Risk assessment method for bridge and tunnel co-construction under complex geological conditions

By constructing a risk assessment method in the construction of bridge and tunnel co-construction and identifying and evaluating the risk sources in four aspects, the risk assessment problems in bridge and tunnel co-construction under complex geological conditions are solved, and the quantitative analysis of unforeseen risks is realized and Control ensures the safe, economical and efficient management of the project.

CN119047839APending Publication Date: 2024-11-29CHINA RAILWAY 15TH BUREAU GROUP CORPORATION LIMITED +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411248224.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-06
Publication Date
2024-11-29

Smart Images

  • Figure CN119047839A_ABST
    Figure CN119047839A_ABST
Patent Text Reader

Abstract

The invention discloses a risk assessment method for bridge and tunnel co-construction under complex geological conditions, and the method comprises the following steps: constructing risk assessment classifications from four aspects: construction condition risks, structure scheme risks, construction technical risks, and construction period and progress arrangement risks; screening and eliminating each risk source in the construction condition risk, selecting specific risk events, summarizing and analyzing each risk event, and evaluating the risk level of each risk event based on two indexes of risk probability and risk loss; according to the method, risk level assessment of each risk event in the remaining risk assessment classifications is completed in sequence; and integrating the risk level assessment results in the risk assessment classifications, and performing overall risk level assessment of the bridge and tunnel co-construction. The method has the advantages that uncertain factors in construction are analyzed, unpredictable risk factors are converted into quantitative indexes, final decision making is helped to be completed, and potential main risks of engineering are controlled.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of bridge and tunnel construction, and specifically relates to a risk assessment method for bridge and tunnel co-construction under complex geological conditions. Background Art

[0002] With the rapid development of urbanization in my country, traffic congestion in central urban areas with high population density and dense buildings is becoming increasingly serious. In sections where roads cross rivers, building ground bridges and underground tunnels at the same time to form a three-dimensional transportation system can effectively improve the efficiency of cross-river transportation infrastructure.

[0003] During the construction of bridge-tunnel co-construction, the co-construction structure of bridge and tunnel is divided into three main construction steps: tunnel casting, abutment construction and bridge erection. By simultaneously tying and casting the ribbed abutment with the river-crossing section beam and the tunnel top plate to form an integrated structure, the conventional practice of building a tunnel on the side of the bridge in urban municipal transportation construction is avoided, forming a bridge-tunnel co-construction transportation system. However, such projects are rare in China at present, and there is no mature construction experience for reference. Whether it is design, construction, or decision-making, there will be many difficulties and obstacles.

[0004] Therefore, technical personnel in this field need a risk assessment method for the joint construction of bridges and tunnels under complex geological conditions, so as to analyze the uncertainties in the construction, convert the unforeseen risk factors into quantitative indicators, help the owners and relevant departments to make the final decision, and control the potential major risks of the project, so as to achieve the safe, economical and efficient management goals of the project construction. Summary of the invention

[0005] The purpose of the present invention is to provide a risk assessment method for the joint construction of bridges and tunnels under complex geological conditions in accordance with the deficiencies of the above-mentioned prior art. The risk assessment method constructs a risk assessment classification from four aspects, screens and excludes each risk source, selects specific risk events, summarizes and analyzes each risk event, and evaluates the risk level of each risk event based on the two indicators of risk probability and risk loss; according to this method, the risk level assessment of each risk event in the remaining risk assessment categories is completed in turn; the risk level assessment results in each risk assessment classification are combined to conduct an overall risk level assessment of the joint construction of bridges and tunnels, so as to analyze the uncertainties in the construction, convert unforeseen risk factors into quantitative indicators, help complete the final decision, and control the potential major risks of the project.

