Zero-carbon park intelligent system based on AI large model
By adopting an intelligent system based on AI large model in the park and using transformer large model for energy prediction and scheduling, the problem of uneven allocation of energy resources is solved, and efficient utilization and waste reduction of energy resources are achieved.
Patent Information
- Application Number
- CN202410953245.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-16
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2044-07-16
AI Technical Summary
The existing park's single energy power generation system and a single management system lead to uneven distribution of new energy resources, resulting in the problem of waste of energy and failure to maximize the shared use of resources.
Using a zero-carbon park intelligent system based on AI model, nesting transformer models, including a variety of energy generation systems, energy load systems, energy consumption supervision systems and AI model energy operation and maintenance systems, predicting the power load curve and Optimize energy scheduling and achieve reasonable allocation and comprehensive utilization of energy resources.
By rationally allocating energy resources, improving the utilization efficiency of new energy, ensuring the safe and economic operation of the energy network, reducing energy waste, and maximizing the shared use of resources.
Smart Images

Figure CN119093319A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of energy Internet of Things, and in particular to a zero-carbon park intelligent system based on an AI big model. Background Art
[0002] With the rapid development of Internet of Things technology and distributed new energy in recent years, especially the unprecedented scientific and technological progress in the field of distributed new energy power generation technology, in order to meet people's daily life needs and energy material requirements, especially in the fields of industry and commerce, manufacturing factories have higher and higher requirements for energy flow distribution of new energy, especially in the fields of industrial interconnection and energy development. With the continuous advancement of technology, the application of AI big models in the field of energy management will become more and more extensive, bringing revolutionary changes to the energy industry.
[0003] At present, the traditional park energy power generation on the market is relatively simple, the energy dispatching Internet of Things is relatively backward, and it has not yet formed a scale. This cannot solve the advantages of diversified power generation of distributed energy in factories, and cannot bring into play the benefits brought by the comprehensive utilization of distributed energy. The system is relatively simple, resources cannot be flexibly allocated and mobilized, and comprehensive energy utilization cannot be interconnected and synchronized. These links have added many problems to the entire energy industry, leading to uneven distribution of new energy resources in factories and energy waste, etc., so that the entire system does not maximize resource sharing and utilization. Summary of the invention
[0004] The purpose of an embodiment of the present invention is to provide a zero-carbon park intelligent system based on an AI big model, which is used to fully or at least partially solve the problems existing in the above-mentioned prior art, such as the relatively single factory energy generation and the single management system leading to uneven distribution of new energy resources and the resulting energy waste, so that the entire system cannot maximize resource sharing and utilization.
[0005] In order to achieve the above objectives, an embodiment of the present invention provides a zero-carbon park intelligent system based on an AI big model, wherein the system is embedded with a transformer big model, and includes:
[0006] An energy generation system, the energy generation system comprising a PVT power generation and heating system, a photovoltaic power generation system, a wind power generation system, a hydrogen power generation system, an electrochemical energy storage system and an electrothermal phase change energy storage system, wherein the PVT power generation and heating system uses a transformer large model to predict power generation based on historical meteorological data and power generation data; the wind power generation system uses the Encode module and the Decode module of the transformer large model to predict wind power generation within a period of time based on input historical meteorological data and power generation data; the electrochemical energy storage system is used to store energy during periods of abundant wind and light resources, and release energy to supply power during periods of scarce resources and peak electricity consumption; the electrothermal phase change energy storage system is used to convert other forms of energy into thermal energy, and store the thermal energy through a heat storage medium, and extract the stored heat through heat exchange when it is needed;
[0007] Energy load system, the energy load system includes a charging pile system and a park factory equipment load system, wherein the charging pile system includes an AC charging pile, a DC charging pile and a supercharged liquid cooling charging pile, and the park factory equipment load system includes at least a central air conditioning load, an air compressor load, an air energy load, a Ma load composition and the power consumption of heavy-load machines in the factory;
[0008] The park energy consumption supervision system includes an energy consumption monitoring and metering system, an energy auxiliary system and an industrial Internet system, wherein the energy consumption monitoring and metering system is used to collect, measure and calculate the park energy consumption in real time to achieve energy consumption statistics, energy consumption management and assessment, energy efficiency evaluation, energy quota and energy-saving services; the energy auxiliary system is used to monitor the temperature of transformer windings, the temperature of switchgear busbars, the partial discharge monitoring of switchgears and the electrical parameter monitoring of distribution cabinets; the industrial Internet system is used to comprehensively monitor platform services and data link security and provide time series data analysis, and to conduct queries and aggregate analysis of any historical time period;
[0009] The AI large-scale model energy operation and maintenance system includes a park energy dispatching system and an operation and maintenance inspection system, wherein the park energy dispatching system is used to predict the power load curve for a period of time based on the AI large-scale model, and adjust the equipment according to the power consumption in each time period of each day and the pre-set priority and time, so that the equipment layer responds to the energy adjustment instructions issued by the system, realizes the energy release of new energy photovoltaic, wind energy and energy storage media, energy transmission on the incoming line side of the park distribution network, and uses the released energy for other loads.
[0010] Optionally, the photovoltaic power generation system includes: a photovoltaic component, a controller and an inverter, wherein the controller controls the photovoltaic component to convert light energy into direct current, and controls the inverter to convert the direct current into alternating current.
