Temperature control regeneration tower, temperature control method thereof and flue gas low-temperature adsorption regeneration system

By designing a temperature-controlled regeneration tower in the low-temperature flue gas adsorption technology and using multi-stage heating regeneration and temperature adjustment technology, the problem of large heating load in the low-temperature adsorption technology is solved, and the step-by-step recovery and utilization of energy and the complete regeneration of adsorbents are achieved. Improved adsorption efficiency and purification effect.

CN119015818AActive Publication Date: 2024-11-26HUANENG CLEAN ENERGY RES INST +2
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411327632.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-23
Publication Date
2024-11-26
Estimated Expiration
2044-09-23

AI Technical Summary

Technical Problem

In the low-temperature flue gas adsorption technology, the conventional one-stage heating regeneration tower has a large heating load, resulting in high regeneration energy consumption and cost, and the unstable temperature of the adsorbent affects the adsorption effect.

Method used

Design a temperature-controlled regeneration tower, including a preheating section, a heating section and a cooling section, through multi-stage heating regeneration, preheating is used to use the heat discharged from the cooling section to reduce the temperature rise interval of the heating section, and adjust the replacement through the mixing tube. The temperature of the heat medium ensures the stability of the preheating temperature.

Benefits of technology

It effectively reduces the energy consumption and operating costs of the regeneration system, improves the thoroughness of the regeneration and adsorption efficiency of the adsorbent, reduces the contact temperature between the adsorbent and the flue gas, and improves the purification effect of the adsorbent tower.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119015818A_ABST
    Figure CN119015818A_ABST
Patent Text Reader

Abstract

The invention relates to the field of flue gas purification and discloses a temperature control regeneration tower and a temperature control method thereof and a flue gas low-temperature adsorption regeneration system.The temperature control regeneration tower comprises a tower body, a mixing pipe, a temperature measuring device and a control unit, and the tower body is divided into a preheating section, a heating section and a cooling section which are sequentially arranged from top to bottom; the cooling outlet of the cooling section is communicated with the preheating inlet of the preheating section, so that the heat exchange medium which exchanges heat with the adsorbent in the cooling section in the cooling section is supplied into the preheating section to preheat the adsorbent in the preheating section. The outlet end of the mixing pipe communicates with the preheating inlet, and the mixing pipe is used for inputting a temperature adjusting medium. The control unit is used for controlling the temperature of the temperature adjusting medium supplied through the mixing pipe according to the temperature measuring value of the temperature measuring device so that the temperature of the heat exchange medium in the preheating section can be controlled within the preset range. According to the temperature control regeneration tower, the preheating temperature of the preheating section is regulated and controlled, the preheating temperature is stabilized, and the preheating effect is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of flue gas purification, and in particular to a temperature-controlled regeneration tower and a temperature-control method thereof, and a flue gas low-temperature adsorption regeneration system. Background Art

[0002] The large amount of pollutants produced by coal-fired flue gas is one of the important factors that endanger the atmospheric environment and human health. In the related art, an adsorption tower filled with adsorbent is used to adsorb the flue gas, and the adsorbent saturated with adsorption enters the regeneration tower for heating and regeneration. In the related art, the adsorption of pollutants in the flue gas is usually carried out under high temperature environment, that is, the flue gas discharged from the boiler is cooled to about 200°C through the cooling tower, and then enters the adsorption tower for high temperature and adsorption purification. However, the adsorption of high-temperature flue gas has poor adsorption effect, and the content of nitrogen oxides in the clean flue gas after adsorption is high, and it is impossible to achieve near-zero emissions.

[0003] In order to overcome the problem of high-temperature adsorption, a flue gas low-temperature adsorption technology is proposed in the related art, that is, the flue gas is cooled to a low-temperature flue gas below room temperature, for example, and the pollutants in the flue gas are adsorbed and removed from the flue gas by the adsorbent. In low-temperature adsorption, the adsorption capacity of the adsorbent is increased exponentially in a low-temperature environment, which greatly improves the adsorption purification rate compared with the conventional high-temperature flue gas adsorption, and can achieve near-zero flue gas emissions. However, the inventors have realized through research that in the high-temperature adsorption tower, due to heat exchange with the high-temperature flue gas, the adsorbent saturated with adsorption discharged has a high temperature (above 180°C). This high-temperature adsorbent is transported to the regeneration tower, and the heating load of heating to the regeneration temperature (250°C-350°C) is small, and the traditional one-stage heating method can meet the heating requirements. In the low-temperature adsorption process, the adsorbent is in contact with the low-temperature flue gas, resulting in a low discharge temperature (for example, below room temperature). The conventional one-stage heating regeneration tower is used to heat and regenerate the adsorbent. The load of the heater is large, and the regeneration energy consumption and cost remain high, which affects the further development of the low-temperature flue gas adsorption technology. Summary of the invention

[0004] The present invention is based on the inventor's discovery and understanding of the following facts and problems:

[0005] The related art proposes a technical solution that divides the regeneration tower into a preheating section, a heating section and a cooling section from top to bottom, and inputs the heat exchange medium discharged from the cooling section into the preheating section to preheat the adsorbent, heat exchange medium discharged from the preheating section is heated by the heat exchanger of the boiler and then input into the heating section to heat the adsorbent, and the heat exchange medium discharged from the heating section is mixed with hot air and then returned to the boiler. However, the inventors found that the technical solution has the following problems: the temperature of the heat exchange medium discharged from the cooling section fluctuates, resulting in unstable preheating temperature in the preheating section, which affects the preheating effect of the adsorbent.

[0006] The present invention aims to solve one of the technical problems in the related art at least to a certain extent. To this end, the present invention provides a temperature-controlled regeneration tower.

[0007] The present invention also provides a flue gas low-temperature adsorption regeneration system.

