Task offloading and scheduling methods, apparatuses, electronic devices, readable storage media, and program products

By acquiring reliable information on physical layer signal transmission in multi-relay IoT, determining task offloading areas and sub-node scheduling strategies, and constructing a task backlog queue, the problem of low reliability of task offloading in multi-relay IoT is solved, achieving network load balancing and improved task success rate.

CN119521310BActive Publication Date: 2026-11-17CHINA TELECOM CORP LTD TECHNOLOGY INNOVATION CENTER +1
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202411601289.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-11-11
Publication Date
2026-11-17
Estimated Expiration
2044-11-11

AI Technical Summary

Technical Problem

In existing technologies, task offloading reliability is low in multi-relay IoT scenarios, static resource allocation cannot solve the problem of node performance balancing, scheduling algorithms have limitations on the number of users, and complex algorithms experience significant performance degradation in large-scale scenarios.

Method used

By acquiring reliable information on physical layer signal transmission in a multi-relay network, the scheduling strategies for task offloading areas and sub-nodes are determined, a task backlog queue is constructed, resource allocation is optimized, and cross-layer scheduling is performed by combining physical layer and upper-layer network information.

Benefits of technology

It improves the reliability and accuracy of task offloading, optimizes resource utilization, and achieves network load balancing and task success rate in large-scale IoT scenarios.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119521310B_ABST
    Figure CN119521310B_ABST
Patent Text Reader

Abstract

This application relates to a task offloading scheduling method, apparatus, electronic device, computer-readable storage medium, and computer program product. The method includes: acquiring signal transmission reliability information of the physical layer in a multi-relay network; using the signal transmission reliability information to record the transmission reliability of multiple single-hop links in the physical layer; using the multiple single-hop links to realize communication between the source node and the destination node in the multi-relay network; determining the task offloading area of ​​the root node in each single-hop link based on the signal transmission reliability information of the physical layer; the task offloading area includes child nodes whose signal strength meets a preset signal strength threshold; the signal strength is the strength of the signal received by the child node from the root node; and determining the scheduling strategy of the child nodes in each task offloading area by constructing a task backlog queue for the child nodes in each task offloading area. This method can improve task offloading reliability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of communication technology, and in particular to a task offloading and scheduling method, apparatus, electronic device, computer-readable storage medium, and computer program product. Background Technology

[0002] With the rapid development of wireless communication technology, data rates have increased, and system capacity has expanded. The Internet of Things (IoT) has broad application prospects and high application value in areas such as environmental monitoring, intelligent office systems, target monitoring, and traffic flow monitoring.

[0003] For multi-relay IoT scenarios, the scheduling mechanisms in related technologies have many problems. As the number of users increases, static resource allocation cannot solve the problem of node performance balancing; scheduling algorithms have limitations on the number of users that can be scheduled, and once the number of users exceeds the threshold, the algorithm performance drops significantly, making complex scheduling algorithms unsuitable for large-scale IoT scenarios. These factors lead to low reliability of task unloading methods in practical scenarios. Summary of the Invention

[0004] Therefore, it is necessary to provide a task unloading scheduling method, apparatus, electronic device, computer-readable storage medium, and computer program product that can improve the reliability of task unloading in order to address the above-mentioned technical problems.

[0005] Firstly, this application provides a task offloading and scheduling method, including:

[0006] Obtain reliable signal transmission information of the physical layer in a multi-relay network; the reliable signal transmission information is used to record the transmission reliability of multiple single-hop links in the physical layer; the multiple single-hop links are used to realize communication between the source node and the destination node of the multi-relay network;

[0007] Based on the signal transmission reliability information of the physical layer, the task offloading area of ​​the root node in each segment of the single-hop link is determined; the task offloading area includes child nodes whose signal strength meets a preset signal strength threshold; the signal strength is the strength of the signal transmitted by the root node received by the child node;

[0008] By constructing task backlog queues for child nodes within each task unloading area, the scheduling strategy for child nodes within each task unloading area is determined.

