Engineering budget management method, device and equipment and readable storage medium

By acquiring the sub-project packages and key nodes of the project, and using a neural network model to compare the actual progress with the ideal progress, the problem of close connection between project assets, equipment, and materials was solved, enabling timely and lean financial management during the construction process and resolving the issue of fund transfer.

CN118966601AInactive Publication Date: 2024-11-15CHINA THREE GORGES CORPORATION
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202410927656.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-11
Publication Date
2024-11-15
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The lack of close connection between engineering assets, equipment, and materials in existing technologies makes it impossible to detect fund transfer issues in a timely manner during construction, and thus hinders the realization of lean and dynamic management of engineering finances.

Method used

By acquiring the sub-project packages and their key milestones of the project, and using a neural network model to compare the actual progress with the ideal progress, it is determined whether the target key milestones have been reached, the project budget is approved, and the remaining budget is allowed to be disbursed when the project milestones are reached.

Benefits of technology

It has achieved a close connection between project assets, equipment, and materials, enabling timely detection of changes in funds, solving the problem of fund transfer during construction, and realizing lean and dynamic management of project finances.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118966601A_ABST
    Figure CN118966601A_ABST
Patent Text Reader

Abstract

The invention discloses a project budget management method, apparatus and device, and a readable storage medium. The method comprises the steps of obtaining a sub-project package of a project project and each key node of the sub-project package; comparing the actual project progress of the sub-project corresponding to the sub-project package in the current preset time period with an ideal progress list to obtain a comparison result; if a sub-project corresponding to the sub-project package has a target key node associated with budget deduction in the actual project progress of the current preset time period, determining whether the sub-project package reaches the target key node based on the comparison result, if the sub-project package reaches the target key node, approving deduction of the corresponding project budget, and if the sub-project package reaches the target key node, approving deduction of the corresponding project budget. According to the invention, close connection among engineering assets, equipment and materials is realized, change of funds can be found in time, and the technical problem that various possible fund transfer problems in the construction process cannot be found in time in the related technology is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of engineering project management, and in particular to a management method, device, equipment and readable storage medium for an engineering budget. Background Art

[0002] The focus of management work is to complete the construction task in the most economical way within the specified construction period and budget. At present, the management method of post-settlement is mainly used for the management of the construction process. However, there is no close connection between engineering assets, equipment and materials, which makes it impossible to intuitively understand the linkage relationship between the three. The huge amount of funds and data is not in line with the requirements of lean and dynamic management of engineering finance. It is impossible to discover various fund transfer problems that may occur during the construction process in a timely manner. Summary of the invention

[0003] In view of the above technical problems, the present invention provides a project budget management method, device, equipment and readable storage medium.

[0004] To achieve the above object, the present invention provides the following technical solutions:

[0005] In a first aspect, an embodiment of the present invention provides a method for managing a project budget, the method comprising:

[0006] Get the sub-project packages of the project and each key node of the sub-project packages;

[0007] Compare the actual project progress of the sub-project corresponding to the sub-project package in the current preset period with the ideal progress table to obtain a comparison result;

[0008] If the sub-project corresponding to the sub-project package has a target key node associated with budget allocation in the actual project progress of the current preset period, then based on the comparison result, determine whether the sub-project package has reached the target key node;

[0009] If the key target nodes are achieved, the corresponding project budget will be approved and allocated.

[0010] In combination with the first aspect, in one implementation, the step of obtaining the sub-project packages of the project and each key node of the sub-project packages includes:

[0011] Obtain each sub-project package of the project engineering decomposed according to the engineering contract information;

[0012] The construction acceptance result data of each sub-project package of similar project engineering is used as training samples to train the neural network model;

[0013] Through the trained neural network model, the key nodes of each sub-project package are determined.

[0014] In combination with the first aspect, in one embodiment, after the step of comparing the actual project progress of the sub-project corresponding to the sub-project package in the current preset period with the ideal schedule to obtain the comparison result, the method includes:

[0015] If the sub-project corresponding to the sub-project package does not have a target key node for associated budget allocation in the actual project progress of the current preset time period, then take the next preset time period as the current preset time period, return to execute the step of comparing the actual project progress of the sub-project corresponding to the sub-project package in the current preset time period with the ideal schedule to obtain the comparison result.

