Lifting appliance balancing device for moving waste cable

By setting up an adjustable double-sided hook cargo balance device on the main hook of the spreader, and adjusting the center of gravity of the waste cable with an electro-hydraulic push rod and inclination sensor, the problem of inclination and safety hazards during the lifting process is solved, and the problem of waste cable tilt and safety hazards is realized. Safe, stable lifting and movement of used cables.

CN119038390APending Publication Date: 2024-11-29STATE GRID SHANGHAI MUNICIPAL ELECTRIC POWER CO +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410944074.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-15
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

The prior art is difficult to safely and stably lift and move waste cables with certain flexibility and uncertain center of gravity without knowing the center of gravity of the waste cable, which can easily lead to cable tilt and safety hazards.

Method used

The main hook of the suspension gear is equipped with an adjustable double-side hook cargo balance device. By measuring the angle of the suspended wire rope of the double-side hook, the height of the side hook is adjusted by using an electric hydraulic push rod, and combined with the inclination sensor to detect and adjust the center of gravity of the cable to ensure that The balance of the cable during lifting.

Benefits of technology

It realizes rapid automatic adjustment without clear center of gravity, ensures the safety, stable lifting and movement of used cables, avoids cable tilt and safety hazards, and does not require complex 3D software for easy implementation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119038390A_ABST
    Figure CN119038390A_ABST
Patent Text Reader

Abstract

The invention discloses a lifting appliance balancing device for moving waste cables, and belongs to the field of machinery. A lifting appliance balancing device is arranged on the main lifting hook and serves as a medium among the main hook, a steel wire rope and goods; the lifting appliance balancing device is provided with two height-adjustable lifting hooks which are connected with a left steel wire rope and a right steel wire rope and serve as a main correcting mechanism for goods inclination; once the goods are lifted, if inclination is detected, lifting of the goods is temporarily stopped, and height-adjustable side lifting hooks on the two sides of the lifting appliance balancing device automatically correct inclination; once the inclination of the cargo is corrected, the cargo can continue to rise and be placed in its predetermined position. Under the condition that the gravity center position of a hoisted waste cable is not clear, the gravity center of the hoisted cable can be rapidly and automatically adjusted by respectively measuring the angles of steel wire ropes suspended by the lifting hooks on the two sides and then respectively adjusting the heights of the lifting hooks on the two sides through the electric hydraulic push rods; and the waste cable with certain flexibility and uncertain gravity center can be safely and stably lifted and moved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of mechanical devices, and in particular relates to a hanger balancing device for moving waste cables. Background Art

[0002] A common method of moving scrap cables is to use a lifting device with a crane, hook and wire rope. The method of use is: after placing two equal-length wire ropes through the lower side of the scrap cable, connect the four ends of these wire ropes to the main hook, operate the crane to lift the cargo and place it in the desired location.

[0003] The problem with lifting any batch of scrap cables of varying lengths and specifications is that the centre of gravity is unknown, so the cargo tends to tilt as it is lifted off the ground, and the cables could slip out and cause serious injury, posing a safety hazard.

[0004] The utility model patent with the authorization announcement date of March 31, 2010 and the authorization announcement number of CN 201433041 Y discloses "a mechanical grab bucket lower support beam structure", wherein the lower lower pulley seat is provided with a mounting shaft hole at the bottom, and the upper part of the cross beam is provided with a corresponding connecting shaft hole, and the lower lower pulley seat and the cross beam are connected by a connecting shaft and can rotate relative to each other. The cross beam and the lower pulley seat of the utility model can rotate relative to each other, and the opening and closing wire ropes are evenly stressed, which can keep the grab bucket with a good center of gravity balance. When the grab bucket grabs the goods and lifts them, the opening and closing wire ropes will not be separated from the pulley groove and deform the wire rope protective cover, avoiding friction with the wire rope protective cover; and the lower pulley seat and the cross beam connected to each other do not have stress and strain generated during welding, which can ensure the strength of the parent material and avoid tearing; during the grab bucket grabbing process, all bucket petals are stress-dispersed and not easily deformed, effectively extending the service life and improving the safety factor. However, the lifting device it targets is a "grab" with a certain mechanical shape, which cannot adapt to the lifting operation of waste cables with a certain degree of flexibility. Therefore, it cannot be used to solve the practical problem that "the goods tend to tilt when lifted off the ground, and the cables may slip out and cause serious injuries, thus posing a safety hazard."