[0006] The purpose of the present invention is achieved by the following technical solutions:

[0007] A risk assessment method for bridge-tunnel co-construction under complex geological conditions, characterized in that the risk assessment method comprises the following steps:

[0008] S1: Construct risk assessment classification from four aspects, namely: construction condition risk, structural scheme risk, construction technology risk, construction period and schedule risk;

[0009] S1.1: The risk source identification of the construction condition risk involves geological uncertainty, adverse geological conditions, hydrological and meteorological conditions, and surrounding environmental conditions; among which:

[0010] The risk sources of geological uncertainty include soil spatial variability, exploration work uncertainty, and statistical calculation errors;

[0011] The risk sources of adverse geological conditions include underground obstacles, ground subsidence, ground fissures, fill, and soft soil;

[0012] The risk sources of the hydro-meteorological conditions include surface rivers, adverse groundwater distribution, and groundwater corrosiveness;

[0013] The risk sources of the surrounding environmental conditions include above-ground structures and underground pipelines along the route;

[0014] S1.2: The risk identification of the structural scheme risk involves vertical and horizontal line types, structural types, design methods, and foundation types; among which:

[0015] The risk sources of the longitudinal and transverse lines include the horizontal curve of the tunnel, the maximum longitudinal slope rate, and the thickness of the cover soil;

[0016] The risk sources of the structural type include enclosure structure, combined structure, load conditions, section building limits, and waterproof design;

[0017] The risk sources of the design method include inappropriate design method and incorrect calculation parameters;

[0018] The risk sources of the foundation type include unreasonable reinforcement and unreasonable pile foundation arrangement;

[0019] S1.3: The risk identification of the construction technology risks mentioned above involves bored piles, supporting structures, foundation pit dewatering, main structures, and foundation pit excavation; among them:

[0020] The risk sources of bored piles include hole collapse, exposed steel skeleton, broken piles or mud inclusions, hole expansion or shrinkage, encountering underground obstacles, and hole body deflection and bending;

[0021] The risk sources of the supporting structure include support instability and fracture, purlin crushing and twisting, column instability and damage, and connection damage;

[0022] The risk sources of foundation pit dewatering include excessively high water level at the bottom of the pit and water leakage from the retaining structure;

[0023] The risk sources of the main structure include poor concrete pouring quality, unqualified concealed works, box beam falling, and substandard component connection;

[0024] The risk sources of foundation pit excavation include over-excavation of the foundation pit and failure to provide timely support;

[0025] S1.4: The risk sources of construction period and schedule risks include construction equipment arrangement, construction personnel management, improper construction organization design, improper coordination and communication among multiple parties, surrounding facilities, and unexpected problems that cause construction period delays;

[0026] S2:

[0027] S2.1: Evaluate the construction condition risk: compare the risk sources included in the construction condition risk with the corresponding parts of the engineering construction data. If the risk source does not exist in this project, or exists but has no relevance to the risk event, the inspection result is 0; if the risk source exists, but the risk source is a secondary cause of the risk event, the inspection result is 1; if the risk source exists and is the main cause of the risk event, the inspection result is 2;

[0028] The inspection results of 1 and 2 are regarded as risk events, and the risk events existing in the construction condition risks are summarized and analyzed, and the risk level of each risk event is evaluated based on the two indicators of risk probability and risk loss;

[0029] The calculation method of the risk probability is: the number of occurrences of potential risk events divided by the total construction period of the project, the unit of the total construction period of the project is year; the probability level of the calculated risk probability is divided into the following:

[0030] Probability range: greater than 0.3; the central value is 1; the probability level is 5, indicating high probability;

[0031] Probability range: 0.03-0.3; the central value is 0.1; the probability level is 4, indicating possible;

[0032] Probability range: 0.003-0.03; the central value is 0.01; the probability level is 3, indicating chance;

[0033] Probability range: 0.0003-0.003; the central value is 0.001; the probability level is 2, indicating impossibility;

[0034] Probability range: less than 0.0003; the central value is 0.0001; the probability level is 1, which means it is very unlikely;

[0035] The risk loss is divided into the following five levels: A: catastrophic; B: very serious; C: serious; D: need to be considered; E: negligible;

[0036] The criteria for determining the risk level are as follows:

[0037] If the probability level is 1 and the risk loss level is "A: catastrophic", the risk level is Level I;

[0038] If the probability level is 1 and the risk loss level is "B: Very serious", the risk level is Level I;

[0039] If the probability level is 1 and the risk loss level is "C: severe", the risk level is Level I;