[0016] In conjunction with the first aspect, in one implementation, after the step of approving the corresponding engineering budget if the target key node is reached, the method further includes:

[0017] Get the project milestones of the sub-project packages;

[0018] Detecting whether the actual progress of the sub-project corresponding to the sub-project package has reached the project milestone;

[0019] If the project milestone is reached, the remaining budget specified in the sub-project package will be allowed to be allocated.

[0020] In conjunction with the first aspect, in one embodiment, after the step of allowing the entire remaining budget specified in the sub-project package to be allocated if the project milestone is reached, the following steps are included:

[0021] Obtain any sub-project package that has not been obtained from each sub-project package corresponding to the project project, as well as each key node and project milestone of any sub-project package;

[0022] Return to the step of comparing the actual project progress of the sub-project corresponding to the sub-project package with the ideal progress to obtain the comparison result, until all sub-project packages in each sub-project package corresponding to the project project have been obtained, or the budget corresponding to the project project is zero.

[0023] In a second aspect, an embodiment of the present invention provides a device for managing a project budget, the device comprising:

[0024] An acquisition module is configured to acquire sub-project packages of a project and key nodes of the sub-project packages;

[0025] A comparison module is configured to compare the actual progress of the sub-project corresponding to the sub-project package in the current preset period with the ideal progress to obtain a comparison result;

[0026] An information determination module is configured to determine, based on the comparison result, whether the actual progress of the sub-project corresponding to the sub-project package in the current preset period has reached the target key node if there is a target key node associated with budget allocation in the current preset period;

[0027] The budget disbursement module is configured to approve the disbursement of the corresponding project budget if the target key node is reached.

[0028] In conjunction with the second aspect, in one implementation, the budget allocation module is further configured to:

[0029] Get the project milestones of the sub-project packages;

[0030] Detecting whether the actual progress of the sub-project corresponding to the sub-project package has reached the project milestone;

[0031] If the project milestone is reached, the remaining budget specified in the sub-project package will be allowed to be allocated.

[0032] In a third aspect, an embodiment of the present invention further provides an electronic device, comprising: a memory, a processor; the processor is used to read and execute a computer program stored in the memory to implement the steps of the aforementioned project budget management method.

[0033] In a fourth aspect, an embodiment of the present invention further provides a computer storage medium, wherein the computer storage medium stores computer executable instructions, and the computer executable instructions, when executed, implement the steps of the aforementioned method for managing engineering budgets.

[0034] In a fifth aspect, an embodiment of the present invention further provides a computer program product, including a computer program / instruction, which, when executed by a processor, implements the steps of the aforementioned method for managing an engineering budget.

[0035] The beneficial effects brought by the technical solution provided by the embodiment of the present invention include:

[0036] Obtain the sub-project packages of the project engineering and each key node of the sub-project package; compare the actual engineering progress of the sub-project corresponding to the sub-project package in the current preset time period with the ideal schedule to obtain a comparison result; if the sub-project corresponding to the sub-project package has a target key node for associated budget allocation in the actual engineering progress of the sub-project in the current preset time period, then based on the comparison result, determine whether the sub-project package has reached the target key node; if it has reached the target key node, approve the corresponding engineering budget, thereby achieving a close connection between engineering assets and equipment and materials, and being able to discover changes in funds in a timely manner. Through the present invention, the technical problem of being unable to discover in a timely manner various fund transfer problems that may occur during the construction process in the related technology is solved. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0038] Figure 1 It is a flow chart of a first embodiment of a method for managing a project budget of the present invention;

[0039] Figure 2 It is a flow chart of a second embodiment of the method for managing project budget of the present invention;

[0040] Figure 3 It is a flow chart of a third embodiment of the project budget management method of the present invention;

[0041] Figure 4 A schematic diagram of functional modules of an embodiment of a management device for project budget of the present invention;

[0042] Figure 5 The figure is a schematic diagram of the structure of an electronic device according to an embodiment of the present invention. DETAILED DESCRIPTION

[0043] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0044] To make the objectives, technical solutions and advantages of the present invention more clear, the embodiments of the present invention will be described in detail below with reference to the accompanying drawings.