[0009] In one embodiment, obtaining the signal transmission information of the physical layer in a multi-relay network includes:

[0010] Obtain the upper-layer update scheduling information of the physical layer in the multi-relay network;

[0011] Based on the upper-layer update scheduling information, the current network size parameters of the multi-relay network are obtained; the network size parameters include parameters related to signal transmission performance of each segment of the single-hop link.

[0012] Based on the network scale parameters, the signal transmission reliability information of the physical layer is determined.

[0013] In one embodiment, determining the signal transmission reliability information of the physical layer based on the network scale parameter includes:

[0014] Based on the parameters related to signal transmission performance of each segment of the single-hop link, determine the signal-to-noise ratio information of the destination node in each segment of the single-hop link;

[0015] Based on the signal-to-noise ratio information of the destination node in each segment of the single-hop link, the signal transmission reliability information of the physical layer is obtained.

[0016] In one embodiment, the signal-to-noise ratio (SNR) information includes SNR values, and obtaining the physical layer's signal transmission reliability information based on the SNR information of the destination node in each segment of the single-hop link includes:

[0017] Based on the signal-to-noise ratio (SNR) value of the destination node in each segment of the single-hop link, the target probability information of each segment of the single-hop link is obtained; the target probability information is used to characterize the probability that the SNR value of the destination node in the single-hop link is greater than a preset SNR threshold.

[0018] Based on the target probability information of each single-hop link, the signal transmission reliability information of the physical layer is determined.

[0019] In one embodiment, for any single-hop link segment, the signal-to-noise ratio (SNR) information of the destination node in the single-hop link segment is included on the subcarriers allocated in the single-hop link segment.

[0020] The parameters associated with signal transmission performance of any single-hop link segment include at least the current task offloading region identifier of the root node in the single-hop link segment, the current scheduling indication information of the single-hop link segment, the channel gain of the sub-channel of the single-hop link segment, the interference signal of other single-hop links to the destination node in the single-hop link segment, and the transmission signal power of the root node in the single-hop link segment.

[0021] In one embodiment, determining the task offloading region of the root node in each segment of the single-hop link based on the signal transmission reliability information of the physical layer includes:

[0022] For any single-hop link segment, if the transmission reliability of the single-hop link segment does not meet the preset conditions, obtain the task offloading area of ​​the root node in the single-hop link segment after the update.

[0023] Wherein, if the transmission reliability of any single-hop link does not meet the preset conditions, the root node in any single-hop link is used to select a new root node from the relay nodes in the multi-relay network to form a new single-hop link for the destination node in any single-hop link, and then update the current task offloading area.

[0024] In one embodiment, the step of determining the scheduling strategy for the child nodes within each task offloading region by constructing a task backlog queue for each child node within the task offloading region includes:

[0025] Obtain the signal transmission parameters and buffer status of the child nodes within each task unloading area;

[0026] Based on the signal transmission parameters of each child node and the buffer state, a task backlog queue that satisfies a preset resource allocation target is constructed under preset resource allocation constraints; the resource allocation target is to maximize the resource allocation aggregation efficiency of the child nodes in the corresponding task unloading area.

[0027] Based on the resource allocation strategy indicated by the task backlog queue, update the scheduling strategy of the child nodes in each task unloading area.

[0028] Secondly, this application also provides a task offloading scheduling apparatus, comprising:

[0029] The acquisition module is used to acquire signal transmission reliability information of the physical layer in a multi-relay network; the signal transmission reliability information is used to record the transmission reliability of multiple single-hop links in the physical layer; the multiple single-hop links are used to realize communication between the source node and the destination node of the multi-relay network;

[0030] The region determination module is used to determine the task offloading region of the root node in each segment of the single-hop link based on the signal transmission reliability information of the physical layer; the task offloading region includes child nodes whose signal strength meets a preset signal strength threshold; the signal strength is the strength of the signal transmitted by the root node received by the child node;

[0031] The strategy determination module is used to determine the scheduling strategy of the child nodes in each task unloading area by constructing the task backlog queue of the child nodes in each task unloading area.

