Fracturing fracture monitoring-based low-permeability stratum pollution remediation method

By using fracturing fracture monitoring technology in low permeability formations, monitoring and using inclinometer measurement equipment to determine the range of drug injection, the problems of uneven coverage of pharmaceutical agents and difficulty in repairing boundary control in the prior art have been solved, and efficient and accurate pollution has been achieved Repair, shortening construction cycles and reducing costs.

CN119083412APending Publication Date: 2024-12-06JIANGSU DDBS ENVIRONMENT REMEDIATION
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411014481.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-26
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The prior art is difficult to achieve pollution repair in low-permeability formations, and it is difficult to accurately control the coverage range and repair boundaries of the agent, resulting in waste of agents and secondary pollution, long engineering cycles and low repair efficiency.

Method used

Using a method based on fracturing fracture monitoring, the injection wells are built in low-permeability polluted formations, the injection equipment and inclination measurement equipment are installed to form fracturing fractures, and the crack development is monitored in real time through inclination measurement equipment to determine the range of drug injection. Ensure that the agent quickly reaches the contaminated area through the dominant crack channel.

Benefits of technology

It improves the efficiency of drug transmission, avoids secondary pollution and incomplete repair problems caused by excessive or too little drug, shortens the construction cycle, and improves repair efficiency and cost-effectiveness.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083412A_ABST
    Figure CN119083412A_ABST
Patent Text Reader

Abstract

The invention belongs to the field of polluted soil and underground water remediation, and relates to a low-permeability stratum pollution remediation method based on fracturing crack monitoring, which comprises the following steps: 1) constructing an injection well in a low-permeability pollution plume stratum; (2) an injection machine tool is installed in the injection well, and the injection machine tool is communicated with a high-pressure injection system located on the ground; 3) arranging inclination angle measuring equipment on the surface of the low-permeability pollution feather stratum; (4) a fracturing agent is injected into the low-permeability pollution plume stratum through a high-pressure injection system and an injection machine, and fractured fractures are formed; (5) after the fractured fracture is developed, the development condition of the fractured fracture is obtained through inclination angle measuring equipment; and (6) according to the development condition of the fracturing fractures, repairing functional materials are injected into the fracturing fractures at low pressure, and low-permeability stratum repairing is completed. According to the low-permeability stratum pollution remediation method based on fracturing fracture monitoring, the transmission efficiency of the agent can be improved, secondary pollution can be reduced, and the remediation range and the remediation boundary of the agent can be accurately identified.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of contaminated soil and groundwater remediation, and relates to a pollution remediation method, in particular to a low permeability stratum pollution remediation method based on fracturing fracture monitoring. Background Art

[0002] In-situ injection remediation technology is a common technology for the remediation of contaminated soil and groundwater. According to the physicochemical characteristics of the target pollutants, the pollution source and the distribution of its pollution plume in the formation, the corresponding chemical agents are prepared, and the agents are injected into the pollution plume through the injection device to achieve the remediation of the pollution plume. Due to the low injection pressure, this remediation method is often only applicable to contaminated formations with a certain permeability. The introduction of the newly developed pressure injection equipment can form multiple cracks in the formation through fracturing, and form a dominant crack channel for the agent by injecting high-permeability support materials, which promotes the diffusion efficiency of the agent in low-permeability formations, thereby extending this technology to the field of lower permeability formation remediation.

[0003] However, this technology has a potential problem: since underground operations cannot be visualized, how to control the repair agent to completely cover the contaminated area and fully react with the pollutants, so as to avoid excessive injection leading to waste and secondary pollution, and insufficient injection leading to incomplete repair. In addition, this technology has high requirements for low-permeability formations and is difficult to promote in low-permeability clay layers without the help of pressure injection equipment. At the same time, since the agent flows to the contaminated area through the cracks created by pressure, how to characterize and monitor the opening, extension length and extension direction of the cracks is the key to solving this problem.

