Production scheduling intelligent optimization method for production process of process industry enterprise

By analyzing and scheduling the production and raw material usage data of process industrial enterprises, intelligent allocation of work segment resources is achieved, the problem of inaccurate manual scheduling is solved, production efficiency and safety are improved, and production risks are reduced.

CN119294734APending Publication Date: 2025-01-10NANJING AOBO IND INTELLIGENCE TECH RES INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411363753.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-28
Publication Date
2025-01-10

AI Technical Summary

Technical Problem

In the prior art, the production scheduling of process industrial enterprises mainly relies on manual analysis, which leads to inaccurate distribution of employees and raw materials, affects production efficiency and safety, and is unable to respond to production problems quickly, resulting in increased production capacity and costs.

Method used

By collecting and analyzing order data, employee production data and raw material usage data, using the database to calculate the production and raw material usage rates of each section, perform intelligent scheduling, allocating employees and raw material resources, and realizing the transfer, transfer of the section, and allocation of the dispatch area without the need for dispatching area. .

Benefits of technology

It improves the accuracy and effectiveness of production scheduling, quickly responds to the problem of production rate imbalance, and reduces production risks and costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119294734A_ABST
    Figure CN119294734A_ABST
Patent Text Reader

Abstract

The invention discloses a production scheduling intelligent optimization method for a flow industry enterprise production process, and relates to the technical field of production scheduling intelligent optimization, and the method comprises order data analysis, production data collection, production quantity analysis, employee production scheduling, raw material use data collection, use data analysis, and raw material use blending. The method comprises the following steps: analyzing production data of each workshop section, dividing each production workshop section into a transfer-away production workshop section, a transfer-in production workshop section and a non-scheduling production workshop section, scheduling employees according to the production data of the employees of each production workshop section, and dividing each workshop section into a transfer-away processing workshop section, a transfer-in processing workshop section and a non-scheduling processing workshop section according to the production data of each workshop section; through production scheduling, the production efficiency of the whole production process can be improved, and the loss caused by local problems in the production process is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of intelligent optimization of production scheduling, and in particular to an intelligent optimization method for production scheduling of a production process of a process industrial enterprise. Background Art

[0002] With the improvement of people's living standards, the demand for handicrafts is increasing. Process industry refers to the production industry that carries out processes through physical changes and chemical changes. The production process is complex, the division of labor among employees is complex, the production continuity is strong, and the risk is high. If problems occur locally, it will often affect the production process of the entire industrial enterprise. Scheduling can increase production capacity, reduce costs, increase production efficiency, and reduce production risks. Therefore, intelligent optimization of production scheduling is becoming increasingly important.

[0003] Currently, most employee scheduling is done through manual analysis, and the allocation method of staff is obtained through experience. The analysis of the actual work efficiency of each staff member is one-sided, and it is impossible to accurately allocate each staff member to each work section, which affects the collaborative relationship between each work section, reduces production efficiency, and causes one-sided employee scheduling results. At the same time, when employee production problems arise, scheduling cannot be carried out quickly, affecting production capacity and causing a lag in employee scheduling results.

[0004] Currently, most raw material scheduling is done through manual analysis, and the supply of raw materials is obtained through experience. It is unable to balance the relationship between the raw material demand of some processing sections and the excessive raw material supply of some processing sections, resulting in a waste of staff production efficiency, increased transportation and storage costs of raw materials, and increased production risks. Summary of the invention

[0005] In view of the above-mentioned technical deficiencies, the purpose of the present invention is to provide a production scheduling intelligent optimization method for the production process of a process industry enterprise.

[0006] In order to solve the above technical problems, the present invention adopts the following technical solutions: The present invention provides a production scheduling intelligent optimization method for a production process of a process industrial enterprise, comprising the following steps: Step 1, order data analysis: parsing the industrial product orders in the database to obtain a preset production rate and a preset raw material usage rate; Step 2: Production data collection: Collect employee production data; Step 3, production data analysis: Analyze the production data of employees to obtain the current production rate of each section and the current production rate of each employee. According to the current production rate of each section and the preset production rate, obtain each production transfer section. According to the current production rate of each employee in each production transfer section, obtain each employee who can be transferred. Step 4: Employee production scheduling: Obtain the historical production data of each production transfer section of each employee who has been transferred out of production from the database and schedule the employees; Step 5: Usage data collection: collect raw material usage data; Step 6: Usage data analysis: Analyze the raw material usage data to obtain the current usage rate of each section, and then obtain the raw material usage rate of each section. According to the current usage rate of each section and the preset usage rate of the raw materials, each section is divided into a section where each raw material is transferred out, a section where each raw material is not dispatched, and a section where each raw material is transferred in; Step 7. Raw material usage scheduling: Schedule the raw materials according to the raw material usage rate of each work section.