[0032] Thirdly, this application also provides an electronic device. The electronic device includes a memory and a processor, the memory storing a computer program that, when executed by the processor, implements the steps of the method described above.

[0033] Fourthly, this application also provides a computer-readable storage medium. The computer-readable storage medium stores a computer program thereon, which, when executed by a processor, implements the steps of the above-described method.

[0034] Fifthly, this application also provides a computer program product. The computer program product includes a computer program that, when executed by a processor, implements the steps of the above-described method.

[0035] The aforementioned task offloading scheduling method, apparatus, electronic device, computer-readable storage medium, and computer program product acquire reliable signal transmission information of the physical layer in a multi-relay network. This reliable signal transmission information is used to record the transmission reliability of multiple single-hop links in the physical layer. These multiple single-hop links are used to realize communication between the source node and the destination node in the multi-relay network. Based on the reliable signal transmission information of the physical layer, the task offloading area of ​​the root node in each single-hop link is determined. The task offloading area includes child nodes whose signal strength meets a preset signal strength threshold. The signal strength is the strength of the signal received by the child node from the root node. By constructing a task backlog queue for the child nodes within each task offloading area, the scheduling strategy for the child nodes within each task offloading area is determined.

[0036] Thus, by combining reliable signal transmission information of the physical layer in a multi-relay network, the offloading region of the root node in each single-hop link used to realize communication between the source node and the destination node in the multi-relay network is determined. By constructing the task backlog queue of the child nodes in each task offloading region, the scheduling strategy of the child nodes in each task offloading region is determined, realizing the joint scheduling of upper-layer task offloading and physical layer signal transmission. This cross-layer scheduling strategy takes into account physical layer signal transmission, making the scheduling results more accurate and comprehensive, and effectively improving the reliability of task offloading. Attached Figure Description

[0037] To more clearly illustrate the technical solutions in the embodiments of this application or related technologies, the drawings used in the description of the embodiments of this application or related technologies will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this application. For those skilled in the art, other related drawings can be obtained based on these drawings without creative effort.

[0038] Figure 1 This is a flowchart illustrating a task unloading and scheduling method in one embodiment;

[0039] Figure 2 This is a flowchart illustrating the task offloading region steps based on signal transmission reliability in one embodiment.

[0040] Figure 3 This is a flowchart illustrating the steps of updating the scheduling strategy of child nodes within each task unloading area in one embodiment.

[0041] Figure 4 This is a flowchart illustrating another task unloading and scheduling method in one embodiment;

[0042] Figure 5 This is a flowchart illustrating a task unloading and scheduling method in another embodiment;

[0043] Figure 6 This is a structural block diagram of a task offloading scheduling device in one embodiment;

[0044] Figure 7 This is a diagram of the internal structure of an electronic device in one embodiment. Detailed Implementation

[0045] To make the objectives, technical solutions, and advantages of this application clearer, the following detailed description is provided in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative and not intended to limit the scope of this application.

[0046] It should be noted that the terms "first," "second," etc., used in the specification, claims, and accompanying drawings of this disclosure are used to distinguish similar objects and are not necessarily used to describe a specific order or sequence. It should be understood that such data can be interchanged where appropriate so that the embodiments of this disclosure described herein can be implemented in orders other than those illustrated or described herein. The embodiments described in the following exemplary embodiments do not represent all embodiments consistent with this disclosure. Rather, they are merely examples of apparatuses and methods consistent with some aspects of this disclosure as detailed in the appended claims.

[0047] In one embodiment, such as Figure 1 As shown, a task offloading and scheduling method is provided. This embodiment illustrates the method by applying it to an electronic device. It is understood that the electronic device can be a terminal or a cloud server. In this embodiment, the method includes the following steps:

[0048] Step S110: Obtain reliable signal transmission information of the physical layer in the multi-relay network.

[0049] The task offloading and scheduling method provided in this application can be applied to multi-relay IoT scenarios.

