Pressure relief method for external dislocation area of open-off cut of rock burst mine
By adjusting the spacing distance and number of blasting hole groups and blasting in a fan-shaped arrangement, the problem of poor pressure relief effect in an error area outside the impact ground pressure mine is solved, and safety is improved and the safety of the mine is ensured.
Patent Information
- Application Number
- CN202411299771.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-18
- Publication Date
- 2024-11-26
AI Technical Summary
During the mining of impact ground pressure mines, the pressure relief effect of the wrong area outside the cut-out eye is poor, resulting in the inability to guarantee safety.
By determining the tunnel mining status corresponding to the first cut-out eye and the coal mine status in the outer wrong area, adjusting the spacing distance and number of adjacent blasting hole groups, and drilling and explosive blasting are carried out in the form of a fan-shaped arrangement to release the elasticity of the top plate storage Potential energy.
It improves the pressure relief effect of the wrong area outside the opening eye, enhances safety, effectively reduces the risk of impact ground pressure, and ensures the safety of the mine.
Smart Images

Figure CN119021695A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of coal mines, and in particular to a method for relieving pressure in an outer offset area of a rock burst mine cut. Background Art
[0002] Roof blasting is to increase the cracks in the roof rock mass, destroy the integrity and continuity of the roof, and release the elastic energy stored in the roof. During the mining process of rock burst mines, the phenomenon of external dislocation of the cut eye occurs. In the relevant technology, the section coal pillar roof blasting method is usually used to relieve the pressure in the area of external dislocation of the cut eye. However, the pressure relief effect of the section coal pillar is not good, and the safety of the area of external dislocation of the cut eye cannot be guaranteed. Summary of the invention
[0003] The present invention aims to solve one of the technical problems in the related art to at least some extent. To this end, an embodiment of the present invention proposes a pressure relief method for the outer offset area of the cut hole in a rock burst mine, which can improve the pressure relief effect of the outer offset area of the cut hole and improve safety.
[0004] The method for relieving pressure in the outer offset area of an opening in a rock burst mine according to an embodiment of the present invention comprises: determining the coal mine state of the outer offset area of a second opening compared to the first opening according to the mining state of a tunnel corresponding to the first opening, wherein the first opening and the second opening are arranged adjacent to each other in the width direction of the working face; determining the spacing distance between adjacent first blasting hole groups on a side of a first tunnel adjacent to the first opening according to the coal mine state of the outer offset area, wherein the first tunnel is connected to the second opening and is adjacent to the first opening compared to the second tunnel; determining the number of first blasting hole groups according to the spacing distance between adjacent first blasting hole groups on one side of the first opening and the size of the outer offset area in the excavation direction of the working face; drilling a plurality of first blasting hole groups in a fan-shaped arrangement, and installing explosives in each group of the first blasting holes for blasting.
[0005] The method for relieving pressure in the outer offset area of the cut hole in a rock burst mine according to the embodiment of the present invention can improve the pressure relief effect of the outer offset area of the cut hole and improve safety.
[0006] In some embodiments, determining the coal mine status of the outer offset area of the second opening eye compared with the first opening eye based on the mining status of the roadway corresponding to the first opening eye includes: when the mining status of the roadway corresponding to the first opening eye is a goaf, determining the coal mine status of the outer offset area of the second opening eye as a segmented coal pillar; when the mining status of the roadway corresponding to the first opening eye is a working face, determining the coal mine status of the outer offset area of the second opening eye as solid coal.
[0007] In some embodiments, when the mining state of the tunnel corresponding to the first opening is a goaf, the spacing distance between adjacent first blasting hole groups is smaller than the spacing distance between adjacent first blasting hole groups when the mining state of the tunnel corresponding to the first opening is a working face.
[0008] In some embodiments, the spacing distance between adjacent first blasting hole groups on the side of the first tunnel adjacent to the first opening eye is determined according to the coal mine status of the outer staggered area, including: when the coal mine status of the outer staggered area of the second opening eye is a segmented coal pillar, the spacing distance between two adjacent first blasting hole groups is 5m-10m; when the coal mine status of the outer staggered area of the second opening eye is solid coal, the spacing distance between two adjacent first blasting hole groups is 10m-20m.
[0009] In some embodiments, the pressure relief method also includes: drilling on the other side of the first tunnel away from the first opening to form a plurality of second blasting hole groups, wherein the plurality of second blasting hole groups are arranged at intervals in the excavation direction of the working face, and each of the second blasting hole groups is drilled in a fan-shaped arrangement.
