Rail layer for replacing and paving long steel rail of ballast line

By designing a long rail rail replacement and laying machine for ballast lines, the problems of low rail paving efficiency and insufficient equipment functionality in the existing technology are solved, efficient and multi-purpose equipment is realized, and construction is supported in multiple working conditions, reducing costs and personnel injuries. .

CN119021045APending Publication Date: 2024-11-26CHINA RAILWAY 12TH BUREAU GRP CO LTD +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411373976.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-29
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

The existing high-speed railway track laying methods are inefficient and the equipment is not functional enough, resulting in serious waste of equipment value and cannot meet the construction needs of multiple working conditions.

Method used

A ballast line long rail rail replacement laying machine was designed, including frame, cantilever frame, guide dragon mouth, reverse chain and lift rack. By improving the structure of the DJ20 simple rail laying machine, the laying function was added, and a The machine is multi-purpose, supporting efficient paving replacement of new and old rails and construction in various working conditions.

Benefits of technology

It improves construction efficiency, reduces equipment production costs, reduces personnel injuries, and realizes construction in various working conditions that cannot be achieved by traditional methods. It is not affected by tool rail joint plywood, and supports continuous paving change.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021045A_ABST
    Figure CN119021045A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of existing line steel rail replacement and laying, and particularly relates to a ballast line long steel rail replacement and laying machine. Comprising a machine frame, the machine frame comprises a connecting machine frame and an overhanging machine frame, and the connecting machine frame is connected with a flat car of a locomotive to support the overhanging machine frame; a first guide closure gap, a second guide closure gap, a third guide closure gap and a downslope closure gap are further included. The third guide closure gap, the second guide closure gap and the down-slope closure gap are sequentially arranged in the laying direction of the steel rails, the third guide closure gap is installed at the tail of the flat car and located outside the rail, and the first guide closure gap and the down-slope closure gap are installed on the overhanging rack and aligned with the laying position of the steel rails; the first guide closure gap is installed at the overhanging end of the overhanging rack and located below the downslope closure gap. Compared with a traditional manual replacing and laying method, the ballast line long steel rail replacing and laying machine can greatly improve the construction efficiency and reduce the harm of the steel rails to personnel during construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of replacing rails on existing lines, and in particular relates to a long rail replacing track laying machine for ballasted lines. Background Art

[0002] With the rapid development of my country's high-speed railways, the track laying methods of high-speed railways tend to be gradually mature. For the laying of ballasted lines, the current common construction methods in China are "single-sleeper continuous method", "push method" and "manual replacement method". At the same time, with the efforts of engineers, some mechanical replacement methods have also emerged, but these methods are either inefficient or insufficient in the functional exploitation of previous equipment, resulting in serious waste of residual value. In order to alleviate this situation, the purpose of the present invention is to develop a construction equipment that can be attached to existing equipment. Summary of the invention

[0003] An object of the present invention is to solve at least the above problems and to provide at least the advantages which will be described hereinafter.

[0004] The present invention provides the following technical solution: a long rail laying machine for ballasted line, comprising a frame, the frame comprising a connecting frame and a cantilever frame, the connecting frame is connected to a flatbed car of a locomotive to support the cantilever frame;

[0005] It also includes a No. 1 guide mouth, a No. 2 guide mouth, a No. 3 guide mouth and a downslope mouth; the No. 1 guide mouth, the No. 2 guide mouth, the No. 3 guide mouth and the downslope mouth are arranged in groups along the left and right rails;

[0006] The No. 3 guide mouth, No. 2 guide mouth and down-slope mouth are arranged in sequence along the direction of rail laying. The No. 3 guide mouth is installed at the rear of the flatbed car and is located outside the track. The No. 1 guide mouth and down-slope mouth are installed on the cantilever frame and aligned with the rail laying position. The No. 3 guide mouth and No. 2 guide mouth are used to guide the rails. The new rails outside the track are laid after passing through the No. 3 guide mouth, No. 2 guide mouth and down-slope mouth in sequence.