[0005] The utility model with the authorization announcement date of 2014.06.25 and the authorization announcement number of CN 203667788 U discloses an "electrolytic cell steel bar hanging device", which includes a handle, a lifting ring, a suspension beam and a steel bar groove. The handle is installed obliquely on the surface of the steel bar groove, the suspension beam is fixed horizontally on the surface of the steel bar groove, and the lifting ring is fixed vertically on the suspension beam. This technical solution adopts the principle of lever and center of gravity balance, with a simple structure, convenient and safe operation, which can minimize the mechanical and human resources consumed in the process of hanging and installing steel bars, improve production labor efficiency, and make the electrolytic cell steel bars quickly and accurately in place. However, since this technical solution is aimed at a rigid carrier (electrolytic cell steel bar), the center of gravity of this type of load is related to the center point of its geometric shape, so it is very easy to be judged by the operator. This is different from the lifting operation of scrap cables with flexibility (the center of gravity of such "flexible" goods being lifted is difficult to determine at the lifting site), so it cannot be used to prevent the "anti-tilting" problem of scrap cables with certain flexibility during the lifting process.

[0006] How to find the center of gravity of the suspended waste cables as soon as possible through automatic adjustment of the lifting equipment without knowing the center of gravity of the suspended waste cables, and adjust the state of the lifting equipment in time to adapt to different conditions of the suspended waste cables, so as to safely and stably lift and move the waste cables with certain softness and uncertain center of gravity, is a technical problem that needs to be solved urgently in actual work. Summary of the invention

[0007] The technical problem to be solved by the present invention is to provide a balancing device for lifting equipment for moving waste cables. The working mode of an adjustable double-side hook cargo balancing device (CBD) is adopted on the main hook of the lifting equipment. When the center of gravity position of the lifted waste cables is unclear, the center position can be adjusted quickly and automatically by measuring the angles of the steel wire ropes suspended by the double-side hooks respectively, and then adjusting the heights of the two side hooks respectively by the electric hydraulic push rod. The angle of the two side hooks is detected by the inclination sensor (and then the angle of the steel wire ropes suspended by the double-side hooks is indirectly obtained), and the center of gravity of the lifted cables is adjusted. After the adjustment is in place, the hook position can be locked, and the scrap cables with certain flexibility and uncertain center of gravity can be lifted and moved safely and stably.

[0008] The technical solution of the present invention is to provide a balancing device for a hoist for moving waste cables, comprising a main hook, characterized in that:

[0009] A sling balance device is provided on the main hook;

[0010] The balancing device for the sling comprises a rod-shaped main support;

[0011] A hanging hole structure connected to the main hook is provided at the upper end of the main bracket;

[0012] At the lower end of the main support, two groups of electric hydraulic push rods are symmetrically arranged along the longitudinal direction of the main support;

[0013] A set of side hook seats that can be moved longitudinally are respectively arranged on the left and right sides of the main support, and a side hook is respectively arranged in each side hook seat, forming left and right hooks that can be moved longitudinally on both sides of the main support;

[0014] The bottoms of the two sets of electric hydraulic push rods are fixedly connected to the lower end of the main bracket, and the tops of the two sets of electric hydraulic push rods are fixedly connected to the side hook seats. With the extension and retraction of the tops of the two sets of electric hydraulic push rods, the side hook seats can move longitudinally along the two sides of the main bracket, thereby driving the side hooks on the left and right sides of the main bracket to move up and down along the longitudinal direction of the main bracket.

[0015] An inclination sensor is arranged on the hanging hole structure at the upper end of the main bracket to detect the inclination angle of the main bracket;

[0016] At the roots of the left and right side hooks, there are respectively provided an inclination sensor for detecting the inclination angles of the left and right side hooks;

[0017] The side hooks on the left and right sides are connected to the left and right steel ropes and serve as the main correction mechanism for cargo tilt.

[0018] In the technical solution of the present invention, once the cargo is lifted, if any inclination sensor detects a tilt, the lifting of the cargo will be temporarily stopped, and the corresponding side hooks on both sides of the sling balancing device will move up and down along the longitudinal direction of the main bracket through the extension and retraction of the tops of the two electric hydraulic push rods to adjust the overall center of gravity of the suspended cable. After adjustment, the hook position can be locked, and the waste cables with a certain softness and uncertain center of gravity can be lifted and moved safely and stably to correct the tilt; once the tilt of the cargo is corrected, the cargo can continue to be lifted and placed in its predetermined position.

[0019] Specifically, a weight sensor is provided on the contact surface of the hanging hole structure with the main hook to judge whether the overall weight of the hung waste cables exceeds the standard.

[0020] Furthermore, the angle sensor is fixedly connected to the root of the side hook as a whole; the angle sensors fixed at the roots of the left and right side hooks are used to measure the inclination angles of the left and right side hooks, and then to know the angles of the wire ropes suspended by the two side hooks.