[0007] Preferably, the industrial product orders in the database are parsed, and the specific parsing process is as follows: each order information is obtained from the database, including the quantity of industrial products required for the order , Remaining time for order delivery , substitute into the preset production rate calculation formula The preset production rate is obtained , get the quantity of raw materials required for industrial product orders from the database , substitute into the standard usage rate calculation formula In the process, the standard utilization rate of raw materials is obtained through the database to obtain the utilization rate of raw materials. , substitute the preset usage rate formula Get the preset usage rate of raw materials .

[0008] Preferably, the employee production data is collected, and the specific collection process is as follows: according to the industrial product production process in the database, the assembly line is divided into various sections, and sensors are arranged at each employee's workstation in each section. After the employee produces the product, it will be sensed and recorded by the sensor, and a preset time is set for collection. The employee production data is collected from the sensor information, including the production quantity of employee B in the current section of section a for the preset time. , a is the number of each section, , , b is the employee number, , , the current production quantity of each employee in each section of the preset time is summarized to obtain the production quantity of each section of the preset time .

[0009] Preferably, the production data of employees is analyzed, and the specific analysis process is as follows: the production quantity of the preset time section a is Substitute into the rate calculation formula The current production rate of section a is obtained , The preset duration.

[0010] If the current production rate of a section is greater than the preset production rate, it indicates that the section is a production transfer section. The production transfer sections are numbered in descending order of production rate to obtain the number c of each production transfer section. , , substitute the current production rate of each production transfer section into the calculation formula required for production In the above equation, the overflow rate of each production transfer section is obtained. If the current production rate of a section is equal to the preset production rate, it indicates that the section is a production section that does not need to be dispatched. If the current production rate of a section is less than the preset production rate, it indicates that the section is a production transfer section. The production transfer sections are numbered in ascending order according to the current production rate to obtain the number d of each production transfer section. , , substitute the current production rate of each production section into the calculation formula required for production In the process, the required rate of each production transfer section is obtained.

[0011] The employees in each production section are numbered in descending order according to their current production rate, numbered as e. , , substitute the current production rate of each employee in each production transfer section into the loss rate calculation formula In the above equation, the loss rate of the preset number of employees f in the transfer section c is obtained. If the loss rate of the preset number of employees f in the transfer section c is less than the overflow rate of the production transfer section c, the number of employees that can be transferred from the transfer section c is f. If there are multiple numbers of employees that can be transferred from the transfer section c, the largest number is selected as the number of employees that can be transferred from the production transfer section c. According to the order of employees in each production transfer section, the employees before f in each production transfer section are recorded as transferable employees, and the production transfer employees are obtained by summarizing them.

[0012] Preferably, the employee scheduling is specifically carried out as follows: the historical production rate of each production transfer section of each production transfer employee is obtained from the database, and each production transfer employee is numbered in order of historical production rate from small to large, numbered as g, , , according to the current production rate of each production transfer section from small to large, substitute the historical production rate of each production transfer employee in the first production transfer section into the preset acquisition rate calculation formula The preset acquisition rate of the number of employees to be transferred into the first production transfer section is obtained. If a preset acquisition rate of the first production transfer section is greater than or equal to the required rate, the number of employees to be transferred corresponding to the preset acquisition rate is recorded as the number of employees to be transferred into the first production transfer section. If the first production transfer section has multiple numbers of employees to be transferred, the number of employees to be transferred with the smallest preset acquisition rate is selected as the number of employees to be transferred into the first production transfer section.