[0045] In a first aspect, an embodiment of the present invention provides a method for managing a project budget.

[0046] In one embodiment, referring to Figure 1 , Figure 1 FIG. 1 is a flow chart of the first embodiment of the project budget management method of the present invention. Figure 1 As shown in the figure, the management methods of engineering budget include:

[0047] Step S10, obtaining the sub-project packages of the project and each key node of the sub-project packages;

[0048] In some specific embodiments, step S10 includes:

[0049] Obtain each sub-project package of the project engineering decomposed according to the engineering contract information;

[0050] The construction acceptance result data of each sub-project package of similar project engineering is used as training samples to train the neural network model;

[0051] Through the trained neural network model, the key nodes of each sub-project package are determined.

[0052] In this embodiment, the engineering contract is read from the database, and the project is decomposed according to the engineering contract information to obtain the various sub-project packages of the project. That is, the control system obtains the key nodes and project milestones of the project according to the engineering contract information, and then divides the entire project into multiple sub-project packages based on the key nodes and project milestones of the project. Among them, each sub-project package starts or ends with the key nodes and project milestones of the project.

[0053] The construction acceptance result data of each sub-project package of a similar project is obtained, and the construction acceptance result data of each sub-project package of a similar project is used as a training sample to train the neural network model to obtain a trained neural network model. It is easy to imagine that the construction acceptance result data includes each key node of each sub-project package of a similar project.

[0054] By inputting the information of each sub-project package into the trained neural network model, the key nodes corresponding to each sub-project package output by the trained neural network model can be obtained.

[0055] Step S20, comparing the actual project progress of the sub-project corresponding to the sub-project package in the current preset period with the ideal progress table to obtain a comparison result;

[0056] In this embodiment, taking 9:00 to 9:30 as an example for the current preset time period, the actual project progress of the sub-project corresponding to the sub-project package of the project project from 9:00 to 9:30 is compared with the ideal schedule of the sub-project corresponding to the sub-project package of the project project to obtain a comparison result, that is, the ideal progress corresponding to the actual project progress of the sub-project corresponding to the sub-project package in the current preset time period.

[0057] Step S30, if the sub-project corresponding to the sub-project package has a target key node associated with budget allocation in the actual project progress of the current preset period, then based on the comparison result, determine whether the sub-project package has reached the target key node;

[0058] In this embodiment, if the actual project progress of the sub-project corresponding to the sub-project package in the time period from 9:00 to 9:30 has a target key node for the associated budget allocation, then based on the ideal progress corresponding to the actual project progress of the sub-project corresponding to the sub-project package in the current preset time period, it is determined whether the sub-project package has reached the target key node for the associated budget allocation.

[0059] Step S40: if the target key node is reached, the corresponding project budget is approved for payment.

[0060] In this embodiment, if the sub-project package reaches the target key node of the associated budget allocation, it means that the sub-project package has reached the node where payment is required, and the corresponding project budget is approved for allocation, thereby achieving a close connection between project assets and equipment and materials, and being able to detect changes in funds in a timely manner.

[0061] In this embodiment, the sub-project packages of the project project and the various key nodes of the sub-project packages are obtained; the actual project progress of the sub-project corresponding to the sub-project package in the current preset time period is compared with the ideal schedule to obtain a comparison result; if the sub-project corresponding to the sub-project package has a target key node for associated budget allocation in the actual project progress of the sub-project in the current preset time period, then based on the comparison result, it is determined whether the sub-project package has reached the target key node; if it has reached the target key node, the corresponding project budget is approved for allocation, thereby achieving a close connection between project assets and equipment and materials, and being able to discover changes in funds in a timely manner. Through this embodiment, the technical problem of being unable to discover in a timely manner various fund transfer problems that may occur during the construction process in the related technology is solved.