[0021] Specifically, the balancing device of the hoisting device performs dynamic balancing of the hoisted waste cables in the following manner:

[0022] 1) Install the balancing device of the spreader on the main hook;

[0023] 2) Automatic confirmation before cargo lifting;

[0024] 3) The main hook starts to lift the waste cable, and the weight information is monitored at the same time to ensure that the maximum load capacity of the system is not violated;

[0025] 4) Start cargo tilt analysis;

[0026] 5) According to the analysis results, the top ends of the two sets of electric hydraulic push rods are automatically controlled to extend and retract, thereby driving the side hooks on the left and right sides of the main support to move up and down along the longitudinal direction of the main support;

[0027] 6) By adjusting the height of the left and right side hooks, the inclination angle of the wire rope suspended by the side hooks can be adjusted to dynamically adjust the center of gravity of the cargo;

[0028] 7) If the safety parameter ΔY of the weight difference between the left and right wire ropes is ≤50mm, the main hook can continue to lift the waste cable and place it in the expected position;

[0029] 8) If the safety parameter exceeds the preset value of the safety parameter, that is, ΔY>50mm, the height correction of the left and right hook positions is performed until the corrected ΔY≦50mm is obtained;

[0030] 9) The main hook can continue to lift the waste cable and place it in the expected position, completing the lifting and movement of the waste cable.

[0031] Furthermore, in step 2), during the automatic confirmation step before the goods are lifted, the following contents are confirmed:

[0032] 6.1) Confirm that the left hook and the right hook are at the midpoint height of the sling balance device, otherwise adjust them through the corresponding electric hydraulic push rod;

[0033] 6.2) Make sure that the two steel wire ropes of the same length wrapped around the scrap cable are firmly connected to the corresponding left and right hooks to ensure that the two steel wire ropes have the same length.

[0034] Furthermore, once the main hook is raised, the weight sensor system in the spreader counterbalance will start processing the following information:

[0035] 7.1) The red flashing alarm will sound an alarm in the following situations:

[0036] The weight of the waste cables is greater than the maximum system load. In this case, the waste cables are put back to the ground through the main hook.

[0037] 7.2) When the green light is on, the scrap cables can be lifted, and when the cargo quality is stable, the weight stability analysis of the scrap cables can be started;

[0038] The following formula can be used as a condition to determine when the weight of the scrap cable has stabilized:

[0039] Weight of waste cables (t+1) -Weight of scrap cables (t) <10kg;

[0040] Among them, the weight of scrap cables (t+1)-the weight of scrap cables (t) means that the change in the weight of scrap cables from time (t) to time (t+1) is less than 10kg.

[0041] Furthermore, in the cargo tilt analysis of step 4), it is necessary to determine the left and right load positions of the tilted sling balancing device and determine the cargo parameters related to the left and right wire rope connection points, and then judge whether the cargo weight difference between the left and right wire rope distances is within the predetermined safety parameter range; if the cargo weight difference between the left and right wire rope distances exceeds the predetermined safety parameter range, correction is required.

[0042] Specifically, the correction includes correcting the height of the left and right hook positions.

[0043] Furthermore, the corrections will always be made by the same amount, at the same speed and at the same time to compensate for the relatively slow speed of the electrohydraulic actuator and to prevent any unnecessary gyroscopic forces from interfering with the lifting system.

[0044] Compared with the prior art, the advantages of the present invention are:

[0045] 1. The technical solution of the present invention is to set an adjustable double-side hook cargo balancing device (CBD) working mode on the main hook of the sling. When the center of gravity of the hoisted scrap cable is unclear, the center position can be quickly and automatically adjusted by measuring the angles of the steel wire ropes suspended by the double-side hooks respectively, and then adjusting the heights of the two side hooks by the electric hydraulic push rod respectively. The angle of the two side hooks is detected by the inclination sensor (and then the angle of the steel wire ropes suspended by the double-side hooks is indirectly obtained), and the center of gravity of the hoisted cable is adjusted. After the adjustment is in place, the hook position can be locked, so that the scrap cable with a certain softness and uncertain center of gravity can be lifted and moved safely and stably.

[0046] 2. The technical solution of the present invention adopts the most basic mathematical analysis means, based on conventional mathematical analysis methods, to solve the stable lifting calculation of waste cables with certain flexibility and uncertain center of gravity, without the need for complex 3D software, and is easy to implement, easy to accept, and simple and easy to use.