[0007] The No. 1 guide gantry is installed at the cantilever end of the cantilever frame. The No. 1 guide gantry is located below the slope gantry. The old rails pass through the No. 1 guide gantry and are led out to the outside of the track.

[0008] Furthermore, it also includes a No. 1 gantry, a No. 2 gantry, a first fall chain, a second fall chain and a third fall chain; the No. 1 gantry and the No. 2 gantry are installed on the cantilever frame, the No. 1 gantry and the No. 2 gantry are located between the No. 3 guide gantry and the No. 2 guide gantry, the first fall chain is installed on the crossbeam of the No. 1 gantry, the second fall chain is installed on the crossbeam of the No. 2 gantry, the third fall chain is installed on the connecting frame, and the third fall chain is located between the No. 3 guide gantry and the No. 1 gantry; the first fall chain, the second fall chain and the third fall chain are used to assist in lifting the rails and introduce the rails into the corresponding guide gantry.

[0009] Furthermore, a lifting frame is installed at the cantilever end of the cantilever frame, and the lifting frame is connected to the cantilever frame through a cylinder lifting system; the slope dragon mouth and the No. 1 guide dragon mouth are installed on the lifting frame.

[0010] Furthermore, two upper and lower support beams are provided on the lifting frame, the sloped dragon mouth can be slidably assembled on the top of the upper support beam, the No. 1 guide dragon mouth can be slidably hung on the bottom of the lower support beam, a first horizontal pushing cylinder is connected between the sloped dragon mouth and the upper support beam, and a second horizontal pushing cylinder is connected between the No. 1 guide dragon mouth and the lower support beam; the first horizontal pushing cylinder is used to adjust the lateral position of the sloped dragon mouth, and the second horizontal pushing cylinder is used to adjust the lateral position of the No. 1 guide dragon mouth.

[0011] Furthermore, the No. 1 guide dragon mouth includes a support seat, and the lateral rollers on the left and right sides of the support seat and the horizontal rollers on the bottom form a rail channel, the horizontal rollers are used to roll and support the bottom surface of the rail, and the lateral rollers on the left and right sides are used to limit the rail head of the rail; the structures of the No. 1 guide dragon mouth, the No. 2 guide dragon mouth and the No. 3 guide dragon mouth are the same; the support seat of the No. 1 guide dragon mouth is connected to the upper sliding seat, and the upper sliding seat can be slidably mounted on the support beam of the lower layer; the support seat of the No. 2 guide dragon mouth is installed on the cantilever frame by bolts; the support seat of the No. 3 guide dragon mouth is installed on the flatbed car by bolts; the downslope dragon mouth includes a support seat, lateral rollers, horizontal rollers and downslope slide grooves, and the downslope slide grooves are installed at the exit of the rail channel surrounded by the lateral rollers and the horizontal rollers; the support seat of the downslope dragon mouth is connected to the lower sliding seat, and the lower sliding seat can be slidably mounted on the support beam of the lower layer.

[0012] Furthermore, it also includes a rail pressing device, which is installed at the bottom of the cantilever frame and is located between the third fall chain and the second fall chain. The rail pressing device includes a bracket and a horizontal roller, and is used to prevent the rail from tilting and passing through from above.

[0013] Compared with the prior art, the advantages of the present invention are:

[0014] 1. Compared with the traditional mechanical replacement construction in terms of equipment, the present invention improves the structure of the DJ20 simple track laying machine so that the DJ20 simple track laying machine retains the original track laying performance while adding the function of replacement, thus achieving the expectation of one machine for multiple uses and reducing the cost of equipment manufacturing.

[0015] 2. Compared with the traditional "manual replacement method", the long rail replacement track laying machine for ballasted lines of the present invention will greatly improve the construction efficiency and reduce the damage caused by the rails to personnel during construction.

