Rain shed upper pull rod full-glass curtain wall joint and mounting method thereof

By designing pre-arched vertical keels and alternately arranged upper and lower arch keels on the large-span canopy, combining stressed cable-stayed rods and silicone sealant, the structural stability and construction of traditional full-glass curtain walls in large-span canopy are solved. The difficulty issue has achieved a more stable and durable awning design.

CN119163184APending Publication Date: 2024-12-20CHINA CONSTR THIRD ENG BUREAU GRP SOUTH CHINA CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411563571.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-05
Publication Date
2024-12-20

AI Technical Summary

Technical Problem

Traditional all-glass curtain walls face structural stability and durability challenges in large-span canopy design, especially when they withstand strong wind pressure and earthquakes, and construction technology is difficult to ensure accuracy and operability.

Method used

A fully glass curtain wall node of the canopy upper pull rod is designed, using pre-arched vertical keels and alternately arranged upper arch and lower arch keels, combining stressed staggered rods and silicone structural sealant to improve structural stability through articulation and adjustment sections. and installation efficiency.

Benefits of technology

It improves the stability and durability of the large-span canopy, uniformizes the keel's stress, reduces the concentrated stress of the glass curtain wall, simplifies the installation of stress trapezoidal rods, and ensures the safety of the structure and the operability of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119163184A_ABST
    Figure CN119163184A_ABST
Patent Text Reader

Abstract

The invention provides a novel canopy upper pull rod full-glass curtain wall joint and a mounting method thereof. The novel canopy upper pull rod full-glass curtain wall joint is used for improving the structural stability and construction efficiency of a large-span full-glass curtain wall. The joint is composed of vertical keels and transverse keels which are subjected to pre-arching treatment, and the vertical keels are formed by alternately arranging upper arch keels and lower arch keels so as to uniformly disperse internal stress. The rain shielding glass is connected with the keel through the silicone structural sealant, and the stability of the whole structure is enhanced through the arrangement of the stress diagonal draw bar. The installation method comprises the steps of welding the canopy framework, installing the diagonal draw bars, lifting the framework, assembling the diagonal draw bars, laying the rain shielding glass and the like, and the construction process is simplified. The innovative design effectively solves the technical problems encountered in the design and construction of the large-span full-glass curtain wall, and improves the aesthetic property and the practicability of a building.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of glass curtain walls, in particular to a canopy upper tie rod full-glass curtain wall node and an installation method thereof. Background Art

[0002] In modern architectural design, all-glass curtain walls are favored for their beauty and transparency. However, when applied to large-span structures, traditional all-glass curtain walls face many technical challenges, especially in canopy design. Large-span canopies need to withstand large wind pressure and deadweight, while also ensuring the stability and durability of the structure. Canopies supported by traditional steel structures are prone to deflection and deformation in large-span applications, affecting structural stability. These issues not only involve material selection and structural design, but also include the application of construction technology and considerations for later maintenance.

[0003] For example, the structural design of a large-span glass curtain wall needs to take into account the brittle characteristics of glass to ensure safety performance under wind loads and earthquakes. The connection method between the glass panel and the glass rib, the design of the connector, and the overall stability of the glass rib are all key issues in the design. In addition, the construction technology of the large-span steel structure canopy is also a challenge, and appropriate construction methods need to be adopted, such as high-altitude bulk method, ground hoisting method, overall lifting method, etc., to ensure the accuracy and operability of the construction. Summary of the invention

[0004] In order to solve these problems, this technical solution proposes a canopy upper pull rod full glass curtain wall node, which improves the stability and durability of the large-span canopy through innovative structural design, and is implemented using the following technical solutions:

[0005] A canopy upper tie rod full-glass curtain wall node, including a large-span curtain wall steel column and a canopy, the canopy including a vertical keel and a transverse keel, one end of the vertical keel is welded to the steel column, and the other end is welded to the transverse keel, the vertical keel is pre-arched, and the arch degree is 1 / 1600 of the length of the vertical keel, that is, it includes an upper arch keel and a lower arch keel, both ends of the canopy are upper arch keels, and the middle is arranged in an alternating manner of upper arch keels and lower arch keels, the canopy also includes a rain shield, the two ends of the rain shield are respectively supported on two adjacent upper arch keels, and the middle is supported on a lower arch keel between the two adjacent upper arch keels, the rain shield is connected to the upper arch keel and the lower arch keel by silicone structural sealant, and a stress diagonal rod is also provided on the transverse keel, one end of the stress diagonal rod is hinged to the transverse keel, and the other end is hinged to the steel column.