[0004] The commonly used solutions to this technical problem at home and abroad are: 1) Calculate the theoretical dosage according to the contaminated area; 2) Multiply the theoretical dosage by the empirical coefficient to obtain the actual injection dosage according to the actual site hydrogeological conditions and working experience;

[0005] 3) Design the injection point and inject the actual amount of medicine at one time; 4) Build an observation well at the pollution boundary and monitor whether the medicine has reached the area by sampling and testing; 5) Evaluate whether a second injection is needed based on the test results.

[0006] This process assumes that the agent spreads evenly underground, but in reality the effect is often poor due to the heterogeneity of the formation. In addition, the process of injection-well construction-sampling-inspection-adjustment involves a long cycle, which affects the project cycle and reduces the repair efficiency due to the timeliness of the agent. Summary of the invention

[0007] Purpose of the invention: In order to solve the above-mentioned technical problems existing in the background technology, the present invention provides a low permeability formation pollution remediation method based on fracturing fracture monitoring, which can improve the transmission efficiency of the agent, reduce secondary pollution, and accurately identify the agent remediation range and remediation boundary.

[0008] In order to achieve the above object, the present invention adopts the following technical scheme: a low permeability formation pollution remediation method based on fracturing fissure monitoring, the low permeability formation pollution remediation method based on fracturing fissure monitoring comprises the following steps:

[0009] 1) Construction of injection wells in low permeability contaminated plume formations;

[0010] 2) Install the injection equipment in the injection well and connect the injection equipment to the high-pressure injection system on the ground;

[0011] 3) Setting up dip measurement equipment on the surface of low permeability contamination plume formation;

[0012] 4) Injecting fracturing agent into the low permeability contaminated plume formation through a high-pressure injection system and an injection machine to form a fracturing fissure;

[0013] 5) After the development of the hydraulic fractures is completed, the development of the hydraulic fractures is obtained by using the inclination measuring equipment;

[0014] 6) According to the development of the fracturing fissures, the repair functional materials are injected into the fracturing fissures at low pressure to complete the repair of the low permeability formation.

[0015] Preferably, the specific implementation method of setting the inclination measuring device in step 3) adopted in the present invention is: according to the type of the injection well in step 1), an inclinometer is set on the surface of the low permeability contaminated feather formation, and the inclinometer is connected to the online recording and analysis equipment; the inclinometer and the online recording and analysis equipment form an inclination measuring device as a whole; the type of the injection well is a single-hole well, multiple vertical wells or multiple-section horizontal wells.

[0016] Preferably, when the injection well used in the present invention is a single-hole well, the inclinometer is arranged in the following manner:

[0017] With the center of the single hole well as the center of the circle, at least an inner circle inclinometer group and an outer circle inclinometer group are arranged along the circumference of the single hole well;

[0018] The distance between the inner circle inclinometer group and the center of the single hole well is R1, the angle between two adjacent inclinometers in the inner circle inclinometer group is A1, the number of inclinometers arranged in the inner circle inclinometer group is N1, and A1×N1=360;

[0019] The distance between the outer ring inclinometer group and the center of the single-hole well is R2, the included angle between two adjacent inclinometers in the outer ring inclinometer group is A2, the number of inclinometers arranged in the outer ring inclinometer group is N2, and A2×N2 = 360;

[0020] R1 < R2; A1 > A2; N1 < N2; both N1 and N2 are integers.

[0021] Preferably, in the present invention, 2m ≤ R1 ≤ 5m; 5m ≤ R2 ≤ 10m; R2 ≥ 2R1; N1 ≥ 3; N2 ≥ 6.

[0022] Preferably, when the injection well in step 3) adopted by the present invention is a multi-well vertical well or a multi-section horizontal well, the layout method of the inclinometers is: along the connection line of the multi-well vertical wells, at least the inner ring inclinometer group and the outer ring inclinometer group on both sides of the connection line are arranged; both the inner ring inclinometer group and the outer ring inclinometer group include a plurality of inclinometers; the distance between the inner ring inclinometer group and the connection line is D1; the distance between the outer ring inclinometer group and the connection line is D2; D1 < D2.