[0016] 3. The traditional construction method can only be used in one working condition, while the long rail laying machine for ballasted track of the present invention can meet the construction work of two different working conditions, namely "new rail outside the track, old rail outside the track (outside in and out)", "new rail outside the track, old rail installed to the guard rail position (outside in and inside out)".

[0017] 4. Not affected by the tool rail joint splint, can be changed continuously. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 The present invention is a side view of a track laying machine for replacing long rails on a ballasted line;

[0019] Figure 2 The present invention is a top view of a track laying machine for replacing long rails on a ballasted line;

[0020] Figure 3 This is a schematic diagram of the Shunpo Dragon Mouth and the No. 1 Guide Dragon Mouth;

[0021] Figure 4 This is a schematic diagram of the structure of the No. 1 guide dragon mouth.

[0022] In the figure: 1-connecting frame; 2-cantilever frame; 3-flatbed car; 4-No. 1 guide gantry; 4.1-support seat; 4.2-lateral roller; 4.3-horizontal roller; 5-No. 2 guide gantry; 6-No. 3 guide gantry; 7-slope gantry; 7.1-slope slide; 8-No. 1 door frame; 9-No. 2 door frame; 10-first fall chain; 11-second fall chain; 12-third fall chain; 13-lifting frame; 14-cylinder lifting system; 15-support beam; 16-first horizontal push cylinder; 17-second horizontal push cylinder; 18-upper sliding seat; 19-rail pressing device; 20-lower sliding seat. DETAILED DESCRIPTION

[0023] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0024] like Figure 1 , Figure 2As shown: a track laying machine for replacing long rails on ballasted lines, the track laying machine is a DJ20 type track laying machine, including a frame, the frame including a connecting frame 1 and a cantilever frame 2, the connecting frame 1 is connected to a flatbed car 3 of a locomotive to support the cantilever frame 2; a shoulder pole and a counterweight are installed on the connecting frame 1. It also includes a No. 1 guide mouth 4, a No. 2 guide mouth 5, a No. 3 guide mouth 6 and a downslope mouth 7; the No. 1 guide mouth 4, the No. 2 guide mouth 5, the No. 3 guide mouth 6 and the downslope mouth 7 are arranged in groups along the left and right rails.

[0025] The No. 3 guide mouth 6, the No. 2 guide mouth 5 and the down-slope mouth 7 are arranged in sequence along the direction of rail laying, the No. 3 guide mouth 6 is installed at the tail of the flatbed car 3, the No. 3 guide mouth 6 is located outside the track, the No. 1 guide mouth 4 and the down-slope mouth 7 are installed on the cantilever frame 2 and aligned with the rail laying position; the No. 3 guide mouth 6 and the No. 2 guide mouth 5 are used to guide the rails; the new rails outside the track are laid after passing through the No. 3 guide mouth 6, the No. 2 guide mouth 5 and the down-slope mouth 7 in sequence; the new rails are guided to the rail bearing groove under the guiding action of the No. 3 guide mouth 6, the No. 2 guide mouth 5 and the down-slope mouth 7.

[0026] The No. 1 guide gantry 4 is installed at the cantilever end of the cantilever frame 2, and the No. 1 guide gantry 4 is located below the slope gantry 7. The old rail passes through the No. 1 guide gantry 4 and is led out of the track; the old rail is pushed away from the rail bearing groove with the help of the No. 1 guide gantry 4.

[0027] The long rail laying machine for ballasted line has two working modes, namely locomotive traction laying and locomotive push laying.

[0028] Locomotive-driven track laying: the locomotive is in front, and the ballasted line long rail laying machine is behind (the front specifically refers to the construction direction and the starting direction of track laying).

[0029] Locomotive-driven track laying: the equipment is in front, and the ballasted line long rail laying track laying machine is behind (the front specifically refers to the construction direction and the direction in which track laying starts).