[0047] 3. The technical solution of the present invention, CBD is connected to the main hook of the crane, acting as an intermediary between the main hook and the wire rope and the cargo; CBD itself has two adjustable height hooks, connected to the left and right wire ropes, and serves as the main correction mechanism for cargo tilt; once the cargo is lifted, if tilt is detected, then the lifting of the cargo will be temporarily stopped, and the adjustable height hooks on both sides of CBD will be activated to correct the tilt. Once the cargo tilt is corrected, the cargo can continue to be lifted and placed in its predetermined position. BRIEF DESCRIPTION OF THE DRAWINGS

[0048] Figure 1 It is a schematic diagram of the structure of the adjustable double-side hook type cargo balancing device of the present invention;

[0049] Figure 2 It is a schematic diagram of the cross-sectional structure of the adjustable double-side hook type cargo balancing device of the present invention;

[0050] Figure 3 It is a schematic diagram of the installation position of the angle sensor of the present invention;

[0051] Figure 4 It is a schematic diagram of the installation position of the weight sensor of the present invention;

[0052] Figure 5a and Figure 5b It is a schematic diagram of the adjustable double-side hook cargo balancing principle of the present invention;

[0053] Figure 5c It is a schematic diagram of the definition of the analysis diagram of the present invention;

[0054] Figure 6 It is a flowchart of the steps of the cargo balancing method of the present invention;

[0055] Figure 6.1 It is a schematic diagram of the state of the spreader before the cargo is lifted;

[0056] Figure 6.2a It is a schematic diagram of the state of the spreader when the measurement starts;

[0057] Figure 6.2b It is a schematic diagram of the vertical distances between the left and right wire rope connection points and the main hook and pivot;

[0058] Figure 6.2c yes Figure 6.2b A simplified schematic diagram of

[0059] Figure 6.2d It is a schematic diagram of the CBD left and right hook loading points and the tilt angle of the CBD;

[0060] Figure 6.2e It is a calculation diagram for determining the left and right load positions of the tilted CBD;

[0061] Figure 6.2f It is a schematic diagram for determining the parameters related to the connection points of the left and right wire ropes;

[0062] Figure 6.2g It is a calculation diagram for determining cargo parameters related to the left and right wire rope connection points;

[0063] Figure 6.2h It is a parameter diagram of the difference ΔY between the left and right distances;

[0064] Figure 6.3a It is a schematic diagram of the correction principle of the present invention;

[0065] Figure 6.3b It is a schematic diagram of the correction action of the present invention;

[0066] Figure 6.4 This is a schematic diagram of the state of the spreader after the calibration of the present invention is completed. DETAILED DESCRIPTION

[0067] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.

[0068] (I) Concept of cargo balancing device (hereinafter referred to as CBD):

[0069] like Figure 1 and Figure 2 As shown in , the CBD in this technical solution is connected to the main hook 1 of the crane, acting as an intermediary between the main hook and the wire rope and the cargo.

[0070] CBD includes a main support 3. A weight sensor (selected model: HZC-30A) is provided at the contact point between the upper end of the main support and the main hook. Figure 4 as shown in .

[0071] On both sides of the main support, a set of (two) electric hydraulic push rods ( Figure 2 The bottom of the electric hydraulic push rod is fixedly connected to the main bracket as a whole, and the top of the movable rod on the upper part of the two electric hydraulic push rods can be longitudinally moved to a left and right hook ( Figure 1 As the top of the movable rod on the upper part of the electric hydraulic push rod is extended and retracted, the corresponding right (or left) side hook is driven to move up and down along the longitudinal direction of the main bracket (see Figure 2 ).

[0072] The CBD itself has two side hooks with adjustable height ( Figure 1 Indicated by 4, i.e. the aforementioned left and right hooks), which are connected to the left and right wire ropes and serve as the main correction mechanism for the inclination of the cargo.

[0073] like Figure 3As shown in the figure, angle sensors (also called inclination sensors, the selected model is SCMA800) are respectively arranged at the contact point between the main support and the main hook, and at the connection point between the right (or left) side hook and the main support.

[0074] The angle sensor is fixedly connected to the root of the right (or left) side hook. The angle sensor fixed at the root of the two left and right side hooks is used to measure the inclination angles of the two left and right side hooks, and then indirectly know the angles of the wire ropes suspended by the hooks on both sides.

[0075] like Figure 5a and Figure 5b As shown in , once the cargo is lifted, if any angle sensor detects a tilt, the lifting of the cargo will be temporarily stopped, and the adjustable height hooks on both sides of the CBD (i.e., the left and right hooks mentioned above) will be activated. Through the extension and retraction of the top of the movable rod on the upper part of the two electric hydraulic push rods, the corresponding right (or left) side hook is driven to move up and down along the longitudinal direction of the main bracket respectively, to adjust the overall center of gravity of the suspended cable. After adjustment, the hook position can be locked, and the scrap cables with a certain degree of softness and uncertain center of gravity can be lifted and moved safely and stably to correct the tilt.

[0076] Once the tilt of the cargo has been corrected, the cargo can continue to be lifted and placed in its intended location.

