Construction organization BIM simulation method, device and equipment of linear engineering and storage medium

By dividing the work sections and working faces in linear engineering, simulation and resource optimization, the problem of inability to effectively simulate and display the construction organization of linear engineering in the existing technology is solved, and the construction of multiple working faces is effectively achieved Reasonable allocation of organization and progress.

CN119250663AActive Publication Date: 2025-01-03CHINA RAILWAY 18TH BUREAU GRP CO LTD +2
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411327504.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-23
Publication Date
2025-01-03
Estimated Expiration
2044-09-23

AI Technical Summary

Technical Problem

The prior art cannot effectively simulate the construction organization of linear engineering, and it is especially difficult to visually display the simulated construction conditions of multiple working faces.

Method used

A BIM simulation method for construction organization of linear engineering is proposed. By obtaining the overall construction period, the project is divided into work sections, the construction period and working face of each section are determined, and simulation is carried out to determine the construction resources, and the optimization is adjusted based on Resources for construction organization simulation.

Benefits of technology

It realizes effective organizational simulation of the construction conditions of multiple working faces, and can optimize and adjust construction resources to ensure the reasonable allocation of construction progress and the smooth progress of the process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119250663A_ABST
    Figure CN119250663A_ABST
Patent Text Reader

Abstract

The invention provides a construction organization BIM simulation method and device of a linear project, equipment and a storage medium, and the method comprises the steps: obtaining the overall construction period of the linear project; dividing the linear project into at least one working section based on the overall construction period, and determining a section construction period corresponding to each working section; determining at least one working surface corresponding to each working section and a first engineering quantity corresponding to each working surface based on the section construction period; performing analogue simulation on the basis of the section construction period and the first engineering quantity, and determining construction resources corresponding to each working surface; performing optimization adjustment on the first project amount based on the construction resources to obtain a second project amount corresponding to each working surface; and performing construction organization simulation based on the second engineering quantity and the construction resources corresponding to each working surface. According to the technical scheme, the construction conditions of multiple working faces in linear engineering can be effectively organized and simulated at the same time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of engineering construction technology, and in particular to a BIM simulation method, device, equipment and storage medium for construction organization of linear engineering. Background Art

[0002] In the related art, it is impossible to effectively simulate the construction organization of a linear project including multiple working surfaces, and it is difficult to intuitively display the simulated construction conditions of different working surfaces of the linear project. Summary of the invention

[0003] The present application aims to solve one of the technical problems in the related art at least to some extent.

[0004] In the first aspect, the present application proposes a BIM simulation method for the construction organization of a linear project, the method comprising: obtaining the overall construction period of the linear project; dividing the linear project into at least one work section based on the overall construction period, and determining the section construction period corresponding to each of the work sections; determining at least one work surface corresponding to each of the work sections and a first engineering quantity corresponding to each of the work surfaces based on the section construction period; performing simulation based on the section construction period and the first engineering quantity to determine the construction resources corresponding to each of the work surfaces; optimizing and adjusting the first engineering quantity based on the construction resources to obtain a second engineering quantity corresponding to each of the work surfaces; performing construction organization simulation based on the second engineering quantity and the construction resources corresponding to each of the work surfaces.

[0005] In one implementation, the simulation is performed based on the section construction period and the first engineering quantity to determine the construction resources corresponding to each of the working faces, including: configuring initial construction resources for each of the working faces; obtaining the engineering indicators corresponding to each of the working faces; performing dynamic simulation and risk analysis based on the initial construction resources, the engineering indicators and the first engineering quantity to obtain the first construction rate corresponding to each of the working faces; optimizing and adjusting the initial construction resources based on the first construction rate corresponding to each of the working faces to obtain the construction resources corresponding to each of the working faces.

[0006] In one implementation, the first engineering quantity is optimized and adjusted based on the construction resources to obtain the second engineering quantity corresponding to each of the working faces, including: obtaining the second construction rate corresponding to each of the working faces based on the construction resources corresponding to each of the working faces; obtaining the first working face duration corresponding to each of the working faces based on the second construction rate and the first engineering quantity corresponding to each of the working faces; obtaining the first difference value between the first working face durations corresponding to different working faces; obtaining the second difference value between the first working face duration corresponding to each of the working faces and the overall duration; adjusting the first engineering quantity corresponding to each of the working faces based on the first difference value and the second difference value to obtain the second engineering quantity corresponding to each of the working faces.

[0007] In one implementation, the construction organization simulation is performed based on the second engineering quantity and the construction resources corresponding to each of the working faces, including: performing three-dimensional modeling based on the second engineering quantity and the construction resources corresponding to each of the working faces to obtain a working face construction process model corresponding to each of the working faces; obtaining a section construction process model corresponding to each of the working sections based on the working face construction process model corresponding to each of the working faces; obtaining an overall construction process model corresponding to the linear project based on the section construction process model corresponding to each of the working sections; displaying the working face construction process model, the section construction process model and the overall construction process model in an interactive interface; wherein the interactive interface includes at least one window, and each of the window applications displays different construction process models and corresponding model information.

