Large-span multi-layer steel truss corridor and construction method

By setting up connection and fixing mechanisms between steel beams and utilizing lifting equipment and gravity, the problem of complicated construction steps in the construction of multi-story steel truss corridors was solved, and an efficient and stable installation process was achieved.

CN119352638BActive Publication Date: 2025-10-14CHINA CONSTR EIGHT ENG DIV CORP LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202411804089.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-12-10
Publication Date
2025-10-14
Estimated Expiration
2044-12-10

AI Technical Summary

Technical Problem

In the construction of multi-story steel truss corridors, the existing technology causes cumbersome construction steps due to repeated lifting operations, which reduces construction efficiency.

Method used

By setting connecting mechanisms and fixing mechanisms between steel beams, using lifting equipment and gravity, the spacing between steel beams can be adjusted and fixed to avoid repeated lifting. The multi-layer steel trusses can be lifted to the appropriate position at one time using lifting equipment, and the connection stability can be improved through connecting mechanisms and fixing mechanisms.

Benefits of technology

It achieves efficient installation of multi-layer steel trusses, simplifies construction steps, and improves construction efficiency and connection stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119352638B_ABST
    Figure CN119352638B_ABST
Patent Text Reader

Abstract

The application provides a large-span multilayer steel truss corridor and a construction method, including two buildings, the top of each of the two buildings is provided with vertically arranged passages one and two, the two passages two are located below the passages one, the top of the close side of each of the two buildings and above the passages one is fixedly connected with a stop plate, each of the two passages one is provided with a fixing mechanism, and a multilayer steel truss assembly connected with the fixing mechanism is arranged between the two passages one, the multilayer steel truss assembly includes steel beams one, two and three arranged in sequence from top to bottom; the application is convenient for hoisting equipment to hoist the multilayer steel truss to a suitable position at one time, effectively avoids repeated hoisting work, provides convenience for the installation of the multilayer steel truss, and further speeds up the construction efficiency of the multilayer steel truss corridor.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the technical field of building construction, in particular to a large-span multi-layer steel truss corridor and a construction method. BACKGROUND

[0002] With the continuous construction and development of the city, people's design requirements for building use function and appearance modeling are getting higher and higher. Steel truss corridor, as a kind of structure outside the building, can expand space and improve space utilization, and is more and more applied to buildings. When installing some large-span multi-layer steel corridor, the whole lifting installation method is usually used to install each layer of steel truss corridor independently, that is, after the whole steel truss corridor of each layer is assembled on the ground, the assembled steel truss corridor is lifted to the connection position by a crane, and then it is installed with the building, and then the next layer of steel truss corridor is lifted again.

[0003] When constructing a multi-layer steel truss corridor, after the upper layer of steel truss corridor is installed, a plurality of connecting beams need to be hoisted in sequence to fix the upper layer of steel corridor before hoisting the lower layer of steel truss corridor, and then the hoisted lower layer of steel truss corridor is fixed with the plurality of connecting beams hoisted before. In this process, repeated hoisting operations will cause complicated construction steps, which will reduce the construction efficiency of the multi-layer steel truss corridor. SUMMARY

[0004] The purpose of the present application is to provide a large-span multi-layer steel truss corridor and a construction method to solve the above technical problems.

[0005] To solve the above technical problems, the present application provides a construction method for a large-span multi-layer steel truss corridor, comprising the following steps:

[0006] Step one: a steel column is arranged between the two truss ends, a stand is arranged at the top end of the steel beam one, and the stand is connected to the bottom end of the truss, then the steel beam three, the steel beam two and the steel beam one are arranged in order from bottom to top between the two buildings, the through holes on the steel beam three, the steel beam two and the steel beam one are sleeved outside the stabilizing rod, and the hoisting equipment at the top end of the building is connected with the steel column;

[0007] Step two: start the hoisting equipment to pull the steel column, truss, stand and steel beam one to move up synchronously, so that the through hole on the steel beam one slides on the stabilizing rod. During the upward movement, the distance between the steel beam one and the steel beam two will increase due to the gravity of the steel beam two;