[0077] The subject matter of the present invention relates to lifting and moving heavy waste cables weighing up to 3 tons. In such a situation, any one cable falling off may cause serious injury or even death. In such a situation, safety is of utmost importance.

[0078] (II) Characteristics of the lifting system:

[0079] In order to design a CBD, it is necessary to know how the CBD and its design parameters interact with the entire lifting system. To this end, an attempt will be made to discover the characteristics of the lifting system and its components through experiments and theoretical modeling.

[0080] (1) Regardless of the tilt of the CBD, the center of gravity of the cargo is always located vertically below the main hook and CBD pivot.

[0081] (2) The center of gravity of the CBD is always vertically below the main hook and the CBD pivot.

[0082] (3) The cargo tilt is caused by the different horizontal distances between the left and right wire rope connection points and the cargo center of gravity. In turn, this cargo tilt will cause different loads at these two points, which will again affect the cargo tilt.

[0083] (4) CBD tilt is also caused by the different horizontal distances between the left and right wire rope connection points and the cargo center of gravity. Because of the impact on the loads at these two points, this CBD tilt can be predicted by a theoretical model.

[0084] like Figure 6 As shown in the figure, the principle and action process of this technical solution are:

[0085] The CBD is connected to the main hook of the crane and acts as an intermediary between the main hook and the wire rope and cargo.

[0086] The CBD itself has two height-adjustable hooks, which are connected to the left and right wire ropes and serve as the main correction mechanism for cargo tilt.

[0087] Once the cargo is lifted, if tilt is detected, the lifting of the cargo will be temporarily stopped, and the adjustable height hooks on both sides of the CBD (i.e. the left and right hooks mentioned above) will be activated. Through the extension and contraction of the top of the movable rods on the upper part of the two electric hydraulic push rods, the corresponding right (or left) side hooks will be driven to move up and down along the longitudinal direction of the main support to correct the tilt of the cargo (see Figure 5a and 5b ).

[0088] Once the tilt of the cargo has been corrected, the cargo can continue to be lifted and placed in its intended location.

[0089] Through experiments and theoretical modeling, it is found that the CBD lifting system has the following conclusions:

[0090] 1) Regardless of the tilt of the CBD, the center of gravity of the cargo is always vertically located below the main hook and CBD pivot;

[0091] 2) The center of gravity of the CBD is always vertically below the main hook and CBD pivot;

[0092] 3) The cargo tilt is caused by the different horizontal distances between the left and right wire rope connection points and the cargo center of gravity. In turn, this cargo tilt will cause different loads at these two points, which again affects the cargo tilt;

[0093] 4) CBD tilt is also caused by the different horizontal distances between the left and right wire rope connection points and the cargo center of gravity. Because they have an impact on the loads at these two points, this CBD tilt can now be predicted by theoretical models.

[0094] Furthermore, through analysis and experiments, we know that:

[0095] Different initial horizontal distances between the left and right wire rope connection points and the cargo center of gravity will cause these distances to change due to the initial calculated values ​​of cargo tilt, which indicates that the calculation of the data requires an iterative process in order to calculate the final stable cargo tilt angle.

[0096] In theory, all other things being equal, the narrower the CBD, the less cargo tilt.

[0097] A note about the analysis graph. Positive and negative X are normal directions, but Y is reversed, with "up" being negative and down being positive. See Figure 5c as shown in .

[0098] exist Figure 6.2b to Figure 6.2e In , the definitions of various relevant points are as follows:

[0099] Since the data analysis and calculation is based on a two-dimensional plane, the coordinates of the following points are all expressed using the conventional XY axis coordinate representation method, that is, the first value in the coordinate (X, Y) of each point is the X-axis value, and the second value is the Y-axis value.

[0100] (g, h): Coordinates of the tilted CBD left hook loading point, where g is the X-axis value and h is the Y-axis value (the coordinate representation method of the following points is the same and will not be repeated);

[0101] (i, j): Coordinates of the right hook loading point of the inclined CBD;

[0102] CBDTilt: The tilt angle of CBD;

[0103] θ: cargo tilt angle;

[0104] (m, n): coordinates of the left wire rope connection point;

[0105] (p, q); coordinates of the right wire rope connection point.

