Underwater building and construction method thereof

By adopting the design of movable connection components and clamping components and pile foundations in underwater buildings, the problem of anchoring method being unfixed on soft sludge or sandy seabed and being affected by sea current is solved, and the stability of the building is achieved Fix and reduce dependence on subsea conditions.

CN119177684APending Publication Date: 2024-12-24SOUTHERN BRANCH OF CHINA COMM CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411552805.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-01
Publication Date
2024-12-24

AI Technical Summary

Technical Problem

The anchoring method is difficult to fix underwater buildings on soft sludge or sandy seabed, and the buildings are unstable under strong currents or storms and are greatly affected by ocean currents.

Method used

Adopt a design that includes the main body of the building, connector and pile foundation. The connector includes a movable connection component and a clamping component. The movable connection component is movable connection with the pile foundation. The clamping component is jammed with the limiting component on the pile foundation. Roller and drive parts enable stable fixation of the building.

Benefits of technology

It improves the stability of underwater buildings and reduces dependence on subsea conditions. The pile foundation has little requirements for water depth and geological strength, and can stabilize and fix buildings under different subsea environments.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119177684A_ABST
    Figure CN119177684A_ABST
Patent Text Reader

Abstract

The invention provides an underwater building and a construction method thereof. The underwater building comprises a building main body; the connector is connected with the building main body, the connector comprises a connector main body, a movable connecting assembly and a clamping assembly, and the movable connecting assembly and the clamping assembly are both connected with the connector main body; the bottom of the pile foundation is fixed to the seabed, the movable connecting assembly is movably connected with the pile foundation and can move up and down along the pile foundation, a limiting assembly is arranged on the pile foundation, and the clamping assembly is connected with the limiting assembly in a clamped mode. The building body is fixed to the pile foundation and is not affected by ocean currents, and the stability of the building body is improved. The pile foundation has low requirements on water depth, geological strength and the like, and the dependence of a building main body on seabed conditions is reduced. The building body is connected with the pile foundation through the movable connecting assembly and the clamping assembly, fixing of the building body is achieved, and the building body is more stable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of marine engineering technology, and in particular to an underwater building and a construction method thereof. Background Art

[0002] With the development of marine science research, seabed resource development and marine ecological protection, underwater buildings have developed rapidly. At present, underwater buildings are generally fixed by anchoring. Anchoring refers to fixing buildings to the seabed by using anchors and anchor chains. The fixing effect of anchoring depends on the seabed conditions. In soft mud or sandy seabeds, anchors may be difficult to fix, affecting the stability of underwater buildings. In addition, anchoring is greatly affected by ocean currents. In strong ocean currents or storms, the anchor chain may loosen or move, causing the building to be unstable. Summary of the invention

[0003] The embodiment of the present application provides an underwater building and a construction method thereof to solve the problems existing in the related technologies. The technical solution is as follows:

[0004] In a first aspect, an embodiment of the present application provides an underwater building, comprising:

[0005] The main body of the building;

[0006] A connector, the connector is connected to the building body, the connector comprises a connector body, a movable connection component and a snap-on component, and the movable connection component and the snap-on component are both connected to the connector body;

[0007] The pile foundation has its bottom fixed on the seabed, a movable connection component is movably connected to the pile foundation, the movable connection component can move up and down along the pile foundation, a limit position component is arranged on the pile foundation, and the clamping component is clamped with the limit position component.

[0008] In one embodiment, the movable connection component is sleeved on the pile foundation, a roller is provided on the inner wall of the movable connection component, the movable connection component is movably connected to the pile foundation through the roller, and the roller rolls upward or downward along the pile foundation.

[0009] In one embodiment, the clamping assembly includes a clamping claw, which is rotatably connected to the connector body, and the limiting assembly includes a limiting protrusion, and the limiting clamping claw is clamped with the limiting protrusion.

[0010] In one embodiment, the clamping assembly also includes a driving member and a driving ring plate, the driving member is connected to the driving ring plate, the driving member drives the driving ring plate to move up and down, and the driving ring plate is hinged to the claw; in the process of the driving member driving the driving ring plate to move downward, the driving ring plate drives the claw to rotate around the connection between it and the connector body.

