By introducing a tapered surface and elastic sleeve into the pipe joint, the problem of difficulty in pulling out the pipe body after insertion in the prior art is solved, and the water stop performance is improved through the configuration of multiple water stop components and O-rings , realizes reliable connection and convenience of replacement of the pipe body.
Patent Information
- Application Number
- CN202380033047.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Priority Date
- 2022-04-15
- Filing Date
- 2023-04-03
- Publication Date
- 2024-11-22
AI Technical Summary
The existing pipe joints are difficult to pull out after insertion, and the water stopping performance is insufficient, resulting in insufficient length of the pipe body or the casing needs to be damaged for replacement when the sleeve is aging, which increases the cost and operating burden.
A pipe joint with a guide part, a fastening member and an elastic sleeve is designed. Through the cooperation of the tapered surface and the elastic member, the sleeve allows the sleeve to extend outward after connection, so that the pipe can be pulled out without destroying the joint. The body and the configuration of a plurality of water stop components and O-rings ensure sufficient water stop performance.
Reliable insertion and removal of the pipe body is achieved, reducing the risk of insertion difficulties and fluid leakage, while improving water stopping performance and reducing the cost and operating burden of replacing the sleeve.
Smart Images

Figure CN119013499A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to a pipe joint that can be easily connected without tools by simply inserting a flexible and deformable hose or pipe such as a pipe formed of a material such as synthetic resin or rubber. Background Art
[0002] This pipe joint is a convenient pipe joint that can be connected by simply inserting the pipe body, but the insertion of the pipe body encounters certain resistance and cannot be carried out smoothly. Therefore, due to this resistance, the operator may stop the insertion of the pipe midway, and sometimes the pipe body may fall out or fluid may leak due to insufficient insertion of the pipe body. Therefore, in order to prevent such a situation, a structure is proposed in which the operator can feel the insufficient insertion of the pipe body (for example, refer to Patent Document 1).
[0003] Prior art literature
[0004] Patent Literature
[0005] Patent Document 1: Japanese Patent Application Publication No. 2018-3980 Summary of the invention
[0006] Technical issues to be solved by the invention
[0007] The pipe joint of patent document 1 does not rely on the experience of the operator, etc. Whoever performs the insertion operation of the pipe body can reliably ensure that it is inserted to the specified position, and can easily and reliably prevent insufficient insertion of the pipe body. Therefore, the operator or the person in charge of on-site management can safely perform the piping operation of the pipe body.
[0008] However, the pipe joint of Patent Document 1 can reliably insert the pipe body into the specified position, but on the other hand, once the insertion operation is completed, the pipe body cannot be pulled out unless the pipe joint is destroyed or disassembled. At the installation site of the pipe body, sometimes an emergency situation occurs in which the length of the pipe body is found to be insufficient after installation and must be replaced with an appropriate pipe body. Even if this situation does not occur, the sleeve as the anti-detachment component of the pipe body is a consumable part that ages with use. Although it needs to be replaced, it is costly to destroy the joint part with a longer service life. Even a structure that can disassemble the joint will generate a corresponding work burden. Therefore, the inventors of the present invention proposed a pipe joint that allows the sleeve to extend to the outside, and the pipe body can be pulled out by operating the performed part.
[0009] However, it is clear that being able to pull out the pipe body is difficult in terms of water stopping, and it is clear that coping with the problem of water stopping has become a new issue. Therefore, an object of the present invention is to provide a pipe joint that can achieve sufficient water stopping.
[0010] Means for solving technical problems
[0011] The present invention relates to a pipe joint for achieving such an object, characterized in that it comprises: a guide portion provided on a threaded pipe and arranged opposite to the inner surface of a flexible pipe body; a fastening member having a tapered surface provided to be opposite to the outer peripheral surface of the guide portion and gradually increasing in diameter in the insertion direction of the pipe body; a sleeve which can freely reciprocate along the fastening member in the insertion direction of the pipe body and in the opposite direction of the pipe withdrawal direction and can be elastically deformed to expand and reduce the diameter in the radial direction; and an elastic member provided to press the sleeve in the pipe withdrawal direction along the tapered surface, the sleeve having a sleeve protrusion which bites into the outer surface of the pipe body when reducing the diameter, the guide portion having a plurality of water stop members from the inner side to the front side in the insertion direction of the pipe body, the sleeve protrusion being arranged above the water stop member on the inner side in the insertion direction of the pipe body when the connection of the pipe body is completed, and on the other hand, being arranged above the water stop member on the front side in the insertion direction of the pipe body when the internal pressure of the pipe body is high. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 1 is a diagram showing the overall structure of a pipe joint according to an embodiment of the present invention. Figure 1 (a) is the front view, Figure 1 (b) is the right stereogram, Figure 1 (c) is a right-side stereoscopic view when exploded.