[0013] All the employees transferred out of production except the employees who need to be transferred into the first production transfer section are recorded as the remaining employees after the first transfer, and the historical production rate of the second production transfer section of the remaining employees after the first transfer is substituted into the preset acquisition rate calculation formula The preset acquisition rate of each preset number of transferred employees in the second production transfer section is obtained. If a preset acquisition rate of the second production transfer section is greater than or equal to the required rate, the preset number of transferred employees corresponding to the preset acquisition rate is recorded as the required number of transferred employees in the second production transfer section. If the second production transfer section has multiple required numbers of transferred employees, the preset number of transferred employees with the smallest preset acquisition rate is selected as the required number of transferred employees in the second production transfer section, so as to obtain the preset number of transferred employees in each production transfer section.

[0014] The employees transferred from production are sorted in the order of the historical production rate of the first production transfer section, and the employees with the preset number of transferred employees are selected to be transferred from each production transfer section to the first production transfer section; the remaining production transferred employees from the first transfer are sorted in the order of the historical production rate of the second production transfer section, and the employees with the preset number of transferred employees are selected to be transferred from each production transfer section to the second production transfer section, so as to transfer the production transferred employees to each production transfer section.

[0015] Preferably, the raw material usage data is collected, and the specific collection process is as follows: a sensor is arranged at the feed port of each section, and the raw material usage quantity of each section in each past preset purchase cycle is collected, and the average value is calculated to obtain the average raw material usage quantity of each section in the preset purchase cycle. , a is the number of each section, , .

[0016] Preferably, the raw material usage data is analyzed, and the specific analysis process is as follows: Substitute the usage quantity of each section in the preset purchase cycle into the rate calculation formula The current usage rate of each raw material section is obtained , The preset purchase cycle duration is used to substitute the raw material usage quantity of each raw material section and the preset raw material usage rate into the raw material usage rate calculation formula. The raw material utilization rate of each process section is obtained , Preset usage rates for ingredients.

[0017] If the current usage rate of a section is less than the preset raw material usage rate, the section is recorded as a raw material transfer section, and each raw material transfer section is numbered in order of raw material usage rate from small to large to obtain the number i of each raw material transfer section. , , substitute the current usage rate of each raw material transfer section into the material calculation formula The available share of raw material transfer section w in the purchase cycle is obtained , and the total share of the raw materials that can be adjusted is obtained by summarizing If the current usage rate of a section is equal to the preset usage rate of the raw material, the section is recorded as a section without raw material scheduling. If the current usage rate of a section is greater than the preset usage rate of the raw material, the section is recorded as a section for raw material transfer. The sections for raw material transfer are numbered in descending order according to the raw material usage rate to obtain the number j of each section for raw material transfer. , , substitute the current usage rate of each raw material transfer section into the material calculation formula The required transfer share of raw material transfer section w in the purchase cycle is obtained , summarize the total amount of raw materials that need to be transferred in .

[0018] Preferably, the raw materials are scheduled, and the specific scheduling process is as follows: if the total share of raw materials that can be transferred out is less than the total share of raw materials that need to be transferred in, reduce the raw material share of each raw material transfer section, the amount of which is the share of raw materials that can be transferred out of each raw material transfer section, and allocate the total share of raw materials that can be transferred out to the first raw material transfer section according to the production rate of each raw material transfer section from large to small, the amount of which is the share that needs to be transferred in of the first raw material transfer section, and allocate the remaining share of the first allocation to the second raw material transfer section, the amount of which is the share that needs to be transferred in of the second raw material transfer section, when the remaining share of a certain allocation is less than the share that needs to be transferred in of the raw material transfer section, allocate the remaining share of this allocation to the corresponding raw material transfer section, so as to allocate the raw material shares, and substitute the raw material transfer quantity and the raw material transfer quantity into the purchase cycle calculation formula , get the future purchase cycle , The quantity of raw materials required for the order.

[0019] If the total share of raw materials that can be transferred out is equal to the total share of raw materials that need to be transferred in, reduce the raw material share of each raw material transfer section by the amount of raw materials that can be transferred out of each raw material transfer section, and increase the raw material share of each raw material transfer section by the amount of raw materials that need to be transferred in of each raw material transfer section.

[0020] If the total share of raw materials that can be transferred out is equal to the total share of raw materials that need to be transferred in, reduce the raw material share of each raw material transfer section by the amount of raw materials that can be transferred out of each raw material transfer section, increase the raw material share of each raw material transfer section by the amount of raw materials that need to be transferred in of each raw material transfer section, and allocate the remaining share of raw materials after allocation to the section with the highest current production rate.