[0062] Optionally, in one embodiment, after step S20, the following steps are included:

[0063] If the sub-project corresponding to the sub-project package does not have a target key node for associated budget allocation in the actual project progress of the current preset time period, then take the next preset time period as the current preset time period, return to execute the step of comparing the actual project progress of the sub-project corresponding to the sub-project package in the current preset time period with the ideal schedule to obtain the comparison result.

[0064] In this embodiment, if the sub-project corresponding to the sub-project package does not have a target key node associated with the budget allocation in the actual project progress of the current preset period, it means that the sub-project package has not reached the node to be paid, and then continue to detect whether the sub-project package has reached the node to be paid in the next preset period, that is, take the next preset period as the current preset period, and return to the step of comparing the actual project progress of the sub-project corresponding to the sub-project package in the current preset period with the ideal schedule to obtain the comparison result. That is, if the sub-project package has not reached the node to be paid, no change in the transfer of funds will be generated.

[0065] Optionally, in one embodiment, referring to Figure 2 , Figure 2 FIG. 2 is a flow chart of the second embodiment of the project budget management method of the present invention. Figure 2 As shown, after step S40, the following steps are included:

[0066] Step S50, obtaining the project milestone of the sub-project package;

[0067] Step S60, detecting whether the actual progress of the sub-project corresponding to the sub-project package has reached the project milestone;

[0068] Step S70: If the project milestone is reached, the remaining budget specified in the sub-project package is allowed to be allocated.

[0069] In this embodiment, the construction acceptance result data also includes the engineering milestones of each sub-project package of similar project engineering. By inputting the information of each sub-project package into the trained neural network model, the engineering milestones corresponding to each sub-project package output by the trained neural network model can be obtained.

[0070] Milestones include: milestone groups, milestone items, milestone group identification codes, and milestone group and contract associations. Milestone group identification codes include classification codes that indicate the status of milestone completion, such as completion status that has been inspected and accepted, and its technical status is at a specific evaluation level between a predetermined upper limit and a predetermined lower limit.

[0071] Milestone group: a collection of milestone items. There is a one-to-many relationship between milestone groups and milestone items. In electromechanical installation contracts, milestone groups are mainly used to summarize the amount and represent a project sub-item. A milestone group corresponds to multiple sub-projects, each sub-project corresponds to a specific budget amount, and the milestone group corresponds to the total amount.

[0072] Milestone Item: A milestone item is a series of data belonging to a contract milestone group, which divides the milestone group into several sub-items. In a mechanical and electrical installation contract, a milestone item is a representation of the progress of each sub-item.

[0073] Contract settlement by milestone is a supplement to the contract settlement function. Milestone settlement is not only applicable to construction contract settlement, but also to design contracts, procurement contracts and contract settlement itself, and can establish a good relationship with the plan, making the cash flow calculation more realistic. The two routes of settlement based on the bill of quantities and the contract progress milestones also strengthen the connection with the project plan, including procurement contracts, service contracts and administrative contracts for recording internal costs, and establish a corresponding relationship between each sub-item of the project and the project budget, engineering equipment and construction materials.

[0074] Optionally, in one embodiment, referring to Figure 3 , Figure 3 FIG. 2 is a flow chart of a second embodiment of the project budget management method of the present invention. Figure 3 As shown, after step S70, the following steps are included:

[0075] Step S80, obtaining any sub-project package that has not been obtained from each sub-project package corresponding to the project project and each key node and project milestone of the sub-project package;

[0076] Step S90, returning to the step of comparing the actual progress of the sub-project corresponding to the sub-project package with the ideal progress to obtain the comparison result, until all sub-project packages in each sub-project package corresponding to the project project have been obtained, or the budget corresponding to the project project is zero.

[0077] In this embodiment, if the sub-project packages corresponding to the project engineering include sub-project package A, sub-project package B, sub-project package C and sub-project package D, if sub-project package A is obtained in step S10, any sub-project package is selected from sub-project package B, sub-project package C and sub-project package D that have never been obtained, and if any of the selected sub-project packages is sub-project package C, sub-project package C and each key node and engineering milestone of sub-project package C are obtained. At this time, sub-project package C is re-tested, that is, sub-project package C is used as sub-project package A, and step S10 and subsequent steps are returned to execute until all sub-project packages in the sub-project packages corresponding to the project engineering have been obtained, or the budget corresponding to the project engineering is zero, and then the loop ends.