[0011] Optionally, the wind power generation system includes:
[0012] A wind turbine component, comprising at least a wind turbine generator set, a tower, a foundation and cables, wherein the wind turbine component is used to capture wind energy and convert the wind energy into alternating electric energy;
[0013] A grid-connected control component, comprising at least a rectifier module, a grid-connected controller, a load unloader and cables, wherein the grid-connected control component is used to control the normal operation of the wind turbine components;
[0014] An inverter component, comprising at least a grid-connected inverter and a cable, wherein the inverter component is used to invert the direct current output by the grid-connected control component into alternating current and feed the energy into the grid;
[0015] The unloading component is used to control the wind turbine to brake and stop, so as to ensure the safety of the wind turbine under abnormal working conditions.
[0016] Optionally, the hydrogen energy power supply system utilizes photovoltaic electricity generated during the daytime peak hours and valley electricity generated at night to electrolyze water to produce hydrogen, and generates electricity through fuel cells during peak hours of power consumption in the grid.
[0017] Optionally, the electrochemical energy storage system comprises:
[0018] A battery pack for direct current charging or discharging;
[0019] Energy storage converter, used to control the charging and discharging process of the battery pack and perform AC-DC conversion;
[0020] Battery management system, used to monitor the status information of the battery pack;
[0021] Energy management system, responsible for data collection, network monitoring and energy scheduling.
[0022] Optionally, the energy auxiliary system includes:
[0023] Environmental monitoring subsystem, used to monitor temperature and humidity, gas, noise, dust, water leakage and water level;
[0024] Power equipment monitoring subsystem, used to monitor the operating status of air conditioners, dehumidifiers, fans, lighting, water pumps and fresh air fans;
[0025] Security monitoring subsystem, used to monitor smoke, infrared, electronic fence, access control and video.
[0026] Optionally, the industrial Internet of Things system adopts a PaaS platform architecture and is configured with:
[0027] The rule engine is used to implement data repair, cleaning, calculation and analysis, circulation, data alarm and multi-scenario linkage;
[0028] Data subscription and open API interface to support third-party application development and integration;
[0029] A variety of device protocol parsing drivers are used to access multiple devices through gateway access;
[0030] Configure alarm rules on the interface for alarm management.
[0031] Optionally, the park energy dispatching system includes a power supply dispatching system that adopts an economic dispatching algorithm and a big data dispatching algorithm for power supply dispatching. When the economic dispatching algorithm is adopted, the microgrid management is completed in combination with time-of-use electricity prices, new energy output rules, and preset generation, distribution, and use logic; when the big data dispatching algorithm is adopted, on the basis of economic dispatch, the microgrid dispatching granularity is further refined through data aggregation and big data analysis to realize photovoltaic power generation prediction and load prediction.
[0032] Optionally, train a large transformer model according to the following formula:
[0033]
[0034] In the formula, Represents renewable energy power generation data, represents energy consumption data, represents the external energy data of the park, λ represents the price of new energy power generation, k represents the consumption price, δ represents the external energy price, and F * Represents the integration cost.
[0035] Optionally, the power generation is predicted according to the following formula:
[0036]
[0037] In the formula, α, β, ε, η, φ, ω represent the power generation duration coefficient of each energy time period, P V , P T P represents the power generation of the PVT power generation and heating system, W Indicates wind power generation power, P ES1 Represents the electrochemical energy storage release power, P ES2 represents the power released by the phase change energy storage system, P S Indicates the power input to the power system.
[0038] Through the above technical solutions, the management system can make reasonable allocation of the entire energy resources through the transformer big model, and through the supervision and coordination of new energy power generation and comprehensive utilization of new energy in the industrial Internet, it will help factories meet various energy needs, ensure the high penetration of new energy, safe and economic operation of various energy networks, and the reliability and comprehensive utilization efficiency of various energy supplies.
[0039] Other features and advantages of the embodiments of the present invention will be described in detail in the subsequent detailed description. BRIEF DESCRIPTION OF THE DRAWINGS
[0040] The accompanying drawings are used to provide a further understanding of the embodiments of the present invention and constitute a part of the specification. Together with the following specific embodiments, they are used to explain the embodiments of the present invention, but do not constitute a limitation on the embodiments of the present invention. In the accompanying drawings:
[0041] Figure 1 It is a structural schematic diagram of a zero-carbon park intelligent system based on an AI big model provided by an embodiment of the present invention;
[0042] Figure 2 It is a schematic diagram of the architecture of a zero-carbon park intelligent system based on an AI big model provided in an embodiment of the present invention. DETAILED DESCRIPTION
[0043] The specific implementation of the embodiment of the present invention is described in detail below in conjunction with the accompanying drawings. It should be understood that the specific implementation described here is only used to illustrate and explain the embodiment of the present invention, and is not used to limit the embodiment of the present invention.
[0044] Because photovoltaic power generation is during the day, and wind power generation is subject to conditional constraints, we can use energy storage and phase change energy storage to store the unused energy, and use the stored energy at night or during peak hours when electricity prices are high. Based on daily electricity consumption, the AI big model can also predict the electricity load curve for the near future, and coordinate scheduling based on electricity consumption in each time period of the day. If there is no sunshine or wind in the next few days, our energy storage can buy electricity from the State Grid power system, store it, and buy it at a low price. If the electricity is not used up, it can also be sold to the outside at a high price.