[0021] The beneficial effects of the present invention are as follows: 1. The present invention collects the production quantity of employees in each work section, analyzes the production rate of each work section, divides each work section into production sections that are transferred out, transferred in, and do not need to be scheduled according to the standard production rate in the database, and schedules according to the production rate of employees in each work section. While meeting the production needs of each work section, the overall production rate is improved, the accuracy of production scheduling is improved, and when there is a problem of unbalanced production rate, employee scheduling can be carried out quickly, thereby improving the effectiveness of employee scheduling.

[0022] 2. The present invention collects the usage quantity of raw materials in each work section, analyzes the usage rate of each work section, divides each work section into a transfer-out, transfer-in, and a use section that does not need to be scheduled according to the standard usage rate in the database, and schedules the raw materials according to the usage rate of each work section. While meeting the processing needs of each work section, the overall processing rate is improved, and when there is a problem with the raw material supply, the raw materials can be quickly scheduled, reducing production risks. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0024] Figure 1 The present invention is a schematic flow chart of the steps for implementing the method. DETAILED DESCRIPTION

[0025] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0026] See also Figure 1 As shown, the present invention provides a method for intelligent optimization of production scheduling in a process industrial enterprise's production process, the method comprising the following steps: Step 1, order data analysis: parse the industrial product orders in the database to obtain a preset production rate and a preset raw material usage rate.

[0027] In a specific embodiment, the industrial product orders in the database are parsed. The specific parsing process is as follows: each order information is obtained from the database, including the quantity of industrial products required for the order. , Remaining time for order delivery , substitute into the preset production rate calculation formula The preset production rate is obtained , get the quantity of raw materials required for industrial product orders from the database , substitute into the standard usage rate calculation formula In the process, the standard utilization rate of raw materials is obtained through the database to obtain the utilization rate of raw materials. , substitute the preset usage rate formula Get the preset usage rate of raw materials .

[0028] Step 2: Production data collection: Collect employee production data.

[0029] In a specific embodiment, employee production data is collected. The specific collection process is as follows: according to the industrial product production process in the database, the assembly line is divided into various sections, and sensors are arranged at each employee's workstation in each section. After the employee produces the product, it will be sensed and recorded by the sensor. A preset time is set for collection, and the employee production data is collected from the sensor information, including the production quantity of employee B in the current section of section a for the preset time. , a is the number of each section, , , b is the employee number, , , the current production quantity of each employee in each section of the preset time is summarized to obtain the production quantity of each section of the preset time .

[0030] Step 3. Production data analysis: Analyze the production data of employees to obtain the current production rate of each section and the current production rate of each employee. According to the current production rate of each section and the preset production rate, obtain each production transfer section. According to the current production rate of each employee in each production transfer section, obtain each transferable employee.

[0031] In a specific embodiment, the production data of employees is analyzed, and the specific analysis process is as follows: the production quantity of the preset time section a is Substitute into the rate calculation formula The current production rate of section a is obtained , The preset duration.

[0032] If the current production rate of a section is greater than the preset production rate, it indicates that the section is a production transfer section. The production transfer sections are numbered in descending order of production rate to obtain the number c of each production transfer section. , , substitute the current production rate of each production transfer section into the calculation formula required for production In the above equation, the overflow rate of each production transfer section is obtained. If the current production rate of a section is equal to the preset production rate, it indicates that the section is a production section that does not need to be dispatched. If the current production rate of a section is less than the preset production rate, it indicates that the section is a production transfer section. The production transfer sections are numbered in ascending order according to the current production rate to obtain the number d of each production transfer section. , , substitute the current production rate of each production section into the calculation formula required for production In the process, the required rate of each production transfer section is obtained.

[0033] The employees in each production section are numbered in descending order according to their current production rate, numbered as e. , , substitute the current production rate of each employee in each production transfer section into the loss rate calculation formula In the above equation, the loss rate of the preset number of employees f in the transfer section c is obtained. If the loss rate of the preset number of employees f in the transfer section c is less than the overflow rate of the production transfer section c, the number of employees that can be transferred from the transfer section c is f. If there are multiple numbers of employees that can be transferred from the transfer section c, the largest number is selected as the number of employees that can be transferred from the production transfer section c. According to the order of employees in each production transfer section, the employees before f in each production transfer section are recorded as transferable employees, and the production transfer employees are obtained by summarizing them.