[0008] Step three: after the distance between the steel beam one and the steel beam two increases by a certain distance, the linkage mechanism controls the distance between the steel beam one and the steel beam two, and avoids the further increase of the distance between the steel beam one and the steel beam two, and the distance between the steel beam one and the steel beam two is equal to the height of the channel two;

[0009] Step four: in the process of expanding the distance between steel beam one and steel beam two, the position between steel beam one and steel beam two is vertically supported by the stabilizing unit to provide vertical positioning;

[0010] Step five: then the hoisting equipment continues to work, and drives steel beam one and steel beam two to move up synchronously, and then under the action of the gravity of steel beam three, the distance between steel beam two and steel beam three is further increased, and when the distance between steel beam two and steel beam three is equal to the height of channel two, the vertical support between steel beam two and steel beam three is performed by the stabilizing unit to keep the distance between steel beam two and steel beam three fixed;

[0011] Step six: then the hoisting equipment continues to pull steel beam one, steel beam two and steel beam three to move up synchronously, and when the truss moves to the bottom surface of the stop plate, the hoisting equipment stops working;

[0012] Step seven: then the moving unit is started to control the support plate one and the support plate two to move, so that the support plate one and the support plate two slide between steel beam one and steel beam two and between steel beam two and steel beam three, and then the distance between steel beam one and steel beam two and the distance between steel beam two and steel beam three are further fixed.

[0013] The beneficial effects of the present application are:

[0014] 1、The present application, through the design of the building, the channel one, the channel two, the steel beam one, the steel beam two, the steel beam three, the through hole, the truss, the steel column, the stand and the connecting mechanism, facilitates the hoisting equipment to hoist the multi-layer steel truss to the appropriate position at one time, avoids repeated hoisting work, provides convenience for the installation of the multi-layer steel truss, and further speeds up the construction efficiency of the multi-layer steel truss corridor;

[0015] 2、Through the design of the connecting mechanism, the distance between steel beam two and steel beam one can be adjusted and the distance between steel beam three and steel beam two can be adjusted under the action of the gravity of steel beam two and steel beam three during hoisting, so that the connecting mechanism acts automatically under the action of gravity, without the need to set other power equipment to control the action of the connecting mechanism, providing convenience for adjusting the distance between steel beam two and steel beam one and steel beam three;

[0016] 3、The action of the connecting mechanism can make the abutting plate abut the two sliding seats transversely and cooperate with the abutting rod to fix the fixed box and the mounting seat longitudinally, effectively keeping the distance between steel beam one and steel beam two and the distance between steel beam two and steel beam three fixed, and further improving the connection stability of steel beam one, steel beam two and steel beam three;

[0017] 4. By the design of the fixing mechanism, the support plate two and the support plate one are slid to between the steel beam one and the steel beam two and between the steel beam two and the steel beam three, the support to the steel beam one and the steel beam two is effectively realized, the further fixing to the distance between the steel beam two and the steel beam one and the steel beam three is realized, and the connection stability of the multi-layer steel truss is further improved. BRIEF DESCRIPTION OF DRAWINGS

[0018] Figure 1 The overall structure schematic diagram of the large-span multi-layer steel truss corridor is provided in the application.

[0019] Figure 2 The side sectional view of the application is provided. Figure 1

[0020] The main sectional view of the application is provided. Figure 3 Figure 1 The structure schematic diagram of the fixing mechanism is provided.

[0021] Figure 4 The structure schematic diagram of the multi-layer steel truss assembly is provided.

[0022] Figure 5 The structure schematic diagram of the connection mechanism is provided.

[0023] Figure 6 The sectional view of the application is provided.

[0024] Figure 7 Figure 6

[0025] MAIN SYMBOL EXPLANATION

[0026] 1. building; 2. passage one; 3. stabilizing rod; 4. passage two; 5. steel beam one; 6. steel beam two; 7. steel beam three; 8. through hole; 9. truss; 10. steel column; 11. stand column; 12. stop plate; 13. groove one; 14. groove two; 15. sliding groove; 16. support plate one; 17. support plate two; 18. connection rod; 19. screw rod; 20. worm wheel; 21. motor; 22. worm; 23. accommodating groove; 24. fixing base one; 25. fixing base two; 26. sliding base; 27. sliding block; 28. sliding opening; 29. cross rod; 30. connection shaft; 31. push block; 32. notch; 33. fixing cylinder; 34. telescopic rod; 35. spring one; 36. pressing plate; 37. bevel edge; 38. fixing box; 39. mounting base; 40. toothed plate; 41. rotating shaft; 42. gear; 43. pressing rod; 44. locking opening; 45. movable groove; 46. locking rod; 47. spring two. DETAILED DESCRIPTION

[0027] ​​​The following will be combined with the accompanying drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the embodiments described are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field are within the scope of protection of the present invention.