[0008] The temperature-controlled regeneration tower provided by the present invention comprises: a tower body, wherein the tower body is divided into a preheating section for preheating an adsorbent, a heating section for heating the preheated adsorbent to desorb and regenerate the adsorbent, and a cooling section for cooling the regenerated adsorbent, which are arranged in sequence from top to bottom. The heating section is provided with a regeneration gas outlet for discharging the regeneration gas. The preheating section has a preheating inlet for supplying a heat exchange medium into the preheating section to preheat the adsorbent and a preheating outlet for discharging the heat exchange medium in the preheating section. The heating section has a heating inlet for supplying a heat exchange medium into the heating section to heat the adsorbent and a heating outlet for discharging the heat exchange medium in the heating section. The cooling section has a cooling inlet for supplying a heat exchange medium into the cooling section to cool the adsorbent and a cooling outlet for discharging the heat exchange medium in the cooling section. a cooling outlet for the heat exchange medium of the cooling section, wherein the cooling outlet of the cooling section is connected with the preheating inlet of the preheating section, so that the heat exchange medium after heat exchange with the adsorbent in the cooling section in the cooling section is supplied to the preheating section to preheat the adsorbent in the preheating section; a mixing tube, the outlet end of the mixing tube is connected with the preheating inlet, and the mixing tube is used to input a temperature regulating medium to regulate the temperature of the heat exchange medium supplied from the cooling outlet to the preheating section; a temperature measuring device, the temperature measuring device is used to measure the temperature of the heat exchange medium discharged from the cooling outlet; a control unit, the control unit is used to control the temperature of the temperature regulating medium supplied through the mixing tube according to the temperature measured value of the temperature measuring device, so as to control the temperature of the heat exchange medium in the preheating section within a preset range.

[0009] The temperature-controlled regeneration tower provided by the present invention realizes multi-stage heating regeneration by arranging a preheating section, a heating section and a cooling section in the temperature-controlled regeneration tower, that is, the adsorbent is first preheated in the preheating section, and then the preheated adsorbent is heated. This multi-stage heating regeneration method realizes the step-by-step recycling of energy, reduces the temperature rise range of the adsorbent in the heating section, effectively alleviates the heating load of the heater, reduces the energy consumption of the regeneration system, and reduces the operating cost of the regeneration system. The multi-stage heating regeneration method of the adsorbent is conducive to increasing the residence time of the adsorbent in the temperature-controlled regeneration tower, so that the regeneration of the adsorbent is more thorough. In addition, the setting of the cooling section allows the adsorbent to be cooled to a certain extent before leaving the tower, and the cooled adsorbent is transported to the adsorption tower for adsorption, which reduces the contact temperature between the adsorbent and the flue gas in the adsorption tower, and helps to improve the adsorption efficiency of the adsorption tower. In addition, since the heat exchange medium discharged from the cooling section has a certain amount of heat (generally 150°C-250°C) during the heat exchange with the adsorbent, the present invention makes full use of this heat and inputs the heat exchange medium discharged from the cooling section into the preheating section to preheat the adsorbent. The preheating section does not require other heat sources, fully utilizes energy, and effectively reduces energy consumption.

[0010] In addition, the temperature-controlled regeneration tower provided by the present invention is provided with a mixing tube, and the temperature of the temperature-regulating medium supplied by the mixing tube is adjusted according to the temperature control of the heat exchange medium discharged from the cooling outlet, thereby realizing the regulation of the preheating temperature in the preheating section, stabilizing the preheating temperature, and ensuring the preheating effect.

[0011] Optionally, the adsorbent is preheated to 80°C-150°C in the preheating section, and / or the adsorbent is heated to 250°C-350°C in the heating section, and / or the adsorbent is cooled to 50°C-100°C in the cooling section.

[0012] Optionally, the temperature of the heat exchange medium discharged from the cooling outlet is 150°C-250°C, and the temperature of the heat exchange medium discharged from the preheating outlet is 50°C-80°C.

[0013] Optionally, the temperature-controlled regeneration tower also includes a temperature increasing device, which is arranged between the heating inlet and the heating outlet, and is used to heat the heat exchange medium discharged from the heating outlet and then input it into the heating section to indirectly heat the adsorbent in the heating section through heat exchange to desorb and regenerate the adsorbent in the heating section.

[0014] Optionally, the temperature increasing device is a heater; or, the temperature increasing device is a heat exchanger, the cold side inlet of the heat exchanger is connected to the cooling inlet of the cooling section, the cold side outlet of the heat exchanger is connected to the heating inlet of the heating section, and the heat exchanger is connected to the economizer to utilize the high-temperature flue gas discharged from the economizer to heat the heat exchange medium on the cold side of the heat exchanger.

[0015] Optionally, a plurality of first discharge pipes are provided in the preheating section, a plurality of second discharge pipes are provided in the heating section, and a plurality of third discharge pipes are provided in the cooling section, and the first discharge pipe, the second discharge pipe and the third discharge pipe all extend in a vertical direction and are used for the dropping of the adsorbent; a material distribution cavity for forming a material distribution layer is provided above the first discharge pipe, a first transition cavity for forming a first material stacking layer is provided between the preheating section and the heating section, a second transition cavity for forming a second material stacking layer is provided between the heating section and the cooling section, and the regeneration gas outlet is connected to the second transition cavity.

[0016] Optionally, the fabric cavity is provided with a first suction port located above the fabric layer, and the first transition cavity is provided with a second suction port.

[0017] Optionally, the temperature-controlled regeneration tower also includes a mixing device connected between the cooling outlet and the preheating inlet, the mixing device having a mixing chamber, the outlet end of the mixing tube being connected to the mixing chamber, and the mixing chamber being used to mix the temperature control medium and the heat exchange medium discharged from the cooling outlet.