[0011] In one embodiment, the driving ring plate is provided with a first fixing hole, the clamping claw is provided with a second fixing hole, and the driving ring plate is detachably connected to the clamping claw through the first fixing hole and the second fixing hole.

[0012] In one embodiment, a first sealing member is provided on the clamping claw, and the clamping claw is sealed and connected to the limiting protrusion via the first sealing member.

[0013] In one embodiment, a second sealing member is provided on the connector body, and the connector body is sealed and connected to the limiting protrusion via the second sealing member.

[0014] In one embodiment, a ballast tank is provided at the bottom of the building body, and a water inlet is opened on the building body, and the water inlet is connected to the interior of the ballast tank.

[0015] In one embodiment, the underwater building also includes a helipad and a pier, which are respectively located on the sides of the building body, and the helipad and the pier are both located on the sea surface; the building body includes a water traffic layer and an underwater main layer, the water traffic layer is connected to the underwater main layer, the water traffic layer is located on the sea surface, the underwater main layer is located below the sea surface, and the water traffic layer is connected to the helipad and the pier.

[0016] In a second aspect, an embodiment of the present application provides a construction method for an underwater building as described in any one of the above, comprising the following steps:

[0017] Prefabricate the building body and connectors, and connect the connectors to the building body;

[0018] While prefabricating the main building body and connectors, piles are driven on the seabed to place the prefabricated pile foundation on the seabed;

[0019] Transport the building body and connector to the construction site, and connect the movable components of the connector to the pile foundation;

[0020] The main body of the building is slowly lowered, and the movable assembly is moved downward along the pile foundation. After the main body of the building is lowered to a predetermined position, the clamping assembly of the connector body is clamped with the limiting assembly on the pile foundation.

[0021] The advantages or beneficial effects of the above technical solution include at least:

[0022] The underwater building of the embodiment of the present application includes a building body, a connector and a pile foundation. The connector body is connected to the building body. The connector body includes a movable connection component and a clamping component. The movable connection component is movably connected to the pile foundation, and the clamping component is clamped with the limit component on the pile foundation. The building body of the embodiment of the present application is fixed on the pile foundation and will not be affected by the ocean current, thereby improving the stability of the building body. The pile foundation has relatively low requirements on water depth and geological strength, thereby reducing the dependence of the building body on seabed conditions. The building body is connected to the pile foundation through the movable connection component and the clamping component to achieve the fixation of the building body, making the building body more stable.

[0023] The above summary is for illustrative purposes only and is not intended to be limiting in any way. In addition to the illustrative aspects, embodiments and features described above, further aspects, embodiments and features of the present application will be readily apparent by reference to the accompanying drawings and the following detailed description. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] In the accompanying drawings, unless otherwise specified, the same reference numerals throughout the multiple drawings represent the same or similar parts or elements. These drawings are not necessarily drawn to scale. It should be understood that these drawings only depict some embodiments disclosed in the present application and should not be regarded as limiting the scope of the present application.

[0025] Figure 1 This is a schematic diagram of the structure of an underwater building;

[0026] Figure 2 This is a schematic diagram of the structure of an underwater building during its sinking process;

[0027] Figure 3 This is a schematic diagram of the structure after the underwater building is sunk;

[0028] Figure 4 This is a top view of the underwater building;

[0029] Figure 5 It is a top view of the connection between the connector and the pile foundation;

[0030] Figure 6 It is a schematic diagram of the structure of the main body of the building;

[0031] Figure 7 It is a schematic diagram of the structure of the water transportation layer;

[0032] Figure 8 It is a cross-sectional view of the connection between the connector and the pile foundation;

[0033] Description of reference numerals:

[0034] 1. Building body; 2. Connector; 3. Pile foundation; 21. Connector body; 22. Active connection assembly; 23. Clamp assembly; 4. Limit assembly; 221. Roller; 231. Clamping claw; 232. Driving member; 233. Driving ring plate; 234. Bolt; 235. First sealing member; 236. Second sealing member; 11. Ballast tank; 12. Water inlet hole; 13. Through hole; 41. Limiting convex part; 14. Water traffic layer; 15. Underwater main layer; 141. Material warehouse; 151. Equipment room; 5. Helipad; 6. Wharf. DETAILED DESCRIPTION

[0035] In the following, only some exemplary embodiments are briefly described. As those skilled in the art will appreciate, the described embodiments may be modified in various ways without departing from the spirit or scope of the present application. Therefore, the drawings and descriptions are considered to be exemplary and non-restrictive in nature.