[0045] See also Figure 1 As shown, it is a structural schematic diagram of a zero-carbon park intelligent system based on an AI big model provided by an embodiment of the present invention, in which a transformer big model is embedded, including:
[0046] An energy generation system, the energy generation system comprising a PVT power generation and heating system, a photovoltaic power generation system, a wind power generation system, a hydrogen power generation system, an electrochemical energy storage system and an electrothermal phase change energy storage system, wherein the PVT power generation and heating system uses a transformer large model to predict power generation based on historical meteorological data and power generation data; the wind power generation system uses the Encode module and the Decode module of the transformer large model to predict wind power generation within a period of time based on input historical meteorological data and power generation data; the electrochemical energy storage system is used to store energy during periods of abundant wind and light resources, and release energy to supply power during periods of scarce resources and peak electricity consumption; the electrothermal phase change energy storage system is used to convert other forms of energy into thermal energy, and store the thermal energy through a heat storage medium, and extract the stored heat through heat exchange when it is needed;
[0047] Energy load system, the energy load system includes a charging pile system and a park factory equipment load system, wherein the charging pile system includes an AC charging pile, a DC charging pile and a supercharged liquid cooling charging pile, and the park factory equipment load system includes at least a central air conditioning load, an air compressor load, an air energy load, a Ma load composition and the power consumption of heavy-load machines in the factory;
[0048] The park energy consumption supervision system includes an energy consumption monitoring and metering system, an energy auxiliary system and an industrial Internet system, wherein the energy consumption monitoring and metering system is used to collect, measure and calculate the park energy consumption in real time to achieve energy consumption statistics, energy consumption management and assessment, energy efficiency evaluation, energy quota and energy-saving services; the energy auxiliary system is used to monitor the temperature of transformer windings, the temperature of switchgear busbars, the partial discharge monitoring of switchgears and the electrical parameter monitoring of distribution cabinets; the industrial Internet system is used to comprehensively monitor platform services and data link security and provide time series data analysis, and to conduct queries and aggregate analysis of any historical time period;
[0049] The AI large-scale model energy operation and maintenance system includes a park energy dispatching system and an operation and maintenance inspection system, wherein the park energy dispatching system is used to predict the power load curve for a period of time based on the AI large-scale model, and adjust the equipment according to the power consumption in each time period of each day and the pre-set priority and time, so that the equipment layer responds to the energy adjustment instructions issued by the system, realizes the energy release of new energy photovoltaic, wind energy and energy storage media, energy transmission on the incoming line side of the park distribution network, and uses the released energy for other loads.
[0050] In some embodiments, the PVT power generation and heating system uses the heat energy generated by solar PVT components while generating electricity to provide hot water or heating. It is a set of efficient cogeneration systems that couple PVT components and multi-energy systems to achieve power generation and heating at the same time under limited space conditions. It can also meet the needs of the park for electricity, hot water, heating, etc. However, solar power generation is affected by factors such as light intensity, temperature, and cloud thickness, and has large fluctuations. The transformer large model can learn historical weather data and power generation data to predict solar power generation and heat supply in the future. In addition, the transformer large model can also use satellite remote sensing technology to monitor the light intensity on the surface photovoltaic panels in real time to further improve the prediction accuracy.
[0051] In some embodiments, the photovoltaic power generation system includes: a photovoltaic component, a controller, and an inverter, wherein the controller controls the photovoltaic component to convert light energy into direct current, and controls the inverter to convert the direct current into alternating current.
[0052] Specifically, the photovoltaic power generation system is mainly composed of photovoltaic modules, controllers, inverters and other accessories (grid connection does not require batteries). Depending on whether it relies on the public power grid, it is divided into off-grid and grid-connected. The off-grid photovoltaic system is equipped with electrochemical batteries and hydrogen energy with energy storage functions, which can ensure the stability of the system power and supply electricity to the load when the photovoltaic system does not generate electricity at night or when there is insufficient power generation on rainy days. The working principle is that the photovoltaic modules convert light energy into direct current, and the direct current is converted into alternating current under the action of the inverter, ultimately realizing the functions of electricity consumption and Internet access.
[0053] In some embodiments, the wind power generation system includes: a wind turbine component, including at least a wind turbine generator set, a tower, a foundation, and a cable, wherein the wind turbine component is used to capture wind energy and convert the wind energy into alternating electrical energy;
[0054] A grid-connected control component, comprising at least a rectifier module, a grid-connected controller, a load unloader and cables, wherein the grid-connected control component is used to control the normal operation of the wind turbine components;
[0055] An inverter component, comprising at least a grid-connected inverter and a cable, wherein the inverter component is used to invert the direct current output by the grid-connected control component into alternating current and feed the energy into the grid;
[0056] The unloading component is used to control the wind turbine to brake and stop, so as to ensure the safety of the wind turbine under abnormal working conditions.
[0057] In some implementations, wind power generation is affected by many factors such as wind speed, wind direction, and temperature, and has great uncertainty. The Encode and Decode modules of the transformer large model can be used to analyze and learn the input historical meteorological data and power generation data to predict the wind power generation in the future, providing a basis for the grid energy dispatch in the park.