[0006] Furthermore, a steel beam is provided at the connection node between the vertical keel and the steel column, and both ends of the steel beam are respectively connected to the connection nodes between adjacent vertical keels and the steel columns. Curtain wall glass is fixedly installed on adjacent steel columns, and the top of the curtain wall glass is connected to the steel beam by silicone structural sealant.

[0007] Furthermore, the top edge of the curtain wall glass is provided with a top arc and a concave arc, that is, it includes top arc glass and concave arc glass, the arc is 1 / 1600 of the length of the top edge of the curtain wall glass, and the top arc glass and concave arc glass are arranged in an alternating manner.

[0008] Furthermore, the stress inclined tie rod includes an articulated section and an adjusting section. There are two articulated sections, one end of which is provided with an articulated ear, and the other end is provided with a four-hole flange. Both ends of the adjusting section are provided with four-hole flanges. The articulated ears of the two articulated sections are respectively articulated to the steel columns and the transverse keels, and the two ends of the adjusting section are respectively connected to the four-hole flanges of the two articulated sections.

[0009] Furthermore, the adjustment section includes two screw rods and an adjustment ring, the adjustment rod includes two connecting rods parallel to each other and nuts respectively arranged at both ends of the two connecting rods, the two nuts are hinged to the two connecting rods, one end of the two screw rods is connected to a four-hole flange, and the other end is threadedly connected to the two nuts respectively, the threads of the two nuts are mutually reverse threads, and anti-slip rings are arranged on the parts of the two screw rods extending into the interior of the adjustment ring, and the anti-slip rings are threadedly connected to the screw rods.

[0010] The invention also includes a method for installing a canopy upper pull rod full-glass curtain wall node, comprising the following steps:

[0011] Step 1: Weld the vertical and horizontal keels of the canopy on the ground to form a complete canopy frame;

[0012] Step 2: hinge and install the hinged section of the stress diagonal rod at the position of the transverse keel corresponding to the nearest steel column;

[0013] Step 3: After the overall installation of the large-span curtain wall steel columns and steel beams is completed, the hinged section of the stress diagonal rod is hingedly installed at the position of the steel column corresponding to the transverse keel;

[0014] Step 4: Use lifting equipment to lift the canopy frame to the designed elevation, and weld the vertical keel to the steel column;

[0015] Step 5: Assemble the adjustment section of the stress inclined tie rod, screw the two screws into the two nuts respectively, and screw the anti-slip rings into the parts of the two screws extending into the interior of the adjustment ring respectively;

[0016] Step 6: Assemble the stress inclined tie rod, rotate the two nuts and the two hinged sections respectively, align the four-hole flanges on the two screws with the four-hole flanges of the two hinged sections respectively, and connect them respectively with bolts;

[0017] Step 7: After completing the assembly of the stress inclined tie rod, start to rotate the adjustment rod to tighten the entire stress inclined tie rod to a straight line, and continue to rotate the adjustment rod to meet the design tension requirements;

[0018] Step 8: Lay the rainproof glass on the canopy frame, and apply silicone structural sealant between the canopy frame and the rainproof glass to connect them;

[0019] Step 9: Install the curtain wall glass alternately, and apply silicone structural sealant between the steel beam and the curtain wall glass to connect them;

[0020] Step 10: After the silicone structural sealant reaches the designed strength, remove the lifting equipment and complete the installation of the canopy upper tie rod full-glass curtain wall node.