[0008] In an optional implementation, the window includes a main window and at least one sub-window, and the method further includes at least one of the following: in response to a selection operation of the first object on the first sub-window, exchanging the construction process models displayed by the first sub-window and the main window; determining that the first object modifies the model information of any window among the main window and the at least one sub-window, and updating the working surface construction process model, the section construction process model and the overall construction process model based on the modified model information.

[0009] In one implementation, before performing construction organization simulation based on the second engineering quantity and the construction resources corresponding to each of the working faces, the method further includes: determining the predicted working face duration corresponding to each of the working faces based on the second engineering quantity and the construction resources corresponding to each of the working faces; determining the predicted section duration of each of the working sections based on the predicted working face duration; and optimizing and adjusting at least one of the working sections if it is determined that the predicted section duration does not meet preset requirements.

[0010] In the second aspect, the present application proposes a BIM simulation device for the construction organization of a linear project, the device comprising: an acquisition module for acquiring the overall construction period of the linear project; a first processing module for dividing the linear project into at least one work section based on the overall construction period, and determining the section construction period corresponding to each of the work sections; a second processing module for determining at least one work surface corresponding to each of the work sections and a first engineering quantity corresponding to each of the work surfaces based on the section construction period; a third processing module for performing simulation based on the section construction period and the first engineering quantity to determine the construction resources corresponding to each of the work surfaces; a fourth processing module for optimizing and adjusting the first engineering quantity based on the construction resources to obtain a second engineering quantity corresponding to each of the work surfaces; and a fifth processing module for performing construction organization simulation based on the second engineering quantity and the construction resources corresponding to each of the work surfaces.

[0011] In one implementation, the third processing module can be used to: configure initial construction resources for each of the working faces; obtain engineering indicators corresponding to each of the working faces; perform dynamic simulation and risk analysis based on the initial construction resources, the engineering indicators and the first engineering quantity to obtain a first construction rate corresponding to each of the working faces; optimize and adjust the initial construction resources based on the first construction rate corresponding to each of the working faces to obtain the construction resources corresponding to each of the working faces.

[0012] In one implementation, the fourth processing module can be used to: obtain the second construction rate corresponding to each work surface based on the construction resources corresponding to each work surface; obtain the first work surface construction period corresponding to each work surface based on the second construction rate and the first engineering quantity corresponding to each work surface; obtain the first difference value between the first work surface construction periods corresponding to different work surfaces; obtain the second difference value between the first work surface construction period corresponding to each work surface and the overall construction period; adjust the first engineering quantity corresponding to each work surface based on the first difference value and the second difference value to obtain the second engineering quantity corresponding to each work surface.

[0013] In one implementation, the fifth processing module can be used to: perform three-dimensional modeling based on the second engineering quantity and the construction resources corresponding to each of the working surfaces to obtain a working surface construction process model corresponding to each of the working surfaces; obtain a section construction process model corresponding to each of the working sections based on the working surface construction process model corresponding to each of the working surfaces; obtain an overall construction process model corresponding to the linear project based on the section construction process model corresponding to each of the working sections; display the working surface construction process model, the section construction process model and the overall construction process model in an interactive interface; wherein the interactive interface includes at least one window, and each of the window applications displays different construction process models and corresponding model information.

[0014] In an optional implementation, the window includes a main window and at least one sub-window, and the sixth processing module is further used to implement at least one of the following: in response to a selection operation of the first object on the first sub-window, exchanging the construction process models displayed by the first sub-window and the main window; determining that the first object modifies the model information of any window among the main window and the at least one sub-window, and updating the working surface construction process model, the section construction process model and the overall construction process model based on the modified model information.

[0015] In one implementation, the device also includes: a sixth processing module, used to determine the predicted working face duration corresponding to each working face based on the second engineering quantity and the construction resources corresponding to each working face; determine the predicted section duration of each working section based on the predicted working face duration; and if it is determined that the predicted section duration does not meet the preset requirements, optimize and adjust at least one working section.

[0016] In a third aspect, the present application proposes an electronic device comprising: at least one processor; and a memory communicatively connected to the at least one processor; wherein the memory stores instructions executable by the at least one processor, and the instructions are executed by the at least one processor so that the at least one processor can execute the BIM simulation method for construction organization of linear engineering as described in the first aspect.

[0017] In a fourth aspect, the present application proposes a computer-readable storage medium for storing instructions, which, when executed, enables the method described in the first aspect to be implemented.

[0018] In a fifth aspect, the present application proposes a computer program product, including a computer program, which, when executed by a processor, implements the steps of the construction organization BIM simulation method for linear engineering as described in the first aspect.

