the well pit 1, and inflating the airbag 3 at the same time, keeping the water level above the top of the airbag 3, and lifting the wind turbine equipment by lifting equipment; S8, the wind power equipment is raised to the installation height, the installation plate 5 is installed and fixed between the base ring 23, and the installation plate 5 is installed and fixed between the hard structure 4; S9, pumping water out of the well pit 1, deflation of the air bag 3 and taking out the well pit 1; S10, pouring concrete 8 into the well pit 1 to fill it.

[0011] Furthermore, the support member 11 is a tube; The hard structure 4 in S2 is a steel plate or a concrete structure; There are multiple airbags 3, and the multiple airbags 3 are stacked; Add S7.1: When the wind turbine is rising, a hoop 6 is fixed on the tower body 2, and at least one side of the hoop 6 extends out of an anchor 61 to be anchored to the ground; In S8, the mounting plate 5 is formed by splicing a plurality of sector-shaped plates to form a 1 / 2 to 3 / 4 sector-shaped structure, and after S10, the sector-shaped structure is completed to form a circular ring structure; Add S9.1: Backfill the pit 1 with original soil to a height of 54000mm~10000mm from the installation plate.

[0012] Compared with the prior art, the present invention performs assembly at a location below the installation height on the ground, thereby solving the safety problem of having to perform operations at high altitudes. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is a structural diagram of the pit formed during the construction of onshore wind power equipment; Figure 2It is a schematic diagram of the structure of sending air bags into the pit and hoisting the foundation ring into it during the construction of onshore wind power equipment; Figure 3 It is a structural diagram of the tower body being hoisted during the construction of onshore wind power equipment; Figure 4 It is a structural schematic diagram of the wind power equipment assembled during the construction of onshore wind power equipment; Figure 5 It is a structural schematic diagram of the airbag combined with the lifting equipment to lift the wind power equipment to the installation height during the construction of the onshore wind power equipment; Figure 6 It is a schematic diagram of the structure for fixing the wind power equipment during the construction of onshore wind power equipment; Figure 7 It is a schematic diagram of the structure of the bottom of the wind power equipment when the construction of the onshore wind power equipment is completed; Figure 8 It is a top-down cross-sectional view of onshore wind power equipment during construction; Fig. 9 It is a structural diagram of the well pit formed during the construction of offshore wind power equipment; Fig.10 It is a structural diagram of the tower body being hoisted during the construction of offshore wind power equipment; Fig.11 It is a structural schematic diagram of the airbag combined with the lifting equipment to lift the wind power equipment to the installation height during the construction of the offshore wind power equipment; Fig.12 It is a structural diagram of the wind power equipment when the offshore wind power equipment is about to be completed.

[0014] Among them, there are the well pit 1, the support 11, the tower body 2, the nacelle 21, the blades 22, the foundation ring 23, the tower 24, the airbag 3, the hard structure 4, the mounting plate 5, the hoop 6, the anchor 61, the steel mesh 7, and the poured concrete 8. DETAILED DESCRIPTION

[0015] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0016] In the present invention, unless otherwise clearly stipulated and limited, the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.

[0017] As attached Figure 1-8 As shown, a method for installing an onshore wind power equipment is provided, wherein the wind power equipment is assembled at an installation height below the ground, and the wind power equipment is lifted to the installation height and installed and fixed by applying a force including at least one of fluid buoyancy or solid expansion force.

[0018] The assembly is performed at a location below the ground level, thus resolving the safety issue of having to perform work at height.

[0019] Further, such as Figure 1 As shown, the assembly at a position below the installation height on the ground refers to forming a pit 1 from the ground downwards, and the components of the wind power equipment are assembled in the pit 1 .

