Green fabricated building node structure

By designing a green prefabricated building node structure including beams, floor plates, upper wind grooves, and wind tanks, the traditional node structure has the lack of structural strength, ventilation performance, and cable management. Construction and better architectural performance.

CN119352652APending Publication Date: 2025-01-24HENAN XIANGWEI ENVIRONMENTAL PROTECTION TECH GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411372960.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-29
Publication Date
2025-01-24

AI Technical Summary

Technical Problem

The traditional prefabricated building node structure has shortcomings in structural strength, ventilation performance, cable management and construction convenience, and it is difficult to meet the diversified needs of modern buildings for green, efficient and intelligent.

Method used

A green prefabricated building node structure is designed, including exterior walls, interior walls, and floor slabs. Cross beams are set on the upper ends of the exterior walls, and floor slabs are erected on the beams and interior walls to form a stable support structure. At the same time, upwind ducts and downwind ducts are set up to improve ventilation performance, and pre-embedded wire pipes and pre-embedded air ducts are embedded in the third pouring area to facilitate the orderly arrangement of cables and ventilation ducts.

Benefits of technology

Improve the overallness and stability of the node structure, improve the ventilation performance, realize the order of cable management, simplify the construction process, shorten the construction cycle, and reduce the difficulty and cost of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119352652A_ABST
    Figure CN119352652A_ABST
Patent Text Reader

Abstract

The invention discloses a green assembly type building node structure, and relates to the technical field of green assembly type building production, the green assembly type building node structure comprises an outer wall body, an inner wall body and a floor plate, a cross beam is arranged on the side, close to the inner wall body, of the upper end of the outer wall body, and the floor plate is erected on the cross beam and the inner wall body; the side, away from the inner wall body, of the outer wall body extends upwards to wrap the floor plate. Trapezoidal openings are formed in the upper portions of the peripheral edges of the floor plates, first pouring areas are formed in the butt joint positions of the floor plates and the outer wall body, and second pouring areas are formed in the positions, above the inner wall body, of the floor plates and the trapezoidal openings of the adjacent floor plates in a butt joint mode; an upper air groove is formed in the upper part of one side, close to the inner wall body, of the outer wall body, and a lower air groove is formed in the lower part; the beneficial effects are that through ingenious design and innovation, multiple beneficial effects of stable structure, good ventilation, orderly cable management, convenient construction and the like are realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of green prefabricated building production, and in particular to a green prefabricated building node structure. Background Art

[0002] With the rapid development of the construction industry and the enhancement of environmental awareness, green prefabricated buildings have gradually become an important development direction in the construction field due to their advantages such as fast construction speed, low environmental pollution and high resource utilization. However, in the actual application of prefabricated buildings, the stability and functionality of the node structure often become the key factors restricting its widespread promotion. The traditional prefabricated building node structure has many shortcomings in terms of structural strength, ventilation performance, cable management and construction convenience, which makes it difficult to meet the diversified needs of modern buildings for green, efficient and intelligent.

[0003] Specifically, the structural strength of traditional node structures often relies on a large amount of on-site welding and concrete pouring, which not only takes a long construction period, but also easily leads to quality risks. At the same time, the node structure has poor ventilation performance, which easily leads to a decline in indoor air quality and affects the health of residents. In addition, chaotic cable management is also a major drawback of traditional node structures, which not only affects the appearance, but also increases the difficulty of later maintenance and repair. Summary of the invention

[0004] The purpose of the present invention is to provide a green assembled building node structure in order to solve the above problems.

[0005] The present invention achieves the above-mentioned purpose through the following technical solutions:

[0006] A green prefabricated building node structure comprises an outer wall, an inner wall and a floor slab, wherein a crossbeam is arranged at the upper end of the outer wall near one side of the inner wall, the floor slab is mounted on the crossbeam and the inner wall, and the outer wall extends upward away from the inner wall and wraps around the floor slab; trapezoidal openings are arranged on the upper parts of the four edges of the floor slab, the floor slab is docked with the outer wall at the position where the floor slab is docked to form a first pouring area, and the floor slab is docked with the trapezoidal opening of the adjacent floor slab at the position above the inner wall to form a second pouring area; an upper wind trough is provided on the upper part of the outer wall near one side of the inner wall, and a lower wind trough is provided on the lower part, the upper wind trough and the lower wind trough are connected by a connecting pipe, and are connected to an external air supply system through an air inlet pipe.