[0019] The BIM simulation method, device, system, equipment and storage medium for the construction organization of linear engineering provided by the present application can divide the linear engineering into at least one work section based on the overall construction period of the linear engineering, and perform simulation based on the workload of each work section to determine the construction resources corresponding to each work surface, so as to optimize and adjust the workload of the work surface based on the construction resources, thereby performing construction organization simulation based on the optimized workload and construction resources. It is possible to effectively organize and simulate the construction conditions of multiple work surfaces at the same time.

[0020] Additional aspects and advantages of the present application will be given in part in the description below, and in part will become apparent from the description below, or will be learned through the practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] The above and / or additional aspects and advantages of the present application will become apparent and easily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which:

[0022] Figure 1 It is a flow chart of a BIM simulation method for construction organization of a linear project provided in an embodiment of the present application;

[0023] Figure 2 It is a flow chart of another linear engineering construction organization BIM simulation method provided in an embodiment of the present application;

[0024] Figure 3 It is a flow chart of another BIM simulation method for construction organization of linear engineering provided in an embodiment of the present application;

[0025] Figure 4 It is a flow chart of another BIM simulation method for construction organization of linear engineering provided in an embodiment of the present application;

[0026] Figure 5 It is a structural schematic diagram of a BIM simulation device for construction organization of a linear engineering provided in an embodiment of the present application;

[0027] Figure 6 It is a structural schematic diagram of another linear engineering construction organization BIM simulation device provided in an embodiment of the present application;

[0028] Figure 7 It is a schematic diagram of the structure of an electronic device provided in an embodiment of the present application. DETAILED DESCRIPTION

[0029] Embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present application, and should not be construed as limiting the present application.

[0030] The following describes a method and device for simulating the construction organization of a linear engineering project using a BIM (Building Information Modeling) simulation method according to an embodiment of the present application with reference to the accompanying drawings.

[0031] Figure 1 1 is a flow chart of a BIM simulation method for construction organization of a linear project provided in an embodiment of the present application. Figure 1 As shown, the method may include but is not limited to the following steps:

[0032] Step S101: Obtain the overall duration of the linear project.

[0033] Exemplarily, the overall duration expected to complete the project is obtained.

[0034] Step S102: Divide the linear project into at least one work section based on the overall construction period, and determine the section construction period corresponding to each work section.

[0035] Exemplarily, according to the overall construction period and available construction resources of the linear project, the linear project is divided into different work sections, and corresponding construction resources are allocated to each work section, so as to determine the section construction period required to complete each work section based on the construction resources and project volume of each work section.

[0036] Step S103: Determine at least one working surface corresponding to each work section and a first engineering quantity corresponding to each working surface based on the section duration.

[0037] Exemplarily, each work section is divided into multiple work packages, the construction resources required for each work package are evaluated, and different work packages are combined into a work surface according to the actual situation of the construction site, thereby determining at least one work surface corresponding to each work section and the first project quantity corresponding to each work surface.

[0038] Step S104: Perform simulation based on the section construction period and the first engineering quantity to determine the construction resources corresponding to each working surface.

[0039] Exemplarily, based on the first engineering quantity corresponding to the working faces included in each work section and the section duration corresponding to the work section, the construction resources required to complete the first engineering quantity corresponding to each working face within the section duration are determined.

[0040] Step S105: Optimize and adjust the first engineering quantity based on construction resources to obtain a second engineering quantity corresponding to each working surface.

[0041] Exemplarily, the engineering tasks to be completed on each work surface are analyzed, the priorities corresponding to different work surfaces are determined, and the construction resource requirements of each work surface in different time periods are determined; the construction resources of the linear project are matched with the construction resource requirements of each work surface according to different time periods in combination with the priorities corresponding to the work surfaces, and the available construction resources for each work surface in different time periods are determined; the engineering quantities of the work surfaces whose available construction resources cannot meet the construction resource requirements are reallocated, thereby optimizing and adjusting the first engineering quantity of each work surface to obtain the second engineering quantity corresponding to each work surface.

[0042] Step S106: Perform construction organization simulation based on the second engineering quantity and construction resources corresponding to each working surface.

[0043] Exemplarily, a construction organization simulation is performed based on the second engineering quantity and construction resources corresponding to each work surface to generate a BIM model corresponding to the construction process.

[0044] By implementing the embodiments of the present application, the linear project can be divided into at least one work section based on the overall construction period of the linear project, and the construction resources corresponding to each work surface can be determined by simulation based on the workload of each work section, so as to optimize the workload of the work surface based on the construction resources, thereby performing construction organization simulation based on the optimized workload and construction resources. It is possible to effectively organize and simulate the construction conditions of multiple work surfaces in the linear project at the same time.

[0045] In one implementation, the construction resource of each work surface can be determined based on the construction rate of each work surface under different construction resources. As an example, see Figure 2 , Figure 2 FIG. 1 is a flow chart of another linear engineering construction organization BIM simulation method provided by an embodiment of the present application. Figure 2 As shown, the method may include but is not limited to the following steps:

[0046] Step S201: Obtain the overall duration of the linear project.