[0013] Figure 2 is a longitudinal sectional front view showing the overall structure of a pipe joint according to an embodiment of the present invention, Figure 2 (a) indicates the state of the sleeve shrinking when the connection of the pipe body is completed. Figure 2 (b) shows the state where the sleeve is pressed in and the sleeve is expanded in diameter.
[0014] Figure 3 A sleeve for use in a pipe joint according to an embodiment of the present invention. Figure 3 (a) is the front view, Figure 3 (b) is the left stereogram, Figure 3 (c) is the longitudinal section front view.
[0015] Figure 4 is a longitudinal sectional front view showing the overall structure of a pipe joint according to an embodiment of the present invention, Figure 4 (a) indicates when the pipe body starts to connect. Figure 4 (b) shows the middle stage of the pipe connection operation. Figure 4 (c) shows the state where the tube body is pressed into the tube abutment portion before connection is completed.
[0016] Figure 5is a longitudinal sectional front view showing the overall structure of a pipe joint according to an embodiment of the present invention, Figure 5 (a) is the connection state of the pipe body, Figure 5 (b) to (e) show the transition of the state when the internal pressure of the tube body gradually increases.
[0017] Figure 6 yes Figure 5 A partial enlarged view of Figure 6 (a) is the connection state of the pipe body, Figure 6 (b) to (e) show the transition of the state when the internal pressure of the tube body gradually increases.
[0018] Figure 7 is a longitudinal sectional front view showing the overall structure of a pipe joint according to another embodiment of the present invention, Figure 7 (a) indicates the state of the sleeve shrinking when the connection of the pipe body is completed. Figure 7 (b) shows the state where the tube body is not inserted.
[0019] Figure 8 A sleeve for a pipe joint according to another embodiment of the present invention. Figure 8 (a) is the front view, Figure 8 (b) is the left stereogram, Figure 8 (c) is the longitudinal section front view. DETAILED DESCRIPTION
[0020] (Embodiment of the present invention)
[0021] Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.
[0022] like Figure 1 to Figure 3 As shown, the pipe joint A involved in the embodiment of the present invention has as main components: a threaded pipe 1 having a guide portion 14 disposed opposite to the inner surface of a pipe body B; a nut 2 (fastening member) having a nut inner inclined surface 21 (tapered surface) disposed opposite to the outer peripheral surface of the guide portion 14 and inclined in the axial direction thereof; a sleeve 3 that can freely reciprocate along the nut inner inclined surface 21 of the nut 2 in the direction of inserting the pipe body and in the opposite direction of the pipe withdrawal direction, and can be elastically deformed to expand and contract in the radial direction; and a spring 4 that is disposed to press the sleeve 3 in the direction of pipe withdrawal along the nut inner inclined surface 21. In addition, a ring 5 as a spring seat of the spring 4 and an O-ring 6 for water stopping are also provided.
[0023] Figure 1 1 is a diagram showing the overall structure of a pipe joint according to an embodiment of the present invention. Figure 1 (a) is the front view, Figure 1 (b) is the right stereogram, Figure 1(c) is a right-side stereoscopic view when exploded. Figure 2 is a longitudinal sectional front view showing the overall structure of a pipe joint according to an embodiment of the present invention, Figure 2 (a) indicates the state of the sleeve shrinking when the connection of the pipe body is completed. Figure 2 (b) shows the state where the sleeve is pressed in and the sleeve is expanded in diameter.
[0024] The nipple 1 is formed by pressing or other forming processes on a plate made of a metal such as brass, a rigid material such as a hard synthetic resin, or a deformable rigid material such as stainless steel.
