Concrete pouring equipment for large-span stiff skeleton arch bridge

By designing a concrete pouring equipment including a conveying pipe, a mixing system and a telescopic pipe, the problem of difficult pouring and uneven pouring in the middle of a long-span stiff skeleton arch bridge was solved, efficient and uniform concrete pouring was achieved, and the bridge's service life was extended. service life.

CN119332934AActive Publication Date: 2025-01-21CHINA RAILWAY CONSTR BRIDGE ENG BUREAU GRP CO LTD +3
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411741656.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-29
Publication Date
2025-01-21
Estimated Expiration
2044-11-29

AI Technical Summary

Technical Problem

In the construction of large-span strong frame arch bridges, existing concrete pouring equipment is difficult to effectively solve the problems of casting difficulties in the middle, concrete agglomeration, uneven pouring and poor casting quality, resulting in reduced bridge quality and shortened service life.

Method used

Design a large -span -strong skeleton arch bridge concrete irrigation equipment including fixed racks, irrigation mechanisms and mobile institutions. The irrigation mechanism sends concrete to the storage tank by transporting pipelines and L -shaped pipelines, and uses the drive motor to drive the rotating rod and a spiral stirring rod to prevent concrete blocks. The mobile institution achieved the decline of the telescopic pipe and the movement of the irrigation equipment through the hydraulic cylinder and electric pulley to ensure precise concrete irrigation.

Benefits of technology

Effectively avoid the concrete during the pouring process, ensure the uniformity and quality of the irrigation, extend the service life of the large span -strong skeleton arch bridge, and improve the irrigation efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119332934A_ABST
    Figure CN119332934A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of concrete pouring, and discloses large-span stiff skeleton arch bridge concrete pouring equipment which comprises a fixing frame, a pouring mechanism and a moving mechanism are arranged on the outer side of the fixing frame, the pouring mechanism comprises a storage tank, and the top end of the storage tank fixedly communicates with an L-shaped pipeline; the end, away from the storage tank, of the L-shaped pipeline fixedly communicates with a conveying pipeline, and the inner wall of the storage tank is fixedly connected with a bearing. According to the concrete pouring equipment for the large-span stiff skeleton arch bridge, concrete can be conveyed into the storage tank by arranging the conveying pipeline and the L-shaped pipeline, the driving motor is used for driving the rotating rod to rotate, and then the spiral stirring rod is driven to rotate, so that the concrete in the storage tank can be continuously stirred; the problem that the service life of the large-span stiff skeleton arch bridge is shortened due to the fact that the pile foundation of the large-span stiff skeleton arch bridge is long, concrete in a concrete pouring pipeline is prone to caking and pouring is not uniform enough is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of concrete pouring, in particular to a large-span rigid skeleton arch bridge concrete pouring device. Background Art

[0002] Concrete pouring refers to pouring the mixed concrete into a mold. It is usually used in pile foundation construction in construction projects. During the construction of rigid frame arch bridges, concrete transport trucks are needed to transport the concrete directly to the construction site. After that, the concrete is poured using pumping and continuous pouring methods.

[0003] At present, the current pouring devices are often only able to facilitate pouring at both ends of the large-span rigid skeleton arch bridge pile foundation, and the length of the large-span rigid skeleton arch bridge pile foundation is relatively long, and the middle part is difficult to pour. When the concrete in the concrete transport vehicle is transported to the middle part of the large-span rigid skeleton arch bridge pile foundation, the concrete inside the concrete pouring pipe is prone to agglomeration, the pouring is not uniform, and the pouring quality is poor, which can easily lead to the problem of reduced quality and reduced service life of the large-span rigid skeleton arch bridge. Summary of the invention

[0004] The purpose of the present invention is to provide a large-span rigid skeleton arch bridge concrete pouring equipment to solve the problems raised in the above background technology.

