Mine ore pass breaking system collapse branch ore pass filling treatment method
Through the combination of sodium-based bentonite waterproof blanket and modified sulfoaluminate cement, the rapid, safe and efficient management of collapsed branches of the mine breaking system is achieved, and the safety hazards and long construction periods are solved. The treatment is reduced. Cost and water discharge risk.
Patent Information
- Application Number
- CN202411233730.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-04
- Publication Date
- 2024-11-26
AI Technical Summary
In the deep-sliding system of mine, the collapse of branches and shafts has seriously affected the stability of the surrounding shafts, which poses safety risks and may lead to the scrapping of the entire ore-sliding system. The existing treatment methods such as C20 poured concrete backfill and ore graded tailings cementing filling are costly. Problems of long construction period and hidden dangers of water leakage.
Sodium-based bentonite waterproof blanket is used to seal the bottom of the well, combined with modified sulfur aluminate cement as the filling consolidator, and through high water, quick-setting and early strength tailings cement, the existing vertical sand silo filling system is used. , realize fast and safe filling management.
Simplified the governance process, reduced costs and construction periods, improved the management efficiency and safety, avoided hidden dangers of water leakage, shortened the construction cycle, reduced the impact on surrounding wells, and ensured the filling effect of collapsed wells and the stability of the system. .
Smart Images

Figure CN119021748A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of branch chute filling, and in particular to a method for filling and controlling a collapsed branch chute in a mine chute system. Background Art
[0002] A deep chute crushing system of a certain mine includes a vertical No. 1 ore chute, a No. 2 waste rock chute, an inclined chute laterally connected to the two main chutes, and a crushing chamber located below the lower shaft openings of the main chutes and the inclined chutes. Because the rock strata passing through the mining area are well-developed, broken, and poor in integrity, after being built and put into production, after years of ore impact, the 1# chute has collapsed from the original cross-sectional area of about 10m2 to a maximum of about 200m2 with a total volume of nearly 4500m3 at the bottom of the ore discharge funnel 20 meters above the middle and upper part of the branch chute. Since the branch chute cannot be repaired, it is necessary to design another branch chute outside the collapsed range to avoid affecting the production and supply of ore in the upper middle section. The collapsed branch chute has seriously affected the stability of the surrounding 2# chute; secondly, the lower part of the unloading and transportation lane in the upper middle section of the chute is a collapsed empty area, which poses a great safety hazard; thirdly, in serious cases, two or more chutes will be penetrated, resulting in the scrapping of the entire chute system; fourthly, the branch composite joints and fissures at the rock stratum collapse are very developed, and it is necessary to prevent collapse from occurring again during the treatment period. Therefore, it is necessary to reinforce and treat the middle and upper branch chutes of the 1# main chute as quickly as possible, and the normal production of the lower and surrounding chute ore shafts will not be affected during the treatment period.
[0003] If C20 concrete is used to backfill the collapsed branch chute, the production and transportation costs of concrete are high. Due to the constraints of lowering the concrete material from the ground to the underground lifting system, the average pouring capacity is about 50m3 / day without affecting the system production conditions. The control construction period is about 45 days. At the same time, a small amount of water precipitated from the concrete poured into the chute may further soften the rock strata in the collapsed area of the branch chute with developed joints under long-term conditions. During a long control period, new collapses in the well cannot be prevented or the 1# and 2# main chutes may be abandoned and stopped.
[0004] If the mine's graded tailings cementing filling process is used to treat the hidden danger of the abandoned branch chute collapsed void area, although the efficiency of void area management can be improved to a certain extent, the branch chute's steel structure vibrating ore discharge bucket must be dismantled first and a 1m thick reinforced concrete filling retaining wall must be made to seal it. Since the chute parking lot and crushing chamber below the wellhead ore discharge bucket are still supplying ore production, dismantling the branch chute discharge facilities and making a filling retaining wall will inevitably affect the ore supply production of the main chute of the section and the operation directly at the main chute at the bottom of the collapsed void area, there are high altitude and restricted space in the shaft. In addition, when using an average slurry concentration of 73% and a 1:5 lime-sand ratio slurry, the entire branch chute will seep at least 500m3 of filling slurry. If the filling system is filled at a maximum capacity of 1000m3 at a time, each filling will seep more than 100m3. A large amount of filling slurry seeps into the wellhead chamber or rock cracks at the bottom of the branch chute, and enters the main production chute at the bottom of the branch chute, which will easily cause accidents such as chute ore collapse and mudslides. Summary of the invention
[0005] The purpose of the present invention is to provide a method for filling and controlling the collapsed branch chutes in a mine chute system, which provides a safe, efficient and rapid rescue method for the local filling and control of the main chute, avoids affecting the safe production of the mine and reduces the risk of multiple wells being interconnected due to the collapse of the surrounding rock of the chute system caused by a long control construction period.