[0050] Among them, the signal transmission reliability information is used to record the transmission reliability of multiple single-hop links in the physical layer.

[0051] Among them, multiple single-hop links are used to realize communication between the source node and the destination node in a multi-relay network.

[0052] Among them, multi-relay network can refer to the Internet of Things (IoT) in multi-relay IoT scenarios.

[0053] In this multi-relay network, the nodes can be wireless IoT nodes.

[0054] In a multi-relay network, the multi-hop communication link between the source node and the destination node consists of multiple single-hop links.

[0055] In practical implementation, electronic devices can obtain signal transmission reliability information from the physical layer in a multi-relay network. This reliability information is used to record the transmission reliability of multiple single-hop links in the physical layer. Specifically, the signal transmission reliability information can be determined based on the upper-layer update scheduling information of the physical layer.

[0056] Step S120: Based on the reliable signal transmission information of the physical layer, determine the task offloading area of ​​the root node in each single-hop link segment.

[0057] The task unloading area includes sub-nodes whose signal strength meets a preset signal strength threshold.

[0058] The signal strength is the strength of the signal received by the child node from the root node.

[0059] In practice, electronic devices can determine the task offloading area of ​​the root node in each single-hop link based on reliable information from the physical layer signal transmission.

[0060] Specifically, for the child nodes in the task offloading area of ​​the root node in each single-hop link, they can be child nodes in a multi-relay network whose received signal strength from the root node is greater than a preset signal strength threshold.

[0061] Step S130: By constructing the task backlog queue of the child nodes in each task unloading area, the scheduling strategy of the child nodes in each task unloading area is determined.

[0062] In practice, electronic devices can determine the scheduling strategy for child nodes within each task offloading area by constructing a task backlog queue for each child node within that task offloading area.

[0063] In some embodiments, the electronic device can construct a task backlog queue of child nodes in each task offloading area that satisfies a preset resource allocation target under preset resource allocation constraints, wherein the resource allocation target is to maximize the resource allocation aggregation utility of child nodes in the task offloading area.

[0064] In the above task offloading scheduling method, reliable signal transmission information of the physical layer in the multi-relay network is obtained. This reliable signal transmission information is used to record the transmission reliability of multiple single-hop links in the physical layer. These multiple single-hop links are used to realize communication between the source node and the destination node in the multi-relay network. Based on the reliable signal transmission information of the physical layer, the task offloading area of ​​the root node in each single-hop link is determined. The task offloading area includes child nodes whose signal strength meets a preset signal strength threshold. The signal strength is the strength of the signal received by the child node from the root node. By constructing a task backlog queue for the child nodes in each task offloading area, the scheduling strategy for the child nodes in each task offloading area is determined.

[0065] Thus, by combining reliable signal transmission information of the physical layer in a multi-relay network, the offloading region of the root node in each single-hop link used to realize communication between the source node and the destination node in the multi-relay network is determined. By constructing the task backlog queue of the child nodes in each task offloading region, the scheduling strategy of the child nodes in each task offloading region is determined, realizing the joint scheduling of upper-layer task offloading and physical layer signal transmission. This cross-layer scheduling strategy takes into account physical layer signal transmission, making the scheduling results more accurate and comprehensive, and effectively improving the reliability of task offloading.

[0066] In one embodiment, obtaining signal transmission information of the physical layer in a multi-relay network includes: obtaining upper-layer update scheduling information of the physical layer in the multi-relay network; obtaining the current network scale parameters of the multi-relay network based on the upper-layer update scheduling information; the network scale parameters include parameters related to signal transmission performance of each single-hop link; and determining signal transmission reliability information of the physical layer based on the network scale parameters.

[0067] Among them, the upper-layer update scheduling information can be the update scheduling information sent from the upper layer of the physical layer to the physical layer.

[0068] The layer above the physical layer can refer to the network layer and the application layer.