[0005] In order to solve the above technical problems, the present invention provides the following technical solutions: a large-span rigid skeleton arch bridge concrete pouring equipment, comprising a fixed frame, the outer sides of which are respectively provided with a pouring mechanism and a moving mechanism;

[0006] The perfusion mechanism includes a storage tank, the top of the storage tank is fixedly connected with an L-shaped pipe, the end of the L-shaped pipe away from the storage tank is fixedly connected with a conveying pipe, the inner wall of the storage tank is fixedly connected with a bearing, the inner ring of the bearing is fixedly connected with a rotating rod, the top of the storage tank is fixedly connected with a support plate, the left side of the support plate is fixedly connected with a driving motor, the output end of the driving motor is fixedly connected to the top of the rotating rod, the bottom end of the rotating rod is fixedly connected with a spiral stirring rod, the bottom end of the storage tank is fixedly connected with a funnel, the bottom end of the funnel is fixedly connected with a discharge pipe, the bottom end of the discharge pipe is fixedly connected with a telescopic pipe, the bottom end of the telescopic pipe is fixedly connected with a sliding plate, the bottom end of the fixed frame is fixedly connected with two hydraulic cylinders, and the telescopic end of each of the hydraulic cylinders is fixedly connected to the upper surface of the sliding plate;

[0007] The moving mechanism includes two fixed plates, each of which has a slide groove on its upper surface, and three electric pulleys are slidably connected to the inside of each slide groove. Four fixed rods are fixedly connected to the outer surface of the fixed frame, and two groups of fixed rods are fixedly connected to sliding blocks at one end away from each other. The inner wall of each sliding block is fixedly connected to the top of the electric pulley, the inner wall of each slide groove is fixedly connected to a first limit plate, and the bottom surface of each fixed plate is fixedly connected to a second limit plate. The inner wall of each sliding block is provided with a groove, and the outer surface of each second limit plate contacts the inner wall of the groove, and the outer surface of each first limit plate contacts the inner wall of the sliding block.

[0008] Preferably, a sealing ring is fixedly connected to the outer surface of the L-shaped pipe, and the bottom end of the sealing ring is fixedly connected to the top end of the storage tank.

[0009] Preferably, the outer surface of each hydraulic cylinder is fixedly connected to a dustproof shell, and the upper surface of each dustproof shell is fixedly connected to the bottom end of the fixing frame.

[0010] Preferably, a protective sleeve is fixedly connected to the bottom surface of each dustproof housing, and a bottom end of each protective sleeve is fixedly connected to the upper surface of the sliding plate.

[0011] Preferably, the outer surface of each of the protective sleeves is fixedly connected to a reinforcement plate, and the bottom surface of each of the reinforcement plates is fixedly connected to the upper surface of the sliding plate.

[0012] Preferably, the inner wall of each reinforcement plate is threadedly connected with four reinforcement bolts, and the inner wall of each group of reinforcement bolts is threadedly connected to the inner wall of the sliding plate.

[0013] Preferably, a protection box is fixedly connected to the outer surface of the driving motor, and the bottom surface of the protection box is fixedly connected to the top of the storage tank.

[0014] Preferably, a reinforcement ring is fixedly connected to the outer surface of the discharge pipe, and the inner wall of the reinforcement ring is fixedly connected to the outer surface of the telescopic pipe.

[0015] Preferably, the outer surface of each group of the electric pulleys is fixedly connected to two fixing rings, and the top of each group of the fixing rings is fixedly connected to the inner wall of the sliding block.

[0016] Preferably, two limiting rings are fixedly connected to the outer surface of each group of the fixing rods, and one end of each group of the limiting rings away from each other is fixedly connected to one side of the two sliding blocks close to each other.

[0017] Compared with the prior art, the beneficial effects achieved by the present invention are:

[0018] The present invention can transport concrete to a storage tank by being provided with a conveying pipe and an L-shaped pipe, and utilizes a driving motor to drive a rotating rod to rotate, thereby driving a spiral stirring rod to rotate, so that the concrete in the storage tank can be continuously stirred, and the long length of the pile foundation of a large-span rigid skeleton arch bridge and the difficulty in pouring the middle part can be effectively avoided. When the concrete in the concrete transport vehicle is transported to the middle part of the pile foundation of the large-span rigid skeleton arch bridge, the concrete inside the concrete pouring pipe is prone to agglomeration, the pouring is not uniform, and the pouring quality is poor, which easily leads to the problem of reduced quality and reduced service life of the large-span rigid skeleton arch bridge. The telescopic end of the hydraulic cylinder drives the sliding plate to move downward, and then pulls one end of the telescopic pipe to move downward, so that the telescopic pipe can be extended downward, which is convenient for the precise pouring of concrete in the storage tank, and effectively prevents the concrete from being sprayed outward during the pouring process, resulting in the waste of concrete resources and pollution of the external environment. The electric pulley can drive the sliding block to move in the slide groove on the fixed plate, which can facilitate the adjustment of the position of the pouring equipment, enhance the use effect of the device, and improve the pouring efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of the overall three-dimensional structure of the large-span rigid skeleton arch bridge concrete pouring equipment of the present invention;

[0020] Figure 2 It is a structural schematic diagram of the delivery pipeline of the present invention;

[0021] Figure 3 It is a structural schematic diagram of an L-shaped pipeline of the present invention;

[0022] Figure 4 It is a structural schematic diagram of the spiral stirring rod of the present invention;

[0023] Figure 5 It is a structural schematic diagram of the telescopic pipe of the present invention;

[0024] Figure 6 It is a structural schematic diagram of the hydraulic cylinder of the present invention;

[0025] Figure 7 It is a structural schematic diagram of the sliding block of the present invention;

[0026] Figure 8 It is a schematic diagram of the structure of the groove of the present invention;

[0027] Fig. 9 It is a schematic structural diagram of the electric pulley of the present invention.

[0028] Wherein: 1. fixed frame; 2. perfusion mechanism; 201. storage tank; 202. conveying pipeline; 203. L-shaped pipeline; 204. sliding plate; 205. support plate; 206. driving motor; 207. funnel; 208. discharge pipeline; 209. bearing; 210. rotating rod; 211. spiral stirring rod; 212. telescopic pipeline; 213. hydraulic cylinder; 3. moving mechanism; 301. fixed plate; 302. sliding block; 303. fixed rod; 304. first limit plate; 305. second limit plate; 306. slide groove; 307. groove; 308. electric pulley; 4. protective box; 5. sealing ring; 6. protective cover; 7. reinforcement plate; 8. dustproof shell; 9. reinforcement ring; 10. reinforcement bolt; 11. limit ring; 12. fixing ring. DETAILED DESCRIPTION

[0029] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0030] Embodiment 1

[0031] See also Figure 1-9 A large-span rigid skeleton arch bridge concrete pouring equipment comprises a fixed frame 1, a pouring mechanism 2 and a moving mechanism 3 are respectively arranged on the outer side of the fixed frame 1, the pouring mechanism 2 comprises a storage tank 201, the top of the storage tank 201 is fixedly connected with an L-shaped pipe 203, the end of the L-shaped pipe 203 away from the storage tank 201 is fixedly connected with a conveying pipe 202, the inner wall of the storage tank 201 is fixedly connected with a bearing 209, the inner ring of the bearing 209 is fixedly connected with a rotating rod 210, the top of the storage tank 201 is fixedly connected with a support plate 205, and the left side of the support plate 205 is fixedly connected with A driving motor 206, the output end of the driving motor 206 is fixedly connected to the top of a rotating rod 210, the bottom end of the rotating rod 210 is fixedly connected to a spiral stirring rod 211, the bottom end of the storage tank 201 is fixedly connected to a funnel 207, the bottom end of the funnel 207 is fixedly connected to a discharge pipe 208, the bottom end of the discharge pipe 208 is fixedly connected to a telescopic pipe 212, the bottom end of the telescopic pipe 212 is fixedly connected to a sliding plate 204, and the bottom end of the fixed frame 1 is fixedly connected to two hydraulic cylinders 213, and the telescopic end of each hydraulic cylinder 213 is fixedly connected to the upper surface of the sliding plate 204;

[0032] The outer surface of the L-shaped pipe 203 is fixedly connected with a sealing ring 5, and the bottom end of the sealing ring 5 is fixedly connected to the top end of the storage tank 201. The sealing ring 5 can seal the L-shaped pipe 203 and the storage tank 201, effectively preventing leakage during the concrete transportation process;