[0006] To achieve the above-mentioned purpose, the specific technical scheme of a method for filling and treating a collapsed branch chute in a mine chute system of the present invention is as follows:
[0007] A method for filling and treating a collapsed branch chute in a mine chute system, characterized in that it comprises the following steps:
[0008] S1: Waterproof measures: There is no retaining wall to seal and waterproof the leakage head at the bottom of the branch chute;
[0009] S2: Filling process: Use the graded coarse tailings of the mine as filling aggregate, use the equipment of the mine filling cement plant to produce modified sulphoaluminate cement as filling consolidating agent, and realize the high water, fast setting and early strength tailings cementing filling process;
[0010] S3: Filling system: Use the mine's existing vertical sand bin filling system.
[0011] Furthermore, in step S1, when there is no retaining wall for sealing and waterproofing at the bottom of the branch chute, the branch chute of the collapsed 1# main chute is first emptied of the internal slag, and then a sodium-based bentonite waterproof blanket with a length and width of 2m×2m is thrown into the chute at the top of the wellhead, and then the waste rock is poured in for compaction, and finally C20 commercial concrete is poured in to ensure that the waste rock and the waterproof blanket form a high-strength sealed water-blocking plug at the bottom of the well. Many small fiber spaces can be formed in the sodium-based bentonite anti-seepage blanket, so that the bentonite particles cannot roll at will. When encountering water, the bentonite particles will absorb water and expand rapidly. Under the restriction of the upper and lower layers of geotextiles and needles, they will rapidly expand horizontally in the blanket to form a high-density viscous colloidal waterproof layer. The water permeability coefficient of the sodium-based bentonite after water absorption and expansion will drop to K=α×10 -9 cm / s (α=1~9) or less, effectively preventing the leakage of water before the later filling slurry solidifies.
[0012] Furthermore, the number of sodium-based bentonite waterproof blankets thrown in from the wellhead is one hundred.
[0013] Furthermore, 30 cubic meters of the waste rock was poured in.
[0014] Furthermore, 50 cubic meters of the C20 commercial concrete are poured in.
[0015] Further, the step S2 uses high-water, fast-setting, early-strength tailings for cementing filling, and uses the ball mill and other equipment of the mine filling cement solid material plant to produce a modified sulphoaluminate cement, the specific formula of which is 8%-20% of sulphoaluminate cement clinker, 30%-55% of water-quenched slag from iron ore blast furnace or S95 micro-mineral powder, 20%-30% of desulfurized gypsum from power plant, 3%-6% of carbide slag and 0.6%-1.5% of solid sodium silicate, which are ground together to a specific surface area of 4000cm 2 / g, the hydraulic cementitious material with high early strength performance replaces cement powder or ordinary cement as a filling consolidating agent; in addition, the physical properties of the modified sulphoaluminate cement are mainly initial setting time ≥30min; final setting time ≤90min, 0.08mm square sieve residue is not more than 3.0%, and its unit water consumption is more than 2.5 times its own mass. Therefore, after the modified sulphoaluminate cement is used for tailings cementing filling slurry into the empty area, as the hydration reaction proceeds, the excess water of the filling slurry can be quickly solidified to form calcium vanadium after 30 minutes, and the high-water material crystals continue to grow and fill the pore structure in the cement stone. This volume growth is carried out in a limited space, which produces prestress on the wellbore and the formation, thereby increasing the bonding force between the cement stone and the well wall and the formation. The compressive strength of the filling body reaches more than 1Mpa within 3 hours, avoiding the hidden danger of a large amount of filling slurry seeping and silting in the well, and greatly reducing the permeability pressure of the filling body.