[0020] Further, such as Figure 4 As shown, the wind power equipment includes a tower body 2, a nacelle 21, and blades 22. The difference between the depth of the pit 1 and the height of the tower body 2 is equal to the length of the blade 22 plus L, L≥3000mm, and preferably, L is less than or equal to 10000mm. The purpose of limiting the minimum value of L is that the pit 1 should not be too deep. On the one hand, deep digging will increase the cost and reduce the safety factor. On the other hand, when hoisting and installing the blade 22, the blade 22 body does not interfere with the ground, resulting in the possibility of damage to the blade. The purpose of limiting the maximum value of L is that if the pit 1 is too shallow, the hoisting and installation position of the upper structure of the wind power equipment will still be too high.

[0021] Furthermore, the fluid buoyancy refers to providing water in the pit 1 to provide a force for the wind turbine to rise by the water buoyancy, and the solid expansion force refers to providing at least one layer of airbags 3 at the bottom of the pit 1 to provide a force to support the wind turbine to rise by inflating the airbags 3. Preferably, as Figure 5 As shown, the two are used in combination.

[0022] Based on the above description, a method for installing and constructing onshore wind power equipment is formed, and the installation method comprises the following steps: S1, such as Figure 1As shown, a well pit 1 is formed based on digging under the ground; S2. A support member 11 matching with the well pit 1 is lowered into the well pit 1. The support member 11 is a pipe body, and further, a steel pipe or a reinforced concrete pipe body, which is formed by stacking multiple sections of pipe bodies up and down. The support member 11 is sequentially hoisted and sent into the well pit, and finally serves as a deep buried pile foundation of the entire wind power equipment after the construction is completed. S3. A hard structure 4 is arranged on the ground around the top of the support member 11. The hard structure 4 is a steel plate or a concrete structure. For onshore wind power equipment, it is preferably a reinforced concrete structure, which is formed by pre-digging a foundation pit, tying steel bars in the foundation pit and pouring concrete. Preferably, the support member 11 and the hard structure 4 are combined into one (for steel structure welding and concrete structure, refer to other existing technologies); It is determined according to the working conditions whether to pour a layer of concrete structure at the bottom of the pit 1 to level the bottom of the pit and prevent excessive water seepage in the pit during the initial lifting and installation process.

[0023] S4, such as Figure 2 As shown, an uninflated airbag 3 is arranged at the bottom of the pit 1, the airbag 3 is connected to one end of the air pipe, the other end of the air pipe extends out of the pit 1 and is connected to the air supply mechanism, in detail, there are multiple airbags 3, the multiple airbags 3 are stacked, the multi-layer airbags 3 are integrally formed, or the sides of the airbags 3 are glued or hot-melt welded, and the air supply pipes of the multiple airbags 3 extend out of the pit 1 and are supplied with air through an air compressor; S5. A foundation ring 23 for forming the bottom of the tower body 2 is hoisted into the pit 1, and the foundation ring 23 is placed above the airbag 3. According to the working conditions, a support plate is set in advance between the top of the stacked airbag 3 and the foundation ring 23 to prevent the airbag 3 from being damaged due to excessive pressure during subsequent airbag support. S6, such as Figure 3 , 4 As shown, a tower 24 for forming a tower body 2 is hoisted into the pit 1, the tower 24 and the foundation ring 23 are fixedly installed, and other towers 24, a nacelle 21, and blades 22 are further hoisted and installed to form a complete wind power equipment. The installation of the tower 24, the foundation ring 23, the nacelle 21, and the blades 22 belongs to the prior art and will not be repeated here; S7, such as Figure 5 As shown, water is poured into the well 1, and air is inflated into the airbag 3 at the same time, so that the water surface is kept above the top of the airbag 3, and the wind turbine is hoisted by a lifting device. The lifting device provides part of the pulling force on the one hand, and mainly plays a guiding role on the other hand; S7.1: If Figure 6 As shown, when the wind turbine is rising, a hoop 6 is fixed on the tower body 2, and at least one side of the hoop 6 extends outward to be anchored to the ground. Preferably, at least four cables extend outward from the periphery of each hoop 6, and the ends of the cables are fixed to the ground with the anchors 61, and the cables are tightened to maintain lateral stability. S8, such as Figure 8 As shown, the wind power equipment rises to the installation height, and the installation disk 5 is installed and fixed between the base ring 23, and the installation disk 5 is installed and fixed between the hard structure 4. The installation disk 5 is a 1 / 2~3 / 4 fan-shaped structure formed by splicing a plurality of fan-shaped plates, which is used to leave space for subsequent processing. After S10, the fan-shaped structure is completed to form a circular ring structure. In detail, the installation disk 5 includes a fan-shaped disk body, and the inner end of the fan-shaped disk body extends upwardly with a boss that cooperates with the base ring 23. The boss is provided with a mounting hole structure corresponding to the base ring 23, and the two are fixed through the mounting hole; S9, pumping water out of the well pit 1, deflation of the air bag 3 and taking out the well pit 1; S9.1, if Figure 7 As shown, the well pit 1 is backfilled with original soil and compacted to a height of 54000mm to 10000mm from the installation plate. The onshore wind power equipment itself relies on the deep pile structure of the tubular support 11 to be relatively stable, so the lower part of the original soil can be backfilled; S10, pour concrete 8 into the pit 1 to fill it up, the hoisting part of the wind power equipment is installed, and then the electrical equipment in the tower is installed and debugged.