[0040] If the probability level is 1 and the risk loss level is "D: to be considered", the risk level is II;

[0041] If the probability level is 1 and the risk loss level is "E: negligible", the risk level is III;

[0042] If the probability level is 2 and the risk loss level is "A: catastrophic", the risk level is Level I;

[0043] If the probability level is 2 and the risk loss level is "B: Very serious", the risk level is Level I;

[0044] If the probability level is 2 and the risk loss level is "C: severe", the risk level is II;

[0045] If the probability level is 2 and the risk loss level is "D: to be considered", the risk level is III;

[0046] If the probability level is 2 and the risk loss level is "E: negligible", the risk level is III;

[0047] If the probability level is 3 and the risk loss level is "A: catastrophic", the risk level is Level I;

[0048] If the probability level is 3 and the risk loss level is "B: Very serious", the risk level is II;

[0049] If the probability level is 3 and the risk loss level is "C: severe", the risk level is III;

[0050] If the probability level is 3 and the risk loss level is "D: to be considered", the risk level is III;

[0051] If the probability level is 3 and the risk loss level is "E: negligible", the risk level is IV;

[0052] If the probability level is 4 and the risk loss level is "A: catastrophic", the risk level is II;

[0053] If the probability level is 4 and the risk loss level is "B: Very serious", the risk level is III;

[0054] If the probability level is 4 and the risk loss level is "C: severe", the risk level is III;

[0055] If the probability level is 4 and the risk loss level is "D: to be considered", the risk level is IV;

[0056] If the probability level is 4 and the risk loss level is "E: negligible", the risk level is IV;

[0057] If the probability level is 5 and the risk loss level is "A: catastrophic", the risk level is II;

[0058] If the probability level is 5 and the risk loss level is "B: Very serious", the risk level is III;

[0059] If the probability level is 5 and the risk loss level is "C: severe", the risk level is III;

[0060] If the probability level is 5 and the risk loss level is "D: to be considered", the risk level is IV;

[0061] If the probability level is 5 and the risk loss level is "E: negligible", the risk level is IV;

[0062] S2.2: Compare the risk sources included in the structural scheme risk with the corresponding parts of the engineering construction data. If the risk source does not exist in this project, or exists but has no relevance to the risk event, the inspection result is 0; if the risk source exists, but the risk source is a secondary cause of the risk event, the inspection result is 1; if the risk source exists and the risk source is the main cause of the risk event, the inspection result is 2;

[0063] The inspection results of 1 and 2 are regarded as risk events, and the risk events existing in the structural scheme risks are summarized and analyzed, and the risk level of each risk event is evaluated based on the two indicators of risk probability and risk loss;

[0064] S2.3: Compare the risk sources included in the construction technical risks with the corresponding parts of the engineering construction data. If the risk source does not exist in this project, or exists but has no relevance to the risk event, the inspection result is 0; if the risk source exists, but the risk source is a secondary cause of the risk event, the inspection result is 1; if the risk source exists and the risk source is the main cause of the risk event, the inspection result is 2;

[0065] The inspection results of 1 and 2 are regarded as risk events, and the risk events existing in the construction technology risks are summarized and analyzed, and the risk level of each risk event is evaluated based on the two indicators of risk probability and risk loss;

[0066] S2.4: Compare the risk sources included in the construction period and schedule risks with the corresponding parts of the engineering construction data. If the risk source does not exist in this project, or exists but has no relevance to the risk event, the check result is 0; if the risk source exists, but the risk source is a secondary cause of the risk event, the check result is 1; if the risk source exists and the risk source is the main cause of the risk event, the check result is 2;

[0067] The inspection results of 1 and 2 are regarded as risk events, and the risk events existing in the construction technology risks are summarized and analyzed, and the risk level of each risk event is evaluated based on the two indicators of risk probability and risk loss;

[0068] S3: Based on the risk level assessment results of the construction condition risk, the structural scheme risk, the construction technology risk, and the construction period and schedule risk, an overall risk level assessment of the bridge-tunnel co-construction is conducted, including the following steps: assigning a weight of 30% to the risk level assessment result of the construction condition risk, assigning a weight of 20% to the risk level assessment result of the structural scheme risk, assigning a weight of 30% to the risk level assessment result of the construction technology risk, and assigning a weight of 20% to the risk level assessment result of the construction period and schedule risk, multiplying the risk level assessment result of each part by the corresponding weight and adding them up, and rounding the sum result down to an integer is the overall risk level.