[0036] Embodiment 1:

[0037] like Figures 1 to 8 As shown, an embodiment of the present application provides an underwater building, including a building body 1, a connector 2 and a pile foundation 3. The connector 2 is connected to the building body 1, and the connector 2 includes a connector body 21, a movable connection component 22 and a clamping component 23, and the movable connection component 22 and the clamping component 23 are both connected to the connector body 21. The bottom of the pile foundation 3 is fixed to the seabed, and the movable connection component 22 is movably connected to the pile foundation 3. The movable connection component 22 can move up and down along the pile foundation 3. A limit component 4 is provided on the pile foundation 3, and the clamping component 23 is clamped with the limit component 4.

[0038] The building body 1 of the embodiment of the present application is fixed on the pile foundation 3 and will not be affected by the ocean current, thereby improving the stability of the building body 1. The pile foundation 3 has low requirements on water depth and geological strength, thereby reducing the dependence of the building body 1 on seabed conditions. The building body 1 is connected to the pile foundation 3 through the movable connection component 22 and the clamping component 23 to achieve the fixation of the building body 1, making the building body 1 more stable.

[0039] In one embodiment, in order to realize the movable connection between the movable connection component 22 and the pile foundation 3, the movable connection component 22 of this embodiment is sleeved on the pile foundation 3. A roller 221 is provided on the inner wall of the movable connection component 22, and the movable connection component 22 is movably connected to the pile foundation 3 through the roller 221, and the roller 221 rolls up or down along the pile foundation 3.

[0040] Preferably, a plurality of rollers 221 may be provided on the inner wall of the movable connection assembly 22, and the plurality of rollers 221 are evenly distributed on the movable connection assembly 22, and the movable connection assembly 22 contacts the outer peripheral surface of the pile foundation 3 through the rollers 221. During the process of the building body 1 rising or falling, the rollers 221 roll on the outer peripheral surface of the pile foundation 3. During the process of the building body 1 rising or falling, the movable connection assembly 22 limits the position of the building body 1, so as to prevent the position of the building body 1 from being offset during the movement.

[0041] In one embodiment, after the building body 1 is moved to a predetermined position, in order to fix the building body 1, the clamping assembly 23 includes a clamping claw 231, which is rotatably connected to the connector body 21, and the limiting assembly 4 includes a limiting protrusion 41, and the limiting clamping claw 231 is clamped with the limiting protrusion 41. Specifically, one end of the clamping claw 231 can be rotatably connected to the connector body 21 through a bearing, and the clamping claw 231 can rotate around the bearing.

[0042] In one embodiment, in order to drive the claw 231 to move so that the claw 231 is engaged with the limiting protrusion 41, the engaging assembly 23 further includes a driving member 232 and a driving ring plate 233. The driving member 232 is connected to the driving ring plate 233, and the driving member 232 drives the driving ring plate 233 to move up and down, and the driving ring plate 233 is hinged to the claw 231. In one embodiment, the driving ring plate 233 and the claw 231 can be hinged through a fisheye joint. In the process of the driving member 232 driving the driving ring plate 233 to move downward, the driving ring plate 233 drives the claw 231 to rotate around the connection between it and the connector body 21. Preferably, the driving member 232 can be a hydraulic cylinder, and the driving shaft of the hydraulic cylinder is connected to the driving ring plate 233.