[0023] Preferably, in the present invention, 2m ≤ D1 ≤ 5m; 5m ≤ D2 ≤ 10m; D2 ≥ 2D1.

[0024] Preferably, when setting the inclinometer on the surface of the low-permeability contaminated plume formation in step 3) adopted by the present invention, a hard cushion layer is provided at the bottom of the inclinometer.

[0025] Preferably, the specific implementation manner of step 5) adopted by the present invention is:

[0026] 5.1) Measure the azimuth and inclination angle of the ground deformation caused by the fracturing fracture through the inclinometer measurement device;

[0027] 5.2) Calculate and invert the azimuth angle, inclination angle, length, height and thickness of the fracturing fracture according to the azimuth angle and inclination angle measured in step 5.1); wherein, the calculation method is: first, use the data (azimuth angle and inclination angle) monitored by the inclinometer measurement device, combine with the formation information, and apply algorithms such as the least square method and fuzzy optimization to invert the fracture strike, inclination angle and other parameters at each monitoring point; subsequently, perform interpolation calculation on the results of the above-mentioned monitoring points to obtain the data of the entire fracture, and the data includes azimuth angle, inclination angle, length, height and thickness;

[0028] 5.3) Simulate the data obtained in step 5.2) to obtain the three-dimensional fracture development situation, wherein the simulation is to perform three-dimensional characterization and display on the data of the above-mentioned fracture (center position, azimuth angle, inclination angle, length, height and thickness).

[0029] Preferably, step 5) adopted in the present invention further comprises, after step 5.3):

[0030] 5.4) Verify and check the three-dimensional fracture development obtained in step 5.3) to obtain a corrected three-dimensional fracture development.

[0031] Preferably, the verification and calibration method in step 5.4) of the present invention is to use a high-density electrical resistance method, a direct-push drilling coring method or a well construction and monitoring geochemical parameter change method.

[0032] Compared with the prior art, the present invention has the following beneficial effects: the present invention is aimed at high-pressure hydraulic fracturing operations in low-permeability formations, and multiple fracturing fissures are formed, and the fissures are transformed into agent-dominant fissure channels with the aid of high-permeability supporting materials, which not only greatly improves the transmission efficiency of agents or functional materials in low-permeability formations, but also can characterize the direction and range of agent transmission in real time, avoiding secondary pollution or incomplete repair problems caused by excessive or insufficient injection of agents in local areas; in addition, through the low-permeability formation pollution repair method based on fracturing fissure monitoring provided by the present invention, the repair limits of each layer of each well can be obtained, and reasonable injection wells and spacing arrangements can be formulated, saving costs and improving construction efficiency. Obviously, the present invention can improve the applicability of in-situ injection repair technology to soil in contaminated sites, so that it can be applied to low-permeability formations, providing a new treatment method for the field of soil remediation. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] Figure 1 It is a schematic diagram of the principle of the low permeability formation pollution remediation method based on fracturing fracture monitoring provided by the present invention;

[0034] Figure 2 It is a schematic diagram of the concentric inclination measurement layout network adopted by the present invention;

[0035] Figure 3 It is a schematic diagram of the parallel inclination measurement layout network adopted by the present invention;

[0036] Figure 4 It is a schematic diagram of the inclinometer data analysis and inversion results formed by taking a single well single fracturing as an example in the present invention;

[0037] Figure 5 It is a three-dimensional schematic diagram of the development and distribution of underground fracturing (multi-layer fracturing in a single well);

[0038] in:

[0039] 1-injection wellbore; 2-high-pressure injection equipment; 3-inner circle inclinometer group; 4-outer circle inclinometer group; 5-high-pressure injection system; 6-injection pipeline; 7-online recording and analysis equipment; 8-nozzle; 9-dominant fracture channel; 10-pollution plume; 11-data transmission line; 12-packer; 13-well pipe wall. DETAILED DESCRIPTION

