Hydraulic engineering process control and fund settlement management method and system
Through the establishment of project grading and acceptance standards in the construction project of the water conservancy project, the construction of a three -dimensional BIM model, and using smart equipment to adjust the operating speed of the construction equipment to solve the problem of difficulty in controlling construction progress, realize the accuracy of the completion of the project and the accuracy of capital settlement on schedule and fund settlement. Essence
Patent Information
- Application Number
- CN202411505313.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-25
- Publication Date
- 2025-01-28
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Due to the influence of various factors, the progress of water conservancy engineering construction projects is difficult to control, resulting in delays in projects and bringing difficulties to fund settlement work.
By establishing project grading and acceptance standards, constructing refined three -dimensional BIM models, using smart devices to obtain actual construction progress, and generating control instructions according to the expected progress, automatically adjust the operating speed of the construction equipment, and finally complete the fund settlement.
A real -time understanding of construction progress, adjusting the operation speed of the construction equipment, avoiding delayed progress, ensuring that the project is completed on schedule, and accurately complete the settlement of funds according to the acceptance standards.
Smart Images

Figure CN119378813A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of water conservancy engineering, and more specifically to a water conservancy engineering process control and fund settlement management method and system. Background Art
[0002] Water conservancy projects are large in scale, have complex construction conditions, and involve a wide range of areas. They have the following characteristics: they are affected and restricted by hydrology, meteorology, topography, geology, etc., which will have a great impact on the construction of water conservancy projects; water conservancy projects have the characteristics of large project volume and long construction period, requiring the use of large-capacity construction equipment, the use of modern construction technology, high mechanization and scientific construction management methods, resulting in the use of large amounts of funds, materials and labor; most water conservancy projects are carried out in deep mountains and canyons, with construction conditions such as crowded roads and narrow sites, which have a great impact on the progress and speed of the project.
[0003] Therefore, the construction project of a water conservancy project is a highly technical and complex management task. Construction management is to organize, inspect, coordinate and control various processes in the construction of a water conservancy project. Its purpose is to ensure the quality and safety of the project with the least manpower, material resources and funds, in accordance with the design requirements, so that the project can be completed on schedule or ahead of schedule and put into production to achieve benefits.
[0004] However, due to various factors, the progress of the project may be delayed to varying degrees, resulting in the project being unable to be completed on schedule, bringing difficulties to project acceptance and financial settlement. Therefore, how to timely understand the progress of the project, adjust the working speed of the construction equipment according to the actual construction situation, and complete the financial settlement is a technical problem that technical personnel in this field urgently need to solve. Summary of the invention
[0005] In view of this, the present invention provides a water conservancy project process control and fund settlement management method and system, which solves the problems existing in the background technology.
[0006] In order to achieve the above object, the present invention provides the following technical solutions:
[0007] A method for water conservancy project process control and fund settlement management comprises the following steps:
[0008] Classify the water conservancy projects to be built according to the preset rules and establish corresponding acceptance standards;
[0009] According to the construction design drawings and construction plans, a refined 3D BIM model of the water conservancy project is established, and a planned construction model is generated in combination with each stage of project classification;
[0010] Use smart devices to obtain the actual construction progress, generate control instructions based on the expected construction progress of the planned construction model, and automatically adjust the operating speed of the construction equipment;
[0011] Based on the actual construction progress and corresponding acceptance standards, determine whether the acceptance conditions are met and complete the financial settlement.
[0012] Optionally, the water conservancy projects to be constructed are classified according to preset rules, specifically:
[0013] Obtain project information of the water conservancy project to be built and build a basic data model of the project;
[0014] According to the construction stage of the project, the water conservancy project to be built will be divided into unit projects, branch projects and unit projects by adding tasks, editing tasks, deleting tasks, and moving tasks up, down, upgrading or downgrading.
[0015] Optionally, establish corresponding acceptance criteria, specifically:
[0016] The acceptance of water conservancy projects is divided into two stages: completion acceptance and completion acceptance. The acceptance criteria for the completion acceptance stage are the execution of the construction contract and whether the project quality meets the requirements for production. The acceptance criteria for the completion acceptance stage are that the comprehensive evaluation results of the project quality, participating units and construction projects meet the preset requirements.