[0058] Specifically, the wind power generation system: The structure of the wind power generation system is not directly converted from wind energy to electrical energy, and a transition of mechanical energy is required in the middle. The function is to convert the constantly changing wind energy into AC power with constant frequency and voltage or DC power with constant voltage. The wind turbine converts wind energy into AC power. The wind turbine outputs AC power with unstable amplitude and frequency. After being rectified into DC power by the controller, it is output to the inverter power supply, which converts it into AC power with stable amplitude and frequency. After being measured by the watt-hour meter, it is directly fed into the DC power inverter to be converted into AC380V, 50Hz three-phase AC power. It is mainly composed of the following structures: wind turbine part (captures wind energy and converts it into alternating electrical energy; including wind turbines, towers, foundations, cables, etc.), grid-connected control part (controls the safe and normal operation of the wind turbine system, and the built-in rectifier module outputs DC power and limits the maximum output voltage to protect the back-end inverter; including grid-connected controller, unloader, cables, etc.), inverter part (converts the DC power output by the controller into AC power and feeds the energy into the grid, with step-up transformer isolation; including grid-connected inverter, cables, etc.), unloading part (realizes intelligent control of the wind turbine to brake and stop, ensuring the safety of the wind turbine under abnormal conditions).
[0059] In some embodiments, the hydrogen power supply system utilizes photovoltaic electricity generated during the daytime peak hours and valley electricity generated at night to electrolyze water to produce hydrogen, and generates electricity through fuel cells during peak hours of power consumption in the grid.
[0060] Specifically, the hydrogen power generation system: by building an efficient, reliable and stable power supply "renewable energy hydrogen production - hydrogen energy storage and transportation - hydrogen fuel cell cogeneration" energy comprehensive utilization system. Use the photovoltaic power generated during the daytime peak hours and the valley power at night to electrolyze water to produce hydrogen. During the peak power consumption of the power grid, fuel cells are used to generate electricity to ensure sufficient electricity. Core equipment such as efficient electrolysis hydrogen production systems, fuel cell cogeneration systems, hydrogen and battery hybrid energy storage, and multi-port DC converters interconnect the production, storage, and consumption links in energy networks such as electricity, hydrogen, and heat, and realize multifunctional collaborative transformation and deployment such as green electricity hydrogen production, efficient cogeneration of electric heat and hydrogen, flexible interaction between vehicles and the grid, and long-term off-grid operation, forming an electricity-centered electric hydrogen and heat coupled energy Internet demonstration.
[0061] In some embodiments, the electrochemical energy storage system comprises:
[0062] A battery pack for direct current charging or discharging;
[0063] Energy storage converter, used to control the charging and discharging process of the battery pack and perform AC-DC conversion;
[0064] Battery management system, used to monitor the status information of the battery pack;
[0065] The energy management system is responsible for data collection, network monitoring and energy scheduling.
[0066] In some embodiments, chemical, electrothermal phase change energy storage and hydrogen power generation system: Under the new power system, unused energy is stored during the period of abundant power resources, and energy is released to supply power during the period of lack of power resources and peak power consumption, so as to achieve the characteristics of peak shaving and valley filling, comprehensive energy utilization, etc. The electrochemical energy storage system is mainly composed of battery packs, energy storage converters (PCS), battery management systems (BMS), energy management systems (EMS) and other electrical equipment. The principle of the electrothermal phase change energy storage system is to convert other forms of energy into thermal energy, and store the thermal energy under good insulation conditions through a specific heat storage medium, and then extract the stored heat through heat exchange when it is needed. The hydrogen power generation system uses photovoltaic electricity generated during the peak period of the day and valley electricity at night to electrolyze water to produce hydrogen. During the peak period of power consumption in the power grid, fuel cells are used to generate electricity to ensure sufficient electricity. The transformer large model can optimize the charging and discharging strategy of the energy storage system, improve the utilization rate of energy storage equipment, and reduce operating costs. At the same time, the large model can also provide the optimal operation strategy for the energy storage system based on factors such as real-time electricity prices and renewable energy power generation to maximize economic benefits. The transformer model can overcome the intermittent and volatile problems of new energy, achieve buffering and smooth transition of "source-grid-load", ensure the efficiency and safety of the system, and reduce the cost of clean energy. The changes in key mechanisms such as attenuation and thermal runaway of electrochemical material systems cannot be observed by online measurement of multiple internal indicators, so AI data-driven + electrochemical material mechanism model is currently a feasible mode for battery management.
[0067] In some embodiments, the ground source heat pump system: The ground source heat pump system extracts heat from the ground in winter from the soil or surface water (groundwater) at room temperature, and stores the heat of the building in the ground in summer, thereby solving the cold and heat sources for heating and air conditioning in winter and summer. In summer, the heat in the room is transferred to the ground by the unit to cool the room and store heat for winter use. In winter, the heat in the soil is transferred to the room by the heat pump to heat the factory buildings and rooms, and store cold energy for summer use. The earth and soil provide a good source of free energy storage, thus realizing the seasonal conversion of energy. Outdoor geothermal heat exchange system, geothermal heat pump unit and indoor heating and air conditioning terminal system. Among them, the geothermal heat pump machine mainly has two forms: water-water type or water-air type. The heat transfer between the three systems is carried out by water or air heat exchange medium. The heat exchange medium between the geothermal heat pump and the geothermal energy is water, and the heat exchange medium with the building heating and air conditioning terminal can be water or air.