[0025] like Figure 1 As shown in (b) and (c), the internal thread provided on the inner periphery of the nut 2 and the external thread provided on the outer periphery of the cylindrical portion 13 of the threaded pipe 1 (please also refer to Figure 2 (a). ) is screwed into a threaded nipple 1 having a guide portion 14, thereby rotating the nut 2 relative to the threaded nipple 1 and connecting it. The threaded nipple 1 is provided with a tool engaging portion 12 of a hexagonal opposite width used when the nut 2 is screwed. Before the nut 2 is connected to the threaded nipple 1, an O-ring 6 is embedded and installed in an annular recess 15 formed in the guide portion 14 to be held so as not to move in the axial direction, and after the spring 4 and the ring 5 are arranged between the threaded nipple 1 and the nut 2, the nut 2 is connected to the threaded nipple 1. However, the sleeve 3 may not be assembled before the threaded nipple 1 and the nut 2 are connected. In the case of a conventional pipe joint, the sleeve is also forced to be arranged between the threaded nipple and the nut before the two are connected to perform the connection operation, that is, the sleeve cannot be installed afterwards, but in the present invention, the sleeve 3 can be installed even after the threaded nipple 1 and the nut 2 are connected. That is, as in the past, the sleeve can be installed when the threaded pipe 1 and the nut 2 are assembled. On the other hand, even after the threaded pipe 1 and the nut 2 are assembled, the sleeve 3 can be accommodated in the nut 2 by simply pressing the sleeve 3 from the opening of the nut 2 to reduce the diameter of the sleeve 3.
[0026] By inserting the connecting end of the tube body B into the insertion space formed between the guide portion 14 and the sleeve 3, the sleeve 3 overcomes the spring 4 and temporarily moves in the insertion direction N of the tube body B. However, thereafter, the sleeve 3 moves in the opposite direction of the tube insertion direction N, that is, the tube removal direction U, and the connecting end of the tube body B is clamped between the guide portion 14 and the sleeve 3, and is thus connected and maintained in a manner that cannot be removed. Figure 2 (a) indicates this state. And, Figure 2 (b) shows the greatest feature of the present invention, that is, by pressing the pressing portion 31 of the cannula 3, the diameter of the cannula 3 can be expanded in a state where the tube B is connected. In this state, the tube B can be easily removed.
[0027] In addition, in the present embodiment, the pressing portion 31 is formed in a flange shape, but an engaging portion that enables a replacement work fixture to be engaged may also be provided, so that a separately prepared replacement work fixture is engaged and pressed when pressed. It is important that the sleeve 3 extends further in the pipe extraction direction U on the side opposite to the threaded pipe 1 than the nut 2.
[0028] The guide portion 14 is formed integrally with the threaded nipple 1, for example, by being formed of a metal such as brass or a rigid material such as a hard synthetic resin into a cylindrical shape having an outer diameter substantially the same as or slightly smaller than the inner diameter of the tube body B, or by, for example, performing a press process or other forming process on a plate made of a deformable rigid material such as stainless steel, so as to be formed into a thin-walled cylindrical shape having an outer diameter substantially the same as or slightly smaller than the inner diameter of the tube body B. However, the threaded nipple 1 and the guide portion 14 may be formed separately and assembled, or the materials of the two may be different, for example, the threaded nipple 1 may be formed of brass and the guide portion 14 may be formed of resin.
[0029] An annular recess 15 is formed on the outer circumferential surface of the guide portion 14, which is opposite to the inner surface of the tube body B and the inner circumferential surface of the sleeve 3 and extends in the circumferential direction. An O-ring 6 is embedded and installed in the annular recess 15 to be held unable to move axially, and the outer circumferential end of the O-ring 6 is made to protrude slightly from the outer circumferential surface of the guide portion 14 so that it is crimped against the inner surface of the tube body B.
[0030] In the example shown in the figure, two annular recesses 15 and two O-rings 6 are arranged at predetermined intervals on the outer peripheral surface of the guide portion 14 , and the entire outer peripheral surface except the annular recesses 15 is formed into a smooth surface in the tube insertion direction N.
[0031] Furthermore, as another example, although not shown, the O-rings 6 may be arranged at predetermined intervals in three or more sets of the annular recesses 15 so that the O-rings 6 face the axial direction of the guide portion 14 .
[0032] A tube abutment portion 16 as a step is formed on the inner side of the guide portion 14 in the tube insertion direction N so that the insertion completion can be grasped when inserting the tube body B. A ring escape portion 17 (escape portion) is formed on the inner side of the tube abutment portion 16 in the tube insertion direction N as a space where the ring 5 can escape when the sleeve 3 is pressed.
[0033] The nut 2 is made of transparent or colored resin or metal, and a portion of the axial direction thereof is formed into a substantially cylindrical shape having an inner diameter larger than the outer diameter of the sleeve 3. The nut 2 is screwed onto the threaded tube 1 and installed so as to be unable to move axially relative to the guide portion 14 side.
[0034] The inner peripheral surface of the nut 2 is formed with a nut inner inclined surface 21 (tapered surface) as a means for fastening the sleeve 3. The nut inner inclined surface 21 is inclined so as to gradually increase in diameter in the tube insertion direction N and gradually decrease in diameter in the tube removal direction U.