[0018] Optionally, the temperature-controlled regeneration tower also includes a speed measuring device, which is used to measure the flow rate of the heat exchange medium discharged from the cooling outlet. The control unit is also used to adjust the flow rate of the temperature regulating medium input through the mixing tube according to the speed measurement value of the speed measuring device, so as to control the temperature of the heat exchange medium in the preheating section within a preset range.

[0019] The present invention also proposes a temperature control method for a temperature-controlled regeneration tower, characterized in that the temperature control method comprises:

[0020] Setting a preset range of the heat exchange medium in the preheating section;

[0021] The temperature T of the heat exchange medium discharged from the cooling outlet is measured in real time by the temperature measuring device;

[0022] The control unit receives the temperature measurement value of the temperature measuring device. When the control unit determines that T is less than the minimum value of the preset range, the control unit controls the mixing tube to supply the first temperature control medium. When the control unit determines that the temperature T is greater than the maximum value of the preset range, the control unit controls the mixing tube to supply the second temperature control medium, so as to control the temperature of the heat exchange medium in the preheating section within the preset range, wherein the temperature of the first temperature control medium is higher than the temperature of the second temperature control medium.

[0023] The present invention also proposes a flue gas low-temperature adsorption regeneration system, comprising: an adsorption tower, the adsorption tower having a flue gas inlet and a flue gas outlet, low-temperature flue gas below room temperature enters the adsorption tower from the flue gas inlet and contacts with an adsorbent so that the low-temperature flue gas is adsorbed and purified into clean flue gas and discharged from the flue gas outlet; a temperature-controlled regeneration tower, the temperature-controlled regeneration tower is used to regenerate the adsorption saturated adsorbent discharged from the adsorption tower and send the regenerated adsorbent back to the adsorption tower.

[0024] Optionally, the flue gas outlet is communicated with a cooling inlet of the cooling section, so that the clean flue gas discharged from the flue gas outlet is input into the cooling section to indirectly cool the adsorbent in the cooling section. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a structural schematic diagram of a temperature-controlled regeneration tower provided in an embodiment of the present invention.

[0026] Figure 2 It is a schematic diagram of the internal structure of the temperature-controlled regeneration tower provided in an embodiment of the present invention.

[0027] Reference numerals:

[0028] Temperature-controlled regeneration tower 100, tower body 110, preheating section 111, preheating inlet 1111, preheating outlet 1112, first medium flow channel 1113, heating section 112, heating inlet 1121, heating outlet 1122, second medium flow channel 1123, cooling section 113, cooling inlet 1131, cooling outlet 1132, third medium flow channel 1133, regeneration inlet 115, regeneration outlet 116, first feed pipe 1171, second feed pipe 1172, third feed pipe 1173, material distribution layer 1181, first material stacking layer 1182, second material stacking layer 1183, first suction port 1191, second suction port 1192, regeneration gas outlet 1193, pipeline 120, electric heater 130, heating pipe 140, mixing pipe 150, partition 160, fan 170, mixing device 180. DETAILED DESCRIPTION

[0029] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and intended to be used to explain the present invention, but should not be understood as limiting the present invention.

[0030] According to the following Figure 1 and Figure 2The temperature-controlled regeneration tower 100 proposed in an embodiment of the present invention is described. The temperature-controlled regeneration tower 100 includes a tower body 110, a mixing tube 150, a temperature measuring device and a control unit. The tower body 110 is divided into a preheating section 111, a heating section 112 and a cooling section 113 from top to bottom. The adsorbent passes through the preheating section 111, the heating section 112 and the cooling section 113 from top to bottom. The preheating section 111 is used for preheating the adsorbent, and the heating section 112 is used for heating the preheated adsorbent to desorb and regenerate the adsorbent. The cooling section 113 is used to cool the regenerated adsorbent. The heating section 112 is provided with a regeneration gas outlet 1193 for discharging the regeneration gas.

[0031] The preheating section 111 has a preheating inlet 1111 for supplying heat exchange medium into the preheating section 111 to preheat the adsorbent and a preheating outlet 1112 for discharging the heat exchange medium in the preheating section 111. The heating section 112 has a heating inlet 1121 for supplying heat exchange medium into the heating section 112 to heat the adsorbent and a heating outlet 1122 for discharging the heat exchange medium in the heating section 112. The cooling section 113 is correspondingly provided with a cooling inlet 1131 for supplying heat exchange medium into the cooling section 113 to cool the adsorbent and a cooling outlet 1132 for discharging the heat exchange medium in the cooling section 113. The cooling outlet 1132 of the cooling section 113 is connected to the preheating inlet 1111 of the preheating section 111 through the pipeline 120, so that the heat exchange medium after heat exchange with the adsorbent in the cooling section 113 in the cooling section 113 is supplied to the preheating section 111 to preheat the adsorbent in the preheating section 111.

[0032] The low-temperature heat exchange medium enters the cooling section 113 from the cooling inlet 1131 to cool the adsorbent, and the heat exchange medium after heat exchange flows out of the cooling section 113 from the cooling outlet 1132. The heat exchange medium flowing out of the cooling section 113 carries a large amount of heat, and the heat exchange medium enters the preheating section 111 through the pipeline 120 to indirectly preheat the adsorbent in the preheating section 111 by heat exchange, and the heat exchange medium after heat release is discharged from the preheating section 111 from the preheating outlet 1112.

[0033] For the adsorbent, the adsorbent circulates from top to bottom and undergoes preheating, heating regeneration and cooling in sequence. Specifically, the heat exchange medium preliminarily heats the adsorbent entering the temperature-controlled regeneration tower 110 in the preheating section 111, i.e., preheats it. The heat exchange medium further heats the preheated adsorbent in the heating section 112 to completely desorb the pollutants adsorbed by the adsorbent. The heat exchange medium cools the regenerated adsorbent after desorption in the cooling section 113. It can be understood that the temperature of the heat exchange medium in the heating section 112 is higher than the temperature of the heat exchange medium in the preheating section 111.