[0016] Furthermore, the step S3 is filled with the existing vertical sand bin of the mine, and the graded coarse tailings are used as filling aggregate, with an average filling concentration of 70% and a ash-sand ratio of 1:5. The tailings slurry with a concentration of 18% in the beneficiation plant is pumped into the φ150 hydrocyclone on the top of the vertical sand bin by the slurry pump of the filling station for classification, and the graded coarse tailings fall into the vertical sand bin as filling aggregate. When filling and releasing sand, the sand release gate at the bottom of the vertical sand bin is opened, and the 70% concentration mortar is released to the mixing barrel through the "wind and water linkage slurry making method" of the high-pressure wind and high-pressure water of the annular nozzle at the bottom of the bin. At the same time, the filling cementing material in the cement bin is measured by a spiral electronic scale and fed into the mixing barrel for mixing together. The average concentration of mixing and conveying is 70%, and the underground pipeline two-phase flow gravity conveying method enters the upper mouth of the 1# chute.
[0017] The advantages of the present invention are:
[0018] The method of the present invention is simple, safe and reliable, saves materials, reduces construction period and reduces treatment costs. It utilizes existing equipment and systems, such as a vertical sand bin filling system, to improve the feasibility and efficiency of treatment, prevents impacts on surrounding chutes, avoids the impact on mine production due to construction or filling seepage, and ensures the filling effect of collapsed chutes. The efficiency of hidden danger treatment is greatly improved, and the construction period is reduced from the original one and a half months to less than 10 days. The safety conditions of the treatment construction of the present invention are guaranteed, and the approval and management links of dangerous operations such as wellhead operations, hot work, high-altitude operations and restricted empty areas are avoided. The treatment time is shortened and the treatment effect is ensured, preventing impacts on surrounding chutes and avoiding the impact on mine production due to construction or filling seepage during filling treatment, and reducing the risk of continued collapse and penetration with other wells during treatment. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 The steps of the present invention;
[0020] Figure 2 This is a structural diagram of the sodium-based bentonite waterproof blanket of the present invention;
[0021] Figure 3 A conveying diagram for preparing the filling slurry of the present invention;
[0022] Figure 4 This is a process diagram for filling and treating a collapsed branch chute of a chute failure system of the present invention;
[0023] Description of the markings in the figure:
[0024] 1-Vibrating ore bucket; 2-Sodium-based bentonite waterproof blanket; 3-Waste rock; 4-Commercial concrete; 5-Collapse area, tailings filling body. DETAILED DESCRIPTION
[0025] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0026] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0027] like Figure 1-4 As shown, a method for filling and treating a collapsed branch chute in a mine chute system is characterized by comprising the following steps:
[0028] S1: Waterproof measures: There is no retaining wall to seal and waterproof the leakage head at the bottom of the branch chute.
[0029] After the internal slag and rocks were emptied from the branch chute of the collapsed 1# main chute, about 100 sodium-based bentonite waterproof blankets with a length and width of 2m×2m were thrown into the chute at the top of the wellhead, and then about 30m 3 The waste rock is compacted and finally poured into C20 commercial concrete for about 50m 3 First, ensure that the waste rock and the waterproof blanket form a high-strength closed water-blocking plug at the bottom of the well in the collapsed empty area of the branch chute. Many small fiber spaces can be formed in the sodium-based bentonite anti-seepage blanket, so that the bentonite particles cannot roll at will. When encountering water, the bentonite particles will absorb water and expand rapidly. Under the restriction of the upper and lower layers of geotextiles and needles, they will rapidly expand horizontally in the blanket to form a high-density viscous colloidal waterproof layer. The water permeability coefficient of the sodium-based bentonite after water absorption and expansion will drop to K=α×10 -9 cm / s (α=1~9) or less, effectively preventing the leakage of water before the later filling slurry solidifies.