[0069] The advantages of the present invention are: analyzing the uncertain factors in construction, converting unforeseen risk factors into quantitative indicators, helping owners and relevant departments to make the final decision, controlling the potential major risks of the project, and thus achieving the safe, economical and efficient management goals of project construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0070] Figure 1 A risk source identification table for construction condition risks in the present invention;

[0071] Figure 2 A risk source identification table for the structural scheme risks in the present invention;

[0072] Figure 3 A risk source identification table for construction technology risks in the present invention;

[0073] Figure 4 This is a checklist of safety risk events and risk sources for the construction conditions of the bridge-tunnel combined construction section in the present invention;

[0074] Figure 5 This is the risk assessment table for the construction conditions of the bridge-tunnel combined construction section in the present invention;

[0075] Figure 6 A checklist of safety risk events and risk sources for the bridge-tunnel combined construction section structure scheme in the present invention;

[0076] Figure 7 This is the risk assessment table of the bridge-tunnel combined construction section structure scheme in the present invention;

[0077] Figure 8 This is a checklist of technical safety risk events and risk sources for the construction of the bridge-tunnel combined construction section in the present invention;

[0078] Fig. 9 This is the construction technology risk assessment table for the bridge-tunnel combined construction section in the present invention;

[0079] Fig.10 This is the risk assessment table for the construction organization of the bridge-tunnel joint construction section in the present invention.

[0080] Fig.11 This is the overall risk assessment table for the bridge-tunnel combined construction section in the present invention. DETAILED DESCRIPTION

[0081] The features of the present invention and other related features are further described in detail below through embodiments in conjunction with the accompanying drawings to facilitate understanding by those skilled in the art:

[0082] Example: Figure 1-11 As shown, this embodiment specifically relates to a risk assessment method for bridge-tunnel co-construction under complex geological conditions, and the risk assessment method includes the following steps:

[0083] (S1) Check the engineering site of the bridge-tunnel joint construction, collect basic information of the project, and accident cases of similar projects in different parts and items. Construct risk assessment classification from four aspects: construction condition risk, structural scheme risk, construction technology risk, and construction period and schedule risk.

[0084] (S1.1) Figure 1 As shown in the figure, a risk source identification table for the construction condition risk of the bridge-tunnel co-construction structure is established, involving geological uncertainty, adverse geological conditions, hydrological and meteorological conditions, and surrounding environmental conditions; among which:

[0085] The risk sources of geological uncertainty include spatial variability of soil mass, uncertainty in survey work, and statistical calculation errors;

[0086] Risk sources of adverse geological conditions include underground obstacles, ground subsidence, ground fissures, fill, and soft soil;

[0087] Risk sources of hydro-meteorological conditions include surface rivers, adverse groundwater distribution, and groundwater corrosiveness;

[0088] The risk sources of surrounding environmental conditions include above-ground structures and underground pipelines along the line.

[0089] (S1.2) Figure 2 As shown in the figure, a risk source identification table for the structural scheme risk of the bridge-tunnel co-construction structure is established, involving vertical and horizontal line types, structural types, design methods, and foundation types; among them:

[0090] The risk sources of the vertical and horizontal lines include the horizontal curve of the tunnel, the maximum vertical slope rate, and the thickness of the cover soil;

[0091] The risk sources of structural types include enclosure structure, combined structure, load conditions, section building limits, and waterproof design;

[0092] Risk sources of design methods include inappropriate design methods and incorrect calculation parameters;

[0093] The risk sources of foundation types include unreasonable reinforcement and unreasonable pile foundation arrangement.