[0010] In some embodiments, the distance between two adjacent groups of the second blasting holes in the excavation direction of the working face is 10m-20m.
[0011] In some embodiments, the number of first blasting holes in each of the first blasting hole groups is 2 to 4, and the multiple first blasting holes in each group of the first blasting holes are arranged in a fan shape; and / or, the number of second blasting holes in each of the second blasting hole groups is 2 to 4, and the multiple second blasting holes in each group of the second blasting holes are arranged in a fan shape.
[0012] In some embodiments, the first blasting hole extends in a direction away from the first tunnel, the second blasting hole extends in a direction away from the first tunnel, and the extending direction of the first blasting hole is opposite to the extending direction of the second blasting hole.
[0013] In some embodiments, the hole depth of one first blasting hole among two adjacent first blasting holes in each group of the first blasting holes is greater than the hole depth of the other first blasting hole, and the inclination angle of the one first blasting hole is smaller than the inclination angle of the other first blasting hole; and / or, the hole depth of one second blasting hole among two adjacent second blasting holes in each group of the second blasting holes is greater than the hole depth of the other second blasting hole, and the inclination angle of the one second blasting hole is smaller than the inclination angle of the other second blasting hole.
[0014] In some embodiments, the first blast hole is disposed adjacent to a shoulder socket of the first tunnel; and / or the second blast hole is disposed adjacent to a shoulder socket of the first tunnel. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of a method for relieving pressure in an outer offset area of a rock burst mine cut according to an embodiment of the present invention.
[0016] Figure 2 It is a schematic diagram of blasting holes in the outer offset area of the cut hole in a rock burst mine according to an embodiment of the present invention.
[0017] Figure 3 It is a schematic diagram of another perspective of the blasting hole in the outer offset area of the cut hole in the rock burst mine according to an embodiment of the present invention.
[0018] Reference numerals:
[0019] First opening cut 1, second opening cut 2, working surface 3,
[0020] The first lane 41, the second lane 42, the third lane 43, the fourth lane 44,
[0021] The first blasting hole 51, the second blasting hole 52, the third blasting hole 53,
[0022] Section coal pillar 61, bottom plate 71, top plate 72. DETAILED DESCRIPTION
[0023] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and intended to be used to explain the present invention, but should not be understood as limiting the present invention.
[0024] like Figure 1 As shown, the pressure relief method for the outer offset area of the opening eye of a rock burst mine according to the embodiment of the present invention includes: determining the coal mine state of the outer offset area of the second opening eye compared to the first opening eye according to the mining state of the tunnel corresponding to the first opening eye, wherein the first opening eye and the second opening eye are arranged adjacent to each other in the width direction of the working face. Determine the spacing distance between adjacent first blast hole groups on the side of the first tunnel adjacent to the first opening eye according to the coal mine state of the outer offset area, wherein the first tunnel is connected to the second opening eye and is adjacent to the first opening eye compared to the second tunnel. Determine the number of first blast hole groups according to the spacing distance between adjacent first blast hole groups on one side of the first opening eye and the size of the outer offset area in the excavation direction of the working face. Drill multiple first blast hole groups in a fan-shaped arrangement, and install explosives in each group of first blast hole for blasting.
[0025] It should be noted that the inventors found that the method of segmen- tary coal pillar roof blasting was used to relieve pressure in the outer offset area of the cut eye in a rock burst mine. Since the segmen- tary coal pillar side of the outer offset area of the cut eye is actually solid coal, not a simple segmen- tary coal pillar, the use of segmen- tary coal pillar roof blasting will increase the cracks in the roof rock mass, destroy the integrity and continuity of the roof, and release the elastic energy stored in the roof. However, compared with the blasting of the roof on the solid coal side, it cannot effectively release the elastic potential energy stored in the roof, resulting in the impact hazard of the outer offset area of the cut eye still existing, causing certain safety hazards to the working face production, and it is difficult to ensure the safety of the outer offset area.
[0026] Specifically, Figure 2 and Figure 3 As shown, the first opening eye 1 and the second opening eye 2 are adjacent and spaced apart in the width direction of the working surface 3, the width direction of the working surface 3 is consistent with the left-right direction, and the first opening eye 1 and the second opening eye 2 are spaced apart in the front-to-back direction, the second opening eye 2 is located at the rear end of the first opening eye 1, and the second opening eye 2 is offset backward in the front-to-back direction compared to the first opening eye 1 to form an external misalignment area, and this external misalignment area will cause stress concentration and increase the risk of impact ground pressure.