[0035] In the nut of the conventional pipe joint, in order to prevent the sleeve from moving in the pipe extraction direction U, a limiting portion opposed to the sleeve is formed on the front end side of the inner circumference of the nut in the pipe extraction direction U. Therefore, after the threaded pipe and the nut are connected, the sleeve cannot be installed, and the installed sleeve cannot be removed without destroying or disassembling the pipe joint. However, in the embodiment of the present invention, the sleeve 3 can be installed and removed. According to the material and structure of the sleeve 3 described later, Figure 2 In (b), it is easy to understand that in the absence of the tube body B, the sleeve 3 can be easily installed and removed.
[0036] Figure 3 A sleeve for use in a pipe joint according to an embodiment of the present invention. Figure 3 (a) is the front view, Figure 3 (b) is the left stereogram, Figure 3 (c) is the longitudinal section front view.
[0037] The sleeve 3 is formed into a roughly cylindrical shape capable of radial expansion and contraction, and its inner diameter is set to be approximately the same as or larger than the outer diameter of the tube body B when expanding, and smaller than the outer diameter of the tube body B when contracting.
[0038] Furthermore, the sleeve 3 is supported so as to be reciprocatable in the tube insertion direction N and the tube removal direction U along the outer peripheral surface of the guide portion 14 and the nut inner inclined surface 21 of the nut 2 .
[0039] A sleeve protrusion 33 is formed on the inner peripheral surface of the sleeve 3 so as to protrude toward the outer peripheral surface of the guide portion 14 in a state of being annular or nearly annular in the circumferential direction.
[0040] The sleeve protrusion 33 is configured to abut against the front end surface of the connecting end of the tube body B in the tube insertion direction N when the tube body B is inserted, and is formed to shrink and deform its inner end toward the outer surface of the connecting end to be smaller than the outer diameter of the tube body B as it moves in the tube removal direction U.
[0041] The number of the sleeve protrusions 33 is preferably such that a plurality of sleeve protrusions 33 are arranged in the tube insertion direction N. Figure 2 In the example shown, three sleeve protrusions 33 are integrally formed on the inner peripheral surface of the sleeve 3 at predetermined intervals. The three sleeve protrusions 33 are preferably formed in Figure 2The positional relationship above the O-ring 6 arranged on the inner side in the tube insertion direction N in the connection completion state of the tube body B shown in (a).
[0042] The sleeve 3 has a sleeve inclined surface 32 formed on its outer peripheral surface to face the nut inner inclined surface 21 of the nut 2 , and an elastic deformation portion that elastically expands and contracts the sleeve protrusion 33 and the sleeve inclined surface 32 in the radial direction of the sleeve 3 .
[0043] The sleeve inclined surface 32 is arranged in the following relationship: it is formed approximately parallel to the nut inner inclined surface 21 of the nut 2 in a state of being annular or nearly annular along the outer circumferential surface of the sleeve 3, and the maximum diameter portion of the sleeve inclined surface 32 is set to be the same diameter as or slightly smaller than the maximum diameter portion of the nut inner inclined surface 21 when not in contact with the nut inner inclined surface 21, but in the contact state, the sleeve inclined surface 32 has to be reduced in diameter due to the smaller diameter portion of the nut inner inclined surface 21. That is, the sleeve inclined surface 32 is configured to always be elastically pressed against the nut inner inclined surface 21.
[0044] Specifically, the sleeve inclined surface 32 is configured to temporarily move in the tube insertion direction N along the nut inner inclined surface 21 as the sleeve protrusion 33 abuts against the front end surface of the tube body B, and then move in the opposite direction in the tube removal direction U by the spring 4.
[0045] The elastic deformation portion is constructed by cutting a groove or a depression on a part of the axial direction of the sleeve 3, which is easy to elastically deform in the radial direction, and is constructed so that the sleeve inclined surface 32 contacts the inner inclined surface 21 of the nut while moving toward the tube insertion direction N, thereby making the sleeve inclined surface 32 smoothly expand and deform. At the same time, the sleeve inclined surface 32 contacts the inner inclined surface 21 of the nut while moving in the tube extraction direction U, so that the sleeve inclined surface 32 smoothly shrinks and deforms.
[0046] In the example shown in the figure, a sleeve inclined surface 32 is bulged out in a part of the axial direction of the sleeve 3, specifically from the axial middle position to the inner end in the tube insertion direction N, and a plurality of grooves (slits) extending linearly in the axial direction further than the sleeve inclined surface 32 are cut out in the circumferential direction to form.