[0034] It should be supplemented that, by calculating the loss rate, we can obtain the impact of each employee's transfer on each production transfer section. By setting the upper limit of the loss rate as the overflow rate of each section, more employees can be selected for transfer while meeting the basic production needs of each production transfer section.

[0035] Step 4: Employee production scheduling: obtain the historical production data of each production transfer section of each employee who is transferred out of production from the database and schedule the employees.

[0036] In a specific embodiment, the employees are scheduled, and the specific scheduling process is as follows: the historical production rate of each production section of each transferred employee is obtained from the database, and each transferred employee is numbered in order of historical production rate from small to large, and the number is g. , , according to the current production rate of each production transfer section from small to large, substitute the historical production rate of each transferred employee in the first production transfer section into the preset acquisition rate calculation formula The preset acquisition rate of the number of employees to be transferred into the first production transfer section is obtained. If a preset acquisition rate of the first production transfer section is greater than or equal to the required rate, the number of employees to be transferred corresponding to the preset acquisition rate is recorded as the number of employees to be transferred into the first production transfer section. If the first production transfer section has multiple numbers of employees to be transferred, the number of employees to be transferred with the smallest preset acquisition rate is selected as the number of employees to be transferred into the first production transfer section.

[0037] All transferred employees except those who need to be transferred into the first production transfer section are recorded as the remaining employees after the first transfer, and the historical production rate of the second production transfer section of the remaining employees after the first transfer is substituted into the preset acquisition rate calculation formula The preset acquisition rate of each preset number of transferred employees in the second production transfer section is obtained. If a preset acquisition rate of the second production transfer section is greater than or equal to the required rate, the preset number of transferred employees corresponding to the preset acquisition rate is recorded as the required number of transferred employees in the second production transfer section. If the second production transfer section has multiple required numbers of transferred employees, the preset number of transferred employees with the smallest preset acquisition rate is selected as the required number of transferred employees in the second production transfer section, so as to obtain the preset number of transferred employees in each production transfer section.

[0038] Sort the transferred employees in the order of the historical production rate of the first production transfer-in section, select the employees with the preset number of transferred-in employees and transfer them from each production transfer-out section to the first production transfer-in section, sort the remaining transferred employees from the first transfer in the order of the historical production rate of the second production transfer-in section, select the employees with the preset number of transferred-in employees and transfer them from each production transfer-out section to the second production transfer-in section, so as to transfer the transferred employees to each production transfer-in section.

[0039] Step 5: Usage data collection: Collect raw material usage data.

[0040] In a specific embodiment, the raw material usage data is collected, and the specific collection process is as follows: a sensor is arranged at the feed port of each section to collect the raw material usage quantity of each section in each preset purchase cycle in the past, and the average value is calculated to obtain the average raw material usage quantity of each section in the preset purchase cycle. , a is the number of each section, , .

[0041] Step 6. Usage data analysis: Analyze the raw material usage data to obtain the current usage rate of each section, and then obtain the raw material usage rate of each section. According to the current usage rate of each section and the preset raw material usage rate, each section is divided into a raw material transfer section, a raw material non-dispatching section, and a raw material transfer section.

[0042] In a specific embodiment, the raw material usage data is analyzed, and the specific analysis process is as follows: Substitute the usage quantity of each stage of the preset purchase cycle into the rate calculation formula The current usage rate of each raw material section is obtained , The preset purchase cycle duration is used to substitute the raw material usage quantity of each raw material section and the preset raw material usage rate into the raw material usage rate calculation formula. The raw material utilization rate of each process section is obtained , Preset usage rates for ingredients.

[0043] It should be added that , M is the quantity of raw materials that the warehouse can hold.