[0017] Optionally, a refined three-dimensional BIM model of a water conservancy project is established, which specifically includes the following steps:
[0018] Based on the principle of parallel construction of each process and avoiding mutual interference, the construction plan arrangement analysis of each hydraulic structure in the water conservancy project to be built is carried out, and the construction plan is formulated based on the analysis results;
[0019] According to the construction design drawings and construction plans, BIM technology is used to construct a refined three-dimensional BIM model of the water conservancy project that meets the specifications.
[0020] Optionally, generate a planned construction model, specifically:
[0021] Based on the construction plan of the water conservancy project to be built, confirm the expected construction progress of the project;
[0022] Combine the expected construction progress with the refined 3D BIM model of the constructed water conservancy project to build an initial planned construction model;
[0023] Based on the project classification results, the initial planned construction model is divided into time series to obtain the planned construction model of each sub-project.
[0024] Optionally, use smart devices to obtain actual construction progress, specifically:
[0025] The image information of the water conservancy project construction is obtained by using the image acquisition device set up at the construction site;
[0026] According to the image information, the status of construction equipment and hydraulic structures is obtained to determine the construction progress nodes;
[0027] A comparative analysis was conducted based on the refined three-dimensional BIM model of the water conservancy project to obtain the actual construction progress.
[0028] Optionally, the operating speed of the construction equipment is automatically adjusted, specifically:
[0029] According to the planned construction model, obtain the expected construction progress at the current moment;
[0030] If the actual construction progress currently monitored is greater than the expected construction progress at the same time, the actual construction progress is considered to be ahead of schedule; determine whether the current actual construction progress meets the safety standards. If so, maintain the original construction status; otherwise, confirm the hydraulic structures currently under construction and the construction equipment used, and generate control instructions to slow down the operation speed of the construction equipment;
[0031] If the actual construction progress currently monitored is less than the expected construction progress at the same time, the actual construction progress is deemed to be lagging behind; the hydraulic structures currently under construction and the construction equipment used are confirmed, and control instructions are generated to speed up the operation of the construction equipment.
[0032] Optionally, the specific method of fund settlement is:
[0033] When the water conservancy project meets the acceptance criteria, obtain the human resources, materials and construction equipment inputs used to complete the water conservancy project and fill in the cost list;
[0034] According to the cost list and the project completion rate, calculate the labor costs, material costs and equipment costs to obtain the final financial settlement results.
[0035] A water conservancy project process control and fund settlement management system, comprising:
[0036] The project classification module is used to classify the water conservancy projects to be built according to preset rules and establish corresponding acceptance standards;
[0037] The model building module is used to establish a refined three-dimensional BIM model of the water conservancy project according to the construction design drawings and construction plans, and generate a planned construction model in combination with the various stages of project classification;
[0038] Dynamic adjustment module, used to obtain the actual construction progress through intelligent devices, generate control instructions based on the expected construction progress of the planned construction model, and automatically adjust the operating speed of the construction equipment;
[0039] The fund settlement module is used to determine whether the acceptance conditions are met and complete the fund settlement based on the actual construction progress and corresponding acceptance standards.
[0040] It can be seen from the above technical solutions that, compared with the prior art, the present invention discloses a method and system for water conservancy project process control and fund settlement management, which can understand the actual progress of water conservancy project construction in real time, adjust the operating speed of construction equipment according to the actual construction situation, handle the delay problem of construction progress, and ensure that the task is completed on schedule. When the project construction meets the acceptance conditions, the fund settlement is completed according to the actual construction situation. BRIEF DESCRIPTION OF THE DRAWINGS
[0041] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.