[0043] After the claw 231 is engaged with the limiting protrusion 41, in order to achieve the locking of the claw 231, a first fixing hole is provided on the driving ring plate 233, and the claw 231 is provided with a first fixing hole, and the driving ring plate 233 is detachably connected to the claw 231 through the first fixing hole and the second fixing hole. After the claw 231 is engaged with the limiting protrusion 41, a bolt 234 is inserted into the first fixing hole and the second fixing hole, and the claw 231 and the driving ring plate 233 are locked by the bolt 234.

[0044] In one embodiment, in order to achieve a sealed connection between the claw 231 and the limiting protrusion 41, a first sealing member 235 is provided on the claw 231, and the claw 231 is sealedly connected to the limiting protrusion 41 through the first sealing member 235. Preferably, the first sealing member 235 is a metal sealing ring, which contacts the limiting protrusion 41 through the metal sealing ring, thereby achieving sealing between the claw 231 and the limiting protrusion 41.

[0045] In order to achieve a sealed connection between the connector body 21 and the limiting protrusion 41, a second sealing member 236 is provided on the connector body 21, and the connector body 21 is sealed and connected to the limiting protrusion 41 through the second sealing member 236. Preferably, the second sealing member 236 is a rubber sealing ring. After the claw 231 is engaged with the limiting protrusion 41, the second sealing member 236 is squeezed, and the connector body 21 contacts the limiting protrusion 41 through the second sealing member 236 to achieve sealing.

[0046] In one embodiment, after the movable connection assembly 22 is sleeved on the pile foundation 3, the lowering of the building body 1 is achieved by ballasting. Therefore, a ballast tank 11 is provided at the bottom of the building body 1, and a water inlet 12 is opened on the building body 1, and the water inlet 12 is connected to the inside of the ballast tank 11.

[0047] Specifically, a plurality of ballast tanks 11 may be provided at the bottom of the building body 1, and the plurality of ballast tanks 11 are connected to each other through through holes 13, and the water inlet hole 12 provided on the building body 1 is connected to one of the ballast tanks 11. Seawater enters or is discharged from the ballast tank 11 through the water inlet hole 12. After the movable connection assembly 22 is sleeved on the pile foundation 3, the water inlet hole 12 and the through hole 13 may be opened to allow seawater to enter the ballast tank 11 through the water inlet hole 12. With the entry of seawater, the building body 1 slowly descends until it descends to the top of the limiting protrusion 41.

[0048] The building body 1 can be a double-layer structure, wherein the upper layer is the water traffic layer 14, and the lower layer is the underwater main layer 15, the water traffic layer 14 is connected to the underwater main layer 15, the water traffic layer 14 is located on the sea surface, and the underwater main layer 15 is located below the sea surface. The water traffic layer 14 and the underwater main layer 15 can be connected through elevators and stairs. The underwater main layer 15 can be used to build a submarine residence, including a bedroom, a dining room, a living room, and a bathroom. A material warehouse 141 and an equipment room 151 can be built on the water traffic layer 14.

[0049] In one embodiment, the underwater building further includes a helipad 5 and a pier 6, which are respectively located on the sides of the building body 1, and the helipad 5 and the pier 6 are both located on the sea surface. The water traffic layer 14 is connected to the helipad 5 and the pier 6, and the underwater building can be entered by helicopter or boat.

[0050] The construction method of the underwater building of this embodiment is:

[0051] First, the building body 1, connector 2, pile foundation 3, helipad 5 and pier 6 are prefabricated, and the connector 2 is connected to the outside of the building body 1. The connector body 21 can be a steel connector 2. Then, piles are driven on the seabed to erect the pile foundation 3 on the seabed. There can be multiple pile foundations 3, and the multiple pile foundations 3 are respectively erected at predetermined positions on the seabed, and the building body 1 is located between the multiple pile foundations 3. There can also be multiple connectors 2, and the multiple connectors 2 are respectively connected to the building body 1. Then, the movable connection component 22 of the connector 2 is sleeved on the pile foundation 3, the water inlet hole 12 is opened, and the building body 1 is lowered by ballasting. When the building body 1 is lowered, the roller 221 on the movable connection component 22 rolls along the pile foundation 3. When the connector 2 descends to the limit convex portion 41, it stops descending.