[0068] In some embodiments, the energy consumption monitoring and metering system: takes water, electricity, gas, cold, heat, steam, oil and other energy media as monitoring objects, establishes an energy management and control center, conducts real-time collection, metering, calculation and analysis and centralized dispatch management of its energy consumption, and displays the system load in real time and analyzes the system line loss through deep mining and statistical analysis of data. Complete energy consumption, metering, analysis, processing, storage, publishing and other tasks, realize energy consumption statistics, energy consumption management and assessment, energy efficiency evaluation, energy consumption audit, energy efficiency publicity, energy consumption quota, energy saving service, and is responsible for various daily reports, various data curves, pie charts, bar charts and other tasks. The system collects monitoring and metering data of instruments or systems of energy-consuming units at all levels in real time, adds time stamps, connects and stores them in the computer system, and displays the energy data and energy consumption of enterprises in various forms such as geographical distribution maps, process maps, wiring diagrams, trend maps, information charts, etc., to realize online monitoring and metering. At the same time, it can access the production, safety, environmental protection and other data of the enterprise. Through the division and control of system permissions, the dispatching and control functions can be divided into professions (energy, production, environmental protection, safety, etc.), departments, and fields (electricity, water, steam, compressed air, etc.), so as to truly realize the centralized dispatching and management of enterprise production and comprehensively guarantee the production and operation of the enterprise. The energy consumption measurement data is accurate to each independent space of the building, each branch, workshop, process and team of the industrial enterprise, and the time can be accurate to the minute. The relationship between energy consumption and production output in each link is clearly presented, and combined with the performance appraisal of each unit and even individual. Truly achieve the refinement and comprehensiveness of energy management and implement energy saving and consumption reduction work.
[0069] In some embodiments, the energy assistance system includes:
[0070] Environmental monitoring subsystem, used to monitor temperature and humidity, gas, noise, dust, water leakage and water level;
[0071] Power equipment monitoring subsystem, used to monitor the operating status of air conditioners, dehumidifiers, fans, lighting, water pumps and fresh air fans;
[0072] Security monitoring subsystem, used to monitor smoke, infrared, electronic fence, access control and video.
[0073] Specifically, the intelligent auxiliary monitoring system solution for the park power distribution station / switch station is composed of multiple subsystems, including environmental monitoring subsystem, power equipment monitoring subsystem, video monitoring subsystem, security monitoring subsystem, fire monitoring subsystem, lighting control subsystem, etc. Realize system functions: Dynamic monitoring: transformer winding temperature monitoring, switch cabinet busbar temperature measurement, switch cabinet partial discharge monitoring, feeder power temperature monitoring, distribution cabinet electrical parameter monitoring, etc. Environmental monitoring: temperature and humidity, gas (SF6, O2, etc.), noise, dust, water leakage, water level, etc. Security monitoring: smoke, infrared, electronic fence, access control, video, etc. Equipment control: air conditioning, dehumidifier, fan, lighting, water pump, fresh air fan, etc. WeChat push, web page pop-up window, SMS alarm, telephone alarm, on-site sound and light alarm, afterglow broadcast alarm, email alarm, etc.
[0074] In some implementations, the industrial Internet of Things system adopts a PaaS platform architecture and is configured with:
[0075] The rule engine is used to implement data repair, cleaning, calculation and analysis, circulation, data alarm and multi-scenario linkage;
[0076] Data subscription and open API interface to support third-party application development and integration;
[0077] A variety of device protocol parsing drivers are used to access multiple devices through gateway access;
[0078] Configure alarm rules on the interface for alarm management.
[0079] Specifically, the industrial Internet of Things system: adopts the PaaS platform architecture, and the system has the capabilities of wide access to industrial terminal equipment, comprehensive analysis of industrial communication protocols, remote setting and command issuance of equipment, SOE event reporting, etc. At the same time, it uses rule engine technology to realize data repair, cleaning, calculation and analysis, circulation, data alarm, multi-scenario linkage and other functions, providing real-time and accurate energy data statistics and analysis, and comprehensive monitoring platform services and data link security. Through digital modeling of equipment entities and entity relationships, the instantiation and grouping management of equipment is realized; real-time calculation and analysis: through the rule engine, data calculation and circulation are realized; interface configuration of alarm rules supports alarm management; time series data analysis is provided, and query and aggregation analysis of any historical time period is performed.
[0080] In some embodiments, the power supply dispatching system adopts an economic dispatching algorithm and a big data dispatching algorithm for power supply dispatching. When the economic dispatching algorithm is adopted, the microgrid management is completed in combination with time-of-use electricity prices, new energy output rules, and preset generation, distribution, and use logic; when the big data dispatching algorithm is adopted, on the basis of economic dispatch, the microgrid dispatching granularity is further refined through data aggregation and big data analysis to realize photovoltaic power generation prediction and load prediction.
[0081] Specifically, the power supply dispatching system: realizes data collection and monitoring of the power grid in the factory or park area; conducts regional load forecasting and formulates start-up and shutdown plans; compiles inter-provincial and relevant regional power grid power; conducts regional power flow, stability, short-circuit current and offline or online economic operation analysis and calculation; regional power grid relay protection setting calculation; regional system accident handling and maintenance plan arrangement. According to the preset priority and time, the equipment layer responds to the energy adjustment instructions issued by the system and releases power for other loads. Combined with the information collected by the sensor, the system presets multiple scene modes for adjustment. The equipment layer responds to the energy adjustment instructions issued by the system and releases power for other loads. The core of local consumption of new energy is the multi-energy dispatching algorithm, including economic dispatching algorithm and big data dispatching algorithm. Economic dispatch combines time-of-use electricity prices and new energy output rules, presets generation, distribution, and use logic, and completes microgrid management; big data dispatch, based on economic dispatch, realizes photovoltaic power generation forecasting and load forecasting through data aggregation and big data analysis, further refines the granularity of microgrid dispatching, optimizes electricity costs, and improves power efficiency.