[0042] Figure 1 A flow chart of the water conservancy project process control and fund settlement management method provided by the present invention;
[0043] Figure 2 This is a structural diagram of the water conservancy project process control and fund settlement management system provided by the present invention. DETAILED DESCRIPTION
[0044] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0045] The construction of water conservancy projects is large-scale and involves a wide range of aspects. It is affected by factors such as technology, nature, construction links, financial pressure, construction organization design, and engineering accidents, and the progress of the project is difficult to control. In order to ensure that the task is completed on schedule, the embodiment of the present invention discloses a water conservancy project process control and fund settlement management method, such as Figure 1 As shown, the following steps are included:
[0046] Classify the water conservancy projects to be built according to the preset rules and establish corresponding acceptance standards;
[0047] According to the construction design drawings and construction plans, a refined 3D BIM model of the water conservancy project is established, and a planned construction model is generated in combination with each stage of project classification;
[0048] Use smart devices to obtain the actual construction progress, generate control instructions based on the expected construction progress of the planned construction model, and automatically adjust the operating speed of the construction equipment;
[0049] Based on the actual construction progress and corresponding acceptance standards, determine whether the acceptance conditions are met and complete the financial settlement.
[0050] based on Figure 1 As shown in the process control and financial settlement management flow, this embodiment first classifies the water conservancy project to be built before the construction begins, and establishes acceptance standards for projects at each level; combines the three-dimensional model of the water conservancy project with the project classification results to generate a planned construction model related to the construction progress; adjusts the operating speed of the construction equipment according to the actual construction progress and the expected construction progress to avoid delays in the construction progress and affect the final project acceptance and financial settlement.
[0051] Furthermore, the water conservancy projects to be built are classified according to the preset rules, specifically:
[0052] Obtain project information of the water conservancy project to be built and build a basic data model of the project;
[0053] According to the construction stage of the project, the water conservancy project to be built will be divided into unit projects, branch projects and unit projects by adding tasks, editing tasks, deleting tasks, and moving tasks up, down, upgrading or downgrading.
[0054] Due to the large scale of water conservancy projects, it takes a lot of time and manpower to quantify and count a series of important indicators such as the progress of each stage and the overall project, the degree of completion, and the calculation of the completion cost, which makes it difficult for the person in charge to grasp the details of the project in real time, make accurate decisions, and achieve refined management. However, this embodiment can disassemble the project at different stages, and all subsequent adjustments are based on the basic data model, which can solve the problems existing in the traditional project management method, significantly improve the management and decision-making level of the project leader, and improve management efficiency.
[0055] Furthermore, corresponding acceptance criteria are established, specifically:
[0056] The acceptance of water conservancy projects is divided into two stages: completion acceptance and completion acceptance. The acceptance criteria for the completion acceptance stage are the execution of the construction contract and whether the project quality meets the requirements for production. The acceptance criteria for the completion acceptance stage are that the comprehensive evaluation results of the project quality, participating units and construction projects meet the preset requirements.
[0057] Furthermore, a refined three-dimensional BIM model of the water conservancy project is established, which specifically includes the following steps:
[0058] Analyze the construction plan of each hydraulic structure in the water conservancy project to be built (the analysis is mainly based on parallel construction of each process as much as possible and reducing mutual interference among each process), and formulate a construction plan based on the analysis results;
[0059] According to the construction design drawings and construction plans, BIM technology is used to construct a refined three-dimensional BIM model of the water conservancy project that meets the specifications.
[0060] Furthermore, a planned construction model is generated, specifically:
[0061] Based on the construction plan of the water conservancy project to be built, confirm the expected construction progress of the project;
[0062] Combine the expected construction progress with the refined 3D BIM model of the constructed water conservancy project to build an initial planned construction model;
[0063] Based on the project classification results, the initial planned construction model is divided into time series to obtain the planned construction model of each sub-project.
[0064] Furthermore, the actual construction progress is obtained by using smart devices, specifically:
[0065] The image information of the water conservancy project construction is obtained by using the image acquisition device set up at the construction site;
[0066] According to the image information, the status of construction equipment and hydraulic structures is obtained to determine the construction progress nodes;
[0067] A comparative analysis was conducted based on the refined three-dimensional BIM model of the water conservancy project to obtain the actual construction progress.
[0068] In traditional engineering projects, the project leader usually controls the construction progress of the project and analyzes the status of the construction progress by collecting a large amount of project data, but this process requires a lot of manpower. However, this embodiment performs image recognition on the collected on-site construction images to obtain the number of equipment and the current construction status of hydraulic structures, and can judge the progress status in combination with the established three-dimensional model, which can help the project leader control the construction progress conveniently and quickly.