[0052] In the initial state, the claw 231 is in a horizontal state and is located below the driving ring plate 233. Then the driving member 232 is started, and the driving member 232 drives the driving ring plate 233 to move downward. The driving ring plate 233 drives the other end of the claw 231 to move downward, so that the claw 231 rotates around the bearing until the claw 231 is clamped on the limiting protrusion 41. The fixing of the building body 1 is achieved by the clamping of the claw 231 and the limiting protrusion 41 to prevent the displacement of the building body 1. After the claw 231 is clamped with the limiting protrusion 41, the driving ring plate 233 and the claw 231 are fixed by bolts 234, so that the driving ring plate 233 and the claw 231 are fixed together to achieve secondary locking. At this time, the building body 1 is fixed on the pile foundation 3 through the movable connection component 22, the claw 231 and the bolt 234.

[0053] Then, the pile cap is cast on the water traffic layer 14 and the pile foundation 3, and the prefabricated longitudinal beams, cross beams and panels are installed to complete the construction of the main building 1 and the traffic passages of the helipad 5 and the pier 6. Finally, the prefabricated helipad 5 and the pier 6 are transported to the site, the helipad 5 and the pier 6 are connected to the traffic passage, and concrete is poured at the connection to form a complete structure.

[0054] When the connector 2 needs to be repaired, the bolt 234 on the driving ring plate 233 is first removed, and then the driving member 232 is started, and the driving member 232 drives the hydraulic cylinder to move upward, and the claw 231 can be restored to a free state along the bearing. At this time, the connector 2 is restored to a temporary fixed state, which is convenient for underwater maintenance.

[0055] In one embodiment, a plurality of snap-fit ​​components 23 may be provided on each connector 2 , and snap-fitting is achieved through the plurality of snap-fit ​​components 23 and the limiting protrusion 41 .

[0056] The underwater buildings of the present application can be used in the fields of scientific research, tourism and energy development. In view of the defects of the anchoring method in that the geological conditions of the seabed are high and the building stability is poor, the present application fixes the building body 1 on the pile foundation 3, which will not be affected by the ocean current. At the same time, the pile foundation 3 has low requirements for water depth and geological strength. The construction conditions only need to meet the flat bottom, and can be built from shallow sea to island lagoon. In view of the defects of the gravity foundation method in that the ecological environment is affected, the underwater buildings based on the pile foundation 3 can be installed at any depth of water without sinking to the seabed, and have less impact on the seabed ecological environment.

[0057] Embodiment 2:

[0058] The present embodiment is described below with reference to the first embodiment:

[0059] The present application embodiment provides a construction method for an underwater building as described in the above embodiment 1, comprising the following steps:

[0060] S1: Prefabricate a building body 1 and a connector 2, and connect the connector 2 to the building body 1.

[0061] S2: While the building body 1 and the connector 2 are prefabricated, piles are driven on the seabed to erect the pile foundation 3 on the seabed.

[0062] Among them, the apron 5 and the dock 6 also need to be prefabricated, and prefabrication and piling can be carried out at the same time, saving time and improving installation efficiency.

[0063] S3: transport the building body 1 and the connector 2 to the construction site, and flexibly connect the movable components of the connector 2 to the pile foundation 3.

[0064] After prefabrication is completed, the prefabricated structure is transported to a predetermined sea area by a semi-submersible transport vessel for construction. Then the building body 1 is floated on the sea surface, and the movable connection assembly 22 is sleeved on the pile foundation 3 to temporarily fix the building body 1.

[0065] S4: The building body 1 is slowly lowered, and the movable assembly moves downward along the pile foundation 3. After the building body 1 is lowered to a predetermined position, the clamping assembly 23 of the connector body 21 is clamped with the limiting assembly 4 on the pile foundation 3.

[0066] Then, the water inlet hole 12 is opened to allow seawater to enter the ballast tank 11 through the water inlet hole 12, and the building body 1 is slowly lowered by ballast until the second sealing member 236 on the connector body 21 contacts the upper surface of the limiting protrusion 41. Then, the driving member 232 is started, and the driving member 232 drives the driving ring plate 233 to move downward, and the driving ring plate 233 drives the claw 231 to move downward until the claw 231 is engaged with the limiting protrusion 41, and then the bolt 234 is used to fix the driving ring plate 233 and the claw 231.