[0033] The outer surface of each hydraulic cylinder 213 is fixedly connected with a dustproof housing 8, and the upper surface of each dustproof housing 8 is fixedly connected to the bottom end of the fixing frame 1. The dustproof housing 8 can protect the hydraulic cylinder 213, and has a strong protective effect, effectively preventing it from being disturbed by the external environment during use;

[0034] The bottom surface of each dustproof housing 8 is fixedly connected with a protective cover 6, and the bottom end of each protective cover 6 is fixedly connected to the upper surface of the sliding plate 204. The protective cover 6 can protect the telescopic end of the hydraulic cylinder 213, play a strong protective role, and effectively prevent it from being damaged by the outside during the working process;

[0035] The outer surface of each protective cover 6 is fixedly connected with a reinforcing plate 7, and the bottom surface of each reinforcing plate 7 is fixedly connected to the upper surface of the sliding plate 204. The reinforcing plate 7 can reinforce the protective cover 6 and the sliding plate 204, thereby enhancing the stability of the device and effectively avoiding the problem of shaking during operation.

[0036] The inner wall of each reinforcement plate 7 is threadedly connected with four reinforcement bolts 10, and the inner wall of each group of reinforcement bolts 10 is threadedly connected with the inner wall of the sliding plate 204. The reinforcement bolts 10 can be used to reinforce the reinforcement plate 7 and the sliding plate 204, effectively preventing the problem of their position being offset and unstable during use;

[0037] The outer surface of the driving motor 206 is fixedly connected with a protection box 4, and the bottom surface of the protection box 4 is fixedly connected to the top of the storage tank 201. The protection box 4 can protect the driving motor 206, effectively preventing it from being affected by the outside world during operation, resulting in a reduced service life.

[0038] The outer surface of the discharge pipe 208 is fixedly connected with a reinforcement ring 9, and the inner wall of the reinforcement ring 9 is fixedly connected to the outer surface of the telescopic pipe 212. The reinforcement ring 9 can reinforce the discharge pipe 208 and the telescopic pipe 212 to prevent shaking and deviation during concrete pouring.

[0039] The specific implementation method of this embodiment is as follows: first, the delivery pipeline 202 is connected to the concrete delivery pump on the external concrete transport vehicle. When it is necessary to pour the pile foundation of the large-span rigid skeleton arch bridge, the concrete in the concrete transport vehicle is first delivered to the delivery pipeline 202 through the concrete delivery pump. The concrete delivery pump continuously delivers the concrete along the pipeline by means of a piston or extrusion. During the pouring of the large-span rigid skeleton arch bridge, it can deliver the concrete from the mixing station to the pouring position over a long distance. For some arch bridge parts that are higher than the ground or far away from the concrete mixing site, the delivery pump can push the concrete over at a certain pressure, and can deliver a large amount of concrete in a relatively short time. The concrete is poured into the L-shaped pipe 203 to ensure the continuity of the pouring construction, which helps to improve the construction progress of the entire arch bridge. The L-shaped pipe 203 is then transported to the L-shaped pipe 203. The inner lining layer of the L-shaped pipe 203 is made of wear-resistant rubber material, which can effectively reduce the wear and blockage of the pipe wall and ensure the quality of concrete transportation. The internal reinforcement layer is composed of multiple layers of steel wire and epoxy resin and other materials, which can withstand high pressure and tension to ensure that no cracks or breaks occur during the transportation of concrete. The outer surface is made of natural or synthetic rubber material, which has multiple properties such as anti-aging, anti-corrosion and anti-ultraviolet radiation, ensuring the durability and service life of the conveying pipe. The concrete is then transported to the storage tank 201 and then discharged through the funnel 207. The concrete falls into the discharge pipe 208 and is then discharged downward, so that the pile foundation of the large-span rigid skeleton arch bridge can be poured. At the same time, the output end of the driving motor 206 is rotated to drive the rotating rod 210 inside the bearing 209 to rotate, thereby driving the spiral stirring rod 211 inside the storage tank 201 to rotate, thereby continuously stirring the concrete in the storage tank 201, so that the concrete inside the storage tank 201 is always kept in a uniform state, thereby enhancing the applicability of the device and avoiding the long length of the large-span rigid skeleton arch bridge pile foundation, which makes it difficult to pour the middle part, and when the concrete is transported to the storage tank 201, the concrete in the storage tank 201 is continuously stirred. When the concrete in the vehicle is transported to the middle part of the pile foundation of the large-span rigid skeleton arch bridge, the concrete inside the concrete pouring pipe is prone to agglomeration, the pouring is not uniform, and the pouring quality is poor, which can easily lead to reduced quality and reduced service life of the large-span rigid skeleton arch bridge. In addition, during the pouring process, the telescopic end of the hydraulic cylinder 213 is extended to drive the sliding plate 204 to move downward, thereby pulling one end of the telescopic pipe 212 to move downward, and the telescopic pipe 212 can be extended downward, which is convenient for the precise pouring of concrete in the storage tank 201, and effectively prevents the concrete from spraying outward during the pouring process, resulting in waste of concrete resources and pollution of the external environment.