[0047] In the embodiments of the present application, step S201 can be implemented by any of the methods in the embodiments of the present application, and the embodiments of the present application do not limit this and will not be described in detail.

[0048] Step S202: Divide the linear project into at least one work section based on the overall construction period, and determine the section construction period corresponding to each work section.

[0049] In the embodiments of the present application, step S202 can be implemented by any of the methods in the embodiments of the present application, and the embodiments of the present application do not limit this and will not be described in detail.

[0050] Step S203: Determine at least one working surface corresponding to each work section and a first engineering quantity corresponding to each working surface based on the section duration.

[0051] In the embodiments of the present application, step S203 can be implemented by any of the methods in the embodiments of the present application, and the embodiments of the present application do not limit this and will not be described in detail.

[0052] Step S204: configuring initial construction resources for each work surface.

[0053] Exemplarily, the overall available construction resources of the linear project may be evenly allocated to each work surface as the initial construction resources of each work surface.

[0054] Step S205: Obtain engineering indicators corresponding to each working surface.

[0055] The above engineering indicators may include but are not limited to

[0056] Step S206: Perform dynamic simulation and risk analysis based on initial construction resources, engineering indicators and the first engineering quantity to obtain a first construction rate corresponding to each working face.

[0057] Step S207: Optimize and adjust the initial construction resources based on the first construction rate and section duration corresponding to each working face to obtain the construction resources corresponding to each working face.

[0058] Exemplarily, the working face construction period required for the completion of each working face is determined based on the first construction rate corresponding to each working face, and based on the difference between the working face construction period and the section construction period, the initial construction resources of each working face are optimized and adjusted so that the working face construction period required for the completion of each working face after adjustment is less than the section construction period.

[0059] Step S208: Optimize and adjust the first engineering quantity based on construction resources to obtain a second engineering quantity corresponding to each working surface.

[0060] In the embodiments of the present application, step S208 can be implemented in any of the ways in the embodiments of the present application, and the embodiments of the present application do not limit this and will not be described in detail.

[0061] Step S209: Perform construction organization simulation based on the second engineering quantity and construction resources corresponding to each working surface.

[0062] In the embodiments of the present application, step S209 can be implemented in any of the ways in the embodiments of the present application, and the embodiments of the present application do not limit this and will not be described in detail.

[0063] By implementing the embodiments of the present application, the construction rate of each work surface can be obtained based on the initial construction resources configured for each work surface, so as to optimize and adjust the construction resources corresponding to each work surface based on the construction rate of each work surface.

[0064] In one implementation, the construction period required for each work surface can be determined based on the construction resources corresponding to each work surface, so as to adjust the engineering quantity of each work surface based on the construction period required for each work surface. Figure 3 , Figure 3 It is a flow chart of another BIM simulation method for construction organization of linear engineering provided in an embodiment of the present application.

[0065] like Figure 3 As shown, the method may include but is not limited to the following steps:

[0066] Step S301: Obtain the overall duration of the linear project.

[0067] In the embodiments of the present application, step S301 can be implemented by any of the methods in the embodiments of the present application, and the embodiments of the present application do not limit this and will not be described in detail.

[0068] Step S302: Divide the linear project into at least one work section based on the overall construction period, and determine the section construction period corresponding to each work section.

[0069] In the embodiments of the present application, step S302 can be implemented by any of the methods in the embodiments of the present application, and the embodiments of the present application do not limit this and will not be described in detail.

[0070] Step S303: Determine at least one working surface corresponding to each work section and a first engineering quantity corresponding to each working surface based on the section duration.

[0071] In the embodiments of the present application, step S303 can be implemented by any of the methods in the embodiments of the present application, and the embodiments of the present application do not limit this and will not be described in detail.

[0072] Step S304: Perform simulation based on the section construction period and the first engineering quantity to determine the construction resources corresponding to each working surface.

[0073] In the embodiments of the present application, step S304 can be implemented by any of the methods in the embodiments of the present application, and the embodiments of the present application do not limit this and will not be described in detail.

[0074] Step S305: Obtain a second construction rate corresponding to each working surface based on the construction resources corresponding to each working surface.

[0075] Exemplarily, the second construction rate of each working face during the construction process is determined based on the construction resources corresponding to each working face.

[0076] Step S306: Obtain the first working surface construction period corresponding to each working surface based on the second construction rate and the first engineering quantity corresponding to each working surface.

[0077] Exemplarily, based on the second construction rate corresponding to each working face, the first working face construction period required for each working face to complete the corresponding first engineering quantity is determined.

[0078] Step S307: Obtain a first difference value between first working surface durations corresponding to different working surfaces.

[0079] Step S308: Obtain a second difference value between the first working surface duration corresponding to each working surface and the overall duration.