[0040] The present invention aims at the problem that the in-situ remediation technology cannot monitor the diffusion effect of the agent in low permeability formations, causing secondary pollution, incomplete remediation, and agent waste. A corresponding low permeability formation pollution remediation method based on fracturing fissure monitoring is proposed. By characterizing the fissures, the diffusion and coverage of the agent are known. The present invention can improve the application effect of the fracturing in-situ remediation technology. The low permeability formation pollution remediation method based on fracturing fissure monitoring of the present invention can measure the real-time surface morphology changes during the fracturing process according to the arrangement of the inclinometer, thereby calculating the expansion direction and range of the fissure, obtaining the flow channel and coverage range of the agent, and finally accurately obtaining the effective remediation range of the injection point. It not only saves the cost of the agent, avoids secondary pollution, solves the problems of pollution rebound, but also greatly shortens the construction period. It is an efficient and controllable in-situ remediation process.

[0041] The core principle of the present invention is: by arranging surface deformation and inclination measuring equipment (multiple groups) in the high-pressure injection area in advance, during the injection repair operation, the inclination measuring equipment measures and records the surface deformation and angle changes caused by the dominant fracture channel under the fracturing action in real time. Through the data recorded by the inclination measuring equipment, the computer inversion obtains the direction and range of the injected fracture expansion, thereby determining the repair boundary and range. The collected data can be processed, analyzed and converted into a dynamic three-dimensional graphic output, which can be seen at any angle in space, and can be driven to observe the single fracture morphology or the entire fracture network. Finally, according to the development of the fracture, the repair functional material (oxidation / reduction agent, zero-valent iron, activated carbon, etc.) is injected in a low-pressure manner, and quickly flows to the contaminated area through the dominant fracture channel, so as to achieve full contact between the agent and the pollutant, and complete the repair of the low-permeability formation. Among them, the working principle of the inclination measuring device is the same as that of a carpenter's level ruler, which includes two tilt sensors (on orthogonal axes) and precision electronic instruments. When the inclinometer is tilted, the bubble moves to keep consistent with the gravity vector. The movement of the bubbles in the conductive liquid causes the total resistance between the electrodes to change. This is done by measuring a resistor bridge or voltage divider circuit to accurately detect the amount of tilt. Although simple in theory, the devices are extremely sensitive, and using advanced electronics and signal processing techniques, inclinometers can achieve resolutions down to nanoradians.

[0042] Specifically, the low permeability formation contamination remediation method based on fracturing crack monitoring provided by the present invention comprises the following steps:

[0043] 1) Install injection wells in the low-permeability contaminated plume formation and install injection equipment in the wells (with upper and lower packers 12 to prevent cross-contamination). The high-pressure injection equipment 2 is connected to the ground high-pressure injection system 5 (water and remediation functional materials), as Figure 1 shown. When constructing the injection wells, horizontal drilling-injection integrated equipment can also be used to horizontally deploy the injection equipment with packers 12 at the front and back in the contaminated plume 10.

[0044] 2) Install dip measurement equipment on the ground surface. The installation and layout of the equipment should meet the following requirements:

[0045] The dip measurement equipment includes an on-line recording and analysis device 7 (exemplarily, the on-line recording and analysis device 7 used in the present invention can be an embedded wireless analog signal sensor acquisition node, such as the SG-Link-200 type of Lord Company) and a dipmeter connected to the on-line recording and analysis device 7 through a data transmission line 11.

[0046] For the measurement of the fracture of a single-hole well, generally, no less than two circles of dipmeters are arranged around each injection well hole / section. Exemplarily, it can include an inner circle dipmeter group 3 and an outer circle dipmeter group 4. All the instruments are in the same direction and horizontal; the arrangement radius of the inner circle dipmeter group 3 is R1, the arrangement angle is A1, and the arrangement quantity is N1; where A1×N1 = 360; the arrangement radius of the outer circle dipmeter group 4 is R2, the arrangement angle is A2, and the arrangement quantity is N2; where A2×N2 = 360, R1 < R2, A1 > A2, N1 < N2, and they are generally all integers. Exemplarily, R1 should be 2 - 5m, R2 should be 5 - 10m, and R2 should be 2 times of R1. N1 should not be less than 3, N2 should not be less than 6, and they should be arranged staggeredly at a certain angle. As Figure 2 shown, the inner circle dipmeter group 3 and the outer circle dipmeter group 4 together form a concentric dip measurement layout network.