[0027] The first lane 41 and the second lane 42 are arranged at intervals in the left-right direction, and the first lane 41 and the second lane 42 are both connected to the second opening eye 2. The first lane 41 is arranged adjacent to the first opening eye 1. The area between the first lane 41 and the second lane 42 corresponding to the second opening eye 2 is the working surface 3, and the working surface 3 is located between the top plate 72 and the bottom plate 71. It can be understood that one of the first lane 41 and the second lane 42 is an air inlet lane, and the other is a return air lane. The lane corresponding to the first opening eye 1 refers to the third lane 43 and the fourth lane 44 connected to the first opening eye 1. The third lane 43 and the fourth lane 44 are arranged at intervals in the left-right direction. One of the third lane 43 and the fourth lane 44 is an air inlet lane, and the other is a return air lane.
[0028] The method for relieving pressure in the outer staggered area of an opening eye in a rock burst mine according to the embodiment of the present invention determines the coal mine status of the outer staggered area of a second opening eye by the mining status of the tunnel where the first opening eye is located, and determines the spacing distance between the first blasting hole groups on the left side of the first tunnel according to the coal mine status of the outer staggered area, and then determines the number of the first blasting hole groups according to the spacing distance between the first blasting hole groups and the size of the outer staggered area in the front-to-back direction, and drills holes in a fan-shaped arrangement according to the determined number and spacing of the first blasting hole groups, and blasts by installing explosives in the first blasting holes to release the elastic potential energy stored in the roof to relieve pressure, thereby ensuring the pressure relief effect of the outer staggered area of the opening eye and improving the safety of the outer staggered area.
[0029] Furthermore, in this embodiment, the coal mine status of the outer staggered area of the first opening is determined by the mining status of the tunnel corresponding to the first opening, so that the actual situation of the outer staggered area of the opening can be determined, the design accuracy of the blasting hole is improved, the prevention and control of the risk of rock burst is effectively improved, the safety factor of operations in the rock burst risk area is further improved, and the safety of the mine is increased.
[0030] In some embodiments, the coal mine status of the outer offset area of the second opening eye compared with the first opening eye is determined according to the mining status of the tunnel corresponding to the first opening eye, including: when the mining status of the tunnel corresponding to the first opening eye is a goaf, determining the coal mine status of the outer offset area of the second opening eye as a segmented coal pillar; when the mining status of the tunnel corresponding to the first opening eye is a working face, determining the coal mine status of the outer offset area of the second opening eye as solid coal.
[0031] Specifically, the mining state of the tunnel corresponding to the first opening eye 1 refers to the mining state of the area between the third tunnel 43 and the fourth tunnel 44. When the mining state of the area between the third tunnel 43 and the fourth tunnel 44 is a goaf, the outer staggered area of the second opening eye 2 is determined to be a segmented coal pillar 61. When the mining state of the area between the third tunnel 43 and the fourth tunnel 44 is a working face 3, the outer staggered area of the second opening eye 2 is determined to be solid coal. By determining the coal mine state of the outer staggered area based on the mining state of the area between the third tunnel 43 and the fourth tunnel 44, the coal mine state of the outer staggered area can be determined according to actual conditions, providing a reference for the design of blasting holes in the outer staggered area, reducing the stress concentration phenomenon in the outer staggered area of the second opening eye 2, preventing the emergence of rock burst, and improving the pressure relief effect.
[0032] For example, in this embodiment, the mining state of the tunnel corresponding to the first cutting eye 1 is a goaf, and the coal mine state of the outer offset area of the second cutting eye 2 is a section coal pillar 61.
[0033] Furthermore, in this embodiment, by determining the parameters of the drilling arrangement form and the spacing and number of blasting holes when roof blasting is used in the outer staggered area of the cut eye in the rock burst mine, it can be applied to the outer staggered area of the cut eye in the rock burst mine, with a wide range of applications, filling the gap in the related technology for roof blasting in the outer staggered area of the cut eye, and improving the roof pressure relief effect.
[0034] In some embodiments, when the tunnel corresponding to the mining state of the first opening cut is a goaf, the spacing distance between adjacent first blasting hole groups is smaller than the spacing distance between adjacent first blasting hole groups when the mining state of the tunnel corresponding to the first opening cut is a working face.
