Underground concrete aggregate screening and washing workshop and underground concrete aggregate screening and washing system
The combination of the support leg assembly and the suspension beam mechanism simplifies the installation of the crane, solves the problem of complex and time-consuming rock anchor beam construction, realizes the efficient lifting and maintenance of screening and washing equipment in small-span underground workshops, and reduces the construction difficulty and cost.
Patent Information
- Application Number
- CN202411402637.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-09
- Publication Date
- 2025-10-17
- Estimated Expiration
- 2044-10-09
AI Technical Summary
The construction process of rock anchor beams in the existing technology is complicated, time-consuming, difficult to construct and costly, and is not suitable for use in small-span underground concrete aggregate screening and washing workshops.
The combination of support leg assembly and suspension beam mechanism is used for the movable installation of crane. Combined with the support frame and chamber design, it simplifies the construction of lifting and hoisting equipment and reduces the construction difficulty and cost.
It has achieved efficient lifting and daily inspection and maintenance of screening and washing equipment in small-span underground workshops, shortened construction period and reduced costs.
Smart Images

Figure CN119083491B_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the technical field of concrete production, in particular to an underground concrete aggregate screening and washing workshop and an underground concrete aggregate screening and washing system. BACKGROUND
[0002] In large domestic and foreign water conservancy and hydropower projects such as Yangfanggou Power Station high and low line concrete generation system, Yeba Dam concrete system and the like, all are ground type concrete production systems. When the concrete production system needs to be arranged in the underground space, the screening and washing workshop also needs to be arranged in the underground space, and the lifting and hoisting equipment needs to be considered in the space-limited underground arrangement, and the lifting and hoisting equipment is used for lifting and daily maintenance and the like of the screening and washing equipment.
[0003] In the related art, the rock anchor beam is generally used as the installation basis of the lifting and hoisting equipment.
[0004] However, the operation mode of the rock anchor beam needs to go through the processes of blasting, anchoring structure construction, concrete pouring and the like, which is complex in process, time-consuming, high in construction difficulty and cost consumption, and is not conducive to application in small-span underground workshops. SUMMARY
[0005] Therefore, it is necessary to provide an underground concrete aggregate screening and washing workshop and an underground concrete aggregate screening and washing system in view of the problems of the construction process of the operation mode of the rock anchor beam in the related art being complex in process, time-consuming, high in construction difficulty and cost consumption, and being not conducive to application in small-span underground workshops.
[0006] In one aspect, the present application provides an underground concrete aggregate screening and washing workshop, which comprises:
[0007] A first chamber, the first chamber has a support base surface;
[0008] A first support frame, the first support frame comprises a support foot assembly and a suspended beam mechanism, one end of the support foot assembly is uniformly distributed on the support base surface, the other end of the support foot assembly is connected with the suspended beam mechanism, the suspended beam mechanism is used for movably installing a crane, and the crane can move relative to the suspended beam mechanism in a direction parallel to the support base surface;
[0009] A second support frame, the second support frame is arranged on the support base surface, the height of the second support frame in the direction perpendicular to the support base surface is lower than the height of the suspended beam mechanism, and the second support frame is used for installing screening and washing equipment;
[0010] A second chamber;
[0011] A third chamber, the first chamber having opposite first and second side walls, the second and third chambers being disposed on opposite sides of the first chamber, the second chamber extending through the first side wall to communicate with the first chamber, and the third chamber extending through the second side wall to communicate with the first chamber.
[0012] In one embodiment, the first chamber has a first central axis extending from the first side wall toward the second side wall, and the second support frame has a second central axis offset from and parallel to the first central axis, such that the second support frame is offset from the first central axis.
[0013] In one embodiment, the second and third chambers have a third central axis coinciding with the first central axis and the second central axis offset from and parallel to the first central axis, and the second and third chambers are offset from the first central axis in the same direction as the second support frame.
[0014] In one embodiment, the third chamber is tapered along the third central axis and away from the first chamber.
[0015] In one embodiment, the first chamber further has opposite third and fourth side walls, and the underground concrete aggregate screening and washing plant further comprises a fourth chamber disposed on one side of the first chamber and communicating with the third side wall.