[0028] Those skilled in the art should understand that, in the disclosure of the present invention, the terms "longitudinal", "transverse", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like to indicate orientations or positional relationships are based on the orientations or positional relationships shown in the accompanying drawings, which are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, the above terms should not be understood as limiting the present invention.

[0029] It is to be understood that the term "one" should be understood as "at least one" or "one or more", that is, in one embodiment, the number of an element may be one, while in another embodiment, the number of the elements may be multiple, and the term "one" should not be understood as a limitation on the quantity.

[0030] like Figure 1-Figure 7 The present invention provides a long-span multi-layer steel truss corridor and a construction method, comprising the following steps:

[0031] Step 1: Workers weld steel columns 10 between the two ends of the two trusses 9, weld columns 11 on the top of steel beam 1 5, and weld the top of column 11 to the bottom of truss 9. Then, workers arrange steel beam 3 7, steel beam 2 6, and steel beam 1 5 in order from bottom to top and place them between the two buildings 1. The through holes 8 on steel beam 3 7, steel beam 2 6, and steel beam 1 5 are connected to the outside of the stabilizer bar 3, and the lifting equipment at the top of the building 1 is connected to the steel columns 10.

[0032] Step 2: Start the hoisting equipment, which will pull the steel column 10, truss 9, column 11 and steel beam 1 5 upward synchronously, causing the through hole 8 on steel beam 1 5 to slide on the stabilizer bar 3. During the upward movement, due to the gravity of steel beam 2 6, the distance between steel beam 1 5 and steel beam 2 6 will increase, causing the slide 26 to drive the slider 27 to slide in the slide 28, realizing the swing of the cross bar 29;

[0033] The third step is to slide the sliding block 31 toward the recess 32 so that one end of the sliding block 31 contacts the bottom end of the pressure plate 36. When the sliding blocks 31 on both sides of the pressure plate 36 approach each other, the inclined surface of the pushing block 31 slides on the inclined edge 37 of the pressure plate 36 to move the pressure plate 36 downward. The pressure plate 36 pulls the telescopic rod 34 to slide inside the fixed cylinder 33, stretching the spring 1 35. When the bottom end of the pressure plate 36 contacts the side wall of the sliding block 27, the pressure plate 36 is abutted against the two sliding blocks 27, which can prevent the sliding seat 26 from continuing to slide, prevent the cross rod 29 from continuing to swing, and prevent the distance between the steel beam 1 5 and the steel beam 2 6 from further increasing, thereby effectively fixing the distance between the steel beam 1 5 and the steel beam 2 6, and the distance between the steel beam 1 5 and the steel beam 2 6 is equal to the height of the channel 2 4.

[0034] Step 4: As the distance between the first steel beam 5 and the second steel beam 6 increases, the two adjacent toothed plates 40 approach each other. The meshing of the toothed plates 40 and the gear 42 causes the gear 42 to rotate, which in turn drives the rotating shaft 41 to rotate. The rotating shaft 41 drives the pressure rod 43 to swing, causing the pressure rod 43 to rotate to the top of the mounting seat 39.

[0035] When the pressing rod 43 squeezes the locking rod 46, the end of the pressing rod 43 moves downward and compresses the second spring 47. When the pressing plate 36 abuts the two sliders 27, the pressing rod 43 rotates to a vertical state, which makes the lock hole 44 in a vertical state, stops squeezing the locking rod 46, and under the reverse force of the second spring 47, the locking rod 46 is inserted into the lock hole 44 to achieve the locking of the pressing rod 43. This can avoid the situation where the steel beam 1 5 and the steel beam 2 6 are compressed and the spacing becomes smaller. By the lateral abutment of the two slides 26 by the pressing plate 36 and the longitudinal fixation between the fixing box 38 and the mounting seat 39 by the pressing rod 43, the spacing between the steel beam 1 5 and the steel beam 2 6 is effectively kept fixed, thereby improving the stability of the distance between the steel beam 1 5 and the steel beam 2 6 being equal to the height of the channel 2 4.