[0040] Embodiment 2

[0041] See also Figure 1-9The moving mechanism 3 includes two fixed plates 301, each of which is provided with a slide groove 306 on the upper surface of each fixed plate 301, and three electric pulleys 308 are slidably connected inside each slide groove 306. Four fixed rods 303 are fixedly connected to the outer surface of the fixed frame 1, and the ends of the two groups of fixed rods 303 away from each other are fixedly connected to the sliding blocks 302, and the inner wall of each sliding block 302 is fixedly connected to the top of the electric pulley 308, and the inner wall of each slide groove 306 is fixedly connected to the first limiting plate 304, and the bottom surface of each fixed plate 301 is fixedly connected to the second limiting plate 305, and the inner wall of each sliding block 302 is provided with a groove 307, and the outer surface of each second limiting plate 305 is in contact with the inner wall of the groove 307, and the outer surface of each first limiting plate 304 is in contact with the inner wall of the sliding block 302;

[0042] The outer surface of each set of electric pulleys 308 is fixedly connected to two fixing rings 12, and the top of each set of fixing rings 12 is fixedly connected to the inner wall of the sliding block 302. The fixing rings 12 can fix the electric pulleys 308 and the sliding block 302 to avoid the problem of their position being offset and unstable during movement;

[0043] The outer surface of each set of fixing rods 303 is fixedly connected to two limiting rings 11, and the ends of each set of limiting rings 11 that are away from each other are fixedly connected to the side surfaces of the two sliding blocks 302 that are close to each other. The limiting rings 11 can limit the position of the fixing rods 303, thereby playing a role of fixed limiting.

[0044] The specific implementation of this embodiment is: first, two fixed plates 301 are fixedly installed on the large-span rigid skeleton arch bridge, and then the sliding block 302 is installed on the fixed plate 301, so that the electric pulley 308 slides in the slide groove 306, thereby driving the perfusion equipment to move, and during the movement, the first limit plate 304, the second limit plate 305 and the groove 307 can make the sliding block 302 always maintain stable translation, thereby enhancing the use effect of the device, facilitating the adjustment of the position of the perfusion equipment, enhancing the use effect of the device, and improving the perfusion efficiency.