[0047] Furthermore, the three sleeve protrusions 33 are shaped to protrude in the vertical direction in the figure on the back side in the tube insertion direction N, whereas they are shaped to have a 45-degree tapered surface on the front side in the tube insertion direction N.
[0048] Therefore, when the tube body B begins to be inserted, the outer peripheral edge of the front end face of the tube body B contacts the 45-degree conical surface of the sleeve protrusion 33 and the sleeve 3 is pressed in the tube insertion direction N, but the contact between the sleeve inclined surface 32 and the inner inclined surface 21 of the nut is released. As the sleeve protrusion 33 expands and deforms, the outer peripheral edge of the front end face of the tube body B pushes the sleeve protrusion 33 while passing through. After the tube body B is pressed to the specified position, if the sleeve 3 moves in the opposite direction to the tube removal direction U by the spring 4, it is formed to be accompanied by the sleeve protrusion 33. The inner end thereof reliably bites into the outer surface of the tube body B.
[0049] The spring 4 is an elastic body such as a coil spring or a spring that can be elastically deformed in at least one direction, and is configured to be able to deform in the tube insertion direction N and the tube removal direction U, and always elastically presses the sleeve 3 in the tube removal direction U.
[0050] In the example shown in the figure, a coil spring is interposed as a spring 4 between a spring contact portion on the inner side of the space formed by the cylindrical portion 13 and the guide portion 14 of the nipple 1 in the pipe insertion direction N and a ring 5 as a spring retainer arranged on the front side of the sleeve 3 in the pipe insertion direction N, so that the pressing force of the coil spring acts uniformly on the sleeve 3 in the circumferential direction. The ring 5 acts as a spring retainer and has a certain thickness in the pipe insertion direction. It contacts the inner surface of the nut 2 without a gap, so it reciprocates while maintaining a state completely parallel to the nipple 1. Therefore, the sleeve 3 also reciprocates while maintaining a state completely parallel to the nipple 1, so the sleeve 3 does not tilt.
[0051] On the other hand, the tube body B is a tube body formed of a flexible material such as a synthetic resin such as vinyl chloride or silicone rubber or other rubber, such as a hose or tube formed of a soft material, and preferably has a flat inner and outer surfaces.
[0052] As a specific example of the tube body B, in the example shown in the figure, a hose with a single-layer structure is used. Also, as another example, although not shown in the figure, a laminated hose (braided hose) in which multiple or single synthetic resin braids (reinforcement wires) are spirally buried as an intermediate layer between its transparent or opaque outer layer and inner layer, or a spiral reinforced hose in which a synthetic resin or metal belt-shaped reinforcement member with a rectangular cross section and a linear reinforcement member with a circular cross section are spirally wound and integrated as an intermediate layer, or a spiral reinforced hose in which a metal wire or a hard synthetic resin wire is spirally buried, etc. can also be used.
[0053] Furthermore, the threaded nipple 1 is provided with a connection portion 11 to which other equipment (not shown) or other pipes (not shown) are connected, so that the other equipment or other pipes connected thereto via the threaded nipple 1 are connected to the pipe body B connected to the outer peripheral surface of the guide portion 14. In addition, by providing the guide portions 14 at both ends instead of the connection portion 11, it is also possible to function as an intermediate joint.
[0054] (Tube connection process)
[0055] A connection process of the pipe joint A according to the embodiment of the present invention will be described. Figure 4 is a longitudinal sectional front view showing the overall structure of a pipe joint according to an embodiment of the present invention, Figure 4 (a) indicates when the pipe body starts to connect. Figure 4 (b) shows the middle stage of the pipe connection operation. Figure 4 (c) shows the state where the tube body is pressed into the tube abutment portion before connection is completed.
[0056] like Figure 4 As shown in (a), by inserting the connecting end of the tube body B toward the insertion space formed between the guide portion 14 and the sleeve 3, first, the front end surface of the tube body B abuts against the 45-degree tapered surface of the sleeve protrusion 33 in the sleeve 3, and by pressing the tube body B while maintaining this low contact state, the sleeve inclined surface 32 of the sleeve 3 slides along the nut inner inclined surface 21 of the nut 2, and the sleeve 3 including the sleeve protrusion 33 as a whole overcomes the pressing force of the spring 4 and moves in the tube insertion direction N. At this time, if the operation is difficult to perform, the pressing portion 31 of the sleeve 3 can also be used to assist the operator in pressing the sleeve 3. In particular, when strong resistance is felt, it is best to press the sleeve 3 by hand. The reason is that when the tube body B is inserted in a state where the sleeve protrusion 33 is located on the upper part of the O-ring 6, the end of the tube body B strongly contacts the O-ring 6 when the tube body B drills into the inner side of the sleeve protrusion 33 through the 45-degree tapered surface of the sleeve protrusion 33, and the O-ring 6 is lifted up, which becomes a cause of fluid leakage.