[0078] In a second aspect, an embodiment of the present invention further provides a device for managing a project budget.

[0079] In one embodiment, referring to Figure 4 , Figure 4 Schematic diagram of functional modules of an embodiment of a project budget management device of the present invention. Figure 4 As shown, the management device of the project budget includes:

[0080] The acquisition module 10 is configured to acquire the sub-project packages of the project and each key node of the sub-project packages;

[0081] The comparison module 20 is configured to compare the actual progress of the sub-project corresponding to the sub-project package in the current preset period with the ideal progress to obtain a comparison result;

[0082] The information determination module 30 is configured to determine whether the actual progress of the sub-project corresponding to the sub-project package in the current preset period has reached the target key node if there is a target key node associated with budget allocation in the current preset period based on the comparison result;

[0083] The budget disbursement module 40 is configured to approve the disbursement of the corresponding project budget if the target key node is reached.

[0084] Optionally, in one embodiment, the acquisition module 10 is configured to:

[0085] Obtain each sub-project package of the project engineering decomposed according to the engineering contract information;

[0086] The construction acceptance result data of each sub-project package of similar project engineering is used as training samples to train the neural network model;

[0087] Through the trained neural network model, the key nodes of each sub-project package are determined.

[0088] Optionally, in one embodiment, the project budget management device further includes a circulation module configured to:

[0089] If the sub-project corresponding to the sub-project package does not have a target key node for associated budget allocation in the actual project progress of the current preset time period, then take the next preset time period as the current preset time period, return to execute the step of comparing the actual project progress of the sub-project corresponding to the sub-project package in the current preset time period with the ideal schedule to obtain the comparison result.

[0090] Optionally, in one embodiment, the budget allocation module 40 is further configured to:

[0091] Get the project milestones of the sub-project package;

[0092] Detecting whether the actual progress of the sub-project corresponding to the sub-project package has reached the project milestone;

[0093] If the project milestone is achieved, the remaining budget specified in the sub-project package will be allowed to be allocated.

[0094] Optionally, in one embodiment, the circulation module is further configured to:

[0095] Obtain any sub-project package that has not been obtained from each sub-project package corresponding to the project project, as well as each key node and project milestone of any sub-project package;

[0096] Return to the step of comparing the actual project progress of the sub-project corresponding to the sub-project package with the ideal progress to obtain the comparison result, until all sub-project packages in each sub-project package corresponding to the project project have been obtained, or the budget corresponding to the project project is zero.

[0097] Among them, the functional implementation of each module in the above-mentioned project budget management device corresponds to each step in the above-mentioned project budget management method embodiment, and its functions and implementation processes are no longer repeated here.

[0098] In a third aspect, an embodiment of the present invention further provides an electronic device, whose structure is as follows: Figure 5 As shown, it includes: a memory and a processor, wherein the processor is used to read and execute the computer program stored in the memory to implement the aforementioned project budget management method.

[0099] In a fourth aspect, an embodiment of the present invention further provides a computer storage medium, wherein the computer storage medium stores computer executable instructions, and when the computer executable instructions are executed, the aforementioned method for managing a project budget is implemented.

[0100] In the fifth aspect, an embodiment of the present invention provides a computer program product, which is stored in a storage medium and is executed by at least one processor to implement the various processes of the above-mentioned engineering budget management method embodiment, and can achieve the same technical effect. To avoid repetition, it will not be repeated here.

[0101] Finally, it should be noted that: in some processes described in the embodiments of the present invention, multiple operations or steps appearing in a specific order are included, but it should be understood that these operations or steps may not be executed in the order in which they appear in the embodiments of the present invention or may be executed in parallel, and the sequence number of the operation is only used to distinguish between different operations, and the sequence number itself does not represent any execution order. In addition, these processes may include more or fewer operations, and these operations or steps may be executed in sequence or in parallel, and these operations or steps may be combined.