[0044] If the current usage rate of a section is less than the preset raw material usage rate, the section is recorded as a raw material transfer section, and each raw material transfer section is numbered in order of raw material usage rate from small to large to obtain the number i of each raw material transfer section. , , substitute the current usage rate of each raw material transfer section into the material calculation formula The available share of raw material transfer section w in the purchase cycle is obtained , and the total share of the raw materials that can be adjusted is obtained by summarizing If the current usage rate of a section is equal to the preset usage rate of the raw material, the section is recorded as a section without raw material scheduling. If the current usage rate of a section is greater than the preset usage rate of the raw material, the section is recorded as a section for raw material transfer. The sections for raw material transfer are numbered in descending order according to the raw material usage rate to obtain the number j of each section for raw material transfer. , , substitute the current usage rate of each raw material transfer section into the material calculation formula The required transfer share of raw material transfer section w in the purchase cycle is obtained , summarize the total amount of raw materials that need to be transferred in .

[0045] Step 7. Raw material usage scheduling: Schedule the raw materials according to the raw material usage rate of each work section.

[0046] In a specific embodiment, the raw materials are scheduled, and the specific scheduling process is as follows: if the total share of raw materials that can be transferred out is less than the total share of raw materials that need to be transferred in, the raw material share of each raw material transfer section is reduced, and the amount is the share of raw materials that can be transferred out of each raw material transfer section. According to the production rate of each raw material transfer section from large to small, the total share of raw materials that can be transferred out is allocated to the first raw material transfer section, and the amount is the share that needs to be transferred in the first raw material transfer section. The remaining share of the first allocation is allocated to the second raw material transfer section, and the amount is the share that needs to be transferred in the second raw material transfer section. When the remaining share of a certain allocation is less than the share that needs to be transferred in the raw material transfer section, the remaining share of this allocation is allocated to the corresponding raw material transfer section, so as to allocate the raw material shares, and substitute the raw material transfer quantity and the raw material transfer quantity into the purchase cycle calculation formula , get the future purchase cycle , The quantity of raw materials required for the order.

[0047] If the total share of raw materials that can be transferred out is equal to the total share of raw materials that need to be transferred in, reduce the raw material share of each raw material transfer section by the amount of raw materials that can be transferred out of each raw material transfer section, and increase the raw material share of each raw material transfer section by the amount of raw materials that need to be transferred in of each raw material transfer section.

[0048] If the total share of raw materials that can be transferred out is equal to the total share of raw materials that need to be transferred in, reduce the raw material share of each raw material transfer section by the amount of raw materials that can be transferred out of each raw material transfer section, increase the raw material share of each raw material transfer section by the amount of raw materials that need to be transferred in of each raw material transfer section, and allocate the remaining share of raw materials after allocation to the section with the highest current production rate.

[0049] It should be added that if raw material problems occur in some sections, for example, the raw materials in some sections are damaged and cannot be used, the raw material shares of other sections can be quickly dispatched to the problem sections without affecting the normal production of other sections.

[0050] The database includes but is not limited to the quantity requirements of industrial products for orders, order delivery dates, warehouse capacity, employee production rate history records, and raw material usage rate history records.

[0051] The above contents are merely examples and explanations of the concept of the present invention. Those skilled in the art may make various modifications or additions to the specific embodiments described or replace them in a similar manner. As long as they do not deviate from the concept of the invention or exceed the scope defined in this specification, they shall all fall within the protection scope of the present invention.

Claims

1. A production scheduling intelligent optimization method for a process industry enterprise production process, characterized in that: The steps include: Step 1: Order data analysis: Analyze the industrial product orders in the database to obtain the preset production rate and the preset raw material usage rate; Step 2: Production data collection: Collect employee production data; Step 3, production data analysis: Analyze the production data of employees to obtain the current production rate of each section and the current production rate of each employee. According to the current production rate of each section and the preset production rate, obtain each production transfer section. According to the current production rate of each employee in each production transfer section, obtain each employee who can be transferred. Step 4: Employee production scheduling: Obtain the historical production data of each production transfer section of each employee transferred out of production from the database and schedule the employees; Step 5: Usage data collection: collect raw material usage data; Step 6: Usage data analysis: Analyze the raw material usage data to obtain the current usage rate of each section, and then obtain the raw material usage rate of each section. According to the current usage rate of each section and the preset usage rate of the raw materials, each section is divided into a section where each raw material is transferred out, a section where each raw material is not dispatched, and a section where each raw material is transferred in; Step 7. Raw material usage scheduling: Schedule the raw materials according to the raw material usage rate of each work section.