[0069] In practical implementation, electronic devices can obtain upper-layer update scheduling information of the physical layer in a multi-relay network. Based on this information, they can obtain the current network scale parameters of the multi-relay network. These parameters include those related to signal transmission performance for each single-hop link. For example, network scale parameters may include the channel status corresponding to the channel allocated to a node, the signal strength of the root node and destination node in a single-hop link, the number of offloaded nodes in the root node's offload region, and buffer status data. Thus, electronic devices can determine the reliability of signal transmission at the physical layer based on these network scale parameters.

[0070] The technical solution of this embodiment obtains the upper-layer update scheduling information of the physical layer in a multi-relay network; based on the upper-layer update scheduling information, it obtains the current network scale parameters of the multi-relay network; the network scale parameters include parameters related to signal transmission performance of each single-hop link; and based on the network scale parameters, it determines the signal transmission reliability information of the physical layer. Thus, by using the upper-layer update scheduling information of the physical layer, the current network scale parameters of the multi-relay network can be obtained; the network scale parameters include parameters related to signal transmission performance of each single-hop link, thereby allowing for a more accurate determination of the transmission reliability of each single-hop link based on these parameters, and consequently, a more accurate acquisition of the signal transmission reliability information of the physical layer.

[0071] In one embodiment, determining the signal transmission reliability information of the physical layer based on network scale parameters includes: determining the signal-to-noise ratio (SNR) information of the destination node in each single-hop link based on parameters associated with signal transmission performance of each single-hop link segment; and obtaining the signal transmission reliability information of the physical layer based on the SNR information of the destination node in each single-hop link segment.

[0072] In a multi-relay network, the set of wireless IoT nodes is defined as follows: ,node , Randomly distributed in space In the middle, wireless channel resources are There are subcarriers, each with a bandwidth of . Each node The allocated channel resources are defined as follows: ( ) subcarriers, denoted as = .

[0073] Specifically, for any single-hop link segment, the parameters related to signal transmission performance of any single-hop link segment include at least the current task offloading area identifier of the root node in the single-hop link segment, the current scheduling indication information of the single-hop link segment, the channel gain of the sub-channel of the single-hop link segment, the interference signals of other single-hop links to the destination node in the single-hop link segment, and the transmission signal power of the root node in the single-hop link segment.

[0074] The task unloading area identifier is used to identify child nodes belonging to the task unloading area.

[0075] Among them, the current scheduling indication information of the single-hop link is used to characterize whether the single-hop link is scheduled on the subcarrier.

[0076] Specifically, for any single-hop link segment, the signal-to-noise ratio (SNR) information of the destination node in any single-hop link segment includes the SNR information of the destination node in any single-hop link segment on the subcarriers allocated in any single-hop link segment.

[0077] In practice, electronic devices can determine the signal-to-noise ratio (SNR) of the destination node in each single-hop link based on the parameters associated with the signal transmission performance of each single-hop link. Thus, they can obtain reliable signal transmission information at the physical layer based on the SNR of the destination node in each single-hop link.

[0078] Specifically, for any single-hop link segment, the electronic device can determine the signal-to-noise ratio (SNR) of the destination node in that single-hop link based on parameters related to its signal transmission performance. Based on the SNR of the destination node in that single-hop link, the transmission reliability of that single-hop link can be determined. Thus, based on the transmission reliability of each single-hop link segment, the signal transmission reliability information of the physical layer in a multi-relay network can be obtained.

[0079] With a certain single-hop link For example, let's explain how to calculate the signal-to-noise ratio (SNR) of the destination node in a single-hop link: At a certain moment, in a multi-relay network, a single-hop link... root node via sub-channel To single-hop link destination node Send signal, transmit signal power , destination node The obtained signal power is denoted as In subcarriers Above, single-hop link destination node The signal-to-noise ratio (SINR) can be expressed as:

[0080] ;

[0081] In the formula root node The task uninstallation area identifier. Single-hop link In subcarrier On the dispatch indicator, It is a single-hop link root node Transmitted signal power, sub-channel The channel gain is , As the attenuation factor, The distance between nodes. It is the intensity of additive white Gaussian noise. destination node Interference signals from other links were received; specifically, In addition to single-hop links Other single-hop links In addition to subcarriers Other subcarriers On the dispatch indicator, , Except for single-hop links Other single-hop links By means of subcarriers Other subcarriers The transmitted signal power, channel gain, inter-node distance, and attenuation factor.