[0082] In some implementations, the AI large-model energy dispatching and operation and maintenance management system includes functions such as park energy dispatching and system operation and maintenance inspection; the park power supply dispatching system mainly realizes data collection and monitoring of the park power grid, conducts park load forecasting, and formulates production equipment, energy generation equipment, and power system energy park input start and shutdown plans; according to the pre-set priority and time, the equipment layer responds to the energy adjustment instructions issued by the system to realize the energy release of new energy photovoltaic, wind energy and energy storage media, energy transmission on the incoming line side of the park distribution network, and the released energy is used for other loads. The core of the on-site consumption of new energy in the park is the comprehensive dispatching of multiple energy sources and the comprehensive utilization of multiple energy sources, including through energy economic dispatching algorithms and power generation and power consumption big data dispatching algorithms. According to economic dispatch combined with time-of-use electricity prices and new energy output rules, the generation, distribution, and use logic are preset to complete the management of the park power grid.
[0083] In the model scheduling, the specific implementation rules are: Since photovoltaic power is more affected by light and weather, the daytime period is used to realize the power generation of equipment. The PVT photovoltaic thermal system uses light conditions to collect environmental heat and realize the heating conditions of the park. In addition, wind power generation is also affected by the environment. The wind level and size conditions constrain the energy release of the equipment. The AI big model needs to learn the start-up time of wind power generation energy and wind speed, etc., and use the characteristics of electrochemical and material energy storage to collect and release energy. When the park's new energy generation is abundant, energy can be stored through energy storage, and when the power system is abundant, it is low, that is, energy valley value is bought at a low price for later use in the factory park; and when the power system is short of energy, it is sold at a high price at the peak. According to the daily power consumption of the park, the AI big model can also predict the power load curve in the near future, and coordinate the scheduling according to the power consumption in each time period of the day. If there is no sunshine and no wind in the next few days, our energy storage can buy electricity from the State Grid power system at this time, store it, buy it at a low price, and sell it to the outside at a high price when the power is not used up. It can not only realize the coordination of comprehensive energy generation and power consumption of new energy in the park, but also coordinate with the large-scale system dispatch of power system energy, reduce the volatility of the energy system and enhance the robustness of the system.
[0084] In some embodiments, the transformer large model is trained according to the following formula:
[0085]
[0086] In the formula, Represents renewable energy power generation data, Represents energy consumption data, represents the external energy data of the park, λ represents the price of new energy power generation, k represents the consumption price, δ represents the external energy price, and F * Represents the integration cost.
[0087] In some embodiments, the power generation can be predicted according to the following formula:
[0088] In the formula, α, β, ε, η, φ, ω represent the power generation duration coefficient of each energy time period, P V , P T P represents the power generation of the PVT power generation and heating system, W Indicates wind power generation power, P ES1 Represents the electrochemical energy storage release power, P ES2 represents the power released by the phase change energy storage system, P S Indicates the power input to the power system.
[0089] Specifically, we first use the transformer model to predict the power generation data, the power generation power P of the PVT power generation and heating system V , P T 、Wind power generation power P W , electrochemical energy storage release power P ES1 , Phase Change Energy Storage System P ES2 Power system input power P S etc., using energy generation forecasts by time period α, β, ε, η, φ, ω represent the power generation duration coefficients of each energy source in each time period. The transformer model continuously learns and predicts the formulas, and obtains the optimal phased power generation data by training the power generation duration coefficients such as α, β, ε, η, φ, ω, etc. Usually, α and β are affected by light intensity, ε by wind power level, η by chemical energy storage release efficiency, φ by phase change medium release efficiency, and ω by the size of the power system energy load curve.
[0090] In the process of applying to the comprehensive management of new energy, the transformer model is used to analyze a large amount of energy data. (New energy power generation data , Energy consumption data , Park outsourced energy data etc.) for prefabrication, , , , Represent the price of new energy power generation, consumption price, external energy price, and integration cost respectively), through the formula Train to get the optimal data F * In the data processing process, the high-dimensional data set and data noise are considered. Through the Encode and Decode modules of the transformer large model and the extraction of data, effective clustering analysis and cleaning and denoising autoencoder preprocessing are performed to improve the quality of energy data.
[0091] In addition, due to the complexity of the energy system, the large transformer model needs to continuously modify parameters during training, use regularization, dropout and other methods to prevent overfitting and reduce the generalization ability of the model, and optimize model performance through cross-validation and adjustment of hyperparameters. In addition, in order to protect household electricity information and operation data, etc.
[0092] In some implementations, the transformer large model uses the following data security technologies: (1) By using symmetric encryption technology on energy data, the security of data during transmission and storage is ensured; (2) Privacy protection technologies such as differential privacy and homomorphic encryption are used to protect the privacy data on the enterprise side; (3) A strict data access control and audit system is established to prevent internal data leakage.
[0093] Because photovoltaic power generation is during the day, and wind power generation is subject to conditional constraints, we can use energy storage and phase change energy storage to store the unused energy, and use the stored energy at night or during peak hours when electricity prices are high. Based on daily electricity consumption, the AI big model can also predict the electricity load curve for the near future, and coordinate scheduling based on electricity consumption in each time period of the day. If there is no sunshine or wind in the next few days, our energy storage can buy electricity from the State Grid power system, store it, and buy it at a low price. If the electricity is not used up, it can also be sold to the outside at a high price.