[0021] The canopy upper tie rod full glass curtain wall node and the installation method thereof of the present invention have the following significant beneficial effects:

[0022] (1) The awning keel is directly welded to the steel column of the large-span curtain wall. Since the awning glass is large and spans three cantilevered vertical keels, the deflection deformation is large, and the awning steel frame needs to be pre-arched. The alternating upper arch keel and lower arch keel of the present invention can further offset the internal stress and make the force on the entire awning keel more uniform, thereby improving the stability of the awning keel;

[0023] (2) The contact position between the curtain wall glass and the canopy steel beam was pre-processed. The reaction force of the arch is a downward pulling force, so the steel beam needs to be arched. In order to reduce the impact on the glass curtain wall body, the bottom of the glass curtain wall is set in a wave arc shape to match its force. By setting a silicone structural sealant buffer, the steel beam can transmit force more smoothly, avoiding concentrated force on the glass curtain wall.

[0024] (3) By setting up a stress diagonal brace, the splicing efficiency of the diagonal brace can be improved. Since the diagonal brace is a rigid structure, bending will destroy its performance. The installation of the diagonal brace is often affected by the length of the reserved space. If the length of the reserved space is too long, the connection on both sides cannot be guaranteed. If the length of the reserved space is too short, the diagonal brace cannot be placed in the installation position. Therefore, in the face of the installation difficulties caused by the length, an adjustment section is set, and the nut of the adjustment section is hinged to the connecting rod, which further facilitates the assembly and connection installation of the stress diagonal brace. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] In order to more clearly illustrate the technical solutions in the implementation modes of the present application, the drawings required for use in the description of the implementation modes will be briefly introduced below. Obviously, the drawings described below are only some implementation modes of the present application. For those skilled in the art, other drawings can be obtained based on these drawings without creative work.

[0026] Figure 1 It is a structural schematic diagram of the present invention.

[0027] Figure 2 It is a schematic diagram of the keel structure of the canopy of the present invention.

[0028] Figure 3 It is a schematic diagram of the local structure of the present invention.

[0029] Figure 4 It is a schematic diagram of the curtain wall glass of the present invention.

[0030] Figure 5 It is an exploded view of the stress inclined tie rod of the present invention.

[0031] Figure 6 It is a schematic diagram of the local structure of the stress inclined tie rod of the present invention.

[0032] Description of reference numerals:

[0033] 100-steel column, 101-steel beam, 200-canopy, 201-vertical keel, 202-transverse keel, 203-upper arch keel, 204-lower arch keel, 205-rain shield glass, 300-stressed diagonal rod, 301-hinge section, 3011-hinge ear, 3012-four-hole flange, 302-adjustment section, 3021-screw, 3022-adjustment ring, 3023-connecting rod, 3024-nut, 3025-anti-slip ring, 400-curtain wall glass, 401-silicone structural sealant, 402-top arc, 403-concave arc, 404-top arc glass, 405-concave arc glass. DETAILED DESCRIPTION

[0034] The following description of the embodiments will help the public better understand the present invention, but the specific embodiments given by the applicant cannot and should not be regarded as limitations on the technical solutions of the present invention. Any changes to the definitions of components or technical features, or formal rather than substantive changes to the overall structure should be regarded as the scope of protection defined by the technical solutions of the present invention.

[0035] In this application, unless otherwise clearly specified or limited, the terms "installation", "connection", "fixation" and the like should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be internal communication between two elements, or it can be only surface contact, or surface contact connection through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0036] A canopy upper pull rod full glass curtain wall node is realized by the following technical solution:

[0037] The invention comprises a long-span curtain wall steel column 100 and a canopy 200, wherein the canopy 200 comprises a vertical keel 201 and a horizontal keel 202, wherein one end of the vertical keel 201 is welded to the steel column 100, and the other end is welded to the horizontal keel 202, wherein the vertical keel 201 is pre-arched, and the arching degree is 1 / 1600 of the length of the vertical keel 201, namely, an upper arch keel 203 and a lower arch keel 204 are included, and both ends of the canopy 200 are upper arch keels 203, and the middle part is arranged in an alternating manner of the upper arch keel 203 and the lower arch keel 204, and the canopy keel is directly welded to the long-span curtain wall steel column 100, and since the canopy 200 glass is large glass, spanning three cantilevered vertical keels 201, the deflection deformation is large, and the canopy The steel frame needs to be pre-arched, and the alternating arrangement of the upper arch keel 203 and the lower arch keel 204 of the present invention can further offset the internal stress and make the force on the keel of the entire canopy 200 more uniform, thereby improving the stability of the keel of the canopy 200; the canopy 200 also includes a rain shield 205, the two ends of the rain shield 205 are respectively supported on two adjacent upper arch keels 203, and the middle is supported on a lower arch keel 204 between the two adjacent upper arch keels 203, the rain shield 205 is connected to the upper arch keel 203 and the lower arch keel 204 by silicone structural sealant 401, and a stress diagonal rod 300 is also arranged on the transverse keel 202, one end of the stress diagonal rod 300 is hinged to the transverse keel 202, and the other end is hinged to the steel column 100.

[0038] A steel beam 101 is also provided at the connection node between the vertical keel 201 and the steel column 100. Both ends of the steel beam 101 are respectively connected to the connection nodes between the adjacent vertical keel 201 and the steel column 100. Curtain wall glass 400 is fixedly installed on the adjacent steel column 100. The top of the curtain wall glass 400 is connected to the steel beam 101 through a silicone structural sealant 401.

[0039] The top edge of the curtain wall glass 400 is provided with a top arc 402 and a concave arc 403, that is, it includes a top arc glass 404 and a concave arc glass 405, the arc is 1 / 1600 of the length of the top edge of the curtain wall glass 400, and the top arc glass 404 and the concave arc glass 405 are arranged in an alternating manner. The contact position between the curtain wall glass 400 and the canopy steel beam 101 is pre-processed, and the reaction force of the arch is a downward pulling force, so the steel beam 101 needs to be arched. In order to reduce the impact on the glass curtain wall body, the bottom of the glass curtain wall is set to a wave arc to match its force. By setting the silicone structural sealant 401 for buffering, the steel beam 101 can transmit force more smoothly to avoid concentrated force on the glass curtain wall.

[0040] The stress inclined tie rod 300 includes an articulated section 301 and an adjusting section 302. The articulated section 301 is provided with two, one end of the articulated section 301 is provided with an articulated ear 3011, and the other end is provided with a four-hole flange 3012, and both ends of the adjusting section 302 are provided with four-hole flanges 3012. The articulated ears 3011 of the two articulated sections 301 are respectively articulated to the steel column 100 and the transverse keel 202, and the two ends of the adjusting section 302 are respectively connected to the four-hole flanges 3012 of the two articulated sections 301.

[0041] The adjusting section 302 includes two screw rods 3021 and an adjusting ring 3022. The adjusting rod includes two connecting rods 3023 parallel to each other and nuts 3024 respectively arranged at both ends of the two connecting rods 3023. The two nuts 3024 are hinged to the two connecting rods 3023. One end of the two screw rods 3021 is connected to a four-hole flange 3012, and the other end is threadedly connected to the two nuts 3024 respectively. The threads of the two nuts 3024 are mutually reverse threads. Anti-slip rings 3025 are arranged on the parts of the two screw rods 3021 extending into the interior of the adjusting ring 3022. The anti-slip rings 3025 are threadedly connected to the screw rods 3021.

[0042] By setting the stress inclined brace 300, the splicing efficiency of the inclined brace can be improved. Since the inclined brace is a rigid structure, bending will destroy its performance. The installation of the inclined brace is often affected by the length of the reserved space. If the length of the reserved space is too long, the connection on both sides cannot be guaranteed. If the length of the reserved space is too short, the inclined brace cannot be put into the installation position. Therefore, in the face of the installation difficulties caused by the length, an adjustment section 302 is set, and the nut 3024 of the adjustment section 302 is hinged with the connecting rod 3023, which further facilitates the assembly and connection installation of the stress inclined brace 300

[0043] Also included is a method for installing a canopy 200 upper pull rod full glass curtain wall node, comprising the following steps:

[0044] Step 1: welding the vertical keel 201 and the horizontal keel 202 of the canopy 200 on the ground to form a complete canopy 200 skeleton;