[0069] Furthermore, the operating speed of the construction equipment is automatically adjusted, specifically:
[0070] According to the planned construction model, obtain the expected construction progress at the current moment;
[0071] If the actual construction progress currently monitored is greater than the expected construction progress at the same time, the actual construction progress is considered to be ahead of schedule; determine whether the current actual construction progress meets the safety standards. If so, maintain the original construction status; otherwise, confirm the hydraulic structures currently under construction and the construction equipment used, and generate control instructions to slow down the operation speed of the construction equipment;
[0072] If the actual construction progress currently monitored is less than the expected construction progress at the same time, the actual construction progress is deemed to be lagging behind; the hydraulic structures currently under construction and the construction equipment used are confirmed, and control instructions are generated to speed up the operation of the construction equipment.
[0073] In this embodiment, the expected construction progress at the current moment can be understood through the established planned construction model, and the actual construction progress at the current moment can be confirmed by using the construction site image. By comparing the two, it can be determined whether the construction progress is ahead or behind. If the construction progress is behind, the operation speed of the construction equipment can be automatically accelerated to speed up the construction progress and ensure that the water conservancy project can be completed on schedule; if the construction progress is ahead, further attention needs to be paid to whether it meets the safety standards. If it does not meet the standards, the adverse consequences caused by the excessively fast construction progress can be avoided by slowing down the operation speed of the construction equipment.
[0074] Furthermore, the specific method of fund settlement is:
[0075] When the water conservancy project meets the acceptance criteria, obtain the human resources, materials and construction equipment inputs used to complete the water conservancy project and fill in the cost list;
[0076] According to the cost list and the project completion rate, calculate the labor costs, material costs and equipment costs to obtain the final financial settlement results.
[0077] and Figure 1 Corresponding to the method described above, the embodiment of the present invention also provides a water conservancy project process control and fund settlement management system for Figure 1 The specific implementation of the method in the embodiment of the present invention provides a water conservancy project process control and fund settlement management system which can be applied to a computer terminal or various mobile devices, such as Figure 2 As shown, specifically including:
[0078] The project classification module is used to classify the water conservancy projects to be built according to preset rules and establish corresponding acceptance standards;
[0079] The model building module is used to establish a refined three-dimensional BIM model of the water conservancy project according to the construction design drawings and construction plans, and generate a planned construction model in combination with the various stages of project classification;
[0080] Dynamic adjustment module, used to obtain the actual construction progress through intelligent devices, generate control instructions based on the expected construction progress of the planned construction model, and automatically adjust the operating speed of the construction equipment;
[0081] The fund settlement module is used to determine whether the acceptance conditions are met and complete the fund settlement based on the actual construction progress and corresponding acceptance standards.
[0082] In this specification, each embodiment is described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the embodiments can be referred to each other. For the system disclosed in the embodiment, since it corresponds to the method disclosed in the embodiment, the description is relatively simple, and the relevant parts can be referred to the method part.
[0083] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A method for water conservancy project process control and fund settlement management, characterized in that: The following steps are involved: Classify the water conservancy projects to be built according to the preset rules and establish corresponding acceptance standards; According to the construction design drawings and construction plans, a refined 3D BIM model of the water conservancy project is established, and a planned construction model is generated in combination with each stage of project classification; Use smart devices to obtain the actual construction progress, generate control instructions based on the expected construction progress of the planned construction model, and automatically adjust the operating speed of the construction equipment; Based on the actual construction progress and corresponding acceptance standards, determine whether the acceptance conditions are met and complete the financial settlement.
2. A method for water conservancy project process control and fund settlement management according to claim 1, characterized in that: The water conservancy projects to be built are classified according to the preset rules, specifically: Obtain project information of the water conservancy project to be built and build a basic data model of the project; According to the construction stage of the project, the water conservancy project to be built will be divided into unit projects, branch projects and unit projects by adding tasks, editing tasks, deleting tasks, and moving tasks up, down, upgrading or downgrading.