2. The intelligent optimization method for production scheduling of a process industry enterprise according to claim 1 is characterized in that: The industrial product orders in the database are parsed, and the specific parsing process is as follows: Get each order information from the database, including the quantity of industrial products required for the order , Remaining time for order delivery , substitute into the preset production rate calculation formula The preset production rate is obtained , get the quantity of raw materials required for industrial product orders from the database , substitute into the standard usage rate calculation formula , get the standard usage rate of raw materials and get the raw material usage rate through the database , substitute the preset usage rate formula Get the preset usage rate of raw materials .

3. The intelligent optimization method for production scheduling of a process industry enterprise production process according to claim 2 is characterized in that: The specific collection process of employee production data is as follows: According to the industrial product production process in the database, the assembly line is divided into various sections. Sensors are placed at each employee's workstation in each section. After the employee produces the product, it will be sensed and recorded by the sensor. The preset time is set for collection. The employee production data is collected from the sensor information, including the production quantity of employee B in the current section of section a with the preset time. , a is the number of each section, , , b is the employee number, , , the current production quantity of each employee in each section of the preset time is summarized to obtain the production quantity of each section of the preset time .

4. The intelligent optimization method for production scheduling of a process industry enterprise according to claim 3 is characterized in that: The employee production data is analyzed, and the specific analysis process is as follows: Set the production quantity of the preset duration section a Substitute into the rate calculation formula The current production rate of section a is obtained , The preset duration; If the current production rate of a section is greater than the preset production rate, it indicates that the section is a production transfer section. The production transfer sections are numbered in descending order of production rate to obtain the number c of each production transfer section. , , substitute the current production rate of each production transfer section into the calculation formula required for production In the above equation, the overflow rate of each production transfer section is obtained. If the current production rate of a section is equal to the preset production rate, it indicates that the section is a production section that does not need to be dispatched. If the current production rate of a section is less than the preset production rate, it indicates that the section is a production transfer section. The production transfer sections are numbered in ascending order according to the current production rate to obtain the number d of each production transfer section. , , substitute the current production rate of each production section into the calculation formula required for production In the above, the required rate of each production transfer section is obtained; The employees in each production section are numbered in descending order according to their current production rate, numbered as e. , , substitute the current production rate of each employee in each production transfer section into the loss rate calculation formula In the above equation, the loss rate of the preset number of employees f in the transfer section c is obtained. If the loss rate of the preset number of employees f in the transfer section c is less than the overflow rate of the production transfer section c, the number of employees that can be transferred from the transfer section c is f. If there are multiple numbers of employees that can be transferred from the transfer section c, the largest number is selected as the number of employees that can be transferred from the production transfer section c. According to the order of employees in each production transfer section, the employees before f in each production transfer section are recorded as transferable employees, and the production transfer employees are obtained by summarizing them.

5. The intelligent optimization method for production scheduling of a process industry enterprise according to claim 4 is characterized in that: The specific scheduling process for employees is as follows: Obtain the historical production rate of each production transfer section of each production transfer employee from the database, and number each production transfer employee in ascending order of historical production rate, numbered as g. , , according to the current production rate of each production transfer section from small to large, substitute the historical production rate of each production transfer employee in the first production transfer section into the preset acquisition rate calculation formula , obtain the preset acquisition rate of the number of employees to be transferred into the first production transfer section; if a preset acquisition rate of the first production transfer section is greater than or equal to the required rate, the number of employees to be transferred corresponding to the preset acquisition rate is recorded as the number of employees to be transferred into the first production transfer section; if there are multiple numbers of employees to be transferred into the first production transfer section, the number of employees to be transferred with the smallest preset acquisition rate is selected as the number of employees to be transferred into the first production transfer section; All the employees transferred out of production except the employees who need to be transferred into the first production transfer section are recorded as the remaining employees after the first transfer, and the historical production rate of the second production transfer section of the remaining employees after the first transfer is substituted into the preset acquisition rate calculation formula , obtain the preset acquisition rate of each preset number of transferred-in employees of the second production transfer-in section; if a preset acquisition rate of the second production transfer-in section is greater than or equal to the required rate, record the preset number of transferred-in employees corresponding to the preset acquisition rate as the required number of transferred-in employees of the second production transfer-in section; if the second production transfer-in section has multiple required numbers of transferred-in employees, select the preset number of transferred-in employees with the smallest preset acquisition rate as the required number of transferred-in employees of the second production transfer-in section, thereby obtaining the preset number of transferred-in employees of each production transfer-in section; The employees transferred from production are sorted in the order of the historical production rate of the first production transfer section, and the employees with the preset number of transferred employees are selected to be transferred from each production transfer section to the first production transfer section. The remaining production transferred employees from the first transfer are sorted in the order of the historical production rate of the second production transfer section, and the employees with the preset number of transferred employees are selected to be transferred from each production transfer section to the second production transfer section, so as to transfer the production transferred employees to each production transfer section.