[0102] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for managing a project budget, characterized in that: The method comprises: Get the sub-project packages of the project and each key node of the sub-project packages; Compare the actual project progress of the sub-project corresponding to the sub-project package in the current preset period with the ideal progress table to obtain a comparison result; If the sub-project corresponding to the sub-project package has a target key node associated with budget allocation in the actual project progress of the current preset period, then based on the comparison result, determine whether the sub-project package has reached the target key node; If the key target nodes are achieved, the corresponding project budget will be approved and allocated.

2. A method for managing a project budget according to claim 1, characterized in that: The step of obtaining the sub-project packages of the project and each key node of the sub-project packages includes: Obtain each sub-project package of the project engineering decomposed according to the engineering contract information; The construction acceptance result data of each sub-project package of similar project engineering is used as training samples to train the neural network model; Through the trained neural network model, the key nodes of each sub-project package are determined.

3. A method for managing a project budget according to claim 1, characterized in that: After the step of comparing the actual project progress of the sub-project corresponding to the sub-project package in the current preset period with the ideal progress table to obtain the comparison result, the method includes: If the sub-project corresponding to the sub-project package does not have a target key node for associated budget allocation in the actual project progress of the current preset time period, then take the next preset time period as the current preset time period, return to execute the step of comparing the actual project progress of the sub-project corresponding to the sub-project package in the current preset time period with the ideal schedule to obtain the comparison result.

4. A method for managing a project budget according to claim 1, characterized in that: After the step of approving the corresponding project budget if the target key node is reached, the following steps are included: Get the project milestones of the sub-project packages; Detecting whether the actual progress of the sub-project corresponding to the sub-project package has reached the project milestone; If the project milestone is achieved, the remaining budget specified in the sub-project package will be allowed to be allocated.

5. A method for managing a project budget according to claim 4, characterized in that: After the steps described above, if the project milestone is achieved, the full remaining budget specified in the sub-project package will be released, including: Obtain any sub-project package that has not been obtained from each sub-project package corresponding to the project project, as well as each key node and project milestone of any sub-project package; Return to the step of comparing the actual project progress of the sub-project corresponding to the sub-project package with the ideal progress to obtain the comparison result, until all sub-project packages in each sub-project package corresponding to the project project have been obtained, or the budget corresponding to the project project is zero.

6. A project budget management device, characterized in that: The device comprises: An acquisition module is configured to acquire sub-project packages of a project and key nodes of the sub-project packages; A comparison module is configured to compare the actual project progress of the sub-project corresponding to the sub-project package in the current preset period with the ideal progress to obtain a comparison result; An information determination module is configured to determine, based on the comparison result, whether the actual progress of the sub-project corresponding to the sub-project package in the current preset period has reached the target key node if there is a target key node associated with budget allocation in the current preset period; The budget disbursement module is configured to approve the disbursement of the corresponding project budget if the target key node is reached.

7. A project budget management device according to claim 6, characterized in that: The budget disbursement module is also configured to: Get the project milestones of the sub-project packages; Detecting whether the actual progress of the sub-project corresponding to the sub-project package has reached the project milestone; If the project milestone is achieved, the remaining budget specified in the sub-project package will be allowed to be allocated.

8. An electronic device, characterized in that: include: Memory and processor; The processor is used to read and execute the computer program stored in the memory to implement the steps of the project budget management method as described in any one of claims 1-5.

9. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer-executable instructions, and when the computer-executable instructions are executed, the steps of the project budget management method as described in any one of claims 1 to 5 are implemented.

10. A computer program product comprising a computer program / instructions, characterized in that When the computer program / instruction is executed by a processor, the steps of the project budget management method as described in any one of claims 1-5 are implemented.

Citation Information

Patent Citations

  • Project milestone processing method and device, storage medium and electronic equipment

    CN113537954A

  • Method for monitoring collaborative execution condition of investment plan and fund plan of power grid infrastructure project

    CN114240044A

  • Engineering data processing method and system capable of automatically generating visual progress

    CN116797406A

  • Project management and assessment method

    US20080140485A1

  • Method and system for automatic establishment of optimal schedule for construction project

    WO2024010137A1