[0024] A low-position onshore wind power equipment, the wind power equipment includes a tower body 2, a foundation ring 23 is fixed at the bottom of the tower body 2, mounting holes are arranged in an array around the foundation ring 23, and the outside of the foundation ring 23 is fixedly connected to a mounting plate 5 through the mounting holes; a tubular support member 11 is arranged below the mounting plate 5, the support member 11 is buried under the ground, an original soil layer is arranged below the support member 11, a concrete layer is arranged between the original soil layer and the mounting plate 5, a hard structure 4 is arranged on the ground around the top of the support member 11, and the hard structure 4 is fixedly connected to the mounting plate 5.

[0025] Furthermore, the hard structure 4 is a concrete layer, and the hard structure 4 and the mounting plate 5 are fixed by vertical piles that pass through the mounting plate 5 and the hard structure 4 in sequence and extend into the soil layer below the hard structure 4.

[0026] As attached Figure 9-12 As shown, a method for installing an above-water wind power equipment is provided, wherein the wind power equipment is assembled at an installation height lower than the bottom of the water, and the wind power equipment is lifted to the installation height and installed and fixed by the buoyancy of the water body itself combined with the expansion force of the solid.

[0027] Furthermore, the assembling at a position lower than the installation height refers to forming a pit 1 downward from the water bottom, and the components of the wind power equipment are assembled in the pit 1.

[0028] Further, such as Fig.10As shown, the wind power equipment includes a tower body 2, a cabin 21, and blades 22. The sum of the depth of the pit 1, the water depth and H is equal to the height of the tower body 2, ≥5000mm, and preferably, H is less than or equal to 10000mm. The purpose of limiting the minimum value of H is that the pit 1 should not be too deep. On the one hand, deep excavation will increase the cost and reduce the safety factor. On the other hand, too low a depth may cause the cabin 21 to enter water during the assembly process. The purpose of limiting the maximum value of H is that if the pit 1 is too shallow, the hoisting and installation position of the upper structure of the wind power equipment will still be too high.

[0029] Furthermore, the buoyancy of the water body itself combined with the solid expansion force means that at least one layer of airbags 3 is set at the bottom of the pit 1. The supporting force formed by inflating the airbags 3 combined with the water buoyancy provides a force to support the rise of the wind power equipment. The structure of the airbags 3 refers to the above-mentioned onshore wind power equipment and will not be repeated here.