[0016] In one embodiment, the underground concrete aggregate screening and washing plant further comprises a fifth chamber disposed on one side of the first chamber, and the fifth chamber is located on the same side as the fourth chamber and communicates with the third side wall, and the fifth and fourth chambers are spaced apart and extend parallel to each other.
[0017] In one embodiment, the fourth and fifth chambers are disposed on opposite sides of the second central axis offset from the first central axis.
[0018] In one embodiment, the second support frame comprises first and second support platforms arranged adjacent to each other along the second central axis and the first support platform is arranged closer to the second chamber, and the first support platform has a higher height than the second support platform along a direction perpendicular to the support base surface.
[0019] In one embodiment, the support leg assembly comprises a plurality of support rods uniformly distributed along the extension direction of the side wall of the first chamber.
[0020] In another aspect, the application also provides an underground concrete aggregate screening system, comprising the underground concrete aggregate screening workshop as described above, and the underground concrete production system further comprises a crane feeding mechanism, a screening device and a discharging mechanism, the crane is movably installed on the suspension beam mechanism, the feeding mechanism is arranged in the second chamber, the screening device is arranged on the second support frame, and the discharging mechanism is arranged in the third chamber.
[0021] The underground concrete aggregate screening workshop and the underground concrete aggregate screening system described above have the following advantages: one end of the support foot assembly is uniformly distributed on the support base surface, and the other end of the support foot assembly is connected with the suspension beam mechanism, so that the crane can be movably installed on the suspension beam mechanism and can move relative to the suspension beam mechanism in a direction parallel to the support base surface, thereby achieving hoisting of the screening device by the crane and daily operation maintenance. Specifically, the first support frame can be but is not limited to a steel frame or the like structure, which has a shorter construction period, lower construction difficulty and lower cost than the traditional rock anchor beam, and is conducive to popularization and application in small-span underground workshops. BRIEF DESCRIPTION OF DRAWINGS
[0022] Figure 1 FIG. 1 is a front view of the underground concrete aggregate screening system according to an embodiment of the application.
[0023] Figure 2 FIG. 2 is a top view of the underground concrete aggregate screening system shown in FIG. 1. Figure 1
[0024] Figure 3 FIG. 3 is a left view of the underground concrete aggregate screening system shown in FIG. 1. Figure 1
[0025] BRIEF DESCRIPTION OF DRAWINGS
[0026] 100, first chamber; 100a, first central axis; 100b, inspection passage; 110, first side wall; 120, second side wall; 130, third side wall; 140, fourth side wall; 150, support base surface; 200, second chamber; 200a, third central axis; 300, third chamber; 400, fourth chamber; 500, fifth chamber; 600, first support frame; 610, support foot assembly; 611, support rod member; 620, cantilever mechanism; 700, second support frame; 700a, second central axis; 710, first support table; 720, second support table; 800, feeding shaft; 10, crane; 20, feeding mechanism; 30, screening device; 31, first vibrating screen device; 32, second vibrating screen device; 33, spiral sand washing device; 40, discharging mechanism; 41, first discharging belt conveyor; 42, second discharging belt conveyor; 43, third discharging belt conveyor; 60, waste material belt conveyor. DETAILED DESCRIPTION
[0027] In order to make the above objectives, features and advantages of the present application more clear and easily understood, the specific embodiments of the present application are described in detail below with reference to the accompanying drawings. In the following description, a lot of specific details are set forth in order to provide a thorough understanding of the present application. However, the present application can be implemented in many different ways than those described herein, and those skilled in the art can make similar improvements without departing from the spirit of the present application, so the present application is not limited to the specific embodiments disclosed below.
[0028] In the description of the present application, it should be understood that if these terms "center", "longitudinal", "transverse", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like appear, these terms indicate the orientation or positional relationship based on the orientation or positional relationship shown in the drawings, and are only for the purpose of facilitating the description of the present application and simplifying the description, and therefore cannot be understood as indicating or implying that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore cannot be understood as limiting the present application.
[0029] In addition, if these terms "first", "second" appear, these terms are only for the purpose of description, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of the technical features referred to. Therefore, the features limited by "first", "second" can explicitly or implicitly include at least one of the features. In the description of the present application, if the term "a plurality of" appears, the meaning of "a plurality of" is at least two, for example, two, three, etc., unless otherwise specifically limited.