[0030] It also includes a No. 1 gantry 8, a No. 2 gantry 9, a first fall chain 10, a second fall chain 11 and a third fall chain 12; the No. 1 gantry 8 and the No. 2 gantry 9 are installed on the cantilever frame 2, the No. 1 gantry 8 and the No. 2 gantry 9 are located between the No. 3 guide gantry 6 and the No. 2 guide gantry 5, the first fall chain 10 is installed on the crossbeam of the No. 1 gantry 8, the second fall chain 11 is installed on the crossbeam of the No. 2 gantry 9, the third fall chain 12 is installed on the connecting frame 1, and the third fall chain 12 is located between the No. 3 guide gantry 6 and the No. 1 gantry 8; the first fall chain 10, the second fall chain 11 and the third fall chain 12 are used to assist in lifting the rails and introduce the rails into the corresponding guide gantry.

[0031] like Figure 3As shown: the cantilever end of the cantilever frame 2 is equipped with a lifting frame 13, and the lifting frame 13 is connected to the cantilever frame 2 through a cylinder lifting system 14; the sloping dragon mouth 7 and the No. 1 guide dragon mouth 4 are installed on the lifting frame 13. The height of the sloping dragon mouth 7 and the No. 1 guide dragon mouth 4 is adjusted by the lifting frame 13 to relieve the rebound force when the rail falls.

[0032] An upper and lower support beam 15 is provided on the lifting frame 13. The sloping dragon mouth 7 can be slidably assembled on the top of the upper support beam 15, and the No. 1 guide dragon mouth 4 can be slidably hung on the bottom of the lower support beam 15. A first horizontal pushing cylinder 16 is connected between the sloping dragon mouth 7 and the upper support beam 15, and a second horizontal pushing cylinder 17 is connected between the No. 1 guide dragon mouth 4 and the lower support beam 15; the first horizontal pushing cylinder 16 is used to adjust the lateral position of the sloping dragon mouth 7, and the second horizontal pushing cylinder 17 is used to adjust the lateral position of the No. 1 guide dragon mouth 4.

[0033] like Figure 4 As shown: the No. 1 guide gantry 4 includes a support seat 4.1, lateral rollers 4.2 on the left and right sides of the support seat 4.1 and a horizontal roller 4.3 at the bottom to form a rail channel, the horizontal roller 4.3 is used to roll and support the bottom surface of the rail, and the lateral rollers 4.2 on the left and right sides are used to limit the rail head of the rail; the No. 1 guide gantry 4, the No. 2 guide gantry 5 and the No. 3 guide gantry 6 have the same structure; the support seat of the No. 1 guide gantry 4 is connected to the upper sliding seat 18, and the upper sliding seat 18 can be slidably sleeved on the support beam 15 of the lower layer; The support seat of the No. 2 guide dragon mouth 5 is installed on the cantilever frame 2 by bolts; the support seat of the No. 3 guide dragon mouth 6 is installed on the flatbed car 3 by bolts; the downslope dragon mouth 7 includes a support seat 4.1, a lateral roller 4.2, a horizontal roller 4.3 and a downslope slide 7.1, and the downslope slide 7.1 is installed at the exit of the rail channel surrounded by the lateral roller 4.2 and the horizontal roller 4.3; the support seat 4.1 of the downslope dragon mouth 7 is connected to the lower sliding seat 20, and the lower sliding seat 20 can be slidably mounted on the support beam 15 of the lower layer.

[0034] It also includes a rail pressing device 19, which is installed at the bottom of the cantilever frame 2. The rail pressing device 19 is located between the third fall chain 12 and the second fall chain 11. The rail pressing device 19 includes a bracket and a horizontal roller. The rail pressing device 19 is used to prevent the rail from tilting and passing through from above.

[0035] Long rail replacement process of a ballasted line long rail replacement track laying machine:

[0036] 1.1 Check the equipment to ensure normal construction. Before the replacement construction, due to the high efficiency of the track laying machine, the inner fasteners within the construction unit range are completely removed in advance and checked for omissions. Here, the fasteners are "single-sided release" method is adopted, which can not only quickly replace the pavement, but also ensure safe driving.