[0057] There is also such a background. In the embodiment of the present invention, the tapered surface of the sleeve protrusion 33 is set to 45 degrees. If the tapered angle of the sleeve protrusion 33 is greater than 45 degrees, the end of the tube body B and the tapered surface of the sleeve protrusion 33 are in strong contact, and the tube body B is difficult to drill into the inner side of the sleeve protrusion 33, and the sleeve 3 does not expand in diameter, so the insertion of the tube body B becomes difficult. When the tapered angle of the sleeve protrusion 33 is less than 45 degrees, the contact area between the end of the tube body B and the tapered surface of the sleeve protrusion 33 increases, and the force pushing the inner side of the sleeve protrusion 33 becomes stronger, so the end of the tube body B strongly contacts the O-ring 6, and the O-ring 6 is easily lifted. The 45-degree tapered surface of the sleeve protrusion 33 is set to an angle that is well balanced when the sleeve 3 is expanded in the radial direction based on the pressing of the sleeve 3 of the tube body B and the end of the tube body B drilling into the inner side of the sleeve protrusion 33 using the tapered surface of the sleeve protrusion 33. However, depending on the material of the tube B or the strength of the O-ring 6, it is not impossible to implement it even if the taper angle is different. The so-called 45 degrees is only a setting for this embodiment.
[0058] When the O-ring 6 is inserted into the tube body B without rolling it up, Figure 4 As shown in (b), since the sleeve inclined surface 32 of the sleeve 3 is pushed in the tube insertion direction N along the inner inclined surface 21 of the nut, the sleeve 3 expands in diameter due to its own elasticity, and the sleeve inclined surface 32 and the sleeve protrusion 33 also gradually expand and deform. Afterwards, as the sleeve protrusion 33 expands in diameter and deforms, the inner diameter of its front end becomes larger than the outer diameter of the front end of the tube body B, and the front end surface of the tube body B deviates from the 45-degree conical surface of the sleeve protrusion 33. Then, due to the spring elasticity of the spring 4, the sleeve 3 is pushed back in the direction opposite to the insertion direction N of the tube body B, so that the end of the tube body B slides on the 45-degree conical surface of the sleeve protrusion 33, and the tube body B passes through the inner side of the protrusion of the sleeve 3, as shown in FIG. Figure 4 As shown in (c), the pipe body B is inserted until it reaches the pipe abutment portion 16 of the threaded pipe 1.
[0059] On the other hand, when the insertion of the tube body B is completed and the friction force in the tube insertion direction N is released, the sleeve 3 is strongly pressed in the tube withdrawal direction U by the elasticity of the spring 4, and the sleeve 3 is suddenly deformed in diameter, so that the inner end of the sleeve protrusion 33 bites into the outer surface of the tube body B, and the tube body B is clamped between the outer peripheral surface of the guide portion 14 in a manner that it cannot move in the tube withdrawal direction U (refer to Figure 2 (a)).
[0060] In this way, only by inserting the tube body B, a non-removable connection can be completed smoothly and reliably in one touch without the need for tools.
[0061] (Tube body disassembly process)
[0062] Next, the disassembly process of the pipe joint A according to the embodiment of the present invention will be described. In the conventional pipe joint, since the sleeve is completely accommodated in the nut, it is impossible to press it in the pipe insertion direction N. However, in the pipe joint A according to the embodiment of the present invention, the sleeve 3 has an extension portion extending in the pipe extraction direction U on the opposite side of the threaded pipe 1 from the nut 2, and the extension portion has a flange that functions as a pressing portion 31, so that the sleeve 3 can be pressed in the pipe insertion direction N even in a state where the connection of the pipe body B is completed. Figure 2 (b) shows the state where the sleeve 3 is pressed in. Since the ring 5 can enter the ring relief portion 17 of the threaded pipe 1, the sleeve 3 is further pressed inward in the pipe insertion direction N. The sleeve 3 is enlarged in diameter, and the sleeve protrusion 33 does not bite into the pipe body B. If the pipe body B is pulled out while the sleeve 3 is still pressed in, there is no significant resistance from the sleeve protrusion 33, so the pipe body B can be easily pulled out.