[0030] S2: Filling process: Use graded coarse tailings from the mine as filling aggregate, and use the equipment of the mine filling cement plant to produce modified sulphoaluminate cement as a filling consolidating agent to achieve a high-water, fast-setting, early-strength tailings cementitious filling process.
[0031] In step S2, high-water, fast-setting, early-strength tailings are used for cementing and filling, and a modified sulphoaluminate cement is produced by using a ball mill and other equipment in the mine filling cement solids plant. The specific formula is that sulphoaluminate cement clinker accounts for 8%-20%, water-quenched slag from an iron blast furnace or S95 micro-mineral powder accounts for 30%-55%, desulfurized gypsum from a power plant accounts for 20%-30%, calcium carbide slag accounts for 3%-6%, and solid sodium silicate accounts for 0.6%-1.5%, which are ground together to a specific surface area of 4000cm 2 / g, the hydraulic cementitious material with high early strength performance replaces cement powder or ordinary cement as a filling consolidating agent; in addition, the physical properties of the modified sulphoaluminate cement are mainly initial setting time ≥30min; final setting time ≤90min, 0.08mm square sieve residue is not more than 3.0%, and its unit water consumption is more than 2.5 times its own mass. Therefore, after the modified sulphoaluminate cement is used for tailings cementing filling slurry into the empty area, as the hydration reaction proceeds, after 30 minutes, the excess water of the filling slurry can be quickly solidified to form calcium vanadium, and the high-water material crystals continue to grow and fill the pore structure in the cement stone. This volume growth is carried out in a limited space, which produces prestress on both the wellbore and the formation, thereby increasing the bonding force between the cement stone and the well wall and the formation. The compressive strength of the filling body reaches more than 1Mpa within 3 hours, avoiding the hidden danger of a large amount of filling slurry seepage and silting in the well, and greatly reducing the osmotic pressure of the filling body. The strength grade standards of each stage of qualified production and inspection of the modified sulphoaluminate cement are as follows.
[0032]
[0033] S3: Filling system: Filling with the mine's existing vertical sand bin.
[0034] The graded coarse tailings are used as filling aggregate, with an average filling concentration of 70% and a ash-sand ratio of 1:5. The tailings slurry with a concentration of about 18% in the concentrator is pumped into the φ150 hydrocyclone on the top of the vertical sand bin by the slurry pump of the filling station for classification, and the graded coarse tailings fall into the vertical sand bin as filling aggregate. When filling and releasing sand, the sand release gate at the bottom of the vertical sand bin is opened, and the "wind and water linkage slurry making method" of high-pressure wind and high-pressure water in the annular nozzle at the bottom of the bin is used to control the release of about 70% concentration mortar to the mixing barrel. At the same time, the filling cementing material in the cement silo is measured by a spiral electronic scale and fed into the mixing barrel for mixing together. The average concentration of mixing and conveying is 70%, and the underground pipeline two-phase flow gravity conveying method enters the upper mouth of the 1# chute.
[0035] It is to be understood that the present invention is described by some embodiments, and it is known to those skilled in the art that various changes or equivalent substitutions may be made to these features and embodiments without departing from the spirit and scope of the present invention. In addition, under the teachings of the present invention, these features and embodiments may be modified to adapt to specific circumstances and materials without departing from the spirit and scope of the present invention. Therefore, the present invention is not limited by the specific embodiments disclosed herein, and all embodiments falling within the scope of the claims of this application are within the scope of protection of the present invention.
Claims
1. A method for filling and treating a collapsed branch chute in a mine chute system. It is characterized in that The steps include: S1: Waterproof measures: There is no retaining wall to seal and waterproof the leakage head at the bottom of the branch chute; S2: Filling process: Use the graded coarse tailings of the mine as filling aggregate, use the equipment of the mine filling cement plant to produce modified sulphoaluminate cement as filling consolidating agent, and realize the high water, fast setting and early strength tailings cementing filling process; S3: Filling system: Utilize the mine's existing vertical sand bin filling system.