[0067] Then, the pile cap is cast on the water traffic layer 14 and the pile foundation 3, and the prefabricated longitudinal beams, cross beams and panels are installed to complete the construction of the main building 1 and the traffic passages of the helipad 5 and the pier 6. Finally, the prefabricated helipad 5 and the pier 6 are transported to the site, the helipad 5 and the pier 6 are connected to the traffic passage, and concrete is poured at the connection to form a complete structure.

[0068] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine different embodiments or examples described in this specification and the features of different embodiments or examples, unless they are contradictory.

[0069] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include at least one of the features. In the description of this application, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0070] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any technician familiar with the technical field can easily think of various changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.

Claims

1. An underwater structure, characterized in that: include: The main body of the building; A connector, the connector is connected to the building body, the connector comprises a connector body, a movable connection component and a clamping component, the movable connection component and the clamping component are both connected to the connector body; A pile foundation, the bottom of which is fixed to the seabed, the movable connection component is movably connected to the pile foundation, the movable connection component can move up and down along the pile foundation, a limit position component is arranged on the pile foundation, and the clamping component is clamped with the limit position component.

2. The underwater structure according to claim 1, characterized in that: The movable connection component is sleeved on the pile foundation, a roller is arranged on the inner wall of the movable connection component, the movable connection component is movably connected to the pile foundation through the roller, and the roller rolls upward or downward along the pile foundation.

3. The underwater structure according to claim 1, characterized in that: The clamping assembly includes a clamping claw, which is rotatably connected to the connector body. The limiting assembly includes a limiting protrusion, and the limiting clamping claw is clamped with the limiting protrusion.

4. The underwater structure according to claim 3, characterized in that: The clamping assembly further includes a driving member and a driving ring plate, wherein the driving member is connected to the driving ring plate, the driving member drives the driving ring plate to move up and down, and the driving ring plate is hinged to the clamping claw; When the driving member drives the driving ring plate to move downward, the driving ring plate drives the claw to rotate around the connection between the claw and the connector body.

5. The underwater structure according to claim 4, characterized in that: The driving ring plate is provided with a first fixing hole, the clamping claw is provided with a first fixing hole, and the driving ring plate is detachably connected to the clamping claw through the first fixing hole and the second fixing hole.

6. The underwater structure according to claim 3, characterized in that: The clamping claw is provided with a first sealing member, and the clamping claw is sealed and connected to the limiting protrusion through the first sealing member.

7. The underwater structure according to claim 6, characterized in that: The connector body is provided with a second sealing member, and the connector body is sealed and connected to the limiting protrusion via the second sealing member.

8. The underwater structure according to any one of claims 1 to 7, characterized in that: A ballast tank is provided at the bottom of the building body, and a water inlet is opened on the building body, and the water inlet is communicated with the interior of the ballast tank.

9. The underwater structure according to any one of claims 1 to 7, characterized in that: The underwater building also includes a helipad and a pier, which are respectively located on the sides of the building body, and the helipad and the pier are both located on the sea surface; the building body includes an above-water traffic layer and an underwater main layer, the above-water traffic layer is connected to the underwater main layer, the above-water traffic layer is located on the sea surface, the underwater main layer is located below the sea surface, and the above-water traffic layer is connected to the helipad and the pier.

10. A construction method for an underwater structure as claimed in any one of claims 1 to 9, characterized in that: The following steps are involved: Prefabricate the building body and the connector, and connect the connector to the building body; While prefabricating the building body and the connector, driving piles on the seabed to place the prefabricated pile foundation on the seabed; Transporting the building body and the connector to the construction site, and movably connecting the movable component of the connector to the pile foundation; The building body is slowly lowered, and the movable component is moved downward along the pile foundation. After the building body is lowered to a predetermined position, the clamping component of the connector body is clamped with the limiting component on the pile foundation.