[0035] Specifically, when the mining status of the area between the third tunnel and the fourth tunnel is a goaf, it means that the area between the third tunnel and the fourth tunnel has been mined. Mined means that the left rear end of the first tunnel is solid coal, and the left front end of the first tunnel is a goaf, and the roof stress is prone to concentration. When the mining status of the area between the third tunnel and the fourth tunnel is a working face, it means that the area between the third tunnel and the fourth tunnel has not been mined. The unmined state means that the left side of the first tunnel is solid coal. When the left side of the first tunnel is solid coal, the roof stress is evenly distributed. In this embodiment, the spacing distance of the first blasting hole group in the front and rear directions is limited by the coal mine status in two different situations to improve the pressure relief effect of the blasting holes.
[0036] In some embodiments, the spacing distance between adjacent first blasting hole groups on one side of the first tunnel adjacent to the first opening eye is determined according to the coal mine status of the outer staggered area, including: when the coal mine status of the outer staggered area of the second opening eye is a segmented coal pillar, the spacing distance between two adjacent first blasting hole groups is 5m-10m; when the coal mine status of the outer staggered area of the second opening eye is solid coal, the spacing distance between two adjacent first blasting hole groups is 10m-20m.
[0037] The embodiment of the present invention determines different spacing distances between adjacent first blasting hole groups according to different coal mine conditions of the outer staggered area of the second opening, that is, adjusts the spacing distance of the first blasting hole group in the front-to-back direction under different coal mine conditions to ensure the pressure relief effect of the outer staggered area of the opening.
[0038] In some embodiments, the pressure relief method also includes: drilling on the other side of the first tunnel away from the first opening to form a plurality of second blasting hole groups, wherein the plurality of second blasting hole groups are arranged at intervals in the excavation direction of the working face, and each second blasting hole group is drilled in a fan-shaped arrangement.
[0039] Specifically, a plurality of groups of second blasting holes 52 are arranged on the right side of the first tunnel 41. In other words, a plurality of groups of first blasting holes 51 are arranged on the left side of the first tunnel 41, and a plurality of groups of second blasting holes 52 are arranged on the right side of the first tunnel 41. The top plate 72 of the outer offset area of the second opening 2 is depressurized through the first blasting holes 51, and the top plate 72 of the area between the first tunnel 41 and the second tunnel 42 is depressurized through the second blasting holes 52.
[0040] Optionally, a plurality of groups of third blasting holes 53 are provided on the left side of the second tunnel 42 , and the third blasting holes 53 and the second blasting holes 52 are symmetrically arranged.
[0041] In some embodiments, the distance between two adjacent groups of second blasting holes in the excavation direction of the working face is 10m-20m.
[0042] In this embodiment, the spacing distance between adjacent second blasting hole groups in the front-to-back direction is limited to avoid the spacing distance between adjacent second blasting hole groups in the front-to-back direction being too large, which will result in poor pressure relief effect. At the same time, it is also avoided that the spacing distance between adjacent second blasting hole groups in the front-to-back direction is too small, which will affect the stability of the top plate, thereby ensuring the pressure relief effect of the second blasting holes.
[0043] In some embodiments, the number of first blasting holes in each first blasting hole group is 2 to 4, and the multiple first blasting holes in each group of first blasting holes are arranged in a fan shape.
[0044] The number of first blasting holes in multiple groups of first blasting hole groups can be set to be the same or different. For example, the number of first blasting holes in the first group of first blasting hole groups is three, the number of first blasting holes in the second group of first blasting hole groups is four, and the number of first blasting holes in the third group of first blasting hole groups is two. In this embodiment, the number of first blasting holes in multiple groups of first blasting holes is set to three.
[0045] In some embodiments, the number of second blasting holes in each second blasting hole group is 2 to 4, and the plurality of second blasting holes in each group of second blasting holes are arranged in a fan shape.
[0046] The number of second blasting holes in multiple groups of second blasting hole groups can be set to be the same or different. For example, the number of second blasting holes in the first group of second blasting hole groups is three, the number of second blasting holes in the second group of second blasting hole groups is four, and the number of second blasting holes in the third group of second blasting hole groups is two. In this embodiment, the number of second blasting holes in multiple groups of second blasting holes is set to three.
[0047] In some embodiments, the first blasting hole extends in a direction away from the first tunnel, the second blasting hole extends in a direction away from the first tunnel, and the extending direction of the first blasting hole is opposite to the extending direction of the second blasting hole.
[0048] Specifically, Figure 3 As shown, the first blasting hole extends to the left, and the second blasting hole extends to the right. The roof of the outer offset area of the second open cut on the left is blasted through the first blasting hole, and the roof of the working face between the first tunnel and the second tunnel on the right is blasted through the second blasting hole to ensure the safety of working face mining.