2. A method for filling and treating a collapsed branch chute in a mine chute system according to claim 1, It is characterized in that In step S1, when there is no retaining wall for sealing and waterproofing at the bottom of the branch chute, the branch chute of the collapsed 1# main chute is first emptied of the internal slag and then a sodium-based bentonite waterproof blanket with a length and width of 2m×2m is thrown into the chute at the top of the wellhead, and then the waste rock is poured in for compaction, and finally C20 commercial concrete is poured in to ensure that the waste rock and the waterproof blanket form a high-strength sealed water-blocking plug at the bottom of the well. Many small fiber spaces can be formed in the sodium-based bentonite anti-seepage blanket, so that the bentonite particles cannot roll at will. When encountering water, the bentonite particles will absorb water and expand rapidly. Under the restriction of the upper and lower layers of geotextiles and needles, they will rapidly expand horizontally in the blanket to form a high-density viscous colloidal waterproof layer. The water permeability coefficient of the sodium-based bentonite after absorbing water and swelling will drop to K=α×10 -9 cm / s (α=1~9) or less, effectively preventing the leakage of water before the later filling slurry solidifies.
3. According to the method for filling and treating the collapsed branch chute of a mine chute system as described in claim 2, It is characterized in that The number of the sodium-based bentonite waterproof blankets used is one hundred.
4. According to the method for filling and treating the collapsed branch chute of a mine chute system as described in claim 2, It is characterized in that The waste rock poured in was 30 cubic meters.
5. A method for filling and treating a collapsed branch chute in a mine chute system according to claim 2, It is characterized in that Pour 50 cubic meters of C20 commercial concrete.
6. A method for filling and treating a collapsed branch chute in a mine chute system according to claim 1, It is characterized in that In step S2, high-water, fast-setting, early-strength tailings are used for cementing and filling, and a modified sulphoaluminate cement is produced by using a ball mill and other equipment in the mine filling cement solids plant. The specific formula is that sulphoaluminate cement clinker accounts for 8%-20%, water-quenched slag from an iron blast furnace or S95 micro-mineral powder accounts for 30%-55%, desulfurized gypsum from a power plant accounts for 20%-30%, calcium carbide slag accounts for 3%-6%, and solid sodium silicate accounts for 0.6%-1.5%, which are ground together to a specific surface area of 4000cm 2 / g, the hydraulic cementitious material with high early strength performance replaces cement powder or ordinary cement as a filling consolidating agent; in addition, the physical properties of the modified sulphoaluminate cement are mainly initial setting time ≥30min; final setting time ≤90min, 0.08mm square sieve residue is not more than 3.0%, and its unit water consumption is more than 2.5 times its own mass. Therefore, after the modified sulphoaluminate cement is used for tailings cementing filling slurry into the empty area, as the hydration reaction proceeds, the excess water of the filling slurry can be quickly solidified to form calcium vanadium after 30 minutes, and the high-water material crystals continue to grow and fill the pore structure in the cement stone. This volume growth is carried out in a limited space, which produces prestress on the wellbore and the formation, thereby increasing the bonding force between the cement stone and the well wall and the formation. The compressive strength of the filling body reaches more than 1Mpa within 3 hours, avoiding the hidden danger of a large amount of filling slurry seeping and silting in the well, and greatly reducing the permeability pressure of the filling body.
7. A method for filling and treating a collapsed branch chute in a mine chute system according to claim 1, It is characterized in that The step S3 is filled with the existing vertical sand bin of the mine, and the graded coarse tailings are used as filling aggregate, with an average filling concentration of 70% and a ash-sand ratio of 1:
5. The tailings slurry with a concentration of 18% in the concentrator is pumped into the φ150 hydrocyclone on the top of the vertical sand bin by the slurry pump of the filling station for classification, and the graded coarse tailings fall into the vertical sand bin as filling aggregate. When filling and releasing sand, the sand release gate at the bottom of the vertical sand bin is opened, and the "wind and water linkage slurry making method" of the high-pressure wind and high-pressure water of the annular nozzle at the bottom of the bin is used to control the release of 70% concentration mortar to the mixing barrel. At the same time, the filling cementing material in the cement bin is measured by a spiral electronic scale and fed into the mixing barrel for mixing together. The average concentration of mixing and conveying is 70%, and the underground pipeline two-phase flow gravity conveying method enters the upper mouth of the 1# chute.