[0030] Based on the above description, a method for installing a waterborne wind power equipment is formed, characterized in that: the installation method comprises the following steps: S1, such as Fig. 9 As shown, a well pit 1 is formed by digging under the water bottom in underwater operation; S2. A support member 11 matching with the well pit 1 is lowered into the well pit 1. The support member 11 is a steel cage. Compared with onshore wind power equipment, the steel cage is lighter and easier to set up during underwater operation, and there is no need to consider the water blocking capacity preferred during the installation of onshore equipment; S3, a hard structure 4 is arranged on the ground around the top of the support member 11, the hard structure 4 is a steel plate, and the steel plate and the steel cage are preferably fixed by underwater arc welding; S4. An uninflated airbag 3 is arranged at the bottom of the pit 1. The airbag 3 is connected to one end of an air pipe. The other end of the air pipe extends out of the pit 1 and is connected to an air supply mechanism. There are multiple airbags 3. The multiple airbags 3 are stacked and arranged. The multiple airbags 3 are integrally formed, or the sides of the airbags 3 are glued or hot-melt welded. The air supply pipes of the multiple airbags 3 extend out of the pit 1 to the lifting ship or floating platform where the lifting equipment is located and supply air through an air compressor. S5. A foundation ring 23 for forming the bottom of the tower body 2 is hoisted into the pit 1, and the foundation ring 23 is placed above the airbag 3. According to the working conditions, a support plate is set in advance between the top of the stacked airbag 3 and the foundation ring 23 to prevent the airbag 3 from being damaged due to excessive pressure during subsequent airbag support. S6, such as Fig.10 As shown, a tower 24 for forming a tower body 2 is hoisted into the pit 1, the tower 24 and the foundation ring 23 are fixedly installed, and other towers 24, a nacelle 21, and blades 22 are further hoisted and installed to form a complete wind power equipment. The installation of the tower 24, the foundation ring 23, the nacelle 21, and the blades 22 belongs to the prior art and will not be repeated here; S7, such as Fig.11 As shown, the airbag 3 is inflated, and at the same time, the wind turbine is lifted by a lifting device, which provides part of the pulling force on the one hand and mainly plays a guiding role on the other hand; S7.1, if Fig.12 As shown, when the wind turbine is rising, a hoop 6 is fixed on the tower body 2, and the hoop 6 extends out of the anchor 61 to be fixed to the floating bodies in the anchored state on at least two sides. The floating bodies in the anchored state can be a crane ship including a lifting device, or a floating platform with a certain mass that can maintain stability. Preferably, a cable is extended from at least two opposite sides of each hoop 6, and the ends of the cables are fixed to the anchor 61 and fixed to the floating body, and the cables are tightened to maintain lateral stability. S8, the wind power equipment is raised to the installation height, and the installation plate 5 is installed and fixed between the base ring 23, and the installation plate 5 is installed and fixed between the hard structure 4. The installation plate 5 is a 1 / 2 to 3 / 4 fan-shaped structure formed by splicing a plurality of fan-shaped plates. After S10, the fan-shaped structure is completed to form a circular ring structure; S9, deflate the airbag 3 and remove the well 1; S9.1. Tie and fix the steel mesh 7 below the foundation ring 23. Preferably, the transverse reinforcement in the steel mesh 7 extends laterally to the support member 11. The support member 11 is a steel cage. The transverse reinforcement and the steel cage are tied and fixed to form a whole, thereby improving the overall stability. S10, pouring underwater concrete 8 in the pit 1 to form underwater concrete to fill the pit. Compared with onshore wind power equipment, the cost is higher, but it is difficult to backfill the original soil underwater, and the structure is loose, which is not conducive to structural stability.

[0031] A water-based wind power equipment, the wind power equipment comprising a tower body 2, a foundation ring 23 is fixed at the bottom of the tower body 2, mounting holes are arranged in an array around the foundation ring 23, the outside of the foundation ring 23 is fixedly connected to a mounting plate 5 through the mounting holes, and a steel mesh 7 is fixedly connected to the bottom of the mounting plate 5; a tubular support member 11 is arranged below the mounting plate 5, the support member 11 is buried under the bottom of the water, a concrete layer is arranged inside the support member 11, the concrete layer covers the steel mesh 7, a hard structure 4 is arranged on the ground around the top of the support member 11, and the hard structure 4 is fixedly connected to the mounting plate 5.