[0049] In some embodiments, the hole depth of one first blasting hole among two adjacent first blasting holes in each group of first blasting holes is greater than the hole depth of the other first blasting hole, and the inclination angle of one first blasting hole is smaller than the inclination angle of the other first blasting hole.
[0050] It can be understood that the hole depth of the first blasting hole refers to the distance between the opening position and the end hole position of a blasting hole, the inclination angle of the first blasting hole refers to the angle between the connecting line between the opening position and the end hole position of the first blasting hole and the water surface line, the height of the first blasting hole refers to the height difference between the opening position and the end hole position of the first blasting hole, and the horizontal distance of the first blasting hole refers to the horizontal distance between the opening position and the end hole position of the first blasting hole.
[0051] For the convenience of description, it is described by taking the example that each group of first blasting holes includes three first blasting holes. The depth of the first first blasting hole is smaller than the depth of the second first blasting hole, and the depth of the second first blasting hole is smaller than the depth of the third first blasting hole. Accordingly, the inclination angle of the first first blasting hole is greater than the inclination angle of the second first blasting hole, and the inclination angle of the second first blasting hole is greater than the inclination angle of the third first blasting hole.
[0052] In some embodiments, the hole depth of one second blasting hole among two adjacent second blasting holes in each group of second blasting holes is greater than the hole depth of the other second blasting hole, and the inclination angle of one second blasting hole is smaller than the inclination angle of the other second blasting hole.
[0053] For the convenience of description, it is described as an example that each group of second blasting holes includes three second blasting holes. The depth of the first second blasting hole is smaller than the depth of the second second blasting hole, and the depth of the second second blasting hole is smaller than the depth of the third second blasting hole. Accordingly, the inclination angle of the first second blasting hole is greater than the inclination angle of the second second blasting hole, and the inclination angle of the second second blasting hole is greater than the inclination angle of the third second blasting hole.
[0054] In some embodiments, the first blast hole is disposed adjacent to a shoulder socket of the first tunnel.
[0055] In some embodiments, the second blast hole is disposed adjacent to a shoulder socket of the first tunnel.
[0056] The opening position of the first blasting hole in the outer offset area of the cutting eye in this embodiment is arranged near the shoulder of the first tunnel, and the blasting holes of the advance coal mining working face are arranged in a fan shape. It is appropriate to arrange 2 to 4 blasting holes in each fan-shaped section, and the row spacing is preferably 5m to 10m. When the outer offset area is small, the blasting is completed before the working face is put into production; when the outer offset area is large, the advance coal mining working face should not be less than 150m. The size of the outer offset area is not limited in this embodiment, and it is subject to the specific implementation. For example, it can be a specific value of 50 meters or 100 meters.
[0057] In this embodiment, the opening position of the second blasting hole is arranged near the shoulder of the first tunnel, and the blasting holes of the advanced coal mining working face are arranged in a fan shape. Two to four blasting holes should be arranged in each fan-shaped section, and the row spacing should be 10m to 20m. The advanced coal mining working face should not be less than 150m.
[0058] Optionally, the diameters of the first blasting hole and the second blasting hole are 42 mm-100 mm, and the depths of the first blasting hole and the second blasting hole are greater than 10 meters to ensure the blasting effects of the first blasting hole and the second blasting hole.
[0059] The explosives used shall be coal mine explosives with a safety level not lower than level 2, and the charge per hole shall not exceed 100kg; the detonators shall be instantaneous electric detonators permitted in coal mines, millisecond delay electric detonators permitted in coal mines, or digital electric detonators permitted in coal mines, with no less than 2 per hole, and the connection shall generally be parallel in the hole and series between holes; the charge uncoupling coefficient shall not be greater than 1.5; the conductor nominal cross-section of the blasting busbar shall not be less than 1.0mm 2 Coal mines are allowed to use double-core busbars, and the busbar length should meet the distance for avoiding blasting. The sealing material is blister mud, clay blasting mud or blasting mud made of other non-combustible, plastic loose materials. The sealing length should not be less than 1 / 3 of the hole depth and should not be less than 5m.
[0060] In the description of the present invention, it is to be understood that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, “axial”, “radial”, “circumferential”, etc., indicating orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.
[0061] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0062] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0063] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or that the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0064] In the present invention, the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" etc. mean that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the described specific features, structures, materials or characteristics may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.
[0065] It is to be understood that the above embodiments are exemplary and are not to be construed as limiting the present invention. A person skilled in the art may change, modify, replace and modify the above embodiments within the scope of the present invention.