[0106] Based on the previous definition of the coordinates of each point, combined with Figures 6.2b to 6.2g As shown in , we can see the following results:

[0107] Length (0,0) to

[0108] Length (0,0) to

[0109]

[0110] h=La.cos(α+CBTTilt); j=Lb.cos(β+CBTTilt);

[0111] To find the values ​​of n and q, the angle readings on the left and right hook angle sensors, δ and ε, are needed:

[0112] n=h+r.cos(δ); q=j+r.cos(ε);

[0113] The difference ΔY is: ΔY = q – n;

[0114] And the cargo tilt angle θ is:

[0115] (III) Operation process of CBD:

[0116] 1) Install CBD on the main hook;

[0117] 2) First Step - Before Ascension (See Figure 6.1 ):

[0118] 2.1) Confirm that the left adjustable height hook and the right adjustable height hook are both at the height of the midpoint of the CBD;

[0119] 2.2) Confirm that the two steel wire ropes of equal length wrapped around the waste cable are securely connected to the corresponding left and right CBD hooks:

[0120] 3) Step 2 - Measurement (see Figure 6.2a ):

[0121] 3.1) When the CBD is opened, the green light will come on and the main hook can now lift the scrap cable. At the same time, the weight information is monitored to ensure that the maximum load capacity of the system is not violated. Once the cargo is just above the ground, the lifting will stop;

[0122] Once the main hook is raised, the weight sensor system in the CBD starts processing the information:

[0123] 3.1.1) The red flashing alarm will be activated in the following situations:

[0124] CargoMass (weight of waste cables)>maximum system load, in which case the waste cables should be put back on the ground;

[0125] 3.1.2) When the green light is on, the scrap cables can be lifted and when the cargo weight is stable, the cargo tilt analysis can be started. The following formula can be used as the condition to determine when the weight of the scrap cables is stable:

[0126] CargoMass (t+1) -CargoMass (t) <10kg

[0127] Among them, CargoMass(t+1)-CargoMass(t) means that the change in the weight of the waste cables from time (t) to time (t+1) is less than 10kg;

[0128] 3.2) The vertical distance between the left and right wire rope connection points and the main hook and pivot is calculated using the information from the three sets of angle sensors. The difference between these two values ​​is ΔY, see Figure 6.2b and 6.2c :

[0129] CBD angle sensor information = CBD tilt angle (CBDTilt)

[0130] Left and right hook angle sensor information: left hook angle = δ, right hook angle = ε

[0131] Then ΔY=qn

[0132] A. Determine the left and right load positions (g, h) and (i, j) of the tilted CBD:

[0133] like Figure 6.2e As shown in , to determine the points (g, h) and (i, j), we first determine the length from (0, 0) to (c, d), and the length from (0, 0) to (e, f), as well as the angles α and β:

[0134] Length (0,0) to

[0135] Length (0,0) to

[0136] and

[0137] For point (g, h) and point (i, j), we have:

[0138] g=La.sin(α+CBTTilt); h=La.cos(α+CBTTilt);

[0139] as well as

[0140] i=Lb.sin(β+CBTTilt); j=Lb.cos(β+CBTTilt).

[0141] B. Determine the cargo parameters related to the left and right wire rope connection points (m, n) and (p, q):

[0142] See also Figure 6.2f and 6.2g .

[0143] To find (m, n) and (p, q), you first need to determine the length from the cargo's center of gravity to (m, n) and (p, q) and their angles to the cargo's base:

[0144] Set cXa = length from the cargo center of gravity to (m,n); cXb = length from the cargo center of gravity to (p,q);

[0145] σa=angle from cXa to the bottom of the cargo; σb=angle from cXb to the bottom of the cargo;

[0146] Then we have:

[0147]

[0148] Now, you can use these values ​​to determine the angle, δ, of the left rope from the vertical:

[0149]

[0150] This δ formula includes the cargo tilt angle θ, which is initially assumed to be zero (θ=0).

[0151] Given θ = 0:

[0152]

[0153] m=r.sin(δ)+g; n=r.cos(δ)+h;

[0154] Initial p=p0=cXb.cos(θ-σb)=cXb.cos(-σb);

[0155] Before determining q, we need to find the vertical distance from the center of gravity of the cargo to (0, 0), t:

[0156] t=n-cXa.sin(σa+θ)=n-cXa.sin(σa);

[0157] Initial value of q, q0:

[0158] q0=t-cXb.sin(θ-σb)=t-cXb.sin(-σb);

[0159] 3.3) If the difference between the left and right wire rope distances is within the predetermined safety parameters, the main hook can proceed to lift the waste cable and place it in the intended location.

[0160] According to experience, a difference of less than 50 mm is sufficient to ensure the safe movement of a batch of waste cables, namely:

[0161] ΔY≦50mm;

[0162] 3.4) If the difference between the two distances exceeds the safety parameter ΔY>50mm, the difference will be used as a reference value for the next step, see Figure 6.2h as shown in .

[0163] 4) Step 3 - Correction:

[0164] Once the CBD is ready for correction, the green light will begin flashing.

[0165] During the calibration process, the green light will continue to flash until the calibration process is complete.

[0166] When finished, the flashing green light will return to a solid green light.

[0167] 4.1) Correction direction:

[0168] ΔY can be positive or negative: ΔY = q – n;

[0169] Combination Figure 5c As shown in , it can be seen that if ΔY is negative, then q is less than n.