[0094] (S1.3) Figure 3 As shown in the figure, a risk source identification table for the construction technology risks of the bridge-tunnel co-construction structure is established, involving bored piles, supporting structures, foundation pit dewatering, main structures, and foundation pit excavation; among them:

[0095] Risk sources of bored piles include hole collapse, exposed steel bar skeleton, broken piles or mud inclusions, hole expansion or shrinkage, underground obstacles, and hole body deflection and bending;

[0096] Risk sources of supporting structures include support instability and fracture, purlin crushing and twisting, column instability and damage, and joint damage;

[0097] The risk sources of foundation pit dewatering include excessively high water levels at the bottom of the pit and water leakage from the retaining structure;

[0098] Risk sources of the main structure include poor concrete pouring quality, unqualified concealed works, box beam falling, and substandard component connections;

[0099] The sources of risk in foundation pit excavation include over-excavation and failure to provide timely support.

[0100] (S1.3) Risk sources of construction period and schedule risks include construction equipment arrangement, construction personnel management, improper construction organization design, improper coordination and communication among multiple parties, surrounding facilities, and unexpected problems that cause construction period delays.

[0101] (S2) Screen and eliminate various risk sources in construction condition risks, select specific risk events, summarize and analyze each risk event, and evaluate the risk level of each risk event based on the two indicators of risk probability and risk loss.

[0102] (S2.1) Assess construction condition risks:

[0103] like Figure 4 As shown, the risk sources included in the construction condition risk are compared with the corresponding parts of the engineering construction data. If the risk source does not exist in this project, or exists but has no correlation with the risk event, the inspection result is 0; if the risk source exists, but the risk source is a secondary cause of the risk event, the inspection result is 1; if the risk source exists and the risk source is the main cause of the risk event, the inspection result is 2. It should be noted that Figure 4 In the table, ★ indicates the inspection result is 2, ☆ indicates the inspection result is 1, and blank indicates the inspection result is 0.

[0104] Inspection results 1 and 2 are regarded as risk events. All risk events existing in construction condition risks are summarized and analyzed, and the risk level of each risk event is evaluated based on the two indicators of risk probability and risk loss.

[0105] According to the Tunnel Risk Assessment Guidelines developed by the International Tunnel Association in 2004, the "Guidelines for Risk Management of Subway and Underground Projects" issued by the Ministry of Construction in 2007, and the "Guidelines for Safety Risk Assessment of Highway Bridge and Tunnel Project Design" issued by the Ministry of Transport in 2010, the probability (frequency) of risk events is divided into five levels, as shown in the following table:

[0106] Probability range Center value Probability level description Probability level >0.3 1 Very likely 5 0.03~0.3 0.1 possible 4 0.003~0.03 0.01 accidental 3 0.0003~0.003 0.001 impossible 2 <0.0003 0.0001 Very unlikely 1

[0107] The calculation method of risk probability is: the number of occurrences of potential risk events divided by the total construction period of the project, the unit of the total construction period is year; the probability level of the calculated risk probability is divided into the following:

[0108] Probability range: greater than 0.3; the central value is 1; the probability level is 5, indicating high probability;

[0109] Probability range: 0.03-0.3; the central value is 0.1; the probability level is 4, indicating possible;

[0110] Probability range: 0.003-0.03; the central value is 0.01; the probability level is 3, indicating chance;

[0111] Probability range: 0.0003-0.003; the central value is 0.001; the probability level is 2, indicating impossibility;

[0112] Probability range: less than 0.0003; the central value is 0.0001; the probability level is 1, which means it is very unlikely.

[0113] The central values ​​mentioned represent the logarithmic means of the given intervals.

[0114] Risk losses are divided into the following five levels: A: catastrophic; B: very serious; C: serious; D: need to be considered; E: negligible.

[0115] According to the probability and consequence level of accidents, the risk level is divided into four levels, as shown in the table below.

[0116]

[0117] like Figure 5 As shown, for each typical risk, the corresponding risk level is assessed based on the risk probability and risk loss.