Claims
1. A method for relieving pressure in the outer offset area of a rock burst mine cut, characterized in that: include: Determine the coal mine status of the outer offset area of the second opening eye compared to the first opening eye according to the mining status of the roadway corresponding to the first opening eye, wherein the first opening eye and the second opening eye are arranged adjacent to each other in the width direction of the working face; Determine the spacing distance between adjacent first blasting hole groups on one side of a first roadway adjacent to the first opening cut according to the coal mine status of the outer staggered area, wherein the first roadway is connected to the second opening cut and is closer to the first opening cut than the second roadway; Determine the number of the first blast hole groups according to the spacing distance between adjacent first blast hole groups on one side of the first cut hole and the size of the outer staggered area in the excavation direction of the working face; A plurality of the first blasting hole groups are drilled in a fan-shaped arrangement, and explosives are installed in each group of the first blasting holes for blasting.
2. The method for relieving pressure in the outer offset area of the rock burst mine according to claim 1 is characterized in that: The step of determining the coal mine status of the outer offset area of the second opening cut compared to the first opening cut according to the mining status of the roadway corresponding to the first opening cut includes: When the mining state of the roadway corresponding to the first opening cut is a goaf, determining the coal mine state of the outer offset area of the second opening cut is a section coal pillar; When the mining state of the tunnel corresponding to the first cutting eye is a working face, it is determined that the coal mine state of the outer offset area of the second cutting eye is solid coal.
3. The method for relieving pressure in the outer offset area of the rock burst mine according to claim 2 is characterized in that: When the mining state of the tunnel corresponding to the first opening hole is a goaf, the spacing distance between adjacent first blasting hole groups is smaller than the spacing distance between adjacent first blasting hole groups when the mining state of the tunnel corresponding to the first opening hole is a working face.
4. The method for relieving pressure in the outer offset area of the rock burst mine according to claim 3 is characterized in that: The step of determining the spacing distance between adjacent first blasting hole groups on one side of the first tunnel adjacent to the first opening hole according to the coal mine status of the outer staggered area comprises: When the coal mine state in the outer staggered area of the second opening hole is a section coal pillar, the interval distance between two adjacent first blast hole groups is 5m-10m; When the coal mine state of the outer staggered area of the second cutting hole is solid coal, the interval distance between two adjacent first blasting hole groups is 10m-20m.
5. The method for relieving pressure in the outer offset area of the rock burst mine according to claim 2, characterized in that: The pressure relief method further comprises: A plurality of second blasting hole groups are formed by drilling on the other side of the first tunnel away from the first opening, wherein the plurality of second blasting hole groups are arranged at intervals in the excavation direction of the working face, and each of the second blasting hole groups is drilled in a fan-shaped arrangement.
6. The method for relieving pressure in the outer offset area of the rock burst mine according to claim 5, characterized in that: The distance between two adjacent groups of the second blasting holes in the excavation direction of the working face is 10m-20m.
7. The method for relieving pressure in the outer offset area of the rock burst mine according to claim 5, characterized in that: The number of first blasting holes in each of the first blasting hole groups is 2 to 4, and the plurality of first blasting holes in each group of the first blasting holes are arranged in a fan shape; and / or, The number of the second blasting holes in each group of the second blasting holes is 2 to 4, and the multiple second blasting holes in each group of the second blasting holes are arranged in a fan shape.
8. The method for relieving pressure in the outer offset area of the rock burst mine according to claim 7, characterized in that: The first blasting hole extends in a direction away from the first tunnel, the second blasting hole extends in a direction away from the first tunnel, and the extending direction of the first blasting hole is opposite to the extending direction of the second blasting hole.
9. The method for relieving pressure in the outer offset area of the rock burst mine according to claim 7, characterized in that: The hole depth of one of the two adjacent first blasting holes in each group of the first blasting holes is greater than the hole depth of the other first blasting hole, and the inclination angle of the one first blasting hole is less than the inclination angle of the other first blasting hole; and / or, The hole depth of one of the two adjacent second blasting holes in each group of the second blasting holes is greater than the hole depth of the other second blasting hole, and the inclination angle of the one second blasting hole is smaller than the inclination angle of the other second blasting hole.
10. The method for relieving pressure in the outer offset area of the rock burst mine according to claim 7, characterized in that: The first blasting hole is arranged adjacent to a shoulder socket of the first tunnel; and / or the second blasting hole is arranged adjacent to a shoulder socket of the first tunnel.