[0094] In some implementations, the transformer model can learn the start-up time of wind power generation energy, wind speed, etc., and use the characteristics of electrochemistry and material energy storage to collect and release energy. When the park has abundant new energy generation, it can store energy through energy storage, and when the power system has abundant energy, it can buy energy at a low price at the valley value for later use in the factory park; and when the power system is short of energy, it can sell it at a high price at the peak. According to the daily power consumption of the park, the AI model can also predict the power load curve in the near future, and coordinate the dispatch according to the power consumption in each time period of the day. If there is no sunshine or wind in the next few days, our energy storage can buy electricity from the State Grid power system at this time, store it, buy it at a low price, and sell it to the outside at a high price if the electricity is not used up. It can not only realize the coordination of comprehensive energy generation and power consumption of new energy in the park, but also cooperate with the large system dispatch of power system energy, reduce the volatility of the energy system, and enhance the stability of the system.
[0095] In some embodiments, see Figure 2As shown, it is a schematic diagram of the architecture of a zero-carbon park intelligent system based on an AI big model provided by an embodiment of the present invention, wherein the yellow part represents the underlying architecture, and the blue part represents the top-level architecture, wherein the top-level architecture includes a factory energy auxiliary system, a factory energy consumption monitoring system, a comprehensive energy supervision and operation system, an industrial Internet system, and an energy consumption metering system, and the underlying architecture includes a distribution network system, a load system, a charging pile system, a chemical energy storage system, a wind power generation system, a photovoltaic power generation system, a PVT power generation and heating system, a hydrogen power generation system, an electric thermal phase change energy storage system, and a ground source heat pump system.
[0096] The technical effects achieved by this application are as follows: through the development of micro-energy networks to adapt to the new energy power generation resources of the park, the mutual conversion between multiple types of energy input and output, mixed storage of distributed energy and comprehensive demand-side response methods are realized, the volatility and randomness of new energy resources are smoothed, the overall power fluctuation level of distributed power generation systems is reduced, and the safe and economic operation of new energy high-penetration distribution networks is ensured.
[0097] The transformer big model can accurately predict power demand and power generation, as well as energy demand, by analyzing a large amount of historical data, thereby optimizing the production and distribution of new energy in the park, power market transactions, and new energy grid connection. In addition, the transformer big model can also be used to optimize the operation of the power system and improve the operating efficiency and economic benefits of the power grid. It can identify early signs of equipment failure from complex data and provide strong support for the maintenance of energy equipment. At the same time, the transformer big model can also perform predictive maintenance on equipment, reasonably arrange maintenance time and strategies, and reduce operation and maintenance costs.
[0098] In distributed energy systems, transformer big models can help achieve coordinated optimization of each unit and improve energy efficiency. The application of big models provides new perspectives and methods for energy management, which is not only significant in improving the efficiency and reliability of energy use, but also in promoting the digital transformation of the energy industry.
[0099] Through the machine learning technology of the transformer large model, its powerful data processing capabilities and prediction accuracy have brought new changes to energy management. The transformer large model has demonstrated its unique value in many aspects such as intelligent distribution network prediction and optimization, fault diagnosis and predictive maintenance, and distributed energy management. At the same time, the transformer large model has shown significant effects on improving the accuracy of wind and solar power generation predictions and optimizing energy storage systems.
[0100] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.
[0101] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0102] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0103] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0104] In a typical configuration, a computing device includes one or more processors (CPU), input / output interfaces, network interfaces, and memory.
[0105] The memory may include non-permanent memory in a computer-readable medium, random access memory (RAM) and / or non-volatile memory in the form of read-only memory (ROM) or flash RAM. The memory is an example of a computer-readable medium.
[0106] Computer readable media include permanent and non-permanent, removable and non-removable media that can be implemented by any method or technology to store information. Information can be computer readable instructions, data structures, program modules or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technology, compact disk read-only memory (CD-ROM), digital versatile disk (DVD) or other optical storage, magnetic cassettes, magnetic tape magnetic disk storage or other magnetic storage devices or any other non-transmission media that can be used to store information that can be accessed by a computing device. As defined herein, computer readable media does not include temporary computer readable media (transitory media), such as modulated data signals and carrier waves.
[0107] It should also be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, commodity or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, commodity or device. In the absence of more restrictions, the elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the process, method, commodity or device including the elements.
[0108] The above are only embodiments of the present application and are not intended to limit the present application. For those skilled in the art, the present application may have various changes and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application should be included within the scope of the claims of the present application.