[0036] Step 5: As the hoisting equipment continues to work, it will drive the steel beam 1 5 and the steel beam 2 6 to move upward synchronously, and then under the action of the gravity of the steel beam 3 7, the distance between the steel beam 2 6 and the steel beam 3 7 will be further increased. When the distance between the steel beam 2 6 and the steel beam 3 7 is equal to the height of the channel 2 4, the pressure plate 36 will be caused to abut the two slides 26 laterally, and the pressure rod 43 will be used to fix the fixing box 38 and the mounting seat 39 longitudinally, effectively maintaining the distance between the steel beam 2 6 and the steel beam 3 7 fixed;

[0037] Step 6: The hoisting equipment will then continue to pull the steel beam 1 5, the steel beam 2 6 and the steel beam 3 7 upwards synchronously. When the truss 9 moves up to contact the bottom surface of the stop plate 12, the hoisting equipment will stop working.

[0038] Step seven: then start the motor 21, the motor 21 drives the worm 22 rotation, the worm 22 drives the worm gear 20 rotation, the worm gear 20 will drive the screw rod 19 rotation, through the screw rod 19 and the support plate two 17 threaded connection will make the support plate two 17 in the recess one 13 inside horizontal sliding, and make the support plate two 17 drive the adapter rod 18 in the recess one 13 sliding, and the support plate one 16 in the recess two 14 inside sliding, make the support plate two 17 and the support plate one 16 sliding to the steel beam one 5 and the steel beam two 6 between and the steel beam two 6 and the steel beam three 7 between, effectively realize to the steel beam one 5 and the steel beam two 6 support and the steel beam two 6 respectively with the steel beam one 5 and the steel beam three 7 between the further fixed interval, further improve the connection stability of multilayer steel truss.

[0039] Wherein, the large span multilayer steel truss corridor, set between two buildings 1, two buildings 1 along the vertical arrangement of the channel one 2 and at least two channel two 4, two channel two 4 below the channel one 2, two buildings 1 close to one side of the top and located above the channel one 2 are all fixed with stop plate 12, two channel two 4 are all equipped with fixed mechanism, two channel one 2 between is equipped with multilayer steel truss assembly connected with fixed mechanism, here need to pay attention to, the top of two buildings 1 are all installed with hoisting equipment connected with multilayer steel truss assembly, hoisting equipment can be crane, therefore not drawn in the figure;

[0040] The multilayer steel truss assembly comprises steel beam one 5, steel beam two 6 and steel beam three 7 arranged in sequence from top to bottom, the top end and the bottom end of the steel beam two 6 are connected with the steel beam one 5 and the steel beam three 7 through the equally spaced connecting mechanisms respectively, two trusses 9 are symmetrically arranged above the steel beam one 5, it is needed to be noticed that the top surface of the truss 9 will contact with the bottom end of the stop plate 12 after the multilayer steel truss assembly is hoisted by the hoisting equipment, the channel one 2 will be located between the steel beam one 5 and the truss 9, and the two channels two 4 will be located between the steel beam one 5 and the steel beam two 6 and between the steel beam two 6 and the steel beam three 7 respectively, at this time, the hoisting equipment is stopped, the hoisting equipment can be a crane, the two ends between the two adjacent trusses 9 are fixedly connected with the steel column 10, the truss 9 and the top end of the steel beam one 5 are connected through the equally spaced vertical columns 11, the steel beam one 5, the steel beam two 6 and the steel beam three 7 are symmetrically provided with the through holes 8, the two buildings 1 are provided with the stabilizing rods 3 matched with the through holes 8, the thickness of the steel beam two 6 is not less than the sum of the thicknesses of the steel beam one 5 and the steel beam three 7; the multilayer steel truss assembly can be hoisted and slid between the two buildings 1 through the action of the hoisting equipment, the connecting mechanisms will automatically act under the action of gravity, when the channel one 2 is located between the steel beam one 5 and the truss 9, and the two channels two 4 are located between the steel beam one 5 and the steel beam two 6 and between the steel beam two 6 and the steel beam three 7 respectively, then the hoisting equipment is stopped, the process does not need to set other power equipment to control the action of the connecting mechanisms, then the spacing between the steel beam one 5, the steel beam two 6 and the steel beam three 7 can be fixed, and the steel beam one 5, the steel beam two 6 and the steel beam three 7 can be further fixed by cooperating with the design of the fixing mechanism, the connection stability of the multilayer steel truss is further improved.