[0080] Step S309: adjusting the first engineering quantity corresponding to each working surface based on the first difference value and the second difference value to obtain the second engineering quantity corresponding to each working surface.

[0081] Exemplarily, the first engineering quantity corresponding to each working surface is adjusted based on the first difference value and the second difference value to reduce the difference between the working surface durations corresponding to different working surfaces and ensure that the working surface durations corresponding to all working surfaces are less than or equal to the overall duration of the linear project.

[0082] Step S3010: Perform construction organization simulation based on the second engineering quantity and construction resources corresponding to each work surface.

[0083] In the embodiments of the present application, step S3010 can be implemented in any of the ways in the embodiments of the present application, and the embodiments of the present application do not limit this and will not be described in detail.

[0084] By implementing the embodiments of the present application, the construction rate of each working face can be obtained based on the construction resources of each working face, so as to determine the working face duration of each working face based on the construction rate and the engineering quantity of each working face, and thus adjust the engineering quantity of the working face based on the difference between the engineering durations of different working faces and the difference between the engineering durations of different working faces and the overall engineering duration of the linear project, so as to ensure the smooth progress of the linear project construction process.

[0085] In one implementation, the construction organization process can be simulated and modeled based on the second engineering quantity and construction resources corresponding to each work surface. Figure 4 , Figure 4 1 is a flow chart of another linear engineering construction organization BIM simulation method provided by the embodiment of the present application. Figure 4 As shown, the method may include but is not limited to the following steps:

[0086] Step S401: Obtain the overall duration of the linear project.

[0087] In the embodiments of the present application, step S401 can be implemented by any of the methods in the embodiments of the present application, and the embodiments of the present application do not limit this and will not be described in detail.

[0088] Step S402: Divide the linear project into at least one work section based on the overall construction period, and determine the section construction period corresponding to each work section.

[0089] In the embodiments of the present application, step S402 can be implemented by any of the methods in the embodiments of the present application, and the embodiments of the present application do not limit this and will not be described in detail.

[0090] Step S403: Determine at least one working surface corresponding to each work section and a first engineering quantity corresponding to each working surface based on the section duration.

[0091] In the embodiments of the present application, step S403 can be implemented by any of the methods in the embodiments of the present application, and the embodiments of the present application do not limit this and will not be described in detail.

[0092] Step S404: Perform simulation based on the section construction period and the first engineering quantity to determine the construction resources corresponding to each working surface.

[0093] In the embodiments of the present application, step S404 can be implemented by any of the methods in the embodiments of the present application, and the embodiments of the present application do not limit this and will not be described in detail.

[0094] Step S405: Optimize and adjust the first engineering quantity based on construction resources to obtain a second engineering quantity corresponding to each working surface.

[0095] In the embodiments of the present application, step S405 can be implemented in any of the ways in the embodiments of the present application, and the embodiments of the present application do not limit this and will not be described in detail.

[0096] Step S406: Perform three-dimensional modeling based on the second engineering quantity and construction resources corresponding to each working surface to obtain a working surface construction process model corresponding to each working surface.

[0097] Exemplarily, based on the second engineering quantity and construction resources corresponding to each working face, the construction process of each working face is three-dimensionally modeled to obtain a working face construction process model corresponding to the construction process of each working face.

[0098] Step S407: Based on the working surface construction process model corresponding to each working surface, the section construction process model corresponding to each working section is obtained.

[0099] Exemplarily, the working surface construction process models corresponding to each work are combined in chronological order to obtain the section construction process model corresponding to each working section.

[0100] Step S408: Based on the section construction process model corresponding to each work section, the overall construction process model corresponding to the linear project is obtained.

[0101] Exemplarily, the section construction process models corresponding to each work section are integrated in chronological order to obtain an overall construction process model corresponding to the linear process.

[0102] Step S409: displaying the working face construction process model, the section construction process model and the overall construction process model in the interactive interface.

[0103] The interactive interface includes at least one window, and each window is used to display different construction process models and corresponding model information.

[0104] Exemplarily, the overall construction process model corresponding to the linear project can be displayed in the main window of the interactive interface, and the working surface construction process models corresponding to different working surfaces can be displayed in each sub-window.

[0105] In an optional implementation, the above-mentioned window includes a main window and at least one sub-window, and the above-mentioned method also includes at least one of the following: in response to the first object's selection operation on the first sub-window, exchanging the construction process models displayed by the first sub-window and the main window; determining that the first object modifies the model information of any window among the main window and at least one sub-window, and updating the working surface construction process model, the section construction process model and the overall construction process model based on the modified model information.

[0106] As an example, in response to the user's selection operation on the first sub-window, the construction process models displayed in the first sub-window and the main window are exchanged.

[0107] As an example, it is determined that the first object modifies the model information of any one of the main window and at least one sub-window, and the working surface construction process model, the section construction process model and the overall construction process model are updated based on the modified model information.