[0030] In the present application, unless specifically defined otherwise, if there are terms such as "mount", "connect", "connect", "fix" and the like, these terms should be understood in a broad sense. For example, it can be fixedly connected, or it can be detachably connected, or it can be integrated; it can be mechanically connected, or it can be electrically connected; it can be directly connected, or it can be indirectly connected through an intermediate medium; it can be the internal communication of two elements or the interaction relationship between two elements, unless otherwise specifically limited. For those skilled in the art, the specific meaning of the above terms in the present application can be understood according to the specific circumstances.
[0031] In the present application, unless specifically defined otherwise, if there are terms such as "mount", "connect", "connect", "fix" and the like, these terms should be understood in a broad sense. For example, it can be fixedly connected, or it can be detachably connected, or it can be integrated; it can be mechanically connected, or it can be electrically connected; it can be directly connected, or it can be indirectly connected through an intermediate medium; it can be the internal communication of two elements or the interaction relationship between two elements, unless otherwise specifically limited. For those skilled in the art, the specific meaning of the above terms in the present application can be understood according to the specific circumstances.
[0032] It should be noted that if an element is referred to as "fixed to" or "provided on" another element, it can be directly on another element or there can be a middle element. If an element is considered to be "connected" to another element, it can be directly connected to another element or there can be a middle element. If present, the terms "vertical", "horizontal", "up", "down", "left", "right" and similar expressions used in the present application are for illustrative purposes only and are not the only embodiment.
[0033] For large-span power plant of hydropower project, the main role of rock-anchored beam is to anchor the reinforced concrete beam body firmly on the rock by using a certain depth of grouting long anchor rod, and the load borne by the long anchor rod and the rock wall friction is transmitted to the rock mass. The design of rock-anchored beam does not set up column, and fully utilizes the bearing capacity of surrounding rock, compared with ordinary cast-in-place beam, this structure can narrow the span of underground plant, reduce the engineering quantity, reduce the engineering cost, and at the same time increase the stability of the cavern. But because the application of rock-anchored beam is mainly concentrated in the underground plant of large-scale water conservancy hub, which is used for the installation, maintenance and other purposes of mechanical and electrical equipment, its construction is a comprehensive construction technology integrating light surface (pre-splitting) blasting, anchoring technology, concrete technology, stress, strain and displacement measurement technology, which has high technical requirements, great construction difficulty and high construction cost, and is not conducive to popularization and application in small-span underground workshop.
[0034] For the above problems, refer to Figure 1The underground concrete aggregate screening system is provided. Figure 1 A front view structural schematic diagram of the underground concrete aggregate screening system in an embodiment of the present application is shown. The underground concrete aggregate screening system in an embodiment of the present application comprises a crane 10, a feeding mechanism 20, a screening device 30, a discharging mechanism 40 and an underground concrete aggregate screening workshop. The underground concrete aggregate screening workshop in the underground concrete aggregate screening system provided by the present application is improved as follows.
[0035] Continuing to refer to Figure 1 In an embodiment, the underground concrete aggregate screening workshop comprises a first chamber 100, a second chamber 200, a third chamber 300, a first support frame 600 and a second support frame 700. The first chamber 100 has a support base surface 150. The first support frame 600 comprises a support foot assembly 610 and a suspended beam mechanism 620. In combination Figure 2 As shown, one end of the support foot assembly 610 is uniformly distributed on the support base surface 150, and the other end of the support foot assembly 610 is connected with the suspended beam mechanism 620. The suspended beam mechanism 620 is used to movably mount the crane 10, and enables the crane 10 to move in a direction parallel to the support base surface 150 relative to the suspended beam mechanism 620. The second support frame 700 is arranged on the support base surface 150, and the height of the second support frame 700 along the direction perpendicular to the support base surface 150 is lower than the height of the suspended beam mechanism 620, and the second support frame 700 is used to mount the screening device 30. The first chamber 100 has opposite first and second side walls 110 and 120, and the second and third chambers 200 and 300 are arranged on the two sides of the first chamber 100 away from each other, the second chamber 200 penetrates the first side wall 110 to communicate with the first chamber 100, and the third chamber 300 penetrates the second side wall 120 to communicate with the first chamber 110.