[0034] like Figure 1As shown, the outlet end of the mixing tube 150 is connected to the preheating inlet 1111, and is used to input a temperature regulating medium to regulate the temperature of the heat exchange medium supplied from the cooling outlet 1132 to the preheating section 111. The temperature measuring device is used to measure the temperature of the heat exchange medium discharged from the cooling outlet 1132. The control unit is used to control the temperature of the temperature regulating medium supplied through the mixing tube 150 according to the temperature value measured by the temperature measuring device, so as to control the temperature of the heat exchange medium in the preheating section within a preset range to avoid the preheating temperature being too high or too low.

[0035] For example, in some embodiments, the preheating temperature in the preheating section 111 is controlled within 80 degrees Celsius-110 degrees Celsius. If the preheating temperature in the preheating section 111 is too high (for example, more than 110 degrees Celsius), the pollutants adsorbed in the adsorbent will be desorbed in large quantities to generate regeneration gas, which will increase the regeneration gas extraction burden of the preheating section 111. If the preheating temperature in the preheating section 111 is too low (for example, less than 80 degrees Celsius), the heating pressure of the heating section 112 will be increased, the energy consumption of the regeneration tower will be increased, and the regeneration cost will be increased. In addition, due to the insufficient preheating temperature in the preheating section 111, the water vapor released by the adsorbent during the preheating process will condense and contact with the adsorbent to form agglomerates, causing the feed pipe to be blocked. Therefore, controlling the preheating temperature in the preheating section 111 within 80 degrees Celsius-110 degrees Celsius can effectively reduce the heating pressure of the heating section 112, avoid a large amount of desorption of the adsorbent in the preheating section 111, and avoid agglomeration of the adsorbent.

[0036] The temperature-controlled regeneration tower provided by the present invention realizes multi-stage heating regeneration by arranging a preheating section, a heating section and a cooling section in the temperature-controlled regeneration tower, that is, the adsorbent is first preheated in the preheating section, and then the preheated adsorbent is heated. This multi-stage heating regeneration method realizes the step-by-step recycling of energy, reduces the temperature rise range of the adsorbent in the heating section, effectively alleviates the heating load of the heater, reduces the energy consumption of the regeneration system, and reduces the operating cost of the regeneration system. The multi-stage heating regeneration method of the adsorbent is conducive to increasing the residence time of the adsorbent in the temperature-controlled regeneration tower, so that the regeneration of the adsorbent is more thorough. In addition, the setting of the cooling section allows the adsorbent to be cooled to a certain extent before leaving the tower, and the cooled adsorbent is transported to the adsorption tower for adsorption, which reduces the contact temperature between the adsorbent and the flue gas in the adsorption tower, and helps to improve the adsorption efficiency of the adsorption tower. In addition, since the heat exchange medium discharged from the cooling section has a certain amount of heat (generally 150°C-250°C) during the heat exchange with the adsorbent, the present invention makes full use of this heat and inputs the heat exchange medium discharged from the cooling section into the preheating section to preheat the adsorbent. The preheating section does not require other heat sources, fully utilizes energy, and effectively reduces energy consumption.

[0037] In addition, the temperature-controlled regeneration tower provided by the present invention is provided with a mixing tube, and the temperature of the temperature-regulating medium supplied by the mixing tube is adjusted according to the temperature control of the heat exchange medium discharged from the cooling outlet, thereby realizing the regulation of the preheating temperature in the preheating section, stabilizing the preheating temperature, and ensuring the preheating effect.

[0038] Optionally, the heat exchange medium flowing in the temperature-controlled regeneration tower 110 may be gas or liquid.

[0039] Preferably, in order to reduce operating costs, the heat exchange medium circulating in the temperature-controlled regeneration tower 100 is air.

[0040] In some optional embodiments, the heat exchange medium circulating in the pipeline 120 is air, and the temperature control medium is low-temperature air. The air with lower temperature is mixed into the pipeline 120 through the mixing tube 150 to adjust the preheating temperature of the preheating section 111 to avoid the preheating temperature being too high.

[0041] In some optional embodiments, the heat exchange medium circulating in the pipeline 120 is air, and the temperature control medium is high-temperature air. Air with a higher temperature is mixed into the pipeline 120 through the mixing tube 150 to adjust the preheating temperature of the preheating section 111 to avoid the preheating temperature being too low.

[0042] In some embodiments, in the preheating section 111, the heat exchange medium preliminarily heats the adsorbent to 80 degrees Celsius-110 degrees Celsius; in the heating section 112, the heat exchange medium heats the adsorbent to 250 degrees Celsius-350 degrees Celsius to desorb and regenerate the adsorbent; in the cooling section 113, the heat exchange medium cools the adsorbent to 50 degrees Celsius-100 degrees Celsius.

[0043] In some specific embodiments, in the preheating section 111, the heat exchange medium preliminarily heats the adsorbent to 100 degrees Celsius; in the heating section 112, the heat exchange medium heats the adsorbent to 300 degrees Celsius to desorb and regenerate the adsorbent; in the cooling section 113, the heat exchange medium cools the adsorbent to 80 degrees Celsius.

[0044] Optionally, the temperature of the heat exchange medium discharged from the cooling outlet 1132 of the cooling section 113 is 150° C.-250° C. The temperature of the heat exchange medium discharged from the preheating outlet 1112 is 50° C.-80° C.