[0108] By implementing the embodiment of the present application, three-dimensional modeling can be performed based on the second engineering quantity and construction resources corresponding to each working face, and a working face construction process model corresponding to each working face can be obtained. The working face construction process models corresponding to different working faces can be combined in chronological order to obtain a section construction process model and an overall construction process model, and the above models can be visualized, so that construction personnel can understand the overall construction progress of the linear project.

[0109] In some embodiments, before performing construction organization simulation based on the second engineering quantity and construction resources corresponding to each work face, the above method also includes: determining the predicted working face duration corresponding to each work face based on the second engineering quantity and construction resources corresponding to each work face; determining the predicted section duration of each work section based on the predicted working face duration; determining that the predicted section duration does not meet the preset requirements, and optimizing and adjusting at least one work section.

[0110] For example, the construction rate of each working face is determined based on the construction resources of each working face, and the predicted working face duration of each working face is determined based on the construction rate of each working face and the second working face. If the predicted working face duration of a certain working face does not meet the preset requirements, at least one working face is optimized and adjusted. For example, the working faces are re-divided or merged.

[0111] See also Figure 5 , Figure 5 Schematic diagram of a BIM simulation device for linear engineering construction organization provided in an embodiment of the present application. Figure 5 As shown, the device 500 includes: an acquisition module 501, which is used to acquire the overall construction period of the linear project; a first processing module 502, which is used to divide the linear project into at least one work section based on the overall construction period, and determine the section construction period corresponding to each work section; a second processing module 503, which is used to determine at least one work surface corresponding to each work section and a first engineering quantity corresponding to each work surface based on the section construction period; a third processing module 504, which is used to perform simulation based on the section construction period and the first engineering quantity, and determine the construction resources corresponding to each work surface; a fourth processing module 505, which is used to optimize and adjust the first engineering quantity based on the construction resources, and obtain the second engineering quantity corresponding to each work surface; a fifth processing module 506, which is used to perform construction organization simulation based on the second engineering quantity and construction resources corresponding to each work surface.

[0112] In one implementation, the third processing module 504 can be used to: configure initial construction resources for each work face; obtain engineering indicators corresponding to each work face; perform dynamic simulation and risk analysis based on the initial construction resources, engineering indicators and the first engineering quantity to obtain the first construction rate corresponding to each work face; optimize and adjust the initial construction resources based on the construction rate corresponding to each work face to obtain the construction resources corresponding to each work face.

[0113] In one implementation, the fourth processing module 505 can be used to: obtain the second construction rate corresponding to each work surface based on the construction resources corresponding to each work surface; obtain the first work surface construction period corresponding to each work surface based on the second construction rate and the first engineering quantity corresponding to each work surface; obtain the first difference value between the first work surface construction periods corresponding to different work surfaces; obtain the second difference value between the first work surface construction period corresponding to each work surface and the overall construction period; adjust the first engineering quantity corresponding to each work surface based on the first difference value and the second difference value to obtain the second engineering quantity corresponding to each work surface.

[0114] In one implementation, the fifth processing module 506 can be used to: perform three-dimensional modeling based on the second engineering quantity and construction resources corresponding to each working surface to obtain a working surface construction process model corresponding to each working surface; obtain a section construction process model corresponding to each working section based on the working surface construction process model corresponding to each working surface; obtain an overall construction process model corresponding to the linear project based on the section construction process model corresponding to each working section; display the working surface construction process model, the section construction process model and the overall construction process model in an interactive interface; wherein the interactive interface includes at least one window, and each window is used to display different construction process models and corresponding model information.

[0115] In an optional implementation, the window includes a main window and at least one sub-window, and the fifth processing module 506 is also used for at least one of the following: in response to the first object selecting the first sub-window, exchanging the construction process models displayed by the first sub-window and the main window; determining that the first object modifies the model information of any window among the main window and at least one sub-window, and updating the working surface construction process model, the section construction process model and the overall construction process model based on the modified model information.

[0116] In one implementation, the apparatus further includes: a sixth processing module. As an example, see Figure 6 , Figure 6 Schematic diagram of another linear engineering construction organization BIM simulation device provided in the embodiment of the present application. Figure 6As shown, the device 600 also includes a sixth processing module 607, which is used to determine the predicted working face duration corresponding to each working face based on the second engineering quantity and construction resources corresponding to each working face; determine the predicted section duration of each working section based on the predicted working face duration; and optimize and adjust at least one working section if it is determined that the predicted section duration does not meet the preset requirements. Figure 6 Modules 601 to 606 in Figure 5 Modules 501 to 506 in the embodiment have the same structure and function.

[0117] Through the device of the embodiment of the present application, the linear project can be divided into at least one work section based on the overall construction period of the linear project, and the construction resources corresponding to each work surface can be determined by simulation based on the workload of each work section, so as to optimize the workload of the work surface based on the construction resources, thereby performing construction organization simulation based on the optimized workload and construction resources. It is possible to effectively organize and simulate the construction conditions of multiple work surfaces at the same time.