[0045] Step 2: hinge and install the hinge section 301 of the stress diagonal tie rod 300 at the position of the transverse keel 202 corresponding to the nearest steel column 100;

[0046] Step 3: After the large-span curtain wall steel column 100 and the steel beam 101 are installed as a whole, the hinged section 301 of the stress inclined rod 300 is hingedly installed at the position of the steel column 100 corresponding to the transverse keel 202;

[0047] Step 4: Use lifting equipment to lift the canopy 200 frame as a whole to the designed elevation, and weld the vertical keel 201 to the steel column 100;

[0048] Step 5: Assemble the adjustment section 302 of the stress inclined tie rod 300, screw the two screws 3021 into the two nuts 3024 respectively, and screw the anti-slip rings 3025 into the parts of the two screws 3021 extending into the interior of the adjustment ring 3022 respectively;

[0049] Step 6: Assemble the stress inclined tie rod 300, rotate the two nuts 3024 and the two hinged sections 301 respectively, align the four-hole flanges 3012 on the two screws 3021 with the four-hole flanges 3012 of the two hinged sections 301 respectively, and connect them respectively by bolts;

[0050] Step 7: After the stress inclined brace rod 300 is assembled, the adjusting rod is rotated to tighten the entire stress inclined brace rod 300 to a straight line, and the adjusting rod is rotated further to reach the design tension requirement;

[0051] Step 8: Lay the rain shield glass 205 on the frame of the canopy 200, and apply silicone structural sealant 401 between the frame of the canopy 200 and the rain shield glass 205 to connect them;

[0052] Step nine: alternately install the curtain wall glass 400, and apply silicone structural sealant 401 between the steel beam 101 and the curtain wall glass 400 to connect them;

[0053] Step 10: After the silicone structural sealant 401 reaches the design strength, remove the lifting equipment and complete the installation of the canopy 200 upper pull rod full-glass curtain wall node.

[0054] Those skilled in the art should understand that those skilled in the art can implement variations by combining the prior art and the above embodiments, which will not be described in detail here. Such variations do not affect the essential content of the present invention, and will not be described in detail here.

[0055] The above describes the preferred embodiments of the present invention. It should be understood that the present invention is not limited to the above-mentioned specific embodiments, and the devices and structures that are not described in detail should be understood to be implemented in a common manner in the art; any technician familiar with the art can use the above-disclosed methods and technical contents to make many possible changes and modifications to the technical solutions of the present invention without departing from the scope of the technical solutions of the present invention, or modify them into equivalent embodiments of equivalent changes, which does not affect the essential content of the present invention. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solutions of the present invention are still within the scope of protection of the technical solutions of the present invention.

Claims

1. A canopy upper tie rod full glass curtain wall node, characterized in that: The invention comprises a large-span curtain wall steel column (100) and a canopy (200), wherein the canopy (200) comprises a vertical keel (201) and a transverse keel (202), wherein one end of the vertical keel (201) is welded to the steel column (100), and the other end is welded to the transverse keel (202), and the vertical keel (201) is pre-arched, and the arching degree is 1 / 1600 of the length of the vertical keel (201), that is, it comprises an upper arch keel (203) and a lower arch keel (204), and both ends of the canopy (200) are upper arch keels (203), and the middle part uses upper arch keels (203) and lower arch keels (204) alternately. The canopy (200) is arranged in an arranged manner, and further comprises a rain shield glass (205), wherein two ends of the rain shield glass (205) are respectively supported on two adjacent upper arch keels (203), and the middle is supported on a lower arch keel (204) between the two adjacent upper arch keels (203), and the rain shield glass (205) is connected to the upper arch keels (203) and the lower arch keels (204) by silicone structural sealant (401), and a stress inclined brace rod (300) is further arranged on the transverse keel (202), and one end of the stress inclined brace rod (300) is hinged to the transverse keel (202), and the other end is hinged to the steel column (100).