[0063] (About water stop structure)
[0064] The water stopping structure of the pipe joint A according to the embodiment of the present invention will be described. Figure 5 is a longitudinal sectional front view showing the overall structure of a pipe joint according to an embodiment of the present invention, Figure 5 (a) is the connection state of the pipe body, Figure 5 (b) to (e) show the transition of the state when the internal pressure of the tube body gradually increases. Figure 6 yes Figure 5 A partial enlarged view, specifically, a view showing the configuration relationship between the sleeve protrusion 33 and the O-ring 6, Figure 6 (a) is the connection state of the pipe body, Figure 6 (b) to (e) show the transition of the state when the internal pressure of the tube body gradually increases. Figure 6 In the figure, the O-ring 6 is divided into an O-ring on the inner side in the insertion direction of the tube body and an O-ring on the front side, which are respectively represented as O-ring 61 and O-ring 62.
[0065] In the pipe joint A involved in the embodiment of the present invention, the water-stopping structure is also improved. In the pipe joint shown in Patent Document 1, the sleeve may move while tilting, and the pipe body and the O-ring may not be properly compressed, and insufficient water-stopping may occur. In the pipe joint A involved in the embodiment of the present invention, such a situation will not occur. Figure 5 and Figure 6 Provide explanation.
[0066] After the tube B is inserted, Figure 6As shown in (a), the sleeve protrusion 33 is arranged on the upper part of the O-ring 61 on the inner side of the insertion direction of the tube body. At this time, since the sleeve 3 is reduced in diameter, the sleeve protrusion 33 bites into the tube body B to prevent the tube body B from falling off, and at the same time, compresses the tube body B and the O-ring 61 to stop water. When the spring 4 presses the sleeve 3, the outer peripheral surface of the ring 5 guides the sleeve 3 relative to the inner surface of the nut 2 in the axial direction while suppressing the sleeve 3 from tilting inside the nut 2. That is, the movement is stabilized by the parallel surface between the inner surface of the nut 2 and the outer peripheral surface of the ring 5. When the sleeve protrusion 33 is arranged on the upper part of the O-ring 61 on the inner side of the insertion direction of the tube body, by setting the positional relationship of the O-ring 61 between the sleeve protrusion 33 and the sleeve protrusion 33, even if the sleeve 3 is tilted, the tube body B and the O-ring 61 can be compressed to stop water. In the case where there is no positional relationship between the sleeve protrusions 33 and the sleeve protrusions 33, when the sleeve 3 is tilted, the tube body B and the O-ring 61 may not be properly compressed, which may cause insufficient water stopping and fluid leakage. When pressure is applied to the tube body B, the tube body B is subjected to a force to be pulled out of the joint, and in combination with the elastic force of the spring 4, the tube body B and the sleeve 3 move in the tube extraction direction U at the same time. Figure 5 (b) to (e) and Figure 6 (b) to (e) show in stages the state in which the tube body B moves about 1 mm in front of the insertion direction of the tube body after the insertion is completed. The sleeve protrusion 33 bites into the tube body B, so the tube body B moves together with the sleeve 3. At this time, the sleeve 3 is further reduced in diameter through the contact between the inclined surface 21 inside the nut and the inclined surface 32 of the sleeve, and the sleeve protrusion 33 strengthens the bite of the tube body B, which reliably prevents the tube body B from falling off. At the same time, the compression force between the tube body B and the O-ring 61 increases, thereby stopping water. Under relatively low pressure, the O-ring 61 on the inner side of the insertion direction of the tube body stops water (reference Figure 6 (a), (b)), as the pressure increases, the tube body B moves, the sleeve 3 is reduced in diameter, and the O-ring 62 on the front side of the insertion direction of the tube body is used to stop the water (reference Figure 6 (e)). It is also possible to increase the number of sleeve protrusions 33 or the number of O-rings 6 (i.e., O-rings 61, 62), or the area of the elastic body of the O-ring 6. However, when pressure is applied to the tube body B, the tube body B needs to move on the upper part of the O-ring 6. When the friction resistance between the tube body B and the O-ring 6 and the friction resistance between the sleeve inclined surface 32 and the inner inclined surface 21 of the nut increase, the tube body B will not move smoothly, and the sleeve 3 will not shrink in diameter. Therefore, it is necessary to consider the situation where it is difficult to stop water and set the number and area of the O-ring 6.
[0067] (Other embodiments)
[0068] Figure 7 is a longitudinal sectional front view showing the overall structure of a pipe joint according to another embodiment of the present invention, Figure 7 (a) indicates the state of the sleeve shrinking when the connection of the pipe body is completed. Figure 7 (b) shows the state where the tube body is not inserted. Figure 8 A sleeve for a pipe joint according to another embodiment of the present invention. Figure 8 (a) is the front view, Figure 8 (b) is the left stereogram, Figure 8 (c) is the longitudinal section front view.