Claims
1. A zero-carbon park intelligent system based on an AI big model, the system is embedded with a transformer big model, characterized in that: include: An energy generation system, the energy generation system comprising a PVT power generation and heating system, a photovoltaic power generation system, a wind power generation system, a hydrogen power generation system, an electrochemical energy storage system and an electrothermal phase change energy storage system, wherein the PVT power generation and heating system uses a transformer large model to predict power generation based on historical meteorological data and power generation data; the wind power generation system uses the Encode module and the Decode module of the transformer large model to predict wind power generation within a period of time based on input historical meteorological data and power generation data; the electrochemical energy storage system and the electrothermal phase change energy storage system use the transformer large model to optimize charging and discharging strategies according to real-time electricity prices and renewable energy power generation; Energy load system, the energy load system includes a charging pile system and a park factory equipment load system, wherein the charging pile system includes an AC charging pile, a DC charging pile and a supercharged liquid cooling charging pile, and the park factory equipment load system includes at least a central air conditioning load, an air compressor load, an air energy load, a Ma load composition and the power consumption of heavy-load machines in the factory; The park energy consumption supervision system includes an energy consumption monitoring and metering system, an energy auxiliary system and an industrial Internet system, wherein the energy consumption monitoring and metering system is used to collect, measure and calculate the park energy consumption in real time to achieve energy consumption statistics, energy consumption management and assessment, energy efficiency evaluation, energy quota and energy-saving services; the energy auxiliary system is used to monitor the temperature of transformer windings, the temperature of switchgear busbars, the partial discharge monitoring of switchgears and the electrical parameter monitoring of distribution cabinets; the industrial Internet system is used to comprehensively monitor platform services and data link security and provide time series data analysis, and to conduct queries and aggregate analysis of any historical time period; The AI large-scale model energy operation and maintenance system includes a park energy dispatching system and an operation and maintenance inspection system, wherein the park energy dispatching system is used to predict the power load curve for a period of time based on the AI large-scale model, and adjust the equipment according to the power consumption in each time period of each day and the pre-set priority and time, so that the equipment layer responds to the energy adjustment instructions issued by the system, realizes the energy release of new energy photovoltaic, wind energy and energy storage media, energy transmission on the incoming line side of the park distribution network, and uses the released energy for other loads.
2. The management system according to claim 1, characterized in that: The photovoltaic power generation system includes: a photovoltaic component, a controller and an inverter, wherein the controller controls the photovoltaic component to convert light energy into direct current, and controls the inverter to convert the direct current into alternating current.
3. The management system according to claim 1, characterized in that: The wind power generation system comprises: A wind turbine component, comprising at least a wind turbine generator set, a tower, a foundation and cables, wherein the wind turbine component is used to capture wind energy and convert the wind energy into alternating electric energy; A grid-connected control component, comprising at least a rectifier module, a grid-connected controller, a load unloader and cables, wherein the grid-connected control component is used to control the normal operation of the wind turbine components; An inverter component, comprising at least a grid-connected inverter and a cable, wherein the inverter component is used to invert the direct current output by the grid-connected control component into alternating current and feed the energy into the grid; The unloading component is used to control the wind turbine to brake and stop, so as to ensure the safety of the wind turbine under abnormal working conditions.
4. The management system according to claim 1, characterized in that: The hydrogen energy power supply system utilizes photovoltaic electricity generated during the daytime peak hours and valley electricity generated at night to electrolyze water to produce hydrogen, and generates electricity through fuel cells during peak hours of power consumption in the power grid.
5. The management system according to claim 1, characterized in that: The electrochemical energy storage system comprises: A battery pack for direct current charging or discharging; Energy storage converter, used to control the charging and discharging process of the battery pack and perform AC-DC conversion; Battery management system, used to monitor the status information of the battery pack; The energy management system is responsible for data collection, network monitoring and energy scheduling.
6. The management system according to claim 1, characterized in that: The energy auxiliary system comprises: Environmental monitoring subsystem, used to monitor temperature and humidity, gas, noise, dust, water leakage and water level; Power equipment monitoring subsystem, used to monitor the operating status of air conditioners, dehumidifiers, fans, lighting, water pumps and fresh air fans; Security monitoring subsystem, used to monitor smoke, infrared, electronic fence, access control and video.
7. The management system according to claim 1, characterized in that: The industrial Internet of Things system adopts the PaaS platform architecture and is configured with: The rule engine is used to implement data repair, cleaning, calculation and analysis, circulation, data alarm and multi-scenario linkage; Data subscription and open API interface to support third-party application development and integration; A variety of device protocol parsing drivers are used to access multiple devices through gateway access; Configure alarm rules on the interface for alarm management.
8. The management system according to claim 1, characterized in that: The park energy dispatching system includes a power supply dispatching system, which adopts an economic dispatching algorithm and a big data dispatching algorithm for power supply dispatching. When the economic dispatching algorithm is adopted, the microgrid management is completed in combination with time-of-use electricity prices, new energy output rules, and preset generation, distribution, and use logic; when the big data dispatching algorithm is adopted, on the basis of economic dispatch, the microgrid dispatching granularity is further refined through data aggregation and big data analysis to realize photovoltaic power generation prediction and load prediction.
9. The management system according to claim 1, characterized in that: Train the transformer model according to the following formula: In the formula, Represents renewable energy power generation data, represents energy consumption data, represents the external energy data of the park, λ represents the price of new energy power generation, k represents the consumption price, δ represents the external energy price, and F * Represents the integration cost.
10. The management system according to claim 9, characterized in that: The power generation is predicted according to the following formula: In the formula, α, β, ε, η, φ, ω represent the power generation duration coefficient of each energy time period, P V , P T P represents the power generation of the PVT power generation and heating system, W Indicates wind power generation power, P E1 Represents the electrochemical energy storage release power, P ES2 represents the power released by the phase change energy storage system, P S Indicates the power input to the power system.
Citation Information
Patent Citations
Optimized scheduling method for wind-solar storage hybrid system
CN108306331A
Energy management and control method and system based on AI intelligent park
CN117314094A
Smart energy management method and system based on AI algorithm group and large model system
CN118195348A
Microgrid management system and method based on smart park
CN118263983A
Cited By
Zero-carbon park intelligent system based on AI large model
CN121766544A