[0082] For root node users in a single-hop link The task unloading area OZ is defined as the area where the task is received. The set of child nodes whose signal strength is higher than a preset signal strength threshold:

[0083] ;

[0084] in, The preset signal strength threshold, child node Received The signal strength; the task offloading region is a subset of the root node's coverage area.

[0085] Single-hop link The scheduling indicator, specifically in The received scheduling instruction is represented by a binary variable. It means that among them = 1 indicates that on the subcarrier Upward single-hop link Scheduled, otherwise = 0.

[0086] ;

[0087] The technical solution of this embodiment determines the signal-to-noise ratio (SNR) information of the destination node in each single-hop link based on parameters associated with signal transmission performance. Based on this SNR information, the physical layer signal transmission reliability information is obtained. Thus, by determining the SNR information of the destination node in each single-hop link based on parameters associated with signal transmission performance, and since SNR measures the ratio of effective signal to noise, the transmission reliability of the single-hop link can be accurately determined using the SNR information of the destination node in each single-hop link.

[0088] In one embodiment, the signal-to-noise ratio (SNR) information includes SNR values. Based on the SNR information of the destination node in each single-hop link segment, obtaining reliable signal transmission information for the physical layer includes: obtaining target probability information for each single-hop link segment based on the SNR values ​​of the destination node in each single-hop link segment; the target probability information characterizes the probability that the SNR value of the destination node in the single-hop link is greater than a preset SNR threshold; and determining reliable signal transmission information for the physical layer based on the target probability information of each single-hop link segment.

[0089] In specific implementation, during the process of obtaining physical layer signal transmission reliability information based on the signal-to-noise ratio (SNR) information of the destination node in each single-hop link, the electronic device can obtain target probability information of each single-hop link based on the SNR value of the destination node in each single-hop link. The target probability information is used to characterize the probability that the SNR value of the destination node in the single-hop link is greater than a preset SNR threshold. Thus, based on the target probability information of each single-hop link, the transmission reliability of each single-hop link can be determined, and the physical layer signal transmission reliability information can be obtained.

[0090] Specifically, for any single-hop link segment, the electronic device can obtain the target probability information of the single-hop link segment based on the signal-to-noise ratio (SNR) value of the destination node in the single-hop link segment; the target probability information is used to characterize the probability that the SNR value of the destination node in the single-hop link segment is greater than a preset SNR threshold.

[0091] In practical applications, in single-hop downlink middle, The scheduling strategy is determined by The decision was made on the subcarrier. The transmission reliability on the platform is:

[0092] ;

[0093] in, This is the preset signal-to-noise ratio threshold.

[0094] In this embodiment, the signal-to-noise ratio (SNR) information includes SNR values. Target probability information for each single-hop link is obtained based on the SNR values ​​of the destination nodes in each single-hop link segment. This target probability information characterizes the probability that the SNR value of the destination node in a single-hop link is greater than a preset SNR threshold. Based on the target probability information of each single-hop link segment, the signal transmission reliability information of the physical layer is determined. Thus, by calculating the SNR values ​​of the destination nodes in each single-hop link segment and evaluating the target probability information that the SNR value of the destination node in a single-hop link is greater than a preset SNR threshold, the performance of the link can be evaluated more accurately. By introducing the SNR threshold and target probability information, transmission reliability can be quantified into a specific numerical value, which is beneficial for analyzing the signal transmission performance of different single-hop links.

[0095] In one embodiment, determining the task offloading area of ​​the root node in each single-hop link based on the signal transmission reliability information of the physical layer includes: for any single-hop link, if the transmission reliability of any single-hop link does not meet the preset conditions, obtaining the updated task offloading area of ​​the root node in any single-hop link.