[0007] Preferably: shutters are installed at the opening positions of the upper wind slot and the lower wind slot.

[0008] Preferably: a wire box is installed inside the upper wind slot and the lower wind slot.

[0009] Preferably, a waistline is provided on a surface of the outer wall away from the inner wall at a position corresponding to a joint between two upper and lower adjacent outer walls.

[0010] Preferably: a pre-buried wire tube and a pre-buried air duct are pre-buried in the third pouring area, the pre-buried wire tube is connected with the wire box for wiring, and the pre-buried air duct is used to connect the air inlet pipe, the upper air slot, and the lower air slot.

[0011] Preferably: a first connecting steel bar is fixedly installed on the crossbeam, and its upper end extends to the first casting area; main floor slab connecting bars are pre-embedded inside the floor slab, and the first connecting steel bar extends to the first casting area near one end of the outer wall, and the first connecting steel bar extends to the second casting area near one end of the inner wall; a second connecting steel bar is pre-embedded at the upper end of the inner wall, and its upper end extends to the second casting area.

[0012] Preferably: the crossbeam is an I-beam, and the gap between the I-beam and the outer wall and the floor slab forms a third pouring area, and the third pouring area is arranged close to the inner wall and flush with the outer wall surface; the lower end of the first connecting steel bar is welded to the I-beam.

[0013] Preferably: the cross beam is a cast beam, which is arranged on the upper part of the outer wall close to the indoor side, the cast beam is pre-embedded with embedded steel bars, and the lower end of the first connecting steel bar is pre-embedded in the cross beam.

[0014] Compared with the prior art, the present invention has the following beneficial effects:

[0015] 1. Stable structure: The present invention forms a stable supporting structure by arranging a crossbeam at the upper end of the outer wall and erecting a floor slab on the crossbeam and the inner wall. At the same time, the first pouring area formed by the trapezoidal opening design on the four edges of the floor slab and the outer wall, and the second pouring area formed by the floor slab and the trapezoidal opening of the adjacent floor slab above the inner wall further enhance the integrity and stability of the node structure. In addition, the first connecting steel bar fixedly installed on the crossbeam, the main floor slab connecting steel bar embedded inside the floor slab, and the second connecting steel bar embedded at the upper end of the inner wall together constitute a stable connection system, ensuring the stability and safety of the node structure when bearing various loads.

[0016] 2. Good ventilation: The present invention sets an upper trough and a lower trough on one side of the outer wall close to the inner wall, and connects the two through a connecting pipe. In summer, cold air is blown in from the upper trough, and the cold air falls to quickly achieve a cooling effect in the room; conversely, in winter, hot air is blown in from the lower trough, and the hot air floats upward to quickly achieve a heating effect in the room; at the same time, the shutters installed at the openings of the upper trough and the lower trough can adjust the ventilation volume as needed to prevent debris from falling in; this design not only improves the indoor air quality, but also helps to reduce building energy consumption and achieve green energy saving;

[0017] 3. Orderly cable management: The present invention pre-buries pre-buried wire tubes and pre-buried air ducts in the third pouring area, which are used in conjunction with the wire box and air duct on the outer wall to achieve orderly arrangement of cables and ventilation ducts; the pre-buried wire tubes are connected to the wire box for wiring, ensuring the neatness and beauty of the cables and easy maintenance; the pre-buried air ducts are used to extend the air inlet duct to connect the upper air duct and the lower air duct, achieving smooth operation of the ventilation system; this design not only improves the overall aesthetics of the building, but also reduces the difficulty of later maintenance and overhaul;

[0018] 4. Convenient construction: The present invention adopts the concept of prefabricated design, prefabricates and standardizes the main components of the node structure, and then assembles and casts them on site; this construction method not only shortens the construction period, but also reduces the construction difficulty and cost; at the same time, since the stability and functionality of the node structure are fully guaranteed, the construction quality and building safety can be ensured. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0020] Figure 1 It is a structural schematic diagram of Example 1 of a green prefabricated building node structure described in the present invention.