[0118] (S2.2) Figure 6 As shown, the risk sources included in the structural scheme risk are compared with the corresponding parts of the engineering construction data. If the risk source does not exist in this project, or exists but has no correlation with the risk event, the inspection result is 0; if the risk source exists, but the risk source is a secondary cause of the risk event, the inspection result is 1; if the risk source exists and the risk source is the main cause of the risk event, the inspection result is 2. It should be noted that Figure 6 In the table, ★ indicates the inspection result is 2, ☆ indicates the inspection result is 1, and blank indicates the inspection result is 0.

[0119] The inspection results of 1 and 2 are regarded as risk events, and the risk events existing in the structural scheme risk are summarized and analyzed. The risk level of each risk event is evaluated based on the two indicators of risk probability and risk loss. The specific method is described in step S2.1.

[0120] like Figure 7 As shown, for each typical risk, the corresponding risk level is assessed based on the risk probability and risk loss.

[0121] (S2.3) Figure 8 As shown, the risk sources included in the construction technical risks are compared with the corresponding parts of the engineering construction data. If the risk source does not exist in this project, or exists but has no correlation with the risk event, the inspection result is 0; if the risk source exists, but the risk source is the secondary cause of the risk event, the inspection result is 1; if the risk source exists and the risk source is the main cause of the risk event, the inspection result is 2; It should be noted that Figure 6 In the table, ★ indicates the inspection result is 2, ☆ indicates the inspection result is 1, and blank indicates the inspection result is 0.

[0122] The inspection results of 1 and 2 are regarded as risk events. The risk events existing in the construction technical risks are summarized and analyzed. The risk level of each risk event is evaluated based on the two indicators of risk probability and risk loss. The specific method is described in step S2.1.

[0123] like Fig. 9 As shown, for each typical risk, the corresponding risk level is assessed based on the risk probability and risk loss.

[0124] (S2.4) The risk sources included in the construction period and schedule risks are compared with the corresponding parts of the engineering construction data. If the risk source does not exist in this project, or exists but has no correlation with the risk event, the inspection result is 0; if the risk source exists, but the risk source is a secondary cause of the risk event, the inspection result is 1; if the risk source exists and the risk source is the main cause of the risk event, the inspection result is 2.

[0125] Inspection results of 1 and 2 are regarded as risk events. All risk events existing in construction technical risks are summarized and analyzed, and the risk level of each risk event is evaluated based on the two indicators of risk probability and risk loss.

[0126] like Fig.10 As shown, for each typical risk, the corresponding risk level is assessed based on the risk probability and risk loss.

[0127] S3: Comprehensively evaluate the risk level of construction condition risk, structural scheme risk, construction technology risk, construction period and schedule risk to conduct an overall risk level assessment of the bridge-tunnel joint construction, including the following steps: assign a weight of 30% to the risk level assessment result in the construction condition risk, assign a weight of 20% to the risk level assessment result in the structural scheme risk, assign a weight of 30% to the risk level assessment result in the construction technology risk, assign a weight of 20% to the risk level assessment result in the construction period and schedule risk, multiply the risk level assessment result of each part by the corresponding weight and add them up, and round the sum down to an integer to obtain the overall risk level, such as Fig.11 As shown (the construction period and schedule risk columns are omitted in the figure).

[0128] S4: Comprehensively evaluate the risk levels of construction conditions, structural schemes, and construction technologies to determine the overall risk assessment results of the bridge-tunnel co-construction. Then, determine the corresponding risk acceptance criteria based on the risk levels in the table below, and adopt corresponding risk management principles and treatment measures.

[0129]

[0130] In terms of safety risks during the construction preparation period, most risk accidents are at Level II, and the rest are at Level III. The overall risk of the bridge-tunnel combined construction section is relatively high, and the degree is unacceptable. Certain control measures need to be considered during the construction process, and should be taken seriously by all relevant parties.

[0131] During the construction of the bridge-tunnel joint construction section, there are many construction methods, many construction equipment, and complex personnel. The construction period risk caused by improper construction organization is assessed as Level III, which is an acceptable risk. Attention should be paid to the construction situation such as failure to effectively follow the implementation and lax on-site construction supervision during the construction process. In the construction organization design, attention should be paid to the overall arrangement of the formulation and implementation of the construction organization design, so as to make reasonable planning and arrangements in all aspects of organization arrangement, process connection, and progress plan.