3. A method for water conservancy project process control and fund settlement management according to claim 1, characterized in that: Establish corresponding acceptance criteria, specifically: The acceptance of water conservancy projects is divided into two stages: completion acceptance and completion acceptance. The acceptance criteria for the completion acceptance stage are the execution of the construction contract and whether the project quality meets the requirements for production. The acceptance criteria for the completion acceptance stage are that the comprehensive evaluation results of the project quality, participating units and construction projects meet the preset requirements.
4. A method for water conservancy project process control and fund settlement management according to claim 1, characterized in that: Establishing a refined 3D BIM model for a water conservancy project includes the following steps: Based on the principle of parallel construction of each process and avoiding mutual interference, the construction plan arrangement analysis of each hydraulic structure in the water conservancy project to be built is carried out, and the construction plan is formulated based on the analysis results; According to the construction design drawings and construction plans, BIM technology is used to construct a refined three-dimensional BIM model of the water conservancy project that meets the specifications.
5. A method for water conservancy project process control and fund settlement management according to claim 1, characterized in that: Generate a planned construction model, specifically: Based on the construction plan of the water conservancy project to be built, confirm the expected construction progress of the project; Combine the expected construction progress with the refined 3D BIM model of the constructed water conservancy project to build an initial planned construction model; Based on the project classification results, the initial planned construction model is divided into time series to obtain the planned construction model of each sub-project.
6. A method for water conservancy project process control and fund settlement management according to claim 1, characterized in that: Use smart devices to obtain actual construction progress, specifically: The image information of the water conservancy project construction is obtained by using the image acquisition device set up at the construction site; According to the image information, the status of construction equipment and hydraulic structures is obtained to determine the construction progress nodes; A comparative analysis was conducted based on the refined three-dimensional BIM model of the water conservancy project to obtain the actual construction progress.
7. A method for water conservancy project process control and fund settlement management according to claim 1, characterized in that: Automatically adjust the operating speed of construction equipment, specifically: According to the planned construction model, obtain the expected construction progress at the current moment; If the actual construction progress currently monitored is greater than the expected construction progress at the same time, the actual construction progress is considered to be ahead of schedule; determine whether the current actual construction progress meets the safety standards. If so, maintain the original construction status; otherwise, confirm the hydraulic structures currently under construction and the construction equipment used, and generate control instructions to slow down the operation speed of the construction equipment; If the actual construction progress currently monitored is less than the expected construction progress at the same time, the actual construction progress is deemed to be lagging behind; the hydraulic structures currently under construction and the construction equipment used are confirmed, and control instructions are generated to speed up the operation of the construction equipment.
8. A method for water conservancy project process control and fund settlement management according to claim 1, characterized in that: The specific methods of fund settlement are as follows: When the water conservancy project meets the acceptance criteria, obtain the human resources, materials and construction equipment inputs used to complete the water conservancy project and fill in the cost list; According to the cost list and the project completion rate, calculate the labor costs, material costs and equipment costs to obtain the final financial settlement results.
9. A system for implementing a water conservancy project process control and fund settlement management method as claimed in any one of claims 1 to 8, characterized in that: include: The project classification module is used to classify the water conservancy projects to be built according to preset rules and establish corresponding acceptance standards; The model building module is used to establish a refined three-dimensional BIM model of the water conservancy project according to the construction design drawings and construction plans, and generate a planned construction model in combination with the various stages of project classification; Dynamic adjustment module, used to obtain the actual construction progress through intelligent devices, generate control instructions based on the expected construction progress of the planned construction model, and automatically adjust the operating speed of the construction equipment; The fund settlement module is used to determine whether the acceptance conditions are met and complete the fund settlement based on the actual construction progress and corresponding acceptance standards.
Citation Information
Patent Citations
Engineering cost control method based on BIM technology
CN108550020A
BIM-based track engineering construction progress information management method
CN108596423A
Project cost control system based on BIM technology
CN111222786A
Pile plate type soilless roadbed highway construction process
CN111705575A
Digital process and method for supervising civil engineering project experimental detection
CN112101893A
Cited By
Water conservancy project whole-process comprehensive management platform based on modeling technology
CN120258224A