[0047] If measuring the fracture development of multiple vertical wells or multiple horizontal well sections, dip measurement equipment can be arranged in two layers on each side along the layout direction of the wells. The inner measurement D1 should be 2 - 5m, D2 should be 5 - 10m, and D2 should be 2 times of D1. And the inner and outer dip measurement equipment on the same side should be arranged staggeredly as much as possible to avoid crosstalk during data interpretation. As Figure 3 shown, the inner circle dipmeter group 3 and the outer circle dipmeter group 4 together form a parallel dip measurement layout network.

[0048] Preferably, when installing the ground dip measurement equipment, especially the dipmeter, a rigid cushion layer should be set to achieve the rigid conduction of the surface deformation to the dip measurement equipment.

[0049] 3) The ground high-pressure injection system 5 injects the fracturing agent (usually water or proppant) into the formation at high pressure through the injection pipeline 6 to form fracturing cracks. After the fracturing cracks are developed, the repair functional materials (oxidation / reduction agents, zero-valent iron, activated carbon, etc.) are injected at low pressure, and flow rapidly to the contaminated area through the dominant fracture channels, so as to achieve full contact between the agents and the pollutants and complete the repair of the low-permeability formation.

[0050] 4) The inclination measuring equipment measures the surface deformation and angle change caused by the dominant fracture channel 9; the fracture direction and extension length of this injection are obtained through the data of step 2), thereby defining the repair boundary, providing a reference for the dosage of the agent, the spacing and location of the well points, etc., and guiding the next large-scale repair.

[0051] Specifically, the data of each fracturing is analyzed, and the azimuth and inclination of the inclinometer group are finally calculated and inverted to obtain the azimuth, inclination, length, height and thickness of the fracturing range (such as Figure 4 ). The above data are simulated to obtain the three-dimensional crack development (such as Figure 5 By carrying out fracturing tests at other layers and well locations in sequence, the development and diffusion radius of all fracturing ranges at different well locations and depths can be obtained.

[0052] 5) Cross-validation and verification of the direction and scope of fracture development: The fracture development conditions obtained by the above methods need to be cross-validated by other geophysical or drilling methods, such as high-density electrical resistance method or direct-push drilling core sampling or well construction to monitor the changes in geochemical parameters. The data obtained in this step can be used to correct the fracture development conditions.

[0053] The technical solution provided by the present invention will be described in detail below in conjunction with embodiments:

[0054] Embodiment 1:

[0055] A former pesticide factory workshop plot was demolished. After site investigation, soil and groundwater pollution was found. The pollutants were mainly pesticides, chlorinated organic solvents and other organic matter. The pollution depth was 3-4.5m. A certain yard area was selected for the implementation demonstration of the present invention. The area was a typical low-permeability clay layer with a permeability coefficient of 3×10 -7 ~6×10 -7 cm / s, plasticity index 11.0-17.5%, porosity 7.6-8.4%, soil particle size distribution: powder particles in the range of 0.005-0.01mm account for 33%, particles with a size of 0.01-0.05mm account for 41%, and fine powder particles less than 0.005mm account for 26%.

[0056] 1) Well construction: Use Geoprobe7822T spiral drill to construct a borehole with a depth of 8m and a diameter of 200mm. After the drilling is completed, put 110m PVC well pipe in the hole. The well pipe is a white pipe without sieve. Then put water, cement and bentonite in a mass ratio of 10:7:3 as the mud filler of the well pipe protective wall 13. The thickness of the well pipe protective wall 13 is about 40 to 60mm. Since the clay layer of this project is continuous and hard, the thickness of the well pipe protective wall 13 can be selected to be thinner. After the well is constructed, let it stand for 48 hours until the cement is hardened and formed.