[0045] Embodiment 3

[0046] See also Figure 1-9The specific implementation method of this embodiment is as follows: first, the delivery pipeline 202 is connected to the concrete delivery pump on the external concrete transport vehicle. When it is necessary to pour the pile foundation of the large-span rigid skeleton arch bridge, the concrete in the concrete transport vehicle is first delivered to the delivery pipeline 202 through the concrete delivery pump. The concrete delivery pump continuously delivers the concrete along the pipeline by means of a piston or extrusion. In the pouring of the large-span rigid skeleton arch bridge, it can transport the concrete from the mixing station to the pouring position over a long distance. For some arch bridge parts that are higher than the ground or far away from the concrete mixing site, the delivery pump can push the concrete over with a certain pressure, and can deliver a large amount of concrete in a short time, ensuring the continuity of the pouring construction, which helps to improve the overall The concrete is then transported to the L-shaped pipe 203, the inner lining of which is made of wear-resistant rubber material, which can effectively reduce the wear and blockage of the pipe wall and ensure the quality of concrete transportation. The inner reinforcement layer is composed of multiple layers of steel wire and epoxy resin and other materials, which can withstand high pressure and tension to ensure that no cracks or breaks occur during the concrete transportation process. The outer surface is made of natural or synthetic rubber material, which has multiple properties such as anti-aging, anti-corrosion and anti-ultraviolet radiation, which ensures the durability and service life of the conveying pipe. The concrete is then transported to the storage tank 201, and then falls into the discharge pipe 208 through the funnel 207, and then discharged downward, so that the pile foundation of the large-span rigid skeleton arch bridge can be poured, and While pouring the pile foundation of the large-span rigid skeleton arch bridge, the output end of the driving motor 206 is rotated to drive the rotating rod 210 inside the bearing 209 to rotate, thereby driving the spiral stirring rod 211 inside the storage tank 201 to rotate, thereby continuously stirring the concrete in the storage tank 201, so that the concrete inside the storage tank 201 is always kept in a uniform state, thereby enhancing the applicability of the device and avoiding the long length of the large-span rigid skeleton arch bridge pile foundation and the difficulty in pouring the middle part. When the concrete in the concrete transport vehicle is transported to the middle part of the large-span rigid skeleton arch bridge pile foundation, the concrete inside the concrete pouring pipe is prone to caking, the pouring is not uniform, the pouring quality is poor, and it is easy to The problem of reduced quality and reduced service life of the long-span rigid skeleton arch bridge is solved. During the pouring process, the telescopic end of the hydraulic cylinder 213 is extended to drive the sliding plate 204 to move downward, thereby pulling one end of the telescopic pipe 212 to move downward, so that the telescopic pipe 212 can be extended downward, which is convenient for the precise pouring of concrete in the storage tank 201, and effectively prevents the concrete from being sprayed outward during the pouring process, resulting in waste of concrete resources and pollution of the external environment. By fixing the two fixed plates 301 on the long-span rigid skeleton arch bridge, and then installing the sliding block 302 on the fixed plate 301, the electric pulley 308 is made to slide in the slide groove 306, so that the pouring equipment can be driven to move.In addition, during the movement, the first limiting plate 304, the second limiting plate 305 and the groove 307 can keep the sliding block 302 in stable translation, thereby enhancing the use effect of the device, facilitating the adjustment of the position of the perfusion device, enhancing the use effect of the device, and improving the perfusion efficiency.

[0047] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0048] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A large-span rigid skeleton arch bridge concrete pouring device, comprising a fixing frame (1), characterized in that: The outer sides of the fixed frame (1) are respectively provided with a pouring mechanism (2) and a moving mechanism (3); The pouring mechanism (2) comprises a storage tank (201), the top end of the storage tank (201) is fixedly connected to an L-shaped pipe (203), one end of the L-shaped pipe (203) away from the storage tank (201) is fixedly connected to a delivery pipe (202), the inner wall of the storage tank (201) is fixedly connected to a bearing (209), the inner ring of the bearing (209) is fixedly connected to a rotating rod (210), the top end of the storage tank (201) is fixedly connected to a support plate (205), the left side of the support plate (205) is fixedly connected to a drive motor (206), and the output end of the drive motor (206) is connected to the rotating rod The top end of the rotating rod (210) is fixedly connected, the bottom end of the rotating rod (210) is fixedly connected with a spiral stirring rod (211), the bottom end of the storage tank (201) is fixedly connected with a funnel (207), the bottom end of the funnel (207) is fixedly connected with a discharge pipe (208), the bottom end of the discharge pipe (208) is fixedly connected with a telescopic pipe (212), the bottom end of the telescopic pipe (212) is fixedly connected with a sliding plate (204), the bottom end of the fixed frame (1) is fixedly connected with two hydraulic cylinders (213), and the telescopic end of each hydraulic cylinder (213) is fixedly connected to the upper surface of the sliding plate (204); The moving mechanism (3) comprises two fixed plates (301), each of the fixed plates (301) having a slide groove (306) on its upper surface, each of the slide grooves (306) having three electric pulleys (308) slidably connected thereto, the outer surface of the fixed frame (1) having four fixed rods (303) fixedly connected thereto, two sets of fixed rods (303) having ends away from each other fixedly connected thereto a sliding block (302), the inner wall of each sliding block (302) being in contact with the electric pulley (308), and the inner wall of each sliding block (302) being in contact with the electric pulley (308). 8), the inner wall of each of the slide grooves (306) is fixedly connected to a first limit plate (304), the bottom surface of each of the fixed plates (301) is fixedly connected to a second limit plate (305), the inner wall of each of the sliding blocks (302) is provided with a groove (307), the outer surface of each of the second limit plates (305) is in contact with the inner wall of the groove (307), and the outer surface of each of the first limit plates (304) is in contact with the inner wall of the sliding block (302).