[0036] In an embodiment, the crane 10 of the underground concrete aggregate screening system is movably mounted on the suspended beam mechanism 620, the feeding mechanism 20 is arranged in the second chamber 200, the screening device 30 is mounted on the second support frame 700, and the discharging mechanism 40 is arranged in the third chamber 300.
[0037] The one end of the support foot assembly 610 is evenly distributed on the support base surface 150, and the other end of the support foot assembly 610 is connected with the cantilever beam mechanism 620, so that the crane 10 can be movably installed on the cantilever beam mechanism 620, and the crane 10 can move relative to the cantilever beam mechanism 620 in a direction parallel to the support base surface 150, so that the crane 10 can hoist the screening equipment 30 and perform daily operation maintenance. Specifically, the first support frame 600 can be implemented as a steel frame, and compared with the construction mode of the traditional rock anchor beam, the first support frame 600 is used as the installation base of the crane 10, so that the construction period is shorter, the construction difficulty is lower, and the cost can be effectively saved, which is beneficial to popularization and application in small-span underground workshops.
[0038] Specifically, during operation of the underground concrete aggregate screening system, the aggregate to be screened is first transported by the feeding mechanism 20 in the first chamber 100 and fed to the screening equipment 30; then the aggregate is screened by the screening operation of the screening equipment 30, and finally the finished product is output from the third chamber 300 by the discharging mechanism 40. Understandably, the height of the first chamber 100 can be adaptively set according to the height of the screening equipment 30, or the height of the second support bracket can be adjusted to adapt to the height of the first chamber 100, which will not be described here.
[0039] Optionally, the feeding mechanism 20 can be implemented as a feeding belt conveyor. The screening equipment 30 can be implemented as a first vibrating screen device 31, a second vibrating screen device 32, and a spiral sand washing device 33. The first vibrating screen device 31 and the second vibrating screen device 32 are used for secondary screening operation of the aggregate, and the spiral sand washing device 33 is used for washing, grading, and removing impurities of the aggregate, as well as washing operation of fine and coarse materials.
[0040] The first vibrating screen device 31 is connected with the feeding mechanism 20 and a first discharging belt conveyor 41. The first discharging belt conveyor 41 can directly output the finished product meeting the requirements from the third chamber 300 after the screening of the first vibrating screen device 31.
[0041] Optionally, the spiral sand washing device 33 is also connected with a waste belt conveyor 60, which is used for outputting waste.
[0042] Adaptively, the second support frame 700 can but not limited to include a first support table 710 and a second support table 720, the first support table 710 and the second support table 720 are arranged adjacent along the extending direction of the second central axis 700a, and the first support table 710 is arranged on the side close to the second chamber 200, the setting height of the first support table 710 along the direction perpendicular to the support base surface 150 is higher than the setting height of the second support table 720, so as to meet the arrangement requirements of the first vibrating screen device 31 and the second vibrating screen device 32.
[0043] Adaptively, in combination with Figure 2 As shown, the first chamber 100 can but not limited to also have a third side wall 130 and a fourth side wall 140 opposite to each other, and the underground concrete aggregate screening workshop further includes a fourth chamber 400, the fourth chamber 400 is arranged on one side of the first chamber 100 and communicates with the third side wall 130, and the fourth chamber 400 is used to arrange the waste belt conveyor 60, so as to meet the transportation requirements of the waste.
[0044] In addition, the first vibrating screen device 31 also has a primary screening discharge port (not shown), which communicates with the feed port (not shown) of the second vibrating screen device 32. The discharge mechanism 40 can but not limited to be implemented to include the first discharge belt conveyor 41, and further include a second discharge belt conveyor 42 and a third discharge belt conveyor 43, the second discharge belt conveyor 42 and the third discharge belt conveyor 43 are respectively connected with the two secondary screening discharge ports of the second vibrating screen device 32, so as to output different finished products through the second discharge belt conveyor 42 and the third discharge belt conveyor 43.
[0045] Preferably, continuing to refer to 2, the second chamber 200 and the third chamber 300 have a coincident third central axis 200a, so that the second chamber 200 and the third chamber 300 can be arranged in a straight line, so as to improve the efficiency of aggregate conveying and optimize the conveying route.