[0170] Therefore, the left CBD hook should be raised and the right CBD hook should be lowered:

[0171] Increase the correction amount of the left CBD hook: δd<0 (negative),

[0172] Reduce the right CBD hook correction amount: δh>0 (positive), such as Figure 6.3a As shown:

[0173] Therefore, the formula for the correction direction is:

[0174] Δd∝ΔY and Δh∝-ΔY;

[0175] 4.2) Correction amount:

[0176] The corrections for the left and right CBD hooks will be based on ΔY. Additionally, the corrections for the left and right CBD hooks will be equal and in opposite directions in order to simplify the correction algorithm and offset any gyroscopic reaction during electrohydraulic actuator activation.

[0177] 4.2.1) 100% ΔY correction:

[0178] This means that the rise of the left CBD hook plus the drop of the right CBD hook will equal ΔY or:

[0179] |Δd|+|Δf|=ΔY;

[0180] and

[0181] |Δd|=|Δf|;

[0182] For details, please refer to Figure 6.3a and Figure 6.3b as shown in .

[0183] 4.2.4) Optimal correction value:

[0184] After calculation and experiment, the result of ΔY≦50mm after correction is acceptable, so the following conclusions are obtained:

[0185] The optimal total CBD hook correction value is 95% of ΔY.

[0186] 4.3) Calibration process:

[0187] The default position of the adjustable height hooks on both sides of the CBD (i.e. the left and right side hooks mentioned above) will be at the midpoint of the correction range, which will allow a maximum correction value of 500 mm, with one CBD hook raised 250 mm and the other lowered 250 mm.

[0188] Corrections will always be made by the same amount, at the same speed and at the same time, which will help compensate for the relatively slow speed of the electrohydraulic actuator and prevent any unwanted gyroscopic forces from interfering with the lifting system.

[0189] 6.5) Step 4 - Final Placement:

[0190] Once ΔY is within 50mm (such as Figure 6.4 ), the correction process is completed, the flashing green light will return to a constant green light, the main hook can be raised, and the waste cable can then be placed in its intended position.

[0191] In summary, the technical solution of the present invention is to set an adjustable double-side hook cargo balancing device (CBD) working mode on the main hook of the sling. When the center of gravity of the suspended waste cable is unclear, the center of gravity of the suspended cable can be quickly and automatically adjusted by measuring the angles of the steel wire ropes suspended by the double-side hooks respectively, and then adjusting the heights of the two side hooks respectively through the electric hydraulic push rods. This enables the waste cables with certain softness and uncertain center of gravity to be lifted and moved safely and stably.

[0192] In addition, the implementation of the technical solution of the present invention does not require complicated 3D software and is easy to implement, easy to accept, and simple and convenient.

[0193] In the technical solution of the present invention, CBD is connected to the main hook of the crane, acting as an intermediary between the main hook and the wire rope and the cargo; CBD itself has two adjustable-height hooks, connected to the left and right wire ropes, and serves as the main correction mechanism for cargo tilt; once the cargo is lifted, if tilt is detected, then the lifting of the cargo will be temporarily stopped, and the adjustable-height hooks on both sides of CBD will be activated to correct the tilt. Once the cargo tilt is corrected, the cargo can continue to be lifted and placed in its predetermined position.

[0194] The invention can be widely used in the field of design and manufacture of sling balancing devices.

Claims

1. A balancing device for lifting equipment used to move waste cables, comprising a main hook, characterized in that: A sling balance device is provided on the main hook; The balancing device for the sling comprises a rod-shaped main support; A hanging hole structure connected to the main hook is provided at the upper end of the main bracket; At the lower end of the main support, two groups of electric hydraulic push rods are symmetrically arranged along the longitudinal direction of the main support; A set of side hook seats that can be moved longitudinally are respectively arranged on the left and right sides of the main support, and a side hook is respectively arranged in each side hook seat, forming left and right hooks that can be moved longitudinally on both sides of the main support; The bottoms of the two sets of electric hydraulic push rods are fixedly connected to the lower end of the main bracket, and the tops of the two sets of electric hydraulic push rods are fixedly connected to the side hook seats. With the extension and retraction of the tops of the two sets of electric hydraulic push rods, the side hook seats can move longitudinally along the two sides of the main bracket, thereby driving the side hooks on the left and right sides of the main bracket to move up and down along the longitudinal direction of the main bracket. An inclination sensor is arranged on the hanging hole structure at the upper end of the main bracket to detect the inclination angle of the main bracket; At the roots of the left and right side hooks, there are respectively provided an inclination sensor for detecting the inclination angles of the left and right side hooks; The side hooks on the left and right sides are connected to the left and right steel ropes and serve as the main correction mechanism for cargo tilt.