[0041] The two buildings 1 are provided with the groove one 13 and the groove two 14 located on the two sides of the two channels two 4, the bottom ends between the groove one 13 and the groove two 14 are provided with the sliding groove 15, the sliding groove 15 is a U-shaped structure, the fixing mechanism comprises the support plate one 16 slidably arranged in the groove two 14 and the support plate two 17 slidably arranged in the groove one 13, the support plate one 16 and the support plate two 17 are U-shaped structures, the bottom ends between the support plate one 16 and the support plate two 17 are connected through the connecting rod 18 slidably arranged in the sliding groove 15, the connecting rod 18 is a U-shaped structure, the two adjacent support plate two 17 are provided with the moving unit, the moving unit comprises the screw rod 19 rotatably arranged on the inner wall of the groove one 13, the screw rod 19 penetrates the middle position of the support plate two 17, the support plate two 17 is threadedly connected with the screw rod 19, one end of the screw rod 19 is fixedly sleeved with the worm wheel 20, the bottom end of the lower groove one 13 is provided with the motor 21, the output shaft of the motor 21 is connected with the worm 22 extending into the inner part of the upper groove one 13, the worm 22 is meshingly connected with the two worm wheels 20, the outer walls of the support plate two 17 and the support plate one 16 are in contact with the bottom surface of the steel beam one 5, the top surface and the bottom surface of the steel beam two 6 and the top surface of the steel beam three 7 respectively;

[0042] When the channel one 2 is located between the steel beam one 5 and the truss 9, and the two channel two 4 are located between the steel beam one 5 and the steel beam two 6 and between the steel beam two 6 and the steel beam three 7 respectively, the support plate one 16 and the support plate two 17 can be moved between the steel beam one 5 and the steel beam two 6 and between the steel beam two 6 and the steel beam three 7 by moving the unit, so as to provide the possibility for the support plate one 16 and the support plate two 17 to support and fix the steel beam one 5, the steel beam two 6 and the steel beam three 7, thereby further improving the connection stability of the multi-layer steel truss.

[0043] The connecting mechanism comprises accommodating grooves 23 opened at the bottom end of the steel beam one 5, the top end and the bottom end of the steel beam two 6 and the top end of the steel beam three 7, a fixed seat one 24 is installed in each of the accommodating grooves 23 at the bottom end of the steel beam one 5 and the steel beam two 6, two fixed cylinders 33 are symmetrically installed at the two ends of the fixed seat one 24, the fixed cylinder 33 is a cavity structure with an open bottom end, a fixed seat two 25 is installed in each of the accommodating grooves 23 at the top end of the steel beam two 6 and the steel beam three 7, a mounting seat 39 is symmetrically installed at the two sides of the fixed seat two 25, the fixed cylinder 33 and the mounting seat 39 are connected through a stabilizing unit, a recess 32 is opened at the middle position of the side close to the fixed seat two 25 of the fixed seat one 24, a sliding seat 26 is slidingly installed at the side close to the fixed seat two 25 of the fixed seat one 24, four sliding seats 26 are rotationally connected through a cross-shaped cross rod 29, an abutting shaft 30 is arranged at the middle position of the cross-shaped cross rod 29, a sliding opening 28 in communication with the recess 32 is symmetrically opened at the side close to the fixed seat two 25 of the fixed seat one 24, a sliding block 27 slidingly installed in the sliding opening 28 is connected to one end of the sliding seat 26, a push block 31 slidingly installed in the sliding opening 28 is installed at the side close to the recess 32 of each of the four sliding blocks 27, the push block 31 is a right triangle structure, an abutting unit connected with the adjacent two push blocks 31 is arranged in the recess 32, the abutting unit comprises three fixed cylinders 33 equidistantly fixed to the top end of the recess 32, a telescopic rod 34 is slidingly installed in each of the fixed cylinders 33, the fixed cylinder 33 and the telescopic rod 34 are connected through a spring one 35, the three telescopic rods 34 are connected through an abutting plate 36 slidingly installed in the inner wall of the recess 32, an inclined edge 37 is opened at the two ends of the abutting plate 36, the inclined edge 37 is in sliding contact with the inclined surface of the push block 31;