[0046] Optionally, the first chamber 100 has a first central axis 100a extending in the direction from the first side wall 110 to the second side wall 120, and the second support frame 700 has a second central axis 700a, the second central axis 700a deviates from and is parallel to the first central axis 100a, so that the second support frame 700 deviates from the first central axis 100a, so that a maintenance passage 100b can be formed in the first chamber 100, so as to facilitate the maintenance work of the maintenance workers.
[0047] More preferably, the third central axis 200a is parallel to the first central axis 100a, the second central axis 700a deviates from and is parallel to the first central axis 100a, and the second chamber 200 and the third chamber 300 deviate from the first central axis 100a in the same direction as the second support frame 700. This makes it easier for the loading mechanism 20 and the discharging mechanism 40 to be arranged in a position that is adapted to the screening and washing equipment 30, which helps to optimize the aggregate conveying route and improve the screening and washing efficiency.
[0048] Preferably, the third chamber 300 is along the third central axis 200a and gradually expands in the direction away from the first chamber 100, so that the first discharge belt conveyor 41, the second discharge belt conveyor 42 and the third discharge belt conveyor 43 are staggered with each other. On the one hand, it helps to meet the layout requirements of the first discharge belt conveyor 41, the second discharge belt conveyor 42 and the third discharge belt conveyor 43, and on the other hand, it helps to reduce the excavation material of the third chamber 300, thereby shortening the construction period, reducing construction costs and improving the safety of the chamber structure.
[0049] Optionally, combined Figure 1 and Figure 3 As shown, the movement mode of the crane 10 can be, but is not limited to, implemented as the suspension beam mechanism 620 being able to move relative to the support leg assembly 610 along the first direction, thereby driving the crane 10 to move along the first direction X; in addition, see Figure 3 The crane 10 can move relative to the suspension beam mechanism 620 along the second direction Y, thereby realizing the all-round movement of the crane 10 in the planar direction parallel to the supporting base surface 150, so as to ensure the preliminary lifting operation of the screening and washing equipment 30 and daily inspection and maintenance operations, such as the lifting and replacement of related screening and washing structures.
[0050] Optionally, see Figure 2 The support foot assembly 610 may include, but is not limited to, multiple support rods 611, and the multiple support rods 611 are evenly distributed along the extension direction of the side wall of the first chamber 100. This helps to make full use of the spatial characteristics of the first chamber 100, so that the support rods 611 can be arranged at the edge of the first chamber 100, reducing interference with the layout of the screening and washing equipment 30. In addition, it helps to increase the layout range of the maintenance channel 100b in the first chamber 100, ensuring that maintenance workers have sufficient walking and maintenance space, and improving maintenance convenience.
[0051] Optionally, see Figure 2The underground concrete aggregate screening and washing plant can further include a fifth chamber 500, which is arranged on one side of the first chamber 100 and is located on the same side of the fourth chamber 400 and communicates with the third side wall 130. The fifth chamber 500 is arranged in parallel with the fourth chamber 400. Specifically, the fifth chamber 500 is used for transporting slag during the excavation stage of the underground concrete aggregate screening and washing plant, and is used as an access channel for related equipment during the construction of the underground concrete aggregate screening and washing plant. In addition, the fifth chamber 500 is also used as a main access channel for maintenance personnel, thereby solving the problem of the lower passage of the underground concrete aggregate screening and washing plant during construction.
[0052] Preferably, the fourth chamber 400 and the fifth chamber 500 are arranged on the opposite side of the second central axis 700a deviated from the first central axis 100a. In this way, the arrangement of the maintenance passage 100b can be adapted to arrange the fourth chamber 400 and the fifth chamber 500 on the side close to the maintenance passage 100b, thereby facilitating the maintenance personnel to enter and exit the fifth chamber 500 and to perform maintenance work on the equipment in the fourth chamber 400.
[0053] Optionally, the underground concrete aggregate screening and washing plant can further include a feeding shaft 800, which is used to supply materials to the upward feeding mechanism 20 to meet the feeding requirements during the screening and washing operation.
[0054] The technical features of the above-described embodiments can be combined in any manner. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described, but as long as the combinations of the technical features do not contradict, they should be considered as within the scope of the present disclosure.