2. The canopy top tie rod full glass curtain wall node according to claim 1, characterized in that: A steel beam (101) is also provided at the connection node between the vertical keel (201) and the steel column (100), and two ends of the steel beam (101) are respectively connected to the connection nodes between the adjacent vertical keel (201) and the steel column (100), and the adjacent steel column (100) is fixedly installed with a curtain wall glass (400), and the top of the curtain wall glass (400) is connected to the steel beam (101) by a silicone structural sealant (401).

3. The canopy top tie rod full glass curtain wall node according to claim 2, characterized in that: The top edge of the curtain wall glass (400) is provided with a top arc (402) and a concave arc (403), that is, it includes a top arc glass (404) and a concave arc glass (405), the arc is 1 / 1600 of the length of the top edge of the curtain wall glass (400), and the top arc glass (404) and the concave arc glass (405) are arranged in an alternating manner.

4. The canopy top tie rod full glass curtain wall node according to claim 1, characterized in that: The stress inclined brace (300) comprises an articulated section (301) and an adjusting section (302), wherein two articulated sections (301) are provided, one end of the articulated section (301) is provided with an articulated ear (3011), and the other end is provided with a four-hole flange (3012), and both ends of the adjusting section (302) are provided with four-hole flanges (3012), the articulated ears (3011) of the two articulated sections (301) are respectively articulated to the steel column (100) and the transverse keel (202), and the two ends of the adjusting section (302) are respectively connected to the four-hole flanges (3012) of the two articulated sections (301).

5. The canopy top tie rod full glass curtain wall node according to claim 4, characterized in that: The adjusting section (302) comprises two screw rods (3021) and an adjusting ring (3022); the adjusting rod comprises two connecting rods (3023) parallel to each other and nuts (3024) respectively arranged at both ends of the two connecting rods (3023); the two nuts (3024) are hinged to the two connecting rods (3023); one end of the two screw rods (3021) is connected to a four-hole flange (3012); the other end is respectively threadedly connected to the two nuts (3024); the threads of the two nuts (3024) are mutually reverse threads; the portions of the two screw rods (3021) extending into the interior of the adjusting ring (3022) are respectively provided with anti-slip rings (3025); the anti-slip rings (3025) are threadedly connected to the screw rods (3021).

6. The method for installing a canopy top tie rod full glass curtain wall node according to claim 5, characterized in that: The following steps are involved: Step 1: welding the vertical keel (201) and the horizontal keel (202) of the canopy (200) on the ground to form a complete canopy (200) skeleton; Step 2: hinge and install the hinge section (301) of the stress inclined tie rod (300) at the position of the transverse keel (202) corresponding to the nearest steel column (100); Step 3: After the large-span curtain wall steel column (100) and the steel beam (101) are installed as a whole, the hinged section (301) of the stress inclined rod (300) is hingedly installed at the position of the steel column (100) corresponding to the transverse keel (202); Step 4: Use a lifting device to lift the canopy (200) frame as a whole to the designed elevation, and weld the vertical keel (201) to the steel column (100); Step 5: Assemble the adjustment section (302) of the stress inclined tie rod (300), screw the two screws (3021) into the two nuts (3024) respectively, and screw the anti-slip rings (3025) into the parts of the two screws (3021) extending into the interior of the adjustment ring (3022); Step 6: Assemble the stress inclined tie rod (300), rotate the two nuts (3024) and the two hinged sections (301) respectively, align the four-hole flanges (3012) on the two screw rods (3021) with the four-hole flanges (3012) of the two hinged sections (301), and connect them respectively by bolts; Step 7: After the stress inclined brace (300) is assembled, the adjusting rod is rotated to tighten the entire stress inclined brace (300) to a straight line, and the adjusting rod is rotated further to reach the design tension requirement; Step 8: Lay the rainproof glass (205) on the frame of the canopy (200), and apply silicone structural sealant (401) between the frame of the canopy (200) and the rainproof glass (205) to connect them; Step nine: alternately install the curtain wall glass (400), and apply silicone structural sealant (401) between the steel beam (101) and the curtain wall glass (400) to connect them; Step 10: After the silicone structural sealant (401) reaches the designed strength, remove the lifting equipment and complete the installation of the tie rod full glass curtain wall node of the canopy (200).