[0057] 2) Installation and commissioning of pressurized equipment: The equipment is equipped with a high-pressure water injection pump, a mud pump, a chemical pump and an air injection pump. The high-pressure water injection pump is used to inject high-pressure water for hydraulic fracturing, the mud pump is used to transport special mud materials, and the chemical pump is used to inject repair functional materials and chemicals.

[0058] 3) Deformation and inclination measuring equipment is arranged around the injection well. For example, the inclination measuring equipment used in the present invention includes an inclinometer and an online recording and analysis device 7. A total of 12 inclinometers are arranged in the inner and outer circles. The 4 inclinometers in the inner circle are spaced 90° apart, and the 8 inclinometers in the outer circle are spaced 45° apart. Figure 2 The inner circle radius is 3m and the outer circle radius is 5m.

[0059] 4) After the above-mentioned pressurizing equipment is connected and debugged, the injection work of the injection short section can be carried out. According to the situation of the pollution plume 10 area, this example starts injection at 2.5m, 4.0m and 5.5m underground. First, the injection short section is hoisted and placed in the injection wellbore 1, and lowered until the nozzle 8 is at a depth of 2.5m. The dosage and pressure of the injection should be comprehensively considered based on factors such as geology, formation conditions, type and concentration of pollutants, and selected remediation agents / functional materials. In this example, the pressure of fracturing injection is 55Mpa, the flow rate is 93L / min, and the high-pressure water injection pump is turned on. The high-pressure jet penetrates the PVC pipe wall and the cement bentonite wall layer for about 20s-30s. After the penetration, the injection is continued for 60-180s. Pay attention to observe and measure the uplift of the ground. The uplift in the center area of ​​the fracturing varies from about 1 to 3cm.

[0060] 5) After high-pressure water injection fracturing is completed, the mortar is composed of a mixture of fine sand and guar gum (0.5% to 2%). Among them, (1) the ratio of fine sand to guar gum is 1.2 to 1.5 kg fine sand / L guar gum; (2) the volume of fine sand (pile volume) accounts for the total volume of mortar is between 0.47 and 0.64. The injection pressure is 100 to 500 kpa, and it lasts for 2 to 5 minutes. When the mortar fills the fracturing pores, the construction of the first layer of high permeability support layer is completed. A total of about 2,400 kg of fine sand is injected into the high permeability support layer.

[0061] 6) After the proppant is stabilized, the azimuth and inclination of each inclinometer are analyzed based on the data collected by the inclinometer. Combined with the relative coordinate position of the inclinometer and other information, the inclinometer data is modeled and algorithm inverted to obtain the azimuth, inclination, length, width and thickness of the overall direction of the fracture in this fracturing, determine the fracture boundary, and draw a three-dimensional diagram of the fracture development through graphic modeling.

[0062] 7) According to steps 4), 5) and 6), the second and third sections (4.0 m and 5.5 m) are subjected to fracturing operations.

[0063] 8) According to the degradation of the agent, after a certain period of time, the agent pump is turned on and the agent or functional material is injected along the high permeability support layer. The pressure is 0.1-10MPa and the flow rate is 5-15L / min. The total amount of agent is calculated based on the crack opening, length and pollution concentration.

[0064] The results of this example show that in low permeability formations, the injection and fracturing zone formed by high-pressure water can reach more than 3m, that is, the permeability transformation range can reach more than 3m (as shown in Table 1). Through this data, when arranging the fracturing wells, it is ensured that the influence range of the fracturing well superposition fully covers the high-concentration pollution plume area. This method can be used to inject repair agents and materials for a long time to solve the agent diffusion problem in low permeability formations.

[0065] Table 1 Summary of case fracturing results

[0066]

Claims

1. A method for remediating low permeability formation pollution based on fracturing fissure monitoring, characterized by: The described repair method includes the following steps: 1) Construct injection wells in the low-permeability contaminated plume formation; 2) Install injection equipment in the injection wells and connect the injection equipment to a high-pressure injection system on the ground; 3) Set up dip measurement equipment on the surface of the low-permeability contaminated plume formation; 4) Inject fracturing agents into the low-permeability contaminated plume formation through the high-pressure injection system and the injection machine to form fracturing fissures; 5) After the development of the fracturing fissures is completed, obtain the development situation of the fracturing fissures through the dip measurement equipment; 6) According to the development situation of the fracturing fissures, inject repair functional materials at low pressure into the fracturing fissures to complete the repair of the low-permeability formation.