[0045] In some embodiments, the temperature-controlled regeneration tower further includes a mixing device 180 connected between the cooling outlet 1132 and the preheating inlet 1111. The mixing device 180 has a mixing chamber. The outlet end of the mixing tube 150 is connected to the mixing chamber of the mixing device 180. The mixing chamber is used to mix the temperature-adjusting medium and the heat exchange medium discharged from the cooling outlet 1132. The temperature-adjusting medium is input into the mixing device 180 through the mixing tube 150. After the temperature-adjusting medium is mixed with the heat exchange medium input into the mixing device 180 from the cooling outlet 1132, it enters the preheating inlet 1111 to preheat the adsorbent in the preheating section 111. The setting of the mixing device 180 makes the temperature-adjusting medium and the heat exchange medium mix more evenly, and makes the temperature of the heat exchange medium input into the preheating section 111 more stable. In addition, the mixing device 180 also plays a buffering role, so that the flow rate of the heat exchange medium input into the preheating section 111 is controllable and is not affected by the flow rate of the mixing tube 140 and the flow rate of the cooling outlet 1132.

[0046] In some embodiments, the temperature-controlled regeneration tower 100 further includes a velocity measuring device, which is used to measure the flow rate of the heat exchange medium discharged from the cooling outlet 1132. The control unit is also used to adjust the flow rate of the temperature-adjusting medium input through the mixing tube 150 according to the velocity value measured by the velocity measuring device, so as to control the temperature of the heat exchange medium in the preheating section 111 within a preset range. This is to avoid the instability of the flow rate of the heat exchange medium discharged from the cooling outlet 1132, and the heat exchange medium cannot be effectively temperature-adjusted only by referring to the temperature value. In other words, the control unit can comprehensively determine the temperature and flow rate of the temperature-adjusting medium input through the mixing tube 150 according to the temperature measurement result of the temperature measuring device and the flow rate measurement result of the velocity measuring device, so as to better control the temperature of the heat exchange medium input to the preheating section 111.

[0047] The inventors found that the related technology still has the following problems: in the low-temperature adsorption technology, since the temperature of the adsorbent input into the preheating section is relatively low (usually below room temperature), the temperature of the heat exchange medium discharged from the preheating section is not high (usually 60°C-80°C). It can be seen that there is less heat with usable value in this part of the heat exchange medium. The heat exchange medium discharged from the preheating section is input into the heat exchanger of the boiler system for heat exchange and temperature increase with the high-temperature flue gas, and then input into the heating section. The modification is difficult, the pipeline is long, and the cost is high. Therefore, the cost performance is not high in actual application; in addition, the temperature of the heat exchange medium discharged from the heating section is generally around 200°C-220°C, while the temperature of the hot air returned to the furnace is generally above 260°C. If the two are mixed and input into the boiler, it will affect the operating conditions of the boiler to a certain extent, and have a certain impact on the normal operation of the boiler.

[0048] In order to solve the above technical problems, Figure 1As shown, in some embodiments of the present invention, room temperature air enters the cooling section 113 from the cooling inlet 1131, and the air discharged from the preheating outlet 1112 is directly discharged. The heat exchange medium discharged from the preheating outlet of the preheating section is directly discharged and no longer input into the boiler for reuse, which reduces the number and length of pipelines, and reduces the equipment construction cost and equipment complexity.

[0049] like Figure 1 As shown, the temperature-controlled regeneration tower 100 further includes a heating device 130, which is disposed between the heating inlet 1121 and the heating outlet 1122. The heating device 130 is used to heat the heat exchange medium discharged from the heating outlet 1122 and then input it into the heating section 112 to indirectly heat the adsorbent in the heating section 112 through heat exchange to desorb and regenerate the adsorbent in the heating section 112. The heating section realizes the self-circulation of the heat exchange medium, and the heat of the heating section comes from the heating device 130, which does not need to be coupled with the boiler system, reduces the number and length of pipelines, makes the regeneration tower relatively independent, and also avoids affecting the operation of the boiler.

[0050] In some optional embodiments, such as Figure 1 As shown, the temperature increasing device 130 is an electric heater, which is arranged on the heating pipe 140, and the heating pipe 140 is connected to the heating inlet 1121 and the heating outlet 1122. The electric heater is used to heat the heat exchange medium discharged from the cooling outlet 1132 and then input it into the heating section 112 to indirectly heat the adsorbent in the heating section 112 through heat exchange to desorb and regenerate the adsorbent in the heating section 112. The heating pipe 140 is connected to a fan 170 to drive the hot air in the heating pipe 140, so that the air circulates in the heating pipe 140 and the heating section 112.

[0051] In some alternative embodiments, the temperature increasing device 130 may be a heat exchanger, the cold side inlet of the heat exchanger is connected to the heating outlet 1122, the cold side outlet of the heat exchanger is connected to the heating inlet 1121, and the heat exchanger is connected to the economizer to heat the heat exchange medium on the cold side of the heat exchanger using the high temperature flue gas discharged from the economizer. In other words, the hot side inlet of the heat exchanger is connected to the high temperature flue gas outlet of the economizer, the high temperature flue gas is input to the hot side of the heat exchanger, and heat is exchanged with the heat exchange medium on the cold side of the heat exchanger to heat the heat exchange medium, and the heated heat exchange medium is input into the heating section 112 to heat the adsorbent in the regeneration heating section 112.

[0052] In some embodiments, Figure 2As shown, the preheating section 111 has a first medium flow channel 1113 for circulating heat exchange medium, the first medium flow channel 1113 connects the preheating inlet 1111 and the preheating outlet 1112, the heating section 112 has a second medium flow channel 1123 for circulating heat exchange medium, the second medium flow channel 1123 connects the heating inlet 1121 and the heating outlet 1122, and the cooling section 113 has a third medium flow channel 1133 for circulating heat exchange medium, the third medium flow channel 1133 connects the cooling inlet 1131 and the cooling outlet 1132. The heat exchange medium circulates in the first medium flow channel 1113 to indirectly exchange heat with the adsorbent to preheat the adsorbent, the heat exchange medium circulates in the second medium flow channel 112 to indirectly exchange heat with the adsorbent to heat the adsorbent so as to regenerate the adsorbent, and the heat exchange medium circulates in the third medium flow channel 1133 to indirectly exchange heat with the adsorbent to cool the adsorbent.