[0044] When the hoisting device hoists the multi-layer steel truss to move upward, the distance between the steel beam one 5 and the steel beam two 6 is equal to the height of the channel two 4 under the action of gravity, so that the steel beam two 6 can realize synchronous movement with the steel beam one 5, when the distance between the steel beam two 6 and the steel beam three 7 is equal to the height of the channel two 4, the steel beam two 6 can realize synchronous movement with the steel beam three 7, when the distance between the steel beam one 5 and the steel beam two 6 and the distance between the steel beam two 6 and the steel beam three 7 are equal to the height of the channel two 4, the synchronous upward movement of the steel beam one 5, the steel beam two 6 and the steel beam three 7 can be realized under the continuous work of the hoisting device, the distance between the fixed seat one 24 and the fixed seat two 25 can be increased in the process of swinging of the cross rod 29, the lifting of the pressing plate 36 can be realized in the increasing process, when the distance is increased to the height of the channel two 4, the pressing plate 36 can press between the two push blocks 31, so that the distance is further increased due to the continuous swinging of the cross rod 29, so that the distance between the steel beam one 5 and the steel beam two 6 and the distance between the steel beam two 6 and the steel beam three 7 can be fixed, the action of the connecting mechanism can be realized by the gravity itself in the process, so that the action of the remaining power mechanism is not needed.

[0045] The stable unit comprises a tooth plate 40 fixed to the far side of the two sliding seats 26 and located below the fixed seat one 24, the inside of the fixed box 38 is rotatably installed with a rotating shaft 41, the rotating shaft 41 is fixedly sleeved with a gear 42 and a pressing rod 43, the gear 42 is in meshing connection with the tooth plate 40, the bottom end of the pressing rod 43 is in sliding contact with the top end of the mounting seat 39, the mounting seat 39 is provided with a locking piece connected with the pressing rod 43, the locking piece comprises a lock opening 44 opened at the bottom end of the pressing rod 43, the top end of the mounting seat 39 is provided with a movable slot 45, the inside of the movable slot 45 is slidably connected with a lock rod 46 extending into the inside of the lock opening 44, the bottom end of the movable slot 45 and the bottom end of the lock rod 46 are connected by a spring two 47;

[0046] When the cross rod 29 swings, the tooth plate 40 moves, so that the distance between the fixed seat one 24 and the fixed seat two 25 is increased, the pressing rod 43 is turned over, when the pressing plate 36 presses the push block 31, the pressing rod 43 is in a vertical state, the fixed cylinder 33 is connected with the mounting seat 39, the distance between the fixed seat one 24 and the fixed seat two 25 is effectively fixed, the distance between the steel beam one 5 and the steel beam two 6 and the distance between the steel beam two 6 and the steel beam three 7 can be reduced, and the connection stability of the multi-layer steel truss is improved.

[0047] The present application is not limited to the above-mentioned best embodiment, anyone can derive other various forms of products under the inspiration of the present application, but regardless of any change in shape or structure, any technical solution with the same or similar to the present application falls within the scope of the present application.