[0118] It should be noted that the aforementioned explanation of the embodiment of the BIM simulation method for construction organization of linear engineering is also applicable to the BIM simulation device for construction organization of linear engineering of this embodiment, and will not be repeated here.

[0119] In order to implement the above embodiment, the present application also proposes an electronic device. Figure 7 , Figure 7 Schematic diagram of the structure of the electronic device provided in the embodiment of the present application. Figure 7 As shown, the electronic device 700 includes: a processor 701, and a memory 702 communicatively connected to the processor 701; the memory 702 stores computer-executable instructions; the processor 701 executes the computer-executable instructions stored in the memory to implement the method provided in the aforementioned embodiment.

[0120] In order to implement the above embodiments, the present application also proposes a computer-readable storage medium, in which computer-executable instructions are stored. When the computer-executable instructions are executed by a processor, they are used to implement the methods provided by the above embodiments.

[0121] In order to implement the above embodiments, the present application also proposes a computer program product, including a computer program, which implements the methods provided by the above embodiments when executed by a processor.

[0122] In the description of this application, unless otherwise specified, “ / ” means or, for example, A / B can mean A or B; “and / or” in this article is merely a way to describe the association relationship of associated objects, indicating that there can be three relationships, for example, A and / or B can mean: A exists alone, A and B exist at the same time, and B exists alone.

[0123] In the description of the aforementioned embodiments, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0124] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of this application, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0125] Any process or method description in a flowchart or otherwise described herein may be understood to represent a module, fragment or portion of code comprising one or more executable instructions for implementing the steps of a custom logical function or process, and the scope of the preferred embodiments of the present application includes alternative implementations in which functions may not be performed in the order shown or discussed, including performing functions in a substantially simultaneous manner or in the reverse order depending on the functions involved, which should be understood by technicians in the technical field to which the embodiments of the present application belong.

[0126] The logic and / or steps represented in the flowchart or otherwise described herein, for example, can be considered as an ordered list of executable instructions for implementing logical functions, and can be embodied in any computer-readable medium for use by an instruction execution system, device or apparatus (such as a computer-based system, a system including a processor, or other system that can fetch instructions from an instruction execution system, device or apparatus and execute the instructions), or in combination with these instruction execution systems, devices or apparatuses. For the purpose of this specification, "computer-readable medium" can be any device that can contain, store, communicate, propagate or transmit a program for use by an instruction execution system, device or apparatus, or in combination with these instruction execution systems, devices or apparatuses. More specific examples of computer-readable media (a non-exhaustive list) include the following: an electrical connection with one or more wires (electronic device), a portable computer disk box (magnetic device), a random access memory (RAM), a read-only memory (ROM), an erasable and programmable read-only memory (EPROM or flash memory), a fiber optic device, and a portable compact disk read-only memory (CDROM). In addition, the computer-readable medium may even be paper or other suitable medium on which the program is printed, since the program may be obtained electronically, for example, by optically scanning the paper or other medium and then editing, interpreting or processing in other suitable ways if necessary, and then stored in a computer memory.

[0127] It should be understood that the various parts of the present application can be implemented by hardware, software, firmware or a combination thereof. In the above-mentioned embodiments, multiple steps or methods can be implemented by software or firmware stored in a memory and executed by a suitable instruction execution system. For example, if implemented by hardware, as in another embodiment, it can be implemented by any one of the following technologies known in the art or their combination: a discrete logic circuit having a logic gate circuit for implementing a logic function for a data signal, a dedicated integrated circuit having a suitable combination of logic gate circuits, a programmable gate array (PGA), a field programmable gate array (FPGA), etc.

[0128] A person skilled in the art may understand that all or part of the steps in the method for implementing the above-mentioned embodiment may be completed by instructing related hardware through a program, and the program may be stored in a computer-readable storage medium, which, when executed, includes one or a combination of the steps of the method embodiment.

[0129] In addition, each functional unit in each embodiment of the present application may be integrated into a processing module, or each unit may exist physically separately, or two or more units may be integrated into one module. The above-mentioned integrated module may be implemented in the form of hardware or in the form of a software functional module. If the integrated module is implemented in the form of a software functional module and sold or used as an independent product, it may also be stored in a computer-readable storage medium.

[0130] The storage medium mentioned above may be a read-only memory, a magnetic disk or an optical disk, etc. Although the embodiments of the present application have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limiting the present application. A person of ordinary skill in the art may change, modify, replace and modify the above embodiments within the scope of the present application.

Claims

1. A BIM simulation method for construction organization of linear engineering, characterized in that: include: Get the overall duration of the linear project; Dividing the linear project into at least one working section based on the overall construction period, and determining the section construction period corresponding to each working section; Determine at least one working surface corresponding to each of the working sections and a first engineering quantity corresponding to each of the working surfaces based on the section duration; Perform simulation based on the section construction period and the first engineering quantity to determine the construction resources corresponding to each of the working faces; Optimizing and adjusting the first engineering quantity based on the construction resources to obtain a second engineering quantity corresponding to each of the working faces; A construction organization simulation is performed based on the second engineering quantity and the construction resources corresponding to each of the working surfaces.