[0021] Figure 2 It is a structural schematic diagram of Example 2 of a green prefabricated building node structure described in the present invention.

[0022] The following are the descriptions of the reference numerals:

[0023] 1. Exterior wall; 2. I-beam; 3. First connecting steel bar; 4. Floor slab; 5. Main reinforcement for floor slab connection; 6. Second connecting steel bar; 7. Interior wall; 8. First pouring area; 9. Second pouring area; 10. Third pouring area; 11. Embedded steel bars; 12. Waistline; 13. Upper air trough; 14. Lower air trough; 15. Shutters; 16. Connecting pipe; 17. Air inlet pipe; 18. Embedded wire pipe; 19. Embedded air duct; 20. Junction box. DETAILED DESCRIPTION

[0024] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and the like are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first", "second", and the like may explicitly or implicitly include one or more of the features. In the description of the present invention, unless otherwise specified, "multiple" means two or more.

[0025] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be the internal connection of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood by specific circumstances.

[0026] The present invention will be further described below in conjunction with the accompanying drawings:

[0027] Example 1

[0028] like Figure 1As shown, a green prefabricated building node structure includes an outer wall 1, an inner wall 7 and a floor slab 4. A crossbeam is arranged on the upper end of the outer wall 1 near the inner wall 7. The floor slab 4 is mounted on the crossbeam and the inner wall 7. The outer wall 1 extends upward away from the inner wall 7 to wrap the floor slab 4. Trapezoidal openings are arranged on the upper part of the four edges of the floor slab 4. The first pouring area 8 is formed at the joint position between the floor slab 4 and the outer wall 1. The floor slab 4 is located above the inner wall 7 and is connected to the trapezoidal opening of the adjacent floor slab 4. The second pouring area 9 is formed by connecting the mouth; the cross beam is an I-beam 2, and the gap between the I-beam 2 and the outer wall 1 and the floor slab 4 forms a third pouring area 10, and the third pouring area 10 is arranged flush with the surface of the outer wall 1 on the side close to the inner wall 7; the outer wall 1 is provided with an upper wind groove 13 on the upper part of the side close to the inner wall 7, and a lower wind groove 14 on the lower part, the upper wind groove 13 and the lower wind groove 14 are connected by a connecting pipe 16, and are connected to the indoor and outdoor air exchange system through an air inlet pipe 17.

[0029] The upper and lower wind slots 13 and 14 are both provided with shutters 1 at their openings, the lower wind slot 14 is provided with a skirting board, and a socket is provided on the skirting board; the upper and lower wind slots 13 and 14 are both provided with a wiring box 20 inside.

[0030] A waistline 12 is provided on the surface of the outer wall 1 on one side away from the inner wall 7 , corresponding to the joint position of two upper and lower adjacent outer walls 1 .

[0031] The third pouring area 10 is pre-buried with a pre-buried wire tube 18 and a pre-buried air duct 19 . The pre-buried wire tube 18 is connected to the wire box 20 for wiring. The pre-buried air duct 19 is used to extend the air inlet duct 17 and connect it to the upper air slot 13 and the lower air slot 14 .

[0032] A first connecting steel bar 3 is welded on the I-beam 2, and its upper end extends to the first pouring area 8; a floor slab connecting main reinforcement 5 is pre-embedded inside the floor slab 4, and the first connecting steel bar 3 extends to the first pouring area 8 at one end close to the outer wall 1, and extends to the second pouring area 9 at one end close to the inner wall 7; a second connecting steel bar 6 is pre-embedded at the upper end of the inner wall 7 and extends to the second pouring area 9.

[0033] The ends of the first connecting steel bar 3, the floor slab connecting main steel bar 5 and the second connecting steel bar 6 are respectively in a hook shape, and the first connecting steel bar 3 and the second connecting steel bar 6 both include interconnected transverse steel bars and vertical steel bars.

[0034] Pipes are arranged on both sides of the inner wall 7, the inner side of the outer wall 1 and the floor slab 4, and the pipes are respectively connected to the roof radiator and the underground heating and cooling system. The roof radiator dissipates heat and the underground heating and cooling system is used to cool or heat the room, and the medium is water or air.