[0069] The structures of the threaded pipe 1, the nut 2 and its components, and the spring 4, the ring 5, and the O-ring 6 are completely the same as those of the first embodiment, and only the structure of the sleeve 3' is different from that of the first embodiment. That is, the middle part of the sleeve 3' is a cylinder, and elastic deformation parts that elastically expand and contract in the radial direction of the sleeve 3' are provided at both ends. However, the sleeve 3' is the same as the sleeve 3 in that it extends further than the nut 2 in the pipe extraction direction U on the opposite side of the threaded pipe 1, and the extended part is expanded in diameter in the normal state, so that this part can be used as a pressing part 31'.
[0070] Furthermore, such a sleeve 3 ′ can be assembled from any side of the nut 2 , and thus productivity can be improved.
[0071] In addition, the sleeve can be replaced more easily. As mentioned above, the sleeve is a consumable part that ages with use and needs to be replaced. However, when replacement is needed, the sleeve 3' can be temporarily removed, reversed, and then inserted into the nut 2 again to obtain the same effect as replacement. The reversible structure has such advantages.
[0072] In the above, the pipe joint involved in the embodiment of the present invention is described in detail with reference to the drawings, and its structure is explained, but the specific structure is not limited to these embodiments, and even if there are design changes within the scope of the main purpose of the present invention, it is also included in the present invention. For example, in the embodiment of the present invention, the water stop structure applicable to the pipe joint that can also pull out the pipe body is described, but it is also applicable to the conventional type of pipe joint in which the sleeve is completely accommodated in the pipe joint. However, even in the conventional type of pipe joint, since the pipe body and the sleeve move simultaneously, the configuration relationship between the water stop component and the sleeve protrusion deviates from the appropriate position, so it is very meaningful to prepare a plurality of water stop components from the inner side to the front side of the insertion direction of the pipe body and appropriately set the configuration relationship with the sleeve protrusion. In addition, the fastening component is formed by a nut installed on the threaded pipe by screwing, but it can also be changed to a fastening component that is freely connected to the threaded pipe, or fixed integrally by welding without screwing. In the present invention, since the sleeve can be inserted and removed in the state of the assembled pipe joint, there is no problem even if the threaded pipe and the fastening component are welded.
[0073] Explanation of symbols
[0074] 1-threaded pipe, 11-connecting part, 12-tool engaging part, 13-cylindrical part, 14-guide part, 15-annular recessed part, 16-tube abutting part, 17-ring retreat part (retreat part), 2-nut (fastening part), 21-inner inclined surface of nut (tapered surface), 3-sleeve, 31-pressing part, 32-sleeve inclined surface, 33-sleeve protrusion, 4-spring, 5-ring, 6-O-ring (water-stopping part), 61-O-ring (water-stopping part) on the inner side of the insertion direction of the tube body, 62-O-ring (water-stopping part) on the front side of the insertion direction of the tube body, 3'-sleeve, 31'-pressing part, 32'-sleeve inclined surface, 33'-sleeve protrusion, N-insertion direction of the tube body (tube insertion direction), U-opposite direction to the insertion direction of the tube body (tube withdrawal direction).
Claims
1. A pipe joint, characterized in that: have: The guide portion is disposed on the threaded pipe and is disposed opposite to the inner surface of the flexible pipe body; a fastening member having a tapered surface disposed opposite to the outer peripheral surface of the guide portion and gradually increasing in diameter toward the insertion direction of the tube body; The sleeve is reciprocatingly movable along the fastening member in the direction of inserting the tube body and in the opposite direction of pulling out the tube, and is elastically deformable in radial direction to expand and contract the diameter; and The elastic component is configured to press the sleeve along the tapered surface in the direction of pulling out the tube, The sleeve has a sleeve protrusion that bites into the outer surface of the tube body when the diameter is reduced. The guide portion has a plurality of water-stopping components from the inner side to the front side in the insertion direction of the tube body. The sleeve protrusion is arranged above the water stop component on the inner side of the insertion direction of the tube body when the connection of the tube body is completed. On the other hand, when the internal pressure of the tube body is high, it is arranged above the water stop component on the front side of the insertion direction of the tube body.
2. The pipe joint according to claim 1, characterized in that: The sleeve has an extension portion extending in the tube extraction direction opposite to the insertion direction of the tube body more than the fastening component, and the extension portion acts as a pressing portion for pressing the sleeve in the insertion direction of the tube body to expand its diameter when the inserted tube body is extracted.