2. The balancing device for lifting equipment used to move waste cables according to claim 1, characterized in that Once the cargo is lifted, if any inclination sensor detects a tilt, the lifting of the cargo will be temporarily stopped. Through the extension and retraction of the tops of the two electric hydraulic push rods, the corresponding side hooks on both sides of the sling balance device will move up and down along the longitudinal direction of the main bracket to adjust the overall center of gravity of the lifted cable. After adjustment, the hook position can be locked, and the scrap cables with certain softness and uncertain center of gravity can be lifted and moved safely and stably to correct the tilt; Once the tilt of the cargo has been corrected, the cargo can continue to be lifted and placed in its intended location.

3. The balancing device for lifting equipment used to move waste cables according to claim 1, characterized in that A weight sensor is provided on the contact surface of the hanging hole structure with the main hook to judge whether the overall weight of the hung waste cables exceeds the standard.

4. The balancing device for lifting equipment used to move waste cables according to claim 1, characterized in that The angle sensor is fixedly connected to the root of the side hook as a whole; The angle sensors fixed at the roots of the left and right side hooks are used to measure the inclination angles of the left and right side hooks, and then to know the angles of the wire ropes suspended by the hooks on both sides.

5. The balancing device for lifting equipment used to move waste cables according to claim 1, characterized in that The balancing device of the lifting device performs dynamic balancing of the hoisted waste cables in the following manner: 1) Install the balancing device of the spreader on the main hook; 2) Automatic confirmation before cargo lifting; 3) The main hook starts to lift the waste cable, and the weight information is monitored at the same time to ensure that the maximum load capacity of the system is not violated; 4) Start cargo tilt analysis; 5) According to the analysis results, the top ends of the two sets of electric hydraulic push rods are automatically controlled to extend and retract, thereby driving the side hooks on the left and right sides of the main support to move up and down along the longitudinal direction of the main support; 6) By adjusting the height of the left and right side hooks, the inclination angle of the wire rope suspended by the side hooks can be adjusted to dynamically adjust the center of gravity of the cargo; 7) If the safety parameter ΔY of the weight difference between the left and right wire ropes is ≤50mm, the main hook can continue to lift the waste cable and place it in the expected position; 8) If the safety parameter exceeds the preset value of the safety parameter, that is, ΔY>50mm, the height correction of the left and right hook positions is performed until the corrected ΔY≦50mm is obtained; 9) The main hook can continue to lift the waste cable and place it in the expected position, completing the lifting and movement of the waste cable.

6. The balancing device for lifting equipment used to move waste cables according to claim 5, characterized in that In step 2), during the automatic confirmation step before the goods are lifted, the following contents are confirmed: 6.1) Confirm that the left hook and the right hook are at the midpoint height of the sling balance device, otherwise adjust them through the corresponding electric hydraulic push rod; 6.2) Make sure that the two steel wire ropes of the same length wrapped around the scrap cable are firmly connected to the corresponding left and right hooks to ensure that the two steel wire ropes have the same length.

7. The balancing device for lifting equipment used to move waste cables according to claim 1, characterized in that Once the main hook is raised, the weight sensor system in the spreader counterbalance starts processing the following information: 7.1) The red flashing alarm will sound an alarm in the following situations: The weight of the waste cables is greater than the maximum system load. In this case, the waste cables are put back to the ground through the main hook. 7.2) When the green light is on, the scrap cables can be lifted, and when the cargo quality is stable, the weight stability analysis of the scrap cables can be started; The following formula can be used as a condition to determine when the weight of the scrap cable has stabilized: Weight of waste cables (t+1) -Weight of scrap cables (t) <10kg Among them, the weight of scrap cables (t+1)-the weight of scrap cables (t) means that the change in the weight of scrap cables from time (t) to time (t+1) is less than 10kg.

8. The sling balancing device for moving waste cables according to claim 1 is characterized in that in the cargo tilt analysis of step 4), it is necessary to determine the left and right load positions of the tilted sling balancing device and determine the cargo parameters related to the left and right wire rope connection points, and then determine whether the cargo weight difference between the left and right wire rope distances is within a predetermined safety parameter range; if the cargo weight difference between the left and right wire rope distances exceeds the predetermined safety parameter range, correction is required.

9. The balancing device for lifting equipment used to move waste cables according to claim 8, characterized in that The correction includes correcting the height of the left and right hook positions.

10. The balancing device for lifting equipment used to move waste cables according to claim 9, characterized in that The corrections described will always be made by the same amount, at the same speed and at the same time to compensate for the relatively slow speed of the electrohydraulic actuator and to prevent any unnecessary gyroscopic forces from disturbing the lifting system.