[0037] 1.2 Locomotive alignment:

[0038] 1.2.1 The new rail passes through the No. 3 guide hole 6, the No. 2 guide hole 5 and the Shunpo hole 7 in sequence:

[0039] First, remove the horizontal roller of the No. 3 guide mouth 6, align the rail head of the new rail to the No. 3 guide mouth 6, use the third fall chain 12 to lift the rail head to the height of the No. 3 guide mouth 6, run the locomotive to make the new rail pass through the No. 3 guide mouth 6 and then stop, install the horizontal roller of the No. 3 guide mouth 6 and then release the third fall chain 12, and try to pull the locomotive to make the new rail continue to pass through the No. 2 guide mouth 5 and the slope mouth 7 (in this process, use the second fall chain 11 and the third fall chain 12 to adjust the rail head of the new rail), and the alignment of the new rail is completed.

[0040] 1.2.2 The old rail passes through the No. 1 guide hole 4:

[0041] Align the rail head of the old rail to the No. 1 guide mouth 4, use the first fall chain 10 to hang the rail head and lift it to the height of the No. 1 guide mouth 4 and adjust the No. 1 guide mouth 4 laterally, then the locomotive tries to pull the old rail through the No. 1 guide mouth 4 and then release the first fall chain 10, and the alignment of the old rail is completed.

[0042] 1.3 Locomotive traction rail change:

[0043] 1.3.1 Check the road conditions around the locomotive;

[0044] 1.3.2 Start the locomotive and report the rail replacement situation to the locomotive driver in real time;

[0045] 1.3.3 The new rails are outside the track, and the old rails are placed outside the track (outside in and out):

[0046] Adjust the sloped dragon mouth 7 to the groove, and the No. 1 guide dragon mouth 4 to the outside of the road, and then the replacement operation can be carried out.

[0047] 1.3.4 The new rails are outside the track and the old rails are installed to the guard rail position (outside in and inside out):

[0048] Adjust the downslope gantry 7 to fit into the groove, and align the No. 1 guide gantry 4 with the center of the track, and then the re-laying operation can be carried out;

[0049] 1.3.5 Adjust the lifting frame 13 and place the buffer pads:

[0050] When the rail replacement is almost finished, place the buffer pad. Adjust the height of the lifting frame 13 to release the stress of the rail part to prevent the rail from rebounding.

[0051] 1.3.6 Long rails fall to the ground and fasteners are locked:

[0052] After the rails land, use the track lifter to lift the rails and remove the buffer blocks. Then use the screw machine to install the fasteners and lock the rails.

[0053] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A long rail laying machine for ballasted track, comprising a frame, the frame comprising a connecting frame (1) and a cantilever frame (2), the connecting frame (1) being connected to a flatbed car (3) of a locomotive to support the cantilever frame (2); Features: It also includes a No. 1 guide mouth (4), a No. 2 guide mouth (5), a No. 3 guide mouth (6) and a downslope mouth (7); the No. 1 guide mouth (4), the No. 2 guide mouth (5), the No. 3 guide mouth (6) and the downslope mouth (7) are arranged in groups along the left and right rails respectively; The No. 3 guide gantry (6), the No. 2 guide gantry (5) and the downhill gantry (7) are arranged in sequence along the direction of laying the rails. The No. 3 guide gantry (6) is installed at the rear of the flatbed car (3). The No. 3 guide gantry (6) is located outside the track. The No. 1 guide gantry (4) and the downhill gantry (7) are installed on the cantilever frame (2) and aligned with the rail laying position. The No. 3 guide gantry (6) and the No. 2 guide gantry (5) are used to guide the rails. The new rails outside the track are laid after passing through the No. 3 guide gantry (6), the No. 2 guide gantry (5) and the downhill gantry (7) in sequence. A guide gantry (4) is installed at the cantilever end of the cantilever frame (2). The guide gantry (4) is located below the slope gantry (7). The old rail passes through the guide gantry (4) and is led out to the outside of the track.