2. The low permeability formation pollution remediation method based on fracturing fissure monitoring according to claim 1 is characterized by: The specific implementation method of setting up the dip measurement equipment in step 3) is: Set up inclinometers on the surface of the low-permeability contaminated plume formation according to the type of injection well in step 1), and connect the inclinometers to online recording and analysis equipment; The inclinometers and the online recording and analysis equipment together form the dip measurement equipment; The type of the injection well is a single-hole well, multiple vertical wells or multiple horizontal wells.

3. The low permeability formation pollution remediation method based on fracturing fissure monitoring according to claim 2 is characterized by: When the injection well is a single-hole well, the layout method of the inclinometers is: Taking the center of the single-hole well as the center of the circle, at least arrange an inner circle inclinometer group and an outer circle inclinometer group along the circumferential direction of the single-hole well; The distance between the inner circle inclinometer group and the center of the single-hole well is R1, the included angle between two adjacent inclinometers in the inner circle inclinometer group is A1, the number of inclinometers arranged in the inner circle inclinometer group is N1, and A1×N1 = 360; The distance between the outer circle inclinometer group and the center of the single-hole well is R2, the included angle between two adjacent inclinometers in the outer circle inclinometer group is A2, the number of inclinometers arranged in the outer circle inclinometer group is N2, and A2×N2 = 360; R1 < R2; A1 > A2; N1 < N2; Both N1 and N2 are integers.

4. The low permeability formation pollution remediation method based on fracturing crack monitoring according to claim 3 is characterized by: 2m ≤ R1 ≤ 5m; 5m ≤ R2 ≤ 10m; R2 ≥ 2R1; N1 ≥ 3; N2 ≥ 6.

5. The low permeability formation pollution remediation method based on fracturing fissure monitoring according to claim 2 is characterized by: When the injection well in step 3) is multiple vertical wells or multiple horizontal wells, the layout method of the inclinometers is: Along the connection line of the multiple vertical wells, at least arrange an inner circle inclinometer group and an outer circle inclinometer group on both sides of the connection line; Both the inner circle inclinometer group and the outer circle inclinometer group include multiple inclinometers; The distance between the inner circle inclinometer group and the connection line is D1; The distance between the outer circle inclinometer group and the connection line is D2; D1 < D2.

6. The low permeability formation contamination remediation method based on fracturing fissure monitoring according to claim 5 is characterized by: 2m ≤ D1 ≤ 5m; 5m ≤ D2 ≤ 10m; D2 ≥ 2D1.

7. The low permeability formation contamination remediation method based on fracturing fissure monitoring according to any one of claims 2 to 6, characterized in that: When setting up the inclinometers on the surface of the low-permeability contaminated plume formation in step 3), set up a hard cushion at the bottom of the inclinometers.

8. The low permeability formation contamination remediation method based on fracturing fissure monitoring according to claim 7 is characterized by: The specific implementation method of step 5) is: 5.1) Measure the azimuth and dip of the surface deformation caused by the fracturing fissures through the dip measurement equipment; 5.2) Calculate and invert the azimuth, dip, length, height and thickness of the fracturing fissures according to the azimuth and dip measured in step 5.1); 5.3) Simulate the data obtained in step 5.2) to obtain the three-dimensional fissure development situation.

9. The low permeability formation contamination remediation method based on fracturing fissure monitoring according to claim 8 is characterized by: After step 5.3) in step 5), it further includes: 5.4) Verify and check the three-dimensional fracture development obtained in step 5.3) to obtain a revised three-dimensional fracture development.

10. The low permeability formation pollution remediation method based on fracturing fissure monitoring according to claim 9 is characterized in that: The verification and calibration method in step 5.4) is to use the high-density electrical resistance method, the direct-push drilling coring method or the well construction monitoring geochemical parameter change method.