[0055] The above-described embodiments only express several implementation manners of the present application, and the description is relatively specific and detailed, but it should not be understood as a limitation on the patent scope of the present application. It should be noted that for those skilled in the art, some modifications and improvements can be made without departing from the concept of the present application, and these modifications and improvements are within the protection scope of the present application. Therefore, the patent protection scope of the present application should be subject to the appended claims.
Claims
1. An underground concrete aggregate screening and washing workshop, characterized in that: The underground concrete aggregate screening and washing workshop includes: a first chamber having a supporting base surface; a first support frame, the first support frame comprising a support leg assembly and a suspension beam mechanism, one end of the support leg assembly being evenly distributed on the support base surface, the other end of the support leg assembly being connected to the suspension beam mechanism, the suspension beam mechanism being used for movably mounting a crane and enabling the crane to move relative to the suspension beam mechanism in a direction parallel to the support base surface; a second support frame, the second support frame being arranged on the support base surface, the height of the second support frame in a direction perpendicular to the support base surface being lower than the height of the suspension beam mechanism, and the second support frame being used to install the screening and washing equipment; Second chamber; The third chamber, the first chamber has a first side wall and a second side wall opposite to each other, the second chamber and the third chamber are respectively arranged on two sides of the first chamber away from each other, the second chamber passes through the first side wall to be connected with the first chamber, and the third chamber passes through the second side wall to be connected with the first chamber.
2. The underground concrete aggregate screening and washing workshop according to claim 1, characterized in that: The first chamber has a first central axis extending along the first side wall toward the second side wall, and the second support frame has a second central axis, which deviates from and is parallel to the first central axis, so that the second support frame deviates from the first central axis.
3. The underground concrete aggregate screening and washing workshop according to claim 2, characterized in that: The second chamber and the third chamber have a coincident third central axis, the third central axis is parallel to the first central axis, the second central axis deviates from and is parallel to the first central axis, and the second chamber and the third chamber deviate from the first central axis in the same direction as the second support frame.
4. The underground concrete aggregate screening and washing workshop according to claim 3, characterized in that: The third chamber is arranged along the third central axis and gradually expands in a direction away from the first chamber.
5. The underground concrete aggregate screening and washing workshop according to claim 2, characterized in that: The first chamber also has a third side wall and a fourth side wall opposite to each other. The underground concrete aggregate screening and washing workshop also includes a fourth chamber. The fourth chamber is arranged on one side of the first chamber and communicates with the third side wall.
6. The underground concrete aggregate screening and washing workshop according to claim 5, characterized in that: The underground concrete aggregate screening and washing workshop also includes a fifth chamber, which is arranged on one side of the first chamber. The fifth chamber and the fourth chamber are located on the same side and are connected to the third side wall. The fifth chamber and the fourth chamber are spaced apart and extend parallel to each other.
7. The underground concrete aggregate screening and washing workshop according to claim 6, characterized in that: The fourth chamber and the fifth chamber are arranged on opposite sides of the second central axis in a direction deviating from the first central axis.
8. The underground concrete aggregate screening and washing workshop according to claim 2, characterized in that: The second support frame includes a first support platform and a second support platform. The first support platform and the second support platform are arranged adjacent to each other along the extension direction of the second central axis and the first support platform is arranged on a side close to the second chamber. The setting height of the first support platform in the direction perpendicular to the supporting base surface is higher than the setting height of the second support platform.
9. The underground concrete aggregate screening and washing workshop according to any one of claims 1 to 8, characterized in that: The support foot assembly includes a plurality of support rods, and the plurality of support rods are evenly distributed along the extension direction of the side wall of the first chamber.
10. An underground concrete aggregate screening and washing system, characterized in that: The underground concrete aggregate screening and washing workshop comprises the underground concrete aggregate screening and washing workshop according to any one of claims 1 to 9, and the underground concrete production system further comprises a crane, a loading mechanism, a screening and washing device, and a discharging mechanism, the crane is movably mounted on the suspension beam mechanism, the loading mechanism is arranged in the second chamber, the screening and washing device is installed on the second support frame, and the discharging mechanism is arranged in the third chamber.
Citation Information
Patent Citations
Gravel mixing system and method for underground cavern
CN107263730A
Chamber
CN107829754A