Claims

1. The construction method of a long-span multi-story steel truss corridor is characterized by: The following steps are involved: Step 1: a steel column (10) is set between the ends of the two trusses (9), a column (11) is set at the top of the steel beam (5), and the top of the column (11) is connected to the bottom of the truss (9), and then the steel beam (3) (7), the steel beam (2) (6) and the steel beam (1) (5) are arranged in order from bottom to top and placed between the two buildings (1), so that the through holes (8) on the steel beam (3) (7), the steel beam (2) (6) and the steel beam (1) (5) are sleeved on the outside of the stabilizer bar (3), and the lifting equipment at the top of the building (1) is connected to the steel column (10); Step 2: Start the hoisting equipment to pull the steel column (10), truss (9), column (11) and steel beam 1 (5) upward synchronously, so that the through hole (8) on steel beam 1 (5) slides on the stabilizing rod (3). During the upward movement, the distance between steel beam 1 (5) and steel beam 2 (6) increases due to the gravity of steel beam 2 (6); Step 3: After the distance between the first steel beam (5) and the second steel beam (6) increases to a certain distance, the connection mechanism controls the distance between the first steel beam (5) and the second steel beam (6) and prevents the distance between the first steel beam (5) and the second steel beam (6) from further increasing, and the distance between the first steel beam (5) and the second steel beam (6) is equal to the height of the second channel (4); Step 4: During the process of expanding the distance between the first steel beam (5) and the second steel beam (6), vertically support the position between the first steel beam (5) and the second steel beam (6) through the stabilizing unit to provide vertical positioning; Step 5: The hoisting equipment then continues to work, driving the steel beam 1 (5) and the steel beam 2 (6) to move upward synchronously, and then under the action of the gravity of the steel beam 3 (7), the distance between the steel beam 2 (6) and the steel beam 3 (7) is further increased. When the distance between the steel beam 2 (6) and the steel beam 3 (7) is equal to the height of the channel 2 (4), the stabilizing unit between the steel beam 2 (6) and the steel beam 3 (7) performs vertical support to keep the distance between the steel beam 2 (6) and the steel beam 3 (7) fixed; Step 6: The hoisting equipment then continues to pull the steel beam 1 (5), the steel beam 2 (6) and the steel beam 3 (7) upwards synchronously, and the hoisting equipment stops working when the truss (9) moves upwards to contact the bottom surface of the stop plate (12); Step 7: Then start the moving unit to control the support plate 1 (16) and the support plate 2 (17) to move, so that the support plate 1 (16) and the support plate 2 (17) slide between the steel beam 1 (5) and the steel beam 2 (6) and between the steel beam 2 (6) and the steel beam 3 (7), thereby further fixing the distance between the steel beam 1 (5) and the steel beam 2 (6) and the steel beam 2 (6) and the steel beam 3 (7); The connection mechanism includes a receiving groove (23) opened at the bottom end of steel beam 1 (5), the top and bottom end of steel beam 2 (6) and the top end of steel beam 3 (7), a fixing seat 1 (24) is installed in the receiving groove (23) at the bottom end of steel beam 1 (5) and steel beam 2 (6), and a fixing cylinder (33) is symmetrically installed at both ends of the fixing seat 1 (24), and the fixing cylinder (33) is a cavity structure with an open bottom end, a fixing seat 2 (25) is installed in the receiving groove (23) at the top end of steel beam 2 (6) and steel beam 3 (7), and mounting seats (39) are symmetrically installed on both sides of the fixing seat 2 (25), and the fixing cylinder (33) and the mounting seat (39) are connected by a stabilizing unit, and the middle position of the fixing seat 1 (24) and the fixing seat 2 (25) on the side close to each other is opened. A notch (32) is provided, and a slide seat (26) is slidably installed on the side where the fixed seat 1 (24) and the fixed seat 2 (25) are close to each other. The four slide seats (26) are rotatably connected through a cross rod (29). A connecting shaft (30) is provided at the middle position of the cross rod (29). A slide seat (28) connected to the notch (32) is symmetrically opened on the side where the fixed seat 1 (24) and the fixed seat 2 (25) are close to each other. One end of the slide seat (26) is connected to a slider (27) that slides inside the slide seat (28). A push block (31) that slides inside the slide seat (28) is installed on the side where the four sliders (27) are close to the notch (32). A pressing unit connected to two adjacent push blocks (31) is provided inside the notch (32). The pressing unit comprises three fixed cylinders (33) fixed to the top of the recess (32) at equal distances, and telescopic rods (34) are slidably installed inside the fixed cylinders (33). The fixed cylinders (33) and the telescopic rods (34) are connected by a spring (35). The three telescopic rods (34) are connected by a pressing plate (36) sliding on the inner wall of the recess (32). Both ends of the pressing plate (36) are provided with bevels (37), and the bevels (37) are in sliding contact with the inclined surface of the push block (31).