Claims

1. A risk assessment method for bridge-tunnel co-construction under complex geological conditions, characterized by The risk assessment method comprises the following steps: S1: Construct risk assessment classification from four aspects, namely: construction condition risk, structural scheme risk, construction technology risk, construction period and schedule risk; S1.1: The risk source identification of the construction condition risk involves geological uncertainty, adverse geological conditions, hydrological and meteorological conditions, and surrounding environmental conditions; among which: The risk sources of geological uncertainty include soil spatial variability, exploration work uncertainty, and statistical calculation errors; The risk sources of adverse geological conditions include underground obstacles, ground subsidence, ground fissures, fill, and soft soil; The risk sources of the hydro-meteorological conditions include surface rivers, adverse groundwater distribution, and groundwater corrosiveness; The risk sources of the surrounding environmental conditions include above-ground structures and underground pipelines along the route; S1.2: The risk identification of the structural scheme risk involves vertical and horizontal line types, structural types, design methods, and foundation types; among which: The risk sources of the longitudinal and transverse lines include the horizontal curve of the tunnel, the maximum longitudinal slope rate, and the thickness of the cover soil; The risk sources of the structural type include enclosure structure, combined structure, load conditions, section building limits, and waterproof design; The risk sources of the described design method include inappropriate design method and incorrect calculation parameters; The risk sources of the foundation type include unreasonable reinforcement and unreasonable pile foundation arrangement; S1.3: The risk identification of the construction technology risks mentioned above involves bored piles, supporting structures, foundation pit dewatering, main structures, and foundation pit excavation; among them: The risk sources of bored piles include hole collapse, exposed steel skeleton, broken piles or mud inclusions, hole expansion or shrinkage, underground obstacles, and hole body deflection and bending; The risk sources of the supporting structure include support instability and fracture, purlin crushing and distortion, column instability and damage, and connection damage; The risk sources of foundation pit dewatering include excessively high water level at the bottom of the pit and water leakage from the retaining structure; The risk sources of the main structure include poor concrete pouring quality, unqualified concealed works, box beam falling, and substandard component connection; The risk sources of foundation pit excavation include over-excavation of the foundation pit and failure to provide timely support; S1.4: The risk sources of construction period and schedule risks include construction equipment arrangement, construction personnel management, improper construction organization design, improper coordination and communication among multiple parties, surrounding facilities, and unexpected problems that cause construction period delays; S2: S2.1: Evaluate the construction condition risk: compare the risk sources included in the construction condition risk with the corresponding parts of the engineering construction data. If the risk source does not exist in this project, or exists but has no relevance to the risk event, the inspection result is 0; if the risk source exists, but the risk source is a secondary cause of the risk event, the inspection result is 1; if the risk source exists and is the main cause of the risk event, the inspection result is 2; The inspection results of 1 and 2 are regarded as risk events, and the risk events existing in the construction condition risks are summarized and analyzed, and the risk level of each risk event is evaluated based on the two indicators of risk probability and risk loss; The calculation method of the risk probability is: the number of occurrences of potential risk events divided by the total construction period of the project, the unit of the total construction period of the project is year; the probability level of the calculated risk probability is divided into the following: Probability range: greater than 0.3; the central value is 1; the probability level is 5, indicating high probability; Probability range: 0.03-0.3; the central value is 0.1; the probability level is 4, indicating possible; Probability range: 0.003-0.03; the central value is 0.01; the probability level is 3, indicating chance; Probability range: 0.0003-0.003; the central value is 0.001; the probability level is 2, indicating impossibility; Probability range: less than 0.0003; the central value is 0.0001; the probability level is 1, which means it is very unlikely; The risk loss is divided into the following five levels: A: catastrophic; B: very serious; C: serious; D: need to be considered; E: negligible; The criteria for determining the risk level are as follows: If the probability level is 1 and the risk loss level is "A: catastrophic", the risk level is Level I; If the probability level is 1 and the risk loss level is "B: Very serious", the risk level is Level I; If the probability level is 