2. A ballasted track long rail laying machine according to claim 1, Features: The invention also comprises a first gantry (8), a second gantry (9), a first fall chain (10), a second fall chain (11) and a third fall chain (12); the first gantry (8) and the second gantry (9) are installed on the cantilever frame (2); the first gantry (8) and the second gantry (9) are located between the third guide gantry (6) and the second guide gantry (5); the first fall chain (10) is installed on the cross beam of the first gantry (8); the second fall chain (11) is installed on the cross beam of the second gantry (9); the third fall chain (12) is installed on the connecting frame (1); the third fall chain (12) is located between the third guide gantry (6) and the first gantry (8); the first fall chain (10), the second fall chain (11) and the third fall chain (12) are used to assist in lifting the rails and guide the rails into the corresponding guide gantry.

3. A ballasted track long rail laying machine according to claim 2, Features: A lifting frame (13) is installed at the cantilever end of the cantilever frame (2), and the lifting frame (13) is connected to the cantilever frame (2) through an oil cylinder lifting system (14); the slope dragon mouth (7) and the first guide dragon mouth (4) are installed on the lifting frame (13).

4. A ballasted line long rail laying machine according to claim 3, Features: The lifting frame (13) is provided with two upper and lower support beams (15); the sloping dragon mouth (7) can be slidably assembled on the top of the upper support beam (15); the No. 1 guide dragon mouth (4) can be slidably suspended on the bottom of the lower support beam (15); a first horizontal push cylinder (16) is connected between the sloping dragon mouth (7) and the upper support beam (15); a second horizontal push cylinder (17) is connected between the No. 1 guide dragon mouth (4) and the lower support beam (15); the first horizontal push cylinder (16) is used to adjust the horizontal position of the sloping dragon mouth (7); the second horizontal push cylinder (17) is used to adjust the horizontal position of the No. 1 guide dragon mouth (4).

5. The long rail laying machine for ballasted track according to claim 1, Features: The No. 1 guide gantry (4) comprises a support seat (4.1), lateral rollers (4.2) on the left and right sides of the support seat (4.1) and a horizontal roller (4.3) at the bottom form a rail channel, the horizontal roller (4.3) is used to roll and support the bottom surface of the rail, and the lateral rollers (4.2) on the left and right sides are used to limit the rail head of the rail; the No. 1 guide gantry (4), the No. 2 guide gantry (5) and the No. 3 guide gantry (6) have the same structure; the support seat of the No. 1 guide gantry (4) is connected to the upper sliding seat (18), and the upper sliding seat (18) can be slidably mounted on the support beam (15) of the lower layer; the No. 2 guide gantry (4) is connected to the upper sliding seat (18), and the upper sliding seat (18) can be slidably mounted on the support beam (15) of the lower layer; The support seat of the forward dragon mouth (5) is installed on the cantilever frame (2) by bolts; the support seat of the No. 3 guide dragon mouth (6) is installed on the flatbed car (3) by bolts; the downhill dragon mouth (7) includes a support seat (4.1), a lateral roller (4.2), a horizontal roller (4.3) and a downhill slide (7.1), and the downhill slide (7.1) is installed at the exit of the rail channel surrounded by the lateral roller (4.2) and the horizontal roller (4.3); the support seat (4.1) of the downhill dragon mouth (7) is connected to the lower sliding seat (20), and the lower sliding seat (20) can be slidably mounted on the support beam (15) of the lower layer.

6. A long rail laying machine for ballasted track according to any one of claims 2 to 5, Features: The invention also comprises a rail pressing device (19), which is installed at the bottom of the cantilever frame (2), and is located between the third fall chain (12) and the second fall chain (11). The rail pressing device (19) comprises a bracket and a horizontal roller, and is used to prevent the rail from tilting and passing through from above.