[0053] Preferably, in order to extend the residence time of the heat exchange medium in the temperature-controlled regeneration tower 110 to achieve a better heat exchange effect and improve energy utilization efficiency, at least one of the first medium flow channel 1113, the second medium flow channel 1123, and the third medium flow channel 1133 is a serpentine flow channel.

[0054] As an example, in Figure 2 In the illustrated embodiment, a plurality of partitions 160 are respectively provided in the preheating section 111, the heating section 112 and the cooling section 113. The partitions 160 are arranged horizontally and spaced apart in the vertical direction, respectively forming a serpentine first medium flow channel 1113, a serpentine second medium flow channel 1123 and a serpentine third medium flow channel 1133 in the preheating section 111, the heating section 112 and the cooling section 113. The arrangement of the serpentine first medium flow channel 1113, the serpentine second medium flow channel 1123 and the serpentine third medium flow channel 1133 prolongs the flow path and residence time of the heat exchange medium therein, facilitates the complete heat exchange of the heat exchange medium, can further improve the energy utilization rate, and reduces the operating cost of the regeneration device.

[0055] In some embodiments, a regeneration inlet 115 is provided at the top of the temperature-controlled regeneration tower 110 , and a regeneration outlet 116 is provided at the bottom of the temperature-controlled regeneration tower 110 . The adsorbent to be regenerated enters the temperature-controlled regeneration tower 110 from the regeneration inlet 115 , and the regenerated adsorbent is discharged from the regeneration outlet 116 .

[0056] like Figure 2As shown, a plurality of first feed pipes 1171, a plurality of second feed pipes 1172 and a plurality of third feed pipes 1173 are provided in the temperature-controlled regeneration tower 110. The first feed pipes 1171 are arranged in parallel in the preheating section 111 to form a first feed layer, the second feed pipes 1172 are arranged in parallel in the heating section 112 to form a second feed layer, and the third feed pipes 1173 are arranged in parallel in the cooling section 113 to form a third feed layer. The first feed pipes 1171, the second feed pipes 1172 and the third feed pipes 1173 all extend in a vertical direction for the adsorbent to fall. The adsorbent entering from the regeneration inlet 115 flows through the first feed pipe 1171, the second feed pipe 1172 and the third feed pipe 1173 in sequence and is discharged from the regeneration outlet 116. The first feed pipe 1171, the second feed pipe 1172 and the third feed pipe 1173 extending in the vertical direction allow the adsorbent to fall smoothly and avoid adsorbent blockage, that is, the first feed pipe 1171, the second feed pipe 1172 and the third feed pipe 1173 play a guiding role, guiding the adsorbent to flow from top to bottom. In each feed layer, a plurality of first feed pipes 1171, a plurality of second feed pipes 1172 and a plurality of third feed pipes 1173 are arranged in parallel, respectively, which can increase the heat exchange area, so that the adsorbent inside the feed pipe and the heat exchange medium outside can achieve effective and uniform heat exchange, improve the heat exchange efficiency, and achieve excellent heat exchange effect.

[0057] In the preheating section 111, a first medium flow channel 1113 is defined between the outer side of the first feed pipe 1171 and the inner wall surface of the temperature-controlled regeneration tower 110. In the heating section 112, a second medium flow channel 1123 is defined between the outer side of the second feed pipe 1172 and the inner wall surface of the temperature-controlled regeneration tower 110. In the cooling section 113, a third medium flow channel 1133 is defined between the outer side of the third feed pipe 1173 and the inner wall surface of the temperature-controlled regeneration tower 110.

[0058] Furthermore, if Figure 2 As shown, a distribution cavity for forming a distribution layer 1181 is provided below the regeneration inlet 115 and above the first discharge pipe 1171. The distribution layer 1181 is formed by the adsorbent entering the temperature-controlled regeneration tower 110 from the regeneration inlet 115 and accumulating on the top of the first discharge pipe 1171. The adsorbent entering the regeneration tower 110 from the regeneration inlet 115 is first accumulated in the distribution layer 1181, and then enters a plurality of parallel first discharge pipes 1171 and flows downward along the first discharge pipes 1171. The formation of the distribution layer 1181 helps to evenly distribute the adsorbent in the plurality of first discharge pipes 1171, so that the adsorbent can be naturally distributed to the plurality of first discharge pipes 1171.

[0059] The adsorbent in the cloth layer 1181 gradually falls into the first discharge pipe 1171. A first transition chamber for forming a first material layer 1182 is provided between the preheating section 111 and the heating section 112, that is, a first material layer 1182 is formed between the first discharge layer and the second discharge layer. In order to prevent the heat exchange medium from flowing between the regeneration section 112 and the preheating section 111, the top of the first transition chamber is isolated from the first medium flow channel 1113 by a partition, and the bottom of the first transition chamber is isolated from the second medium flow channel 1123 by a partition, that is, the first transition chamber is defined by two partitions spaced apart in the vertical direction, and the partition is connected to the inner wall surface of the regeneration tower 110. It can be understood that the bottom end of the first discharge pipe 1171 is connected to the first transition chamber through the upper partition, and the top opening of the second discharge pipe 1172 is connected to the first transition chamber through the lower partition, so that the adsorbent can flow smoothly.