2. The large-span rigid skeleton arch bridge concrete pouring equipment according to claim 1 is characterized by: A sealing ring (5) is fixedly connected to the outer surface of the L-shaped pipe (203), and the bottom end of the sealing ring (5) is fixedly connected to the top end of the storage tank (201).

3. The large-span rigid skeleton arch bridge concrete pouring equipment according to claim 1 is characterized in that: The outer surface of each hydraulic cylinder (213) is fixedly connected to a dustproof housing (8), and the upper surface of each dustproof housing (8) is fixedly connected to the bottom end of the fixing frame (1).

4. The large-span rigid skeleton arch bridge concrete pouring equipment according to claim 3 is characterized by: The bottom surface of each dustproof housing (8) is fixedly connected to a protective sleeve (6), and the bottom end of each protective sleeve (6) is fixedly connected to the upper surface of the sliding plate (204).

5. The large-span rigid skeleton arch bridge concrete pouring equipment according to claim 4 is characterized in that: The outer surface of each protective sleeve (6) is fixedly connected to a reinforcement plate (7), and the bottom surface of each reinforcement plate (7) is fixedly connected to the upper surface of the sliding plate (204).

6. The large-span rigid skeleton arch bridge concrete pouring equipment according to claim 5 is characterized by: The inner wall of each reinforcement plate (7) is threadedly connected to four reinforcement bolts (10), and the inner wall of each group of reinforcement bolts (10) is threadedly connected to the inner wall of the sliding plate (204).

7. The large-span rigid skeleton arch bridge concrete pouring equipment according to claim 1 is characterized by: The outer surface of the driving motor (206) is fixedly connected to a protection box (4), and the bottom surface of the protection box (4) is fixedly connected to the top of the storage tank (201).

8. The large-span rigid skeleton arch bridge concrete pouring equipment according to claim 1 is characterized by: A reinforcement ring (9) is fixedly connected to the outer surface of the discharge pipe (208), and the inner wall of the reinforcement ring (9) is fixedly connected to the outer surface of the telescopic pipe (212).

9. The large-span rigid skeleton arch bridge concrete pouring equipment according to claim 1, characterized in that: The outer surface of each set of the electric pulleys (308) is fixedly connected to two fixing rings (12), and the top end of each set of the fixing rings (12) is fixedly connected to the inner wall of the sliding block (302).

10. The large-span rigid skeleton arch bridge concrete pouring equipment according to claim 1, characterized in that: The outer surface of each set of the fixing rods (303) is fixedly connected to two limiting rings (11), and the ends of each set of the limiting rings (11) that are away from each other are fixedly connected to the side surfaces of the two sliding blocks (302) that are close to each other.

Citation Information

Patent Citations

  • Automatic irregular handle concrete hopper structure

    CN203808522U

  • Give as security out quick -witted protector

    CN206718437U

  • Magnetic levitation track panel laying system for complex section

    CN210439082U

  • Concrete pouring equipment

    CN220261464U

  • Concrete grouting equipment

    CN221561722U