2. The method according to claim 1, characterized in that The performing simulation based on the section construction period and the first engineering quantity to determine the construction resources corresponding to each of the working faces includes: Allocating initial construction resources for each of the working faces; Obtain engineering indicators corresponding to each working surface; Perform dynamic simulation and risk analysis based on the initial construction resources, the engineering indicators and the first engineering quantity to obtain a first construction rate corresponding to each of the working faces; The initial construction resources are optimized and adjusted based on the first construction rate corresponding to each of the working faces to obtain the construction resources corresponding to each of the working faces.

3. The method according to claim 1, characterized in that The optimizing and adjusting the first engineering quantity based on the construction resources to obtain the second engineering quantity corresponding to each of the working faces includes: Acquire a second construction rate corresponding to each of the working faces based on the construction resources corresponding to each of the working faces; Based on the second construction rate and the first engineering quantity corresponding to each of the working faces, respectively, obtaining the first working face construction period corresponding to each of the working faces; Obtaining a first difference value between the first working surface durations corresponding to different working surfaces; Obtaining a second difference value between the first working surface duration corresponding to each of the working surfaces and the overall duration; The first engineering quantity corresponding to each of the working surfaces is adjusted based on the first difference value and the second difference value to obtain the second engineering quantity corresponding to each of the working surfaces.

4. The method according to claim 1, characterized in that The performing of construction organization simulation based on the second engineering quantity and the construction resources corresponding to each of the working faces includes: Perform three-dimensional modeling based on the second engineering quantity and the construction resources corresponding to each of the working faces to obtain a working face construction process model corresponding to each of the working faces; Based on the working surface construction process model corresponding to each of the working surfaces, obtaining the section construction process model corresponding to each of the working sections; Based on the section construction process model corresponding to each of the working sections, an overall construction process model corresponding to the linear project is obtained; The working face construction process model, the section construction process model and the overall construction process model are displayed in an interactive interface; wherein the interactive interface includes at least one window, and each window is used to display a different construction process model and corresponding model information.

5. The method according to claim 4, characterized in that The window includes a main window and at least one sub-window, and the method further includes at least one of the following: In response to the first object selecting the first sub-window, exchanging the construction process models displayed in the first sub-window and the main window; wherein the first sub-window is any one of the at least one sub-window; Determine that the first object modifies the model information of any one of the main window and the at least one sub-window, and update the work surface construction process model, the section construction process model and the overall construction process model based on the modified model information.

6. The method according to claim 1, characterized in that Before performing construction organization simulation based on the second engineering quantity and the construction resources corresponding to each of the working surfaces, the method further includes: Determine the predicted working face duration corresponding to each working face based on the second engineering quantity and the construction resources corresponding to each working face; Determine the predicted section duration of each of the working sections based on the predicted working face duration; It is determined that the predicted section duration does not meet preset requirements, and the at least one working section is optimized and adjusted.

7. A BIM simulation device for construction organization of linear engineering, characterized in that: include: An acquisition module is used to obtain the overall duration of the linear project; A first processing module, configured to divide the linear project into at least one working section based on the overall construction period, and determine a section construction period corresponding to each working section; A second processing module is used to determine at least one working surface corresponding to each of the working sections and a first engineering quantity corresponding to each of the working surfaces based on the section duration; A third processing module is used to perform simulation based on the section construction period and the first engineering quantity to determine the construction resources corresponding to each of the working faces; A fourth processing module, configured to optimize and adjust the first engineering quantity based on the construction resources to obtain a second engineering quantity corresponding to each of the working faces; The fifth processing module is used to perform construction organization simulation based on the second engineering quantity and the construction resources corresponding to each of the working surfaces.

8. An electronic device, characterized in that: include: A processor, and a memory communicatively connected to the processor; The memory stores computer-executable instructions; The processor executes the computer-executable instructions stored in the memory to implement the method according to any one of claims 1 to 6.

9. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer-executable instructions, and when the computer-executable instructions are executed by a processor, they are used to implement the method according to any one of claims 1 to 6.

10. A computer program product, characterized in that The method comprises a computer program, which implements the method according to any one of claims 1 to 6 when being executed by a processor.

Citation Information

Patent Citations

  • Method and device for determining construction technology scheme of long piled wharf project

    CN110258442A

  • BIM-based four-power construction group plan simulation and resource dynamic adjustment method and system

    CN112365113A

  • BIM construction work amount simulation management method and system, equipment and storage medium

    CN113935594A

  • Line laying method, device, equipment and storage medium

    CN116485147A

  • Resource adjustment method and apparatus, computing device cluster, and readable storage medium

    WO2023246330A1