[0032] Furthermore, the hard structure 4 is a steel plate, the hard structure 4 and the support member 11 are fixed by bolts or welding, and the hard structure 4 and the mounting plate 5 are fixed by bolts or welding.

[0033] The above is only a preferred embodiment of the present invention. It should be pointed out that for those skilled in the art, several changes and improvements can be made without departing from the overall concept of the present invention, which should also be regarded as the scope of protection of the present invention.

Claims

1. A method for installing onshore wind power equipment, characterized in that: The installation method is that the wind power equipment is assembled at an installation height below the ground, and the wind power equipment is lifted to the installation height and installed and fixed by a force application method including at least one of fluid buoyancy or solid expansion force.

2. The onshore wind power equipment installation method according to claim 1, characterized in that: The assembly at a position below the installation height on the ground refers to forming a pit (1) from the ground downwards, and the components of the wind power equipment are assembled in the pit (1).

3. The onshore wind power equipment installation method according to claim 2, characterized in that: The wind power equipment comprises a tower body (2), a nacelle (21), and blades (22); the difference between the depth of the well pit (1) and the height of the tower body (2) is equal to the length of the blade (22) plus L, where L is ≥ 3000 mm.

4. The onshore wind power equipment installation method according to claim 2, characterized in that: The fluid buoyancy refers to the provision of water in the well pit (1) to provide a force for the wind power equipment to rise through the water buoyancy.

5. The onshore wind power equipment installation method according to claim 2, characterized in that: The solid expansion force refers to providing a force to support the wind power equipment to rise by providing at least one layer of air bags (3) at the bottom of the pit (1) and inflating the air bags (3).

6. A method for installing an onshore wind power equipment according to any one of claims 1 to 5, characterized in that: The installation method comprises the following steps: S1, forming a well pit (1) by digging under the ground; S2, lowering a support member (11) that matches the well pit (1) into the well pit (1); S3, setting a hard structure (4) on the ground around the top side of the support member (11); S4. An uninflated airbag (3) is arranged at the bottom of the well pit (1), wherein the airbag (3) is connected to one end of an air pipe, and the other end of the air pipe extends out of the well pit (1) and is connected to an air supply mechanism; S5, hoisting a foundation ring (23) for forming the bottom of the tower body (2) into the well pit (1), and placing the foundation ring (23) above the air bag (3); S6, hoisting a tower cylinder (24) for constituting a tower body (2) into the well pit (1), installing and fixing the tower cylinder (24) and the foundation ring (23), and further hoisting other tower cylinders (24), a nacelle (21), and blades (22) into and installing them to form a complete wind power equipment; S7, pouring water into the well pit (1), and at the same time inflating the airbag (3) to keep the water level above the top of the airbag (3), and at the same time lifting the wind turbine equipment by means of a lifting device; S8, the wind power equipment is raised to the installation height, the installation plate (5) is installed and fixed to the base ring (23), and the installation plate (5) is installed and fixed to the hard structure (4); S9, pumping water out of the well pit (1), deflation of the air bag (3) and removal of the well pit (1); S10, pouring concrete (8) into the well pit (1) to fill it.

7. A method for installing onshore wind power equipment according to claim 6, characterized in that: The support member (11) is a tube body; In S2, the hard structure (4) is a steel plate or concrete structure; There are multiple airbags (3), and the multiple airbags (3) are stacked. Add S7.1: When the wind turbine is rising, a hoop (6) is fixed on the tower body (2), and at least one side of the hoop (6) extends out of an anchor (61) and is anchored to the ground; In S8, the mounting plate (5) is formed by splicing a plurality of sector-shaped plates to form a 1 / 2 to 3 / 4 sector-shaped structure, and after S10, the sector-shaped structure is completed to form a circular ring structure; Add S9.1: Backfill the pit (1) with original soil to a height of 4000 mm to 10000 mm from the mounting plate (5).