[0060] A second transition chamber for forming a second material layer 1183 is provided between the heating section 112 and the cooling section 113, that is, a second material layer 1183 is formed between the second lower material layer and the third lower material layer. The regeneration gas outlet 1193 is connected to the second transition chamber. The desorption of the adsorbent to produce regeneration gas mainly occurs in the second material layer 1183. In order to prevent the heat exchange medium from flowing between the regeneration section 112 and the cooling section 113, the top of the second transition chamber is isolated from the second medium flow channel 1123 by a partition, and the bottom of the second transition chamber is isolated from the third medium flow channel 1133 by a partition, that is, the second transition chamber is defined by two partitions spaced apart in the vertical direction, and the partition is connected to the inner wall surface of the regeneration tower 110. It can be understood that the bottom end of the second material discharge pipe 1172 is connected to the first transition chamber through the upper partition, and the top opening of the third material discharge pipe 1173 is connected to the second transition chamber through the lower partition, so that the adsorbent can flow smoothly.

[0061] After the adsorbent to be regenerated enters from the regeneration inlet 115, it accumulates to form a cloth layer 1181. The adsorbent in the cloth layer 1181 and the preheated adsorbent that falls into the first discharge pipe 1171 are in a heated state, and will undergo partial desorption to produce regeneration gas containing water vapor. This part of the regeneration gas is easy to agglomerate with the adsorbent to form material blocks with relatively large particles, which causes the discharge pipe to be blocked.

[0062] In order to avoid the blockage problem caused by material agglomeration, in some embodiments, as Figure 2 As shown, the cloth chamber is provided with a first suction port 1191 located above the cloth layer 1181 , and the first suction port 1191 is used to timely extract the regeneration gas generated in the preheating section 111 and the cloth layer 1181 .

[0063] In some embodiments, Figure 2As shown, the first transition chamber is provided with a second suction port 1192 for timely extracting the regeneration gas to prevent the water vapor in the regeneration gas from causing the material to agglomerate.

[0064] The temperature control method of the temperature control regeneration tower provided in the embodiment of the present invention comprises:

[0065] Setting a preset range of the heat exchange medium in the preheating section 111;

[0066] The temperature T of the heat exchange medium discharged from the cooling outlet 1132 is measured in real time by a temperature measuring device;

[0067] The control unit receives the temperature value measured by the temperature measuring device. When the control unit determines that the temperature T is less than the minimum value of the preset range, the control unit controls the mixing tube 150 to supply the first temperature regulating medium. When the control unit determines that the temperature T is greater than the maximum value of the preset range, the control unit controls the mixing tube 150 to supply the second temperature regulating medium, so as to control the temperature of the heat exchange medium input into the preheating section 111 within the preset range. The temperature of the first temperature regulating medium is higher than the temperature of the second temperature regulating medium.

[0068] It can be understood that the temperature of the first temperature control medium should be at least higher than the minimum value of the preset range, and the temperature of the second temperature control medium should be at least lower than the maximum value of the preheating range temperature.

[0069] Another embodiment of the present invention also provides a flue gas low temperature adsorption regeneration system, which comprises an adsorption tower and a temperature control regeneration tower 100, wherein the temperature control regeneration tower 100 is the temperature control regeneration tower 100 in any of the above embodiments.

[0070] The adsorption tower has a flue gas inlet and a flue gas outlet. Low-temperature flue gas below room temperature enters the adsorption tower from the flue gas inlet and contacts with the adsorbent for adsorption, and becomes clean flue gas and is discharged from the flue gas outlet. The temperature-controlled regeneration tower 100 is used to regenerate the adsorbent saturated with adsorption discharged from the adsorption tower and return the regenerated adsorbent to the adsorption tower. The adsorption tower also has a feed inlet and a discharge port. The regeneration outlet 116 of the temperature-controlled regeneration tower 100 is connected to the feed inlet of the adsorption tower, and the discharge port of the adsorption tower is connected to the regeneration inlet 115 of the temperature-controlled regeneration tower 100, so that the adsorbent saturated with adsorption is sent into the temperature-controlled regeneration tower 100 for regeneration.

[0071] Preferably, the temperature of the low-temperature flue gas is below zero, for example, -80°C to -5°C.

[0072] More preferably, the temperature of the low-temperature flue gas is -20°C to -5°C. The inventors have found through research that the lower the flue gas temperature, the more beneficial it is for adsorption purification. However, if the flue gas temperature is too low, the equipment structure for cooling the flue gas will be complicated and the energy consumption will increase. For example, it is required to set up an insulation layer for the cooling equipment, adsorption tower and pipeline, and the sealing requirements are high, which will increase the cost. In addition, too low temperature conditions will easily cause condensation water to appear in the adsorption tower, causing the adsorbent to stick and clog, affecting the adsorption. Therefore, it is beneficial to cool the flue gas temperature to -20°C to -5°C.

[0073] Since the temperature of the clean flue gas discharged from the flue gas outlet of the adsorption tower is relatively low, there is still a large amount of available cold energy. In order to fully utilize the cold energy in the low-temperature flue gas, in some embodiments, the flue gas outlet is connected to the cooling inlet 1131 of the cooling section 113, and the clean flue gas discharged from the flue gas outlet is input into the cooling section 113 as a heat exchange medium to indirectly cool the adsorbent in the cooling section 113.

[0074] In the description of the present invention, it is to be understood that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, “axial”, “radial”, “circumferential”, etc., indicating orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.

[0075] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0076] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0077] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0078] In the present invention, the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" etc. mean that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the described specific features, structures, materials or characteristics may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0079] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may change, modify, replace and vary the above embodiments within the scope of the present invention.