2. The construction method of a long-span multi-story steel truss corridor according to claim 1 is characterized by: A building (1) is provided with a channel one (2) and at least two channel twos (4) arranged vertically, the two channel twos (4) being located below the channel one (2), and a stop plate (12) being fixedly connected to the top of one side of the two buildings (1) and located above the channel one (2), and a fixing mechanism being provided on the two channel twos (4), and a multi-layer steel truss assembly connected to the fixing mechanism being provided between the two channel ones (2).

3. The construction method of a long-span multi-story steel truss corridor according to claim 2 is characterized by: The multi-layer steel truss assembly comprises a steel beam 1 (5), a steel beam 2 (6) and a steel beam 3 (7) which are arranged in sequence from top to bottom. The top and bottom ends of the steel beam 2 (6) are connected to the steel beam 1 (5) and the steel beam 3 (7) through a connecting mechanism arranged at equal distances. After the multi-layer steel truss assembly is hoisted and lifted by the hoisting equipment, the channel 1 (2) is located between the steel beam 1 (5) and the truss (9), and the two channels 2 (4) are respectively located between the steel beam 1 (5) and the steel beam 2 (6) and between the steel beam 2 (6) and the steel beam 3 (7).

4. The construction method of a long-span multi-story steel truss corridor according to claim 2 is characterized by: The two buildings (1) are provided with a groove 1 (13) and a groove 2 (14) located on both sides of the passage 2 (4), and a slide groove (15) is provided between the bottom ends of the groove 1 (13) and the groove 2 (14); the fixing mechanism includes a support plate 1 (16) sliding inside the groove 2 (14) and a support plate 2 (17) sliding inside the groove 1 (13); the bottom ends of the support plate 1 (16) and the support plate 2 (17) are connected by a connecting rod (18) sliding inside the slide groove (15), and a moving unit is provided between two adjacent support plates 2 (17); the moving unit includes a connecting rod (18) rotatably installed in the groove 1 (13) The screw rod (19) of the wall is passed through the middle position of the support plate 2 (17). The support plate 2 (17) is threadedly connected to the screw rod (19). One end of the screw rod (19) is fixedly sleeved with a worm gear (20). The bottom end of the lower groove 1 (13) is installed with a motor (21). The output shaft of the motor (21) is connected with a worm gear (22) extending to the inside of the upper groove 1 (13). The worm gear (22) is meshed with the two worm gears (20). The outer walls of the support plate 2 (17) and the support plate 1 (16) are respectively in contact with the bottom surface of the steel beam 1 (5), the top surface and bottom surface of the steel beam 2 (6) and the top surface of the steel beam 3 (7).

5. The construction method of a long-span multi-story steel truss corridor according to claim 1 is characterized by: The stabilizing unit includes a tooth plate (40) fixed to a side away from the two slides (26) and located below the fixed seat (24). A rotating shaft (41) is rotatably installed inside the fixed box (38). A gear (42) and a pressure rod (43) are fixedly sleeved on the rotating shaft (41). The gear (42) is meshed with the tooth plate (40). The bottom end of the pressure rod (43) is in sliding contact with the top end of the mounting seat (39). The mounting seat (39) is provided with a locking member connected to the pressure rod (43).

6. The construction method of a long-span multi-story steel truss corridor according to claim 5, characterized in that: The locking member includes a locking opening (44) opened at the bottom end of the pressing rod (43), a movable groove (45) is opened at the top end of the mounting seat (39), the interior of the movable groove (45) is slidably connected to a locking rod (46) extending to the interior of the locking opening (44), and the bottom end of the movable groove (45) and the bottom end of the locking rod (46) are connected by a second spring (47).

7. A long-span multi-story steel truss corridor, characterized by: The long-span multi-story steel truss corridor is obtained by the construction method according to any one of claims 1 to 6.

Citation Information

Patent Citations

  • Steel corridor and steel corridor mounting method

    CN116591296A

  • Multi-layer steel corridor hovering assembly device and implementation method

    CN118653696A