[0035] Example 2

[0036] like Figure 2As shown, the difference between this embodiment and embodiment 1 is that: the upper ends of the outer wall and the inner wall are equipped with beams, and there is no need to support formwork on site, and there is no need to tie steel bars on site, which reduces labor, pollution and waste. It is factory-produced, has a high degree of intelligence, and the safety factor is greatly improved, shortening the construction period and reducing costs; it is arranged on the upper part of the outer wall 1 close to the indoor side, and the cast beam is pre-embedded with embedded steel bars 11, and the lower end of the first connecting steel bar 3 is pre-embedded in the beam; the cast beam can be customized according to the actual situation on site to better adapt to the complexity and diversity of the building structure; in addition, the cast beam has a stronger integrity and is more tightly connected to the floor slab 4 and the outer wall 1, which is beneficial to improving the overall performance and seismic resistance of the structure.

[0037] The waistline 12, the blinds 15, and the wire box 20 are all universal standard parts or parts known to those skilled in the art. Their structures and principles can be known to those skilled in the art through technical manuals or conventional experimental methods, so they will not be described in detail here.

[0038] The basic principles, main features and advantages of the present invention are shown and described above. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only for illustrating the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, and these changes and improvements all fall within the scope of the present invention to be protected.

Claims

1. A green prefabricated building node structure, comprising an outer wall (1), an inner wall (7) and a floor slab (4), characterized in that: A crossbeam is arranged at the upper end of the outer wall (1) near the inner wall (7), the floor slab (4) is mounted on the crossbeam and the inner wall (7), the outer wall (1) extends upwards away from the inner wall (7) to wrap around the floor slab (4); trapezoidal openings are arranged on the upper parts of the four edges of the floor slab (4), the floor slab (4) is connected with the outer wall (1) to form a first pouring area (8), and the floor slab (4) is connected with the trapezoidal opening of the adjacent floor slab (4) at the upper part of the inner wall (7) to form a second pouring area (9); an upper air trough (13) is provided on the upper part of the side of the outer wall (1) near the inner wall (7), and a lower air trough (14) is provided on the lower part, the upper air trough (13) and the lower air trough (14) are connected through a connecting pipe (16), and are connected to an external air supply system through an air inlet pipe (17).

2. A green prefabricated building node structure according to claim 1, characterized in that: Shutters (15) are installed at the opening positions of the upper air slot (13) and the lower air slot (14).

3. A green prefabricated building node structure according to claim 1, characterized in that: A wire box (20) is installed inside the upper wind slot (13) and the lower wind slot (14).

4. A green prefabricated building node structure according to claim 1, characterized in that: A waistline (12) is provided on a surface of one side of the outer wall (1) away from the inner wall (7) corresponding to a joint position between two upper and lower adjacent outer walls (1).

5. A green prefabricated building node structure according to claim 1, characterized in that: A pre-buried wire tube (18) and a pre-buried air duct (19) are pre-buried in the third pouring area (10); the pre-buried wire tube (18) is connected to the wire box (20) for wiring, and the pre-buried air duct (19) is used to connect the air inlet pipe (17), the upper air slot (13), and the lower air slot (14).

6. A green prefabricated building node structure according to claim 1, characterized in that: A first connecting steel bar (3) is fixedly mounted on the crossbeam, the upper end of which extends into the first pouring area (8); a main floor slab connecting steel bar (5) is pre-buried inside the floor slab (4); the first connecting steel bar (3) extends into the first pouring area (8) at one end close to the outer wall (1), and extends into the second pouring area (9) at one end close to the inner wall (7); a second connecting steel bar (6) is pre-buried at the upper end of the inner wall (7), the upper end of which extends into the second pouring area (9).

7. A green prefabricated building node structure according to claim 5, characterized in that: The crossbeam is an I-beam (2); a third pouring area (10) is formed at a gap between the I-beam (2) and the outer wall (1) and the floor slab (4); the third pouring area (10) is arranged flush with the surface of the outer wall (1) on a side close to the inner wall (7); and the lower end of the first connecting steel bar (3) is welded to the I-beam (2).

8. The green prefabricated building node structure according to claim 5, characterized in that: The cross beam is a cast beam, which is arranged on the upper part of the outer wall (1) close to the indoor side, and the cast beam has embedded steel bars (11) embedded inside, and the lower end of the first connecting steel bar (3) is embedded in the cross beam.