1 and the risk loss level is "C: severe", the risk level is Level I; If the probability level is 1 and the risk loss level is "D: to be considered", the risk level is II; If the probability level is 1 and the risk loss level is "E: negligible", the risk level is III; If the probability level is 2 and the risk loss level is "A: catastrophic", the risk level is Level I; If the probability level is 2 and the risk loss level is "B: Very serious", the risk level is Level I; If the probability level is 2 and the risk loss level is "C: severe", the risk level is II; If the probability level is 2 and the risk loss level is "D: to be considered", the risk level is III; If the probability level is 2 and the risk loss level is "E: negligible", the risk level is III; If the probability level is 3 and the risk loss level is "A: catastrophic", the risk level is Level I; If the probability level is 3 and the risk loss level is "B: Very serious", the risk level is II; If the probability level is 3 and the risk loss level is "C: severe", the risk level is III; If the probability level is 3 and the risk loss level is "D: to be considered", the risk level is III; If the probability level is 3 and the risk loss level is "E: negligible", the risk level is IV; If the probability level is 4 and the risk loss level is "A: catastrophic", the risk level is II; If the probability level is 4 and the risk loss level is "B: Very serious", the risk level is III; If the probability level is 4 and the risk loss level is "C: severe", the risk level is III; If the probability level is 4 and the risk loss level is "D: to be considered", the risk level is IV; If the probability level is 4 and the risk loss level is "E: negligible", the risk level is IV; If the probability level is 5 and the risk loss level is "A: catastrophic", the risk level is II; If the probability level is 5 and the risk loss level is "B: Very serious", the risk level is III; If the probability level is 5 and the risk loss level is "C: severe", the risk level is III; If the probability level is 5 and the risk loss level is "D: to be considered", the risk level is IV; If the probability level is 5 and the risk loss level is "E: negligible", the risk level is IV; S2.2: Compare the risk sources included in the structural scheme risk with the corresponding parts of the engineering construction data. If the risk source does not exist in this project, or exists but has no relevance to the risk event, the inspection result is 0; if the risk source exists, but the risk source is a secondary cause of the risk event, the inspection result is 1; if the risk source exists and the risk source is the main cause of the risk event, the inspection result is 2; The inspection results of 1 and 2 are regarded as risk events, and the risk events existing in the structural scheme risks are summarized and analyzed, and the risk level of each risk event is evaluated based on the two indicators of risk probability and risk loss; S2.3: Compare the risk sources included in the construction technical risks with the corresponding parts of the engineering construction data. If the risk source does not exist in this project, or exists but has no relevance to the risk event, the inspection result is 0; if the risk source exists, but the risk source is a secondary cause of the risk event, the inspection result is 1; if the risk source exists and the risk source is the main cause of the risk event, the inspection result is 2; The inspection results of 1 and 2 are regarded as risk events, and the risk events existing in the construction technology risks are summarized and analyzed, and the risk level of each risk event is evaluated based on the two indicators of risk probability and risk loss; S2.4: Compare the risk sources included in the construction period and schedule risks with the corresponding parts of the engineering construction data. If the risk source does not exist in this project, or exists but has no relevance to the risk event, the check result is 0; if the risk source exists, but the risk source is a secondary cause of the risk event, the check result is 1; if the risk source exists and the risk source is the main cause of the risk event, the check result is 2; The inspection results of 1 and 2 are regarded as risk events, and the risk events existing in the construction technology risks are summarized and analyzed, and the risk level of each risk event is evaluated based on the two indicators of risk probability and risk loss; S3: Based on the risk level assessment results of the construction condition risk, the structural scheme risk, the construction technology risk, and the construction period and schedule risk, an overall risk level assessment of the bridge-tunnel co-construction is conducted, including the following steps: assigning a weight of 30% to the risk level assessment result of the construction condition risk, assigning a weight of 20% to the risk level assessment result of the structural scheme risk, assigning a weight of 30% to the risk level assessment result of the construction technology risk, and assigning a weight of 20% to the risk level assessment result of the construction period and schedule risk, multiplying the risk level assessment result of each part by the corresponding weight and adding them up, and rounding the sum result down to an integer is the overall risk level.