[0096] If the probability that the signal-to-noise ratio (SNR) of the destination node in any single-hop link is greater than a preset SNR threshold is less than a preset probability threshold, then the transmission reliability of any single-hop link is determined to be unsatisfactory under the preset conditions. In this case, the destination node in any single-hop link needs to re-network by selecting a new root node.

[0097] Specifically, the process by which the destination node in any single-hop link re-forms the network by selecting a new root node can be described as follows: based on the current network conditions and the performance of each relay node in the multi-relay network, the destination node in any single-hop link selects a new root node from among the relay nodes to form a new single-hop link for the destination node in any single-hop link. In this way, the original root node in any single-hop link can update its current task offload area, and electronic devices can obtain the updated task offload area from the original root node in any single-hop link.

[0098] The technical solution of this embodiment obtains the updated task offloading area of ​​the root node in any single-hop link when the transmission reliability of any single-hop link does not meet the preset conditions. Specifically, when the transmission reliability of any single-hop link does not meet the preset conditions, the root node in any single-hop link is used to select a new root node from the relay nodes in the multi-relay network of the destination node in any single-hop link, form a new single-hop link for the destination node in any single-hop link, and then update the current task offloading area.

[0099] In this way, by monitoring the transmission reliability of single-hop links, single-hop links whose transmission reliability does not meet preset conditions can be identified in a timely manner. The destination node in such a single-hop link can flexibly select a new root node from among the relay nodes in the multi-relay network to establish a new single-hop link based on the actual situation. This allows for timely selection of a new root node and reconstruction of the single-hop link when transmission reliability fails to meet preset conditions, increasing network redundancy and fault tolerance. Simultaneously, the original root node in a single-hop link can update its current task offloading area, resulting in the updated task offloading area of ​​the root node in the single-hop link, enabling dynamic adjustment of the root node's task offloading area. This flexibility makes resource utilization more efficient, thereby optimizing network load balancing and improving the success rate and efficiency of task offloading.

[0100] For the ease of understanding of those skilled in the art, Figure 2 A flowchart illustrating the task offloading region steps based on signal transmission reliability is provided. For example... Figure 2 As shown, by acquiring the upper-layer update scheduling information of the physical layer in a multi-relay network, and based on the physical layer signal transmission scheme, the current network scale parameters of the multi-relay network are obtained. These network scale parameters include parameters related to the signal transmission performance of each single-hop link segment, used to calculate the transmission reliability of multiple single-hop links in the physical layer. Furthermore, based on the transmission reliability of the single-hop link, it can be determined whether the destination node in the single-hop link needs to be re-networked. If not, the step of acquiring the upper-layer update scheduling information of the physical layer in the multi-relay network is repeated in the next time slot. If so, the relay nodes in the multi-relay network are updated through device discovery and service discovery, so that the destination node in the single-hop link selects a relay node as the new root node, forms a new single-hop link, and reports it to the cloud server. The original root node in this single-hop link updates the number of offload zone nodes.

[0101] In a real network environment, root node users report their location in the network to the cloud server. Child nodes then adjust thresholds based on information from the cloud server, thereby dynamically adjusting the task offloading area and transmission reliability of each root node in the network.

[0102] In one embodiment, the scheduling strategy of the child nodes in each task offloading area is determined by constructing a task backlog queue for the child nodes in each task offloading area, including: obtaining the signal transmission parameters and buffer status of the child nodes in each task offloading area; constructing a task backlog queue that satisfies a preset resource allocation target under preset resource allocation constraints based on the signal transmission parameters and buffer status of each child node; and updating the scheduling strategy of the child nodes in each task offloading area according to the resource allocation strategy indicated by the task backlog queue.

[0103] The resource allocation objective is to maximize the resource allocation aggregation efficiency of child nodes within the corresponding task unloading area.

[0104] The preset resource allocation constraints may include signal transmission reliability, physical layer transmission rate, and stability of the system's long-term average task backlog queue (cache queue).

[0105] The signal transmission parameters of the child nodes within the task offloading area may include the channel occupancy indicator of the