Claims

1. A temperature-controlled regeneration tower, characterized in that: include: A tower body, the tower body is divided into a preheating section for preheating an adsorbent, a heating section for heating the preheated adsorbent to desorb and regenerate the adsorbent, and a cooling section for cooling the regenerated adsorbent, which are arranged in sequence from top to bottom. The heating section is provided with a regeneration gas outlet for discharging regeneration gas. The preheating section has a preheating inlet for supplying a heat exchange medium into the preheating section to preheat the adsorbent and a preheating outlet for discharging the heat exchange medium in the preheating section. The heating section has a heating inlet for supplying a heat exchange medium into the heating section to heat the adsorbent and a heating outlet for discharging the heat exchange medium in the heating section. The cooling section has a cooling inlet for supplying a heat exchange medium into the cooling section to cool the adsorbent and a cooling outlet for discharging the heat exchange medium in the cooling section. The cooling outlet of the cooling section is communicated with the preheating inlet of the preheating section so that the heat exchange medium after heat exchange with the adsorbent in the cooling section in the cooling section is supplied to the preheating section to preheat the adsorbent in the preheating section. a mixing tube, the outlet end of which is in communication with the preheating inlet, and the mixing tube is used to input a temperature regulating medium to regulate the temperature of the heat exchange medium supplied from the cooling outlet to the preheating section; a temperature measuring device, the temperature measuring device being used to measure the temperature of the heat exchange medium discharged from the cooling outlet; A control unit is used to control the temperature of the temperature regulating medium supplied through the mixing tube according to the temperature measured by the temperature measuring device, so as to control the temperature of the heat exchange medium in the preheating section within a preset range.

2. The temperature-controlled regeneration tower according to claim 1, characterized in that: The adsorbent is preheated to 80°C-150°C in the preheating section, and / or the adsorbent is heated to 250°C-350°C in the heating section, and / or the adsorbent is cooled to 50°C-100°C in the cooling section.

3. The temperature-controlled regeneration tower according to claim 2, characterized in that: The temperature of the heat exchange medium discharged from the cooling outlet is 150°C-250°C, and the temperature of the heat exchange medium discharged from the preheating outlet is 50°C-80°C.

4. The temperature-controlled regeneration tower according to any one of claims 1 to 3, characterized in that: It also includes a heating device, which is arranged between the heating inlet and the heating outlet, and is used to heat the heat exchange medium discharged from the heating outlet and then input it into the heating section. The heated heat exchange medium indirectly heats the adsorbent in the heating section through heat exchange in the heating section to desorb and regenerate the adsorbent in the heating section.

5. The temperature-controlled regeneration tower according to claim 1, characterized in that: A plurality of first feed pipes are provided in the preheating section, a plurality of second feed pipes are provided in the heating section, and a plurality of third feed pipes are provided in the cooling section. The first feed pipes, the second feed pipes and the third feed pipes all extend in a vertical direction and are used for the adsorbent to fall. A material distribution cavity for forming a material distribution layer is provided above the first material discharge pipe, a first transition cavity for forming a first material stacking layer is provided between the preheating section and the heating section, a second transition cavity for forming a second material stacking layer is provided between the heating section and the cooling section, the regeneration gas outlet is communicated with the second transition cavity, the material distribution cavity is provided with a first suction port located above the material distribution layer, and the first transition cavity is provided with a second suction port.

6. The temperature-controlled regeneration tower according to claim 1, characterized in that: The temperature-controlled regeneration tower also includes a mixing device connected between the cooling outlet and the preheating inlet, the mixing device has a mixing chamber, the outlet end of the mixing tube is connected to the mixing chamber, and the mixing chamber is used to mix the temperature control medium and the heat exchange medium discharged from the cooling outlet.

7. The temperature-controlled regeneration tower according to claim 1 or 6, characterized in that: It also includes a speed measuring device, which is used to measure the flow rate of the heat exchange medium discharged from the cooling outlet. The control unit is also used to adjust the flow rate of the temperature control medium input through the mixing tube according to the speed value measured by the speed measuring device, so as to control the temperature of the heat exchange medium in the preheating section within a preset range.

8. A temperature control method for a temperature control regeneration tower, characterized in that: The temperature-controlled regeneration tower is a temperature-controlled regeneration tower according to any one of claims 1 to 7, and the temperature control method comprises: Setting a preset range of the heat exchange medium in the preheating section; The temperature T of the heat exchange medium discharged from the cooling outlet is measured in real time by the temperature measuring device; The control unit receives the temperature measurement value of the temperature measuring device. When the control unit determines that the temperature T is less than the minimum value of the preset range, the control unit controls the mixing tube to supply the first temperature control medium. When the control unit determines that the temperature T is greater than the maximum value of the preset range, the control unit controls the mixing tube to supply the second temperature control medium, so as to control the temperature of the heat exchange medium input into the preheating section within the preset range.

9. A flue gas low temperature adsorption regeneration system, characterized in that: include: An adsorption tower, wherein the adsorption tower has a flue gas inlet and a flue gas outlet, and low-temperature flue gas below room temperature enters the adsorption tower from the flue gas inlet and contacts with an adsorbent so that the low-temperature flue gas is adsorbed and purified into clean flue gas and discharged from the flue gas outlet; A temperature-controlled regeneration tower, wherein the temperature-controlled regeneration tower is a temperature-controlled regeneration tower according to any one of claims 1 to 7, and the temperature-controlled regeneration tower is used to regenerate the adsorbent saturated with adsorption discharged from the adsorption tower and return the regenerated adsorbent to the adsorption tower.

10. The flue gas low temperature adsorption regeneration system according to claim 9, characterized in that: The flue gas outlet is communicated with the cooling inlet of the cooling section, so that the clean flue gas discharged from the flue gas outlet is input into the cooling section to indirectly cool the adsorbent in the cooling section.

Citation Information

Patent Citations

  • Heat storage testing and evaluation system using heat transfer oil as heat transfer medium

    CN105092638A

  • Three-section type carbon-based catalyst regeneration tower system

    CN107537591A

  • Medical liquid heating method

    CN115845189A

  • Energy gradient utilization regeneration device and low-temperature flue gas adsorption regeneration system

    CN117753159A

  • Intelligence accuse temperature valve system

    CN206333762U