6. The intelligent optimization method for production scheduling of a process industry enterprise according to claim 1 is characterized in that: The specific collection process of raw material usage data is as follows: Sensors are placed at the feed inlet of each section to collect the raw material usage of each section in each preset purchase cycle in the past, and the average value is calculated to obtain the average raw material usage of each section in the preset purchase cycle , a is the number of each section, , .

7. The intelligent optimization method for production scheduling of a process industry enterprise according to claim 6 is characterized in that: The specific analysis process of analyzing the raw material usage data is as follows: Substitute the usage quantity of each stage in the preset purchase cycle into the rate calculation formula The current usage rate of each raw material section is obtained , The preset purchase cycle duration is used to substitute the raw material usage quantity of each raw material section and the preset raw material usage rate into the raw material usage rate calculation formula. The raw material utilization rate of each process section is obtained , Preset usage rates for raw materials; If the current usage rate of a section is less than the preset raw material usage rate, the section is recorded as a raw material transfer section, and each raw material transfer section is numbered in order of raw material usage rate from small to large to obtain the number i of each raw material transfer section. , , substitute the current usage rate of each raw material transfer section into the material calculation formula The available share of raw material transfer section w in the purchase cycle is obtained , and the total share of the raw materials that can be adjusted is obtained by summarizing If the current usage rate of a section is equal to the preset usage rate of the raw material, the section is recorded as a section without raw material scheduling. If the current usage rate of a section is greater than the preset usage rate of the raw material, the section is recorded as a section for raw material transfer. The sections for raw material transfer are numbered in descending order according to the raw material usage rate to obtain the number j of each section for raw material transfer. , , substitute the current usage rate of each raw material transfer section into the material calculation formula The required transfer share of raw material transfer section w in the purchase cycle is obtained , summarize the total amount of raw materials that need to be transferred in .

8. The intelligent optimization method for production scheduling of a process industry enterprise according to claim 7 is characterized in that: The raw materials are scheduled, and the specific scheduling process is as follows: If the total share of raw materials that can be transferred out is less than the total share of raw materials that need to be transferred in, reduce the share of raw materials of each raw material transfer section, the amount of which is the share of raw materials that can be transferred out of each raw material transfer section, and allocate the total share of raw materials that can be transferred out to the first raw material transfer section according to the production rate of each raw material transfer section from large to small, the amount of which is the share that needs to be transferred in the first raw material transfer section, and allocate the remaining share of the first allocation to the second raw material transfer section, the amount of which is the share that needs to be transferred in the second raw material transfer section. When the remaining share of a certain allocation is less than the share that needs to be transferred in the raw material transfer section, allocate the remaining share of this allocation to the corresponding raw material transfer section, so as to allocate the raw material shares, and substitute the raw material transfer quantity and raw material transfer quantity into the purchase cycle calculation formula , get the future purchase cycle , The quantity of raw materials required for the order; If the total share of raw materials that can be transferred out is equal to the total share of raw materials that need to be transferred in, reduce the share of raw materials in each raw material transfer section by the share of raw materials that can be transferred out of each raw material transfer section, and increase the share of raw materials in each raw material transfer section by the share of raw materials that need to be transferred in of each raw material transfer section; If the total share of raw materials that can be transferred out is equal to the total share of raw materials that need to be transferred in, reduce the raw material share of each raw material transfer section by the amount of raw materials that can be transferred out of each raw material transfer section, increase the raw material share of each raw material transfer section by the amount of raw materials that need to be transferred in of each raw material transfer section, and allocate the remaining share of raw materials after allocation to the section with the highest current production rate.