Underground pipeline area pile group construction path planning method and system based on BIM
The information model of underground pipelines and pile foundations is generated by BIM-based methods, and the shield construction route is planned using dynamic planning algorithms, which solves the high cost and safety hazards caused by relying on labor in the existing technology, and achieves more efficient and safe Construction route planning.
Patent Information
- Application Number
- CN202411326056.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-23
- Publication Date
- 2025-02-14
Smart Images

Figure CN119443429A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of data processing, and in particular to a method and system for planning a construction path of underground pipeline area pile groups based on BIM. Background Art
[0002] Shield construction is generally carried out underground. Due to the existence of very complex pipelines and pile foundations during the construction process, the construction difficulty and risk are high, which places high demands on the planning level of the construction route. If the construction planning is not good, it is easy to cause construction risks or even construction accidents due to pipeline damage or pile foundation structure damage. Existing shield construction route planning technology often relies on manual consideration of the preliminary pipeline detection and investigation results to plan the construction route, and does not consider combining data analysis algorithms to achieve intelligent route planning. Therefore, the existing solutions rely too much on manual judgment, with high labor costs and prone to errors, and cannot guarantee construction efficiency and construction safety. It can be seen that the existing technology has defects that need to be solved urgently. Summary of the invention
[0003] The technical problem to be solved by the present invention is to provide a BIM-based underground pipeline area pile group construction path planning method and system, which can plan and calculate the shield construction route more reasonably and efficiently, improve the visualization of underground construction plans, and reduce labor costs and construction accidents.
[0004] In order to solve the above technical problems, the first aspect of the present invention discloses a BIM-based underground pipeline area pile group construction path planning method, the method comprising: Obtain underground pipeline data and pile foundation distribution records in the target construction area; Generate an underground BIM model corresponding to the target construction area according to the underground pipeline data and pile foundation distribution records, and preset modeling rules; Determine the objective function and restriction conditions of route planning according to the shield construction type and shield construction requirements corresponding to the target construction area; According to the objective function and the constraints, based on the dynamic programming algorithm, the corresponding shield construction route is calculated in the underground BIM model.
[0005] As an optional embodiment, in the first aspect of the present invention, the underground pipeline data includes multiple underground pipelines in the target construction area and corresponding pipeline parameters; the pipeline parameters include pipeline diameter, pipeline material, pipeline type and pipeline depth.
[0006] As an optional embodiment, in the first aspect of the present invention, the pile foundation distribution record includes multiple pile foundation positions and corresponding pile foundation parameters; the pile foundation parameters include pile foundation type and pile foundation diameter; the pile foundation type is a combination of one or more of friction piles, end-bearing piles, non-soil-squeezing piles, partially soil-squeezing piles, soil-squeezing piles, single-row piles and multiple-row piles.
[0007] As an optional implementation, in the first aspect of the present invention, generating an underground BIM model corresponding to the target construction area according to the underground pipeline data and pile foundation distribution records and preset modeling rules includes: Generate a basic BIM model corresponding to the target construction area according to the area information corresponding to the target construction area; For each of the underground pipelines, according to the correspondence between the preset pipeline parameters and the model parameters and the pipeline parameters corresponding to the underground pipeline, determine the pipeline model parameters corresponding to the underground pipeline; Generate a pipeline model corresponding to each underground pipeline in the basic BIM model according to the pipeline model parameters; For each of the pile foundation positions, according to the correspondence between the preset pile foundation parameters and the model parameters and the pile foundation parameters corresponding to the pile foundation position, determining the pile model parameters corresponding to the pile foundation position; Generating a pile foundation model corresponding to each pile foundation position in the basic BIM model according to the pile model parameters; The basic BIM model including the pipeline model and the pile foundation model is determined as the underground BIM model corresponding to the target construction area.
[0008] As an optional implementation, in the first aspect of the present invention, the basic BIM model including the pipeline model and the pile foundation model is determined as the underground BIM model corresponding to the target construction area, including: Determine the pipeline model and the pile foundation model, two mutually located distances of which are less than a first distance threshold, as a group of dangerous models; For each group of danger models, obtaining pipeline model parameters of the pipeline model and pile model parameters of the pile foundation model in the group of danger models; Inputting the pipeline model parameters and pile model parameters of the group of hazard models into the trained associated risk prediction model to obtain the associated risk type corresponding to the group of hazard models; the associated risk type includes at least one of water seepage risk, electric leakage risk, flammable material leakage risk, pile lateral stability risk and pile end stability risk; marking the associated risk type to the pipeline model and the pile foundation model in the group of hazard models; The basic BIM model including the pipeline model and the pile foundation model and the corresponding annotations of the associated risk types is determined as the underground BIM model corresponding to the target construction area.
[0009] As an optional implementation, in the first aspect of the present invention, determining the objective function and restriction conditions of route planning according to the shield construction type and shield construction requirements corresponding to the target construction area includes: Determine the construction difficulty limit according to the shield construction type corresponding to the target construction area and the correspondence between the preset construction type and the construction difficulty; Determine construction cost limits and construction time limits according to shield construction requirements corresponding to the target construction area; Determine the objective function to minimize the route length and route complexity corresponding to the construction route plan; Determining the restriction conditions includes that the predicted construction cost corresponding to the construction route plan meets the construction cost restriction, the predicted construction time corresponding to the construction route plan meets the construction time restriction, and the predicted construction difficulty corresponding to the construction route plan meets the construction difficulty restriction.
[0010] As an optional embodiment, in the first aspect of the present invention, the predicted construction cost, the predicted construction time and the predicted construction difficulty are calculated by inputting the route model data corresponding to the construction route plan into a trained construction parameter prediction model; the construction parameter prediction model is trained by a training data set including multiple training construction route model data and corresponding construction parameter annotations; the construction parameter annotations include construction cost annotations, construction time annotations and construction difficulty annotations; the route model data and the training route model data include model data covered by the route range corresponding to the construction route plan in the underground BIM model; the route range is the union of multiple circle ranges formed with a route point on the construction route plan as the center and a preset radius.
[0011] As an optional implementation, in the first aspect of the present invention, the step of calculating the corresponding shield construction route in the underground BIM model based on the objective function and the constraint conditions and based on a dynamic programming algorithm includes: Iteratively generating a construction route plan in the underground BIM model based on a random route generation algorithm; During the calculation process, the construction parameters corresponding to the construction route scheme are predicted based on the construction parameter prediction model to obtain a prediction result, and the construction route scheme whose prediction result satisfies the restriction condition is retained; Iterate the calculation until the retained construction route plan meets the objective function, converge to obtain the optimal construction route plan, and determine it as the corresponding shield construction route.
[0012] A second aspect of an embodiment of the present invention discloses a BIM-based underground pipeline area pile group construction path planning system, the system comprising: An acquisition module is used to obtain underground pipeline data and pile foundation distribution records in the target construction area; A modeling module, used to generate an underground BIM model corresponding to the target construction area according to the underground pipeline data and pile foundation distribution records, and preset modeling rules; A determination module, used to determine the objective function and restriction conditions of route planning according to the shield construction type and shield construction requirements corresponding to the target construction area; The calculation module is used to calculate the corresponding shield construction route in the underground BIM model based on the objective function and the constraint conditions and based on the dynamic programming algorithm.
[0013] As an optional embodiment, in the second aspect of the present invention, the underground pipeline data includes multiple underground pipelines in the target construction area and corresponding pipeline parameters; the pipeline parameters include pipeline diameter, pipeline material, pipeline type and pipeline depth.
[0014] As an optional embodiment, in the second aspect of the present invention, the pile foundation distribution record includes multiple pile foundation positions and corresponding pile foundation parameters; the pile foundation parameters include pile foundation type and pile foundation diameter; the pile foundation type is a combination of one or more of friction piles, end-bearing piles, non-soil-squeezing piles, partial soil-squeezing piles, soil-squeezing piles, single-row piles and multiple-row piles.
[0015] As an optional implementation, in the second aspect of the present invention, the modeling module generates a specific manner of the underground BIM model corresponding to the target construction area according to the underground pipeline data and pile foundation distribution records and preset modeling rules, including: Generate a basic BIM model corresponding to the target construction area according to the area information corresponding to the target construction area; For each of the underground pipelines, according to the correspondence between the preset pipeline parameters and the model parameters and the pipeline parameters corresponding to the underground pipeline, determine the pipeline model parameters corresponding to the underground pipeline; Generate a pipeline model corresponding to each underground pipeline in the basic BIM model according to the pipeline model parameters; For each of the pile foundation positions, according to the correspondence between the preset pile foundation parameters and the model parameters and the pile foundation parameters corresponding to the pile foundation position, determining the pile model parameters corresponding to the pile foundation position; Generating a pile foundation model corresponding to each pile foundation position in the basic BIM model according to the pile model parameters; The basic BIM model including the pipeline model and the pile foundation model is determined as the underground BIM model corresponding to the target construction area.
[0016] As an optional implementation, in the second aspect of the present invention, the modeling module determines the basic BIM model including the pipeline model and the pile foundation model as a specific manner of the underground BIM model corresponding to the target construction area, including: Determine the pipeline model and the pile foundation model, two mutually located distances of which are less than a first distance threshold, as a group of dangerous models; For each group of danger models, obtaining pipeline model parameters of the pipeline model and pile model parameters of the pile foundation model in the group of danger models; Inputting the pipeline model parameters and pile model parameters of the group of hazard models into the trained associated risk prediction model to obtain the associated risk type corresponding to the group of hazard models; the associated risk type includes at least one of water seepage risk, electric leakage risk, flammable material leakage risk, pile lateral stability risk and pile end stability risk; marking the associated risk type to the pipeline model and the pile foundation model in the group of hazard models; The basic BIM model including the pipeline model and the pile foundation model and the corresponding annotations of the associated risk types is determined as the underground BIM model corresponding to the target construction area.
[0017] As an optional implementation, in the second aspect of the present invention, the determination module determines the specific manner of the objective function and restriction conditions of the route planning according to the shield construction type and shield construction requirements corresponding to the target construction area, including: Determine the construction difficulty limit according to the shield construction type corresponding to the target construction area and the correspondence between the preset construction type and the construction difficulty; Determine construction cost limits and construction time limits according to shield construction requirements corresponding to the target construction area; Determine the objective function to minimize the route length and route complexity corresponding to the construction route plan; Determining the restriction conditions includes that the predicted construction cost corresponding to the construction route plan meets the construction cost restriction, the predicted construction time corresponding to the construction route plan meets the construction time restriction, and the predicted construction difficulty corresponding to the construction route plan meets the construction difficulty restriction.
[0018] As an optional embodiment, in the second aspect of the present invention, the predicted construction cost, the predicted construction time and the predicted construction difficulty are calculated by inputting the route model data corresponding to the construction route plan into a trained construction parameter prediction model; the construction parameter prediction model is trained by a training data set including multiple training construction route model data and corresponding construction parameter annotations; the construction parameter annotations include construction cost annotations, construction time annotations and construction difficulty annotations; the route model data and the training route model data include model data covered by the route range corresponding to the construction route plan in the underground BIM model; the route range is the union of multiple circle ranges formed with a route point on the construction route plan as the center and a preset radius.
[0019] As an optional implementation, in the second aspect of the present invention, the calculation module calculates the specific method of the corresponding shield construction route in the underground BIM model based on the objective function and the constraint conditions and based on the dynamic programming algorithm, including: Iteratively generating a construction route plan in the underground BIM model based on a random route generation algorithm; During the calculation process, the construction parameters corresponding to the construction route scheme are predicted based on the construction parameter prediction model to obtain a prediction result, and the construction route scheme whose prediction result satisfies the restriction condition is retained; Iterate the calculation until the retained construction route plan meets the objective function, converge to obtain the optimal construction route plan, and determine it as the corresponding shield construction route.
[0020] The third aspect of the present invention discloses another BIM-based underground pipeline area pile group construction path planning system, the system comprising: A memory storing executable program code; a processor coupled to the memory; The processor calls the executable program code stored in the memory to execute part or all of the steps in the BIM-based underground pipeline area pile group construction path planning method disclosed in the first aspect of the present invention.
[0021] The fourth aspect of the present invention discloses a computer storage medium, which stores computer instructions. When the computer instructions are called, they are used to execute some or all of the steps in the BIM-based underground pipeline area pile group construction path planning method disclosed in the first aspect of the present invention.
[0022] Compared with the prior art, the embodiments of the present invention have the following beneficial effects: The present invention can generate an underground BIM model corresponding to the target construction area based on underground pipeline data and pile foundation distribution records, and then determine the objective function and restriction conditions of route planning based on the shield construction type and shield construction requirements, thereby calculating an accurate shield construction route in the BIM model based on a dynamic programming algorithm, thereby being able to plan and calculate the shield construction route more reasonably and efficiently, and improving the visualization of underground construction plans, reducing labor costs and construction accidents. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0024] Figure 1 It is a flow chart of a method for planning the construction path of underground pipeline area pile groups based on BIM disclosed in an embodiment of the present invention.
[0025] Figure 2 It is a structural schematic diagram of a BIM-based underground pipeline area pile group construction path planning system disclosed in an embodiment of the present invention.
[0026] Figure 3 It is a structural schematic diagram of another BIM-based underground pipeline area pile group construction path planning system disclosed in an embodiment of the present invention. DETAILED DESCRIPTION
[0027] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0028] The terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish different objects, rather than to describe a specific order. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, device, product or equipment that includes a series of steps or units is not limited to the listed steps or units, but may optionally include steps or units that are not listed, or may optionally include other steps or units that are inherent to these processes, methods, products or equipment.
[0029] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present invention. The appearance of the phrase in various places in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.
[0030] The present invention discloses a method and system for planning the path of underground pipeline area pile group construction based on BIM, which can generate an underground BIM model corresponding to the target construction area based on underground pipeline data and pile foundation distribution records, and then determine the objective function and restriction conditions of route planning based on shield construction type and shield construction requirements, thereby calculating an accurate shield construction route in the BIM model based on a dynamic programming algorithm, so that the shield construction route can be planned and calculated more reasonably and efficiently, and the visualization of underground construction plans can be improved, reducing labor costs and construction accidents. The following are detailed descriptions.
[0031] Embodiment 1 See also Figure 1 , Figure 1 The following is a flow chart of a method for planning the construction path of underground pipeline area piles based on BIM according to an embodiment of the present invention. Figure 1 The BIM-based underground pipeline area pile group construction path planning method described above can be applied to a data processing system / data processing device / data processing server (wherein the server includes a local processing server or a cloud processing server). Figure 1 As shown, the BIM-based underground pipeline area pile group construction path planning method may include the following operations: 101. Obtain underground pipeline data and pile foundation distribution records in the target construction area.
[0032] 102. Generate an underground BIM model corresponding to the target construction area based on the underground pipeline data and pile foundation distribution records, as well as the preset modeling rules.
[0033] 103. Determine the objective function and restriction conditions of route planning according to the shield construction type and shield construction requirements corresponding to the target construction area.
[0034] 104. According to the objective function and constraints, based on the dynamic programming algorithm, the corresponding shield construction route is calculated in the underground BIM model.
[0035] It can be seen that the above-mentioned embodiments of the invention can generate an underground BIM model corresponding to the target construction area based on the underground pipeline data and pile foundation distribution records, and then determine the objective function and restriction conditions of the route planning based on the shield construction type and shield construction requirements, thereby calculating the precise shield construction route in the BIM model based on the dynamic programming algorithm, so that the shield construction route can be planned and calculated more reasonably and efficiently, and the visualization of the underground construction plan can be improved, reducing labor costs and construction accidents.
[0036] As an optional embodiment, in the above steps, the underground pipeline data includes multiple underground pipelines in the target construction area and corresponding pipeline parameters; the pipeline parameters include pipeline diameter, pipeline material, pipeline type and pipeline depth.
[0037] It can be seen that through the above-mentioned optional embodiments, the content of underground pipeline data is limited, which can be used to accurately characterize the pipeline conditions in the construction area, facilitate the subsequent generation of safer shield construction routes, assist in more reasonable and efficient planning and calculation of shield construction routes, and improve the visualization of underground construction plans, reducing labor costs and construction accidents.
[0038] As an optional embodiment, in the above steps, the pile foundation distribution record includes multiple pile foundation positions and corresponding pile foundation parameters; the pile foundation parameters include pile foundation type and pile foundation diameter; the pile foundation type is a combination of one or more of friction piles, end-bearing piles, non-squeezing piles, partially squeezing piles, squeezing piles, single-row piles and multiple-row piles.
[0039] It can be seen that through the above-mentioned optional embodiments, the content of the pile foundation distribution record is limited, which can be used to accurately characterize the pile foundation distribution in the construction area, facilitate the subsequent generation of safer shield construction routes, assist in more reasonable and efficient planning and calculation of shield construction routes, and improve the visualization of underground construction plans, reducing labor costs and construction accidents.
[0040] As an optional embodiment, in the above steps, generating an underground BIM model corresponding to the target construction area according to the underground pipeline data and the pile foundation distribution records and the preset modeling rules includes: Generate a basic BIM model corresponding to the target construction area based on the area information corresponding to the target construction area; For each underground pipeline, according to the correspondence between the preset pipeline parameters and the model parameters and the pipeline parameters corresponding to the underground pipeline, determine the pipeline model parameters corresponding to the underground pipeline; Generate pipeline models corresponding to each underground pipeline in the basic BIM model according to pipeline model parameters; For each pile foundation position, according to the correspondence between the preset pile foundation parameters and the model parameters and the pile foundation parameters corresponding to the pile foundation position, the pile model parameters corresponding to the pile foundation position are determined; Generate a pile foundation model corresponding to each pile foundation position in the foundation BIM model according to the pile model parameters; The basic BIM model including the pipeline model and the pile foundation model is determined as the underground BIM model corresponding to the target construction area.
[0041] It can be seen that through the above-mentioned optional embodiments, it is possible to generate pipeline models and pile foundation models according to underground pipeline data and pile foundation distribution records through the correspondence between preset pipeline parameters and pile foundation parameters and model parameters, so as to obtain an underground BIM model corresponding to an accurate construction area, thereby facilitating the subsequent generation of safer shield construction routes, assisting in more reasonable and efficient planning and calculation of shield construction routes, and improving the visualization of underground construction plans, reducing labor costs and construction accidents.
[0042] As an optional embodiment, in the above steps, the basic BIM model including the pipeline model and the pile foundation model is determined as the underground BIM model corresponding to the target construction area, including: Determine two pipeline models and pile foundation models whose mutual position distance is less than a first distance threshold as a group of dangerous models; For each group of dangerous models, pipeline model parameters of the pipeline model and pile model parameters of the pile foundation model in the group of dangerous models are obtained; Inputting the pipeline model parameters and pile model parameters of the group of hazard models into the trained associated risk prediction model to obtain the associated risk type corresponding to the group of hazard models; optionally, the associated risk type includes at least one of water seepage risk, electric leakage risk, flammable material leakage risk, pile lateral stability risk and pile end stability risk; annotating the associated risk type to the pipeline model and the pile foundation model in the group of hazard models; The basic BIM model including the pipeline model and the pile foundation model and the corresponding annotations of the associated risk types is determined as the underground BIM model corresponding to the target construction area.
[0043] It can be seen that through the above-mentioned optional embodiments, it is possible to screen models with closer distances and perform risk prediction through predictive models to achieve risk labeling of models, so as to obtain an accurate underground BIM model corresponding to the construction area, thereby facilitating the subsequent generation of safer shield construction routes, assisting in more reasonable and efficient planning and calculation of shield construction routes, and improving the visualization of underground construction plans, reducing labor costs and construction accidents.
[0044] As an optional embodiment, in the above steps, determining the objective function and restriction conditions of the route planning according to the shield construction type and shield construction requirements corresponding to the target construction area includes: Determine the construction difficulty limit based on the shield construction type corresponding to the target construction area and the correspondence between the preset construction type and construction difficulty; Determine the construction cost limit and construction time limit according to the shield construction requirements corresponding to the target construction area; Determine the objective function to minimize the route length and route complexity corresponding to the construction route plan; Determining the restriction conditions includes that the predicted construction cost corresponding to the construction route plan meets the construction cost restriction, the predicted construction time corresponding to the construction route plan meets the construction time restriction, and the predicted construction difficulty corresponding to the construction route plan meets the construction difficulty restriction.
[0045] It can be seen that through the above-mentioned optional embodiments, the shield construction type and shield construction requirements corresponding to the target construction area can be analyzed to obtain the specific difficulty limit, cost limit and time limit of the construction, so as to determine a reasonable objective function and constraint conditions, so as to facilitate the subsequent calculation of a safer and compliant shield construction route through a dynamic programming algorithm, assist in realizing a more reasonable and efficient planning and calculation of the shield construction route, and improve the visualization of underground construction plans, thereby reducing labor costs and construction accidents.
[0046] As an optional embodiment, in the above steps, the predicted construction cost, predicted construction time and predicted construction difficulty are calculated by inputting the route model data corresponding to the construction route plan into the trained construction parameter prediction model; the construction parameter prediction model is trained by a training data set including multiple training construction route model data and corresponding construction parameter annotations; the construction parameter annotations include construction cost annotations, construction time annotations and construction difficulty annotations; the route model data and the training route model data include model data covered by the route range corresponding to the construction route plan in the underground BIM model; the route range is the union of multiple circle ranges formed with a route point on the construction route plan as the center and a preset radius.
[0047] It can be seen that through the above-mentioned optional embodiments, the construction cost, construction time and construction difficulty corresponding to the shield construction route can be predicted through the trained construction parameter prediction model, so as to accurately control the calculation of the algorithm, so as to calculate a safer and more compliant shield construction route, assist in achieving more reasonable and efficient planning and calculation of the shield construction route, and improve the visualization of underground construction plans, reducing labor costs and construction accidents.
[0048] As an optional embodiment, in the above steps, according to the objective function and the constraint conditions, based on the dynamic programming algorithm, the corresponding shield construction route is calculated in the underground BIM model, including: Iteratively generate construction route plans in the underground BIM model based on a random route generation algorithm; During the calculation process, the construction parameters corresponding to the construction route plan are predicted based on the construction parameter prediction model to obtain the prediction results, and the construction route plan whose prediction results meet the restriction conditions is retained; The iterative calculation is performed until the retained construction route plan meets the objective function, and the optimal construction route plan is obtained by convergence and determined as the corresponding shield construction route.
[0049] It can be seen that through the above-mentioned optional embodiments, the construction route plan can be iteratively generated in the underground BIM model through the random route generation algorithm, and the optimal shield construction route can be calculated based on the objective function and constraints during the calculation process, so as to achieve more reasonable and efficient planning and calculation of the shield construction route, improve the visualization of the underground construction plan, and reduce labor costs and construction accidents.
[0050] Embodiment 2 See also Figure 2 , Figure 2 Schematic diagram of a BIM-based underground pipeline area pile group construction path planning system disclosed in an embodiment of the present invention. Figure 2 The BIM-based underground pipeline area pile group construction path planning system described above can be applied to a data processing system / data processing device / data processing server (wherein the server includes a local processing server or a cloud processing server). Figure 2 As shown, the BIM-based underground pipeline area pile group construction path planning system may include: The acquisition module 201 is used to acquire underground pipeline data and pile foundation distribution records in the target construction area.
[0051] The modeling module 202 is used to generate an underground BIM model corresponding to the target construction area according to the underground pipeline data and pile foundation distribution records, as well as preset modeling rules.
[0052] The determination module 203 is used to determine the objective function and restriction conditions of the route planning according to the shield construction type and shield construction requirements corresponding to the target construction area.
[0053] The calculation module 204 is used to calculate the corresponding shield construction route in the underground BIM model based on the objective function and the constraints and based on the dynamic programming algorithm.
[0054] It can be seen that the above-mentioned embodiments of the invention can generate an underground BIM model corresponding to the target construction area based on the underground pipeline data and pile foundation distribution records, and then determine the objective function and restriction conditions of the route planning based on the shield construction type and shield construction requirements, thereby calculating the precise shield construction route in the BIM model based on the dynamic programming algorithm, so that the shield construction route can be planned and calculated more reasonably and efficiently, and the visualization of the underground construction plan can be improved, reducing labor costs and construction accidents.
[0055] As an optional embodiment, the underground pipeline data includes multiple underground pipelines in the target construction area and corresponding pipeline parameters; the pipeline parameters include pipeline diameter, pipeline material, pipeline type and pipeline depth.
[0056] It can be seen that through the above-mentioned optional embodiments, the content of underground pipeline data is limited, which can be used to accurately characterize the pipeline conditions in the construction area, facilitate the subsequent generation of safer shield construction routes, assist in more reasonable and efficient planning and calculation of shield construction routes, and improve the visualization of underground construction plans, reducing labor costs and construction accidents.
[0057] As an optional embodiment, the pile foundation distribution record includes multiple pile foundation positions and corresponding pile foundation parameters; the pile foundation parameters include pile foundation type and pile foundation diameter; the pile foundation type is a combination of one or more of friction piles, end-bearing piles, non-soil-squeezing piles, partial soil-squeezing piles, soil-squeezing piles, single-row piles and multiple-row piles.
[0058] It can be seen that through the above-mentioned optional embodiments, the content of the pile foundation distribution record is limited, which can be used to accurately characterize the pile foundation distribution in the construction area, facilitate the subsequent generation of safer shield construction routes, assist in more reasonable and efficient planning and calculation of shield construction routes, and improve the visualization of underground construction plans, reducing labor costs and construction accidents.
[0059] As an optional embodiment, the modeling module generates a specific method of an underground BIM model corresponding to the target construction area according to the underground pipeline data and pile foundation distribution records and the preset modeling rules, including: Generate a basic BIM model corresponding to the target construction area based on the area information corresponding to the target construction area; For each underground pipeline, according to the correspondence between the preset pipeline parameters and the model parameters and the pipeline parameters corresponding to the underground pipeline, determine the pipeline model parameters corresponding to the underground pipeline; Generate pipeline models corresponding to each underground pipeline in the basic BIM model according to pipeline model parameters; For each pile foundation position, according to the correspondence between the preset pile foundation parameters and the model parameters and the pile foundation parameters corresponding to the pile foundation position, the pile model parameters corresponding to the pile foundation position are determined; Generate a pile foundation model corresponding to each pile foundation position in the foundation BIM model according to the pile model parameters; The basic BIM model including the pipeline model and the pile foundation model is determined as the underground BIM model corresponding to the target construction area.
[0060] It can be seen that through the above-mentioned optional embodiments, it is possible to generate pipeline models and pile foundation models according to underground pipeline data and pile foundation distribution records through the correspondence between preset pipeline parameters and pile foundation parameters and model parameters, so as to obtain an underground BIM model corresponding to an accurate construction area, thereby facilitating the subsequent generation of safer shield construction routes, assisting in more reasonable and efficient planning and calculation of shield construction routes, and improving the visualization of underground construction plans, reducing labor costs and construction accidents.
[0061] As an optional embodiment, the modeling module determines the basic BIM model including the pipeline model and the pile foundation model as the specific manner of the underground BIM model corresponding to the target construction area, including: Determine two pipeline models and pile foundation models whose mutual position distance is less than a first distance threshold as a group of dangerous models; For each group of dangerous models, pipeline model parameters of the pipeline model and pile model parameters of the pile foundation model in the group of dangerous models are obtained; Inputting the pipeline model parameters and pile model parameters of the group of hazard models into the trained associated risk prediction model to obtain the associated risk type corresponding to the group of hazard models; optionally, the associated risk type includes at least one of water seepage risk, electric leakage risk, flammable material leakage risk, pile lateral stability risk and pile end stability risk; annotating the associated risk type to the pipeline model and the pile foundation model in the group of hazard models; The basic BIM model including the pipeline model and the pile foundation model and the corresponding annotations of the associated risk types is determined as the underground BIM model corresponding to the target construction area.
[0062] It can be seen that through the above-mentioned optional embodiments, it is possible to screen models with closer distances and perform risk prediction through predictive models to achieve risk labeling of models, so as to obtain an accurate underground BIM model corresponding to the construction area, thereby facilitating the subsequent generation of safer shield construction routes, assisting in more reasonable and efficient planning and calculation of shield construction routes, and improving the visualization of underground construction plans, reducing labor costs and construction accidents.
[0063] As an optional embodiment, the determination module determines the specific manner of the objective function and restriction conditions of the route planning according to the shield construction type and shield construction requirements corresponding to the target construction area, including: Determine the construction difficulty limit based on the shield construction type corresponding to the target construction area and the correspondence between the preset construction type and construction difficulty; Determine the construction cost limit and construction time limit according to the shield construction requirements corresponding to the target construction area; Determine the objective function to minimize the route length and route complexity corresponding to the construction route plan; Determining the restriction conditions includes that the predicted construction cost corresponding to the construction route plan meets the construction cost restriction, the predicted construction time corresponding to the construction route plan meets the construction time restriction, and the predicted construction difficulty corresponding to the construction route plan meets the construction difficulty restriction.
[0064] It can be seen that through the above-mentioned optional embodiments, the shield construction type and shield construction requirements corresponding to the target construction area can be analyzed to obtain the specific difficulty limit, cost limit and time limit of the construction, so as to determine a reasonable objective function and constraint conditions, so as to facilitate the subsequent calculation of a safer and compliant shield construction route through a dynamic programming algorithm, assist in realizing a more reasonable and efficient planning and calculation of the shield construction route, and improve the visualization of underground construction plans, thereby reducing labor costs and construction accidents.
[0065] As an optional embodiment, the predicted construction cost, predicted construction time and predicted construction difficulty are calculated by inputting the route model data corresponding to the construction route plan into the trained construction parameter prediction model; the construction parameter prediction model is trained by a training data set including multiple training construction route model data and corresponding construction parameter annotations; the construction parameter annotations include construction cost annotations, construction time annotations and construction difficulty annotations; the route model data and the training route model data include model data covered by the route range corresponding to the construction route plan in the underground BIM model; the route range is the union of multiple circle ranges formed with a route point on the construction route plan as the center and a preset radius.
[0066] It can be seen that through the above-mentioned optional embodiments, the construction cost, construction time and construction difficulty corresponding to the shield construction route can be predicted through the trained construction parameter prediction model, so as to accurately control the calculation of the algorithm, so as to calculate a safer and more compliant shield construction route, assist in achieving more reasonable and efficient planning and calculation of the shield construction route, and improve the visualization of underground construction plans, reducing labor costs and construction accidents.
[0067] As an optional embodiment, the calculation module calculates the specific method of the corresponding shield construction route in the underground BIM model based on the objective function and the constraint conditions and the dynamic programming algorithm, including: Iteratively generate construction route plans in the underground BIM model based on a random route generation algorithm; During the calculation process, the construction parameters corresponding to the construction route plan are predicted based on the construction parameter prediction model to obtain the prediction results, and the construction route plan whose prediction results meet the restriction conditions is retained; The iterative calculation is performed until the retained construction route plan meets the objective function, and the optimal construction route plan is obtained by convergence and determined as the corresponding shield construction route.
[0068] It can be seen that through the above-mentioned optional embodiments, the construction route plan can be iteratively generated in the underground BIM model through the random route generation algorithm, and the optimal shield construction route can be calculated based on the objective function and constraints during the calculation process, so as to achieve more reasonable and efficient planning and calculation of the shield construction route, improve the visualization of the underground construction plan, and reduce labor costs and construction accidents.
[0069] Embodiment 3 See also Figure 3 , Figure 3 It is another BIM-based underground pipeline area pile group construction path planning system disclosed in an embodiment of the present invention. Figure 3 The BIM-based underground pipeline area pile group construction path planning system described is applied to a data processing system / data processing device / data processing server (wherein the server includes a local processing server or a cloud processing server). Figure 3 As shown, the BIM-based underground pipeline area pile group construction path planning system may include: A memory 301 storing executable program codes; a processor 302 coupled to the memory 301; The processor 302 calls the executable program code stored in the memory 301 to execute the steps of the BIM-based underground pipeline area pile group construction path planning method described in the first embodiment.
[0070] Embodiment 4 An embodiment of the present invention discloses a computer-readable storage medium storing a computer program for electronic data exchange, wherein the computer program enables a computer to execute the steps of the BIM-based underground pipeline area pile group construction path planning method described in the first embodiment.
[0071] Embodiment 5 An embodiment of the present invention discloses a computer program product, which includes a non-transitory computer-readable storage medium storing a computer program, and the computer program is operable to enable a computer to execute the steps of the BIM-based underground pipeline area pile group construction path planning method described in Example 1.
[0072] The above describes specific embodiments of the present specification, and other embodiments are within the scope of the appended claims. In some cases, the actions or steps recorded in the claims can be performed in an order different from that in the embodiments and still achieve the desired results. In addition, the processes depicted in the accompanying drawings do not necessarily have to be performed in the specific order or sequential order shown to achieve the desired results. In some embodiments, multitasking and parallel processing are also possible or may be advantageous.
[0073] The systems, devices, modules or units described in the above embodiments may be implemented by computer chips or entities, or by products with certain functions. A typical implementation device is a computer. Specifically, the computer may be, for example, a personal computer, a laptop computer, a cellular phone, a camera phone, a smart phone, a personal digital assistant, a media player, a navigation device, an email device, a game console, a tablet computer, a wearable device, or a combination of any of these devices.
[0074] For the convenience of description, the above device is described by dividing it into various units according to its functions. Of course, when implementing this specification, the functions of each unit can be implemented in the same or multiple software and / or hardware.
[0075] Those skilled in the art will appreciate that the embodiments of this specification may be provided as methods, systems, or computer program products. Therefore, the embodiments of this specification may be in the form of complete hardware embodiments, complete software embodiments, or embodiments in combination with software and hardware. Moreover, the embodiments of this specification may be in the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that contain computer-usable program code.
[0076] This specification is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of this specification. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0077] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0078] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0079] In a typical configuration, a computing device includes one or more processors (CPU), input / output interfaces, network interfaces, and memory.
[0080] The memory may include non-permanent storage in a computer-readable medium, random access memory (RAM) and / or non-volatile memory in the form of read-only memory (ROM) or flash RAM. The memory is an example of a computer-readable medium.
[0081] Computer readable media include permanent and non-permanent, removable and non-removable media that can be implemented by any method or technology to store information. Information can be computer readable instructions, data structures, program modules or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technology, compact disk read-only memory (CD-ROM), digital versatile disk (DVD) or other optical storage, magnetic cassettes, magnetic disk storage or other magnetic storage devices or any other non-transmission media that can be used to store information that can be accessed by a computing device. As defined herein, computer readable media does not include temporary computer readable media (transitory media), such as modulated data signals and carrier waves.
[0082] It should also be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, commodity or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, commodity or device. In the absence of more restrictions, the elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the process, method, commodity or device including the elements.
[0083] This specification may be described in the general context of computer-executable instructions executed by a computer, such as program modules. Generally, program modules include routines, programs, objects, components, data structures, etc. that perform specific tasks or implement specific abstract data types. This specification may also be practiced in distributed computing environments where tasks are performed by remote processing devices connected through a communication network. In a distributed computing environment, program modules may be located in local and remote computer storage media, including storage devices.
[0084] Each embodiment in this specification is described in a progressive manner, and the same or similar parts between the embodiments can be referred to each other, and each embodiment focuses on the differences from other embodiments. In particular, for the system embodiment, since it is basically similar to the method embodiment, the description is relatively simple, and the relevant parts can be referred to the partial description of the method embodiment.
[0085] Finally, it should be noted that the BIM-based underground pipeline area pile group construction path planning method and system disclosed in the embodiment of the present invention only discloses the preferred embodiment of the present invention, which is only used to illustrate the technical solution of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, ordinary technicians in this field should understand that it is still possible to modify the technical solutions recorded in the aforementioned embodiments, or to replace some of the technical features therein by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the various embodiments of the present invention.
Claims
1. A BIM-based underground pipeline area pile group construction path planning method, characterized in that: The method comprises: Obtain underground pipeline data and pile foundation distribution records in the target construction area; Generate an underground BIM model corresponding to the target construction area according to the underground pipeline data and pile foundation distribution records, and preset modeling rules; Determine the objective function and restriction conditions of route planning according to the shield construction type and shield construction requirements corresponding to the target construction area; According to the objective function and the constraints, based on the dynamic programming algorithm, the corresponding shield construction route is calculated in the underground BIM model.
2. The BIM-based underground pipeline area pile group construction path planning method according to claim 1 is characterized in that: The underground pipeline data includes a plurality of underground pipelines in the target construction area and corresponding pipeline parameters; the pipeline parameters include pipeline diameter, pipeline material, pipeline type and pipeline depth.
3. The BIM-based underground pipeline area pile group construction path planning method according to claim 2 is characterized in that: The pile foundation distribution record includes multiple pile foundation positions and corresponding pile foundation parameters; the pile foundation parameters include pile foundation type and pile foundation diameter; the pile foundation type is a combination of one or more of friction piles, end-bearing piles, non-soil-squeezing piles, partial soil-squeezing piles, soil-squeezing piles, single-row piles and multiple-row piles.
4. The BIM-based underground pipeline area pile group construction path planning method according to claim 3 is characterized in that: The step of generating an underground BIM model corresponding to the target construction area according to the underground pipeline data and pile foundation distribution records and preset modeling rules includes: Generate a basic BIM model corresponding to the target construction area according to the area information corresponding to the target construction area; For each of the underground pipelines, according to the correspondence between the preset pipeline parameters and the model parameters and the pipeline parameters corresponding to the underground pipeline, determine the pipeline model parameters corresponding to the underground pipeline; Generate a pipeline model corresponding to each underground pipeline in the basic BIM model according to the pipeline model parameters; For each of the pile foundation positions, according to the correspondence between the preset pile foundation parameters and the model parameters and the pile foundation parameters corresponding to the pile foundation position, determining the pile model parameters corresponding to the pile foundation position; Generating a pile foundation model corresponding to each pile foundation position in the basic BIM model according to the pile model parameters; The basic BIM model including the pipeline model and the pile foundation model is determined as the underground BIM model corresponding to the target construction area.
5. The BIM-based underground pipeline area pile group construction path planning method according to claim 4 is characterized in that: The step of determining the basic BIM model including the pipeline model and the pile foundation model as the underground BIM model corresponding to the target construction area includes: Determine the pipeline model and the pile foundation model, two mutually located distances of which are less than a first distance threshold, as a group of dangerous models; For each group of danger models, obtaining pipeline model parameters of the pipeline model and pile model parameters of the pile foundation model in the group of danger models; Inputting the pipeline model parameters and pile model parameters of the group of hazard models into the trained associated risk prediction model to obtain the associated risk type corresponding to the group of hazard models; the associated risk type includes at least one of water seepage risk, electric leakage risk, flammable material leakage risk, pile lateral stability risk and pile end stability risk; marking the associated risk type to the pipeline model and the pile foundation model in the group of hazard models; The basic BIM model including the pipeline model and the pile foundation model and the corresponding annotations of the associated risk types is determined as the underground BIM model corresponding to the target construction area.
6. The BIM-based underground pipeline area pile group construction path planning method according to claim 5 is characterized in that: Determining the objective function and restriction conditions of route planning according to the shield construction type and shield construction requirements corresponding to the target construction area includes: Determine the construction difficulty limit according to the shield construction type corresponding to the target construction area and the correspondence between the preset construction type and the construction difficulty; Determine construction cost limits and construction time limits according to shield construction requirements corresponding to the target construction area; Determine the objective function to minimize the route length and route complexity corresponding to the construction route plan; Determining the restriction conditions includes that the predicted construction cost corresponding to the construction route plan meets the construction cost restriction, the predicted construction time corresponding to the construction route plan meets the construction time restriction, and the predicted construction difficulty corresponding to the construction route plan meets the construction difficulty restriction.
7. The BIM-based underground pipeline area pile group construction path planning method according to claim 6 is characterized in that: The predicted construction cost, the predicted construction time and the predicted construction difficulty are calculated by inputting the route model data corresponding to the construction route plan into the trained construction parameter prediction model; the construction parameter prediction model is trained by a training data set including a plurality of training construction route model data and corresponding construction parameter annotations; the construction parameter annotations include construction cost annotations, construction time annotations and construction difficulty annotations; the route model data and the training route model data include model data covered by the route range corresponding to the construction route plan in the underground BIM model; the route range is the union of a plurality of circle ranges formed with a route point on the construction route plan as the center and a preset radius.
8. The BIM-based underground pipeline area pile group construction path planning method according to claim 7 is characterized in that: The method of calculating a corresponding shield construction route in the underground BIM model based on the objective function and the constraint conditions and the dynamic programming algorithm includes: Iteratively generating a construction route plan in the underground BIM model based on a random route generation algorithm; During the calculation process, the construction parameters corresponding to the construction route scheme are predicted based on the construction parameter prediction model to obtain a prediction result, and the construction route scheme whose prediction result meets the restriction condition is retained; Iterate the calculation until the retained construction route plan meets the objective function, converge to obtain the optimal construction route plan, and determine it as the corresponding shield construction route.
9. A BIM-based underground pipeline area pile group construction path planning system, characterized in that: The system comprises: An acquisition module is used to obtain underground pipeline data and pile foundation distribution records in the target construction area; A modeling module, used to generate an underground BIM model corresponding to the target construction area according to the underground pipeline data and pile foundation distribution records, and preset modeling rules; A determination module, used to determine the objective function and restriction conditions of route planning according to the shield construction type and shield construction requirements corresponding to the target construction area; The calculation module is used to calculate the corresponding shield construction route in the underground BIM model based on the objective function and the constraint conditions and based on the dynamic programming algorithm.
10. A BIM-based underground pipeline area pile group construction path planning system, characterized in that: The system comprises: A memory storing executable program code; a processor coupled to the memory; The processor calls the executable program code stored in the memory to execute the BIM-based underground pipeline area pile group construction path planning method as described in any one of claims 1-8.
Citation Information
Patent Citations
Method based on application of BIM in pipe drawing of power pipe
CN108280623A
Path planning method and device
CN111144601A
Geotechnical engineering construction dynamic optimization method and system
CN117521185A
BIM-based pipeline automatic analysis and arrangement application and construction guidance method
CN117951768A
Intelligent construction method, system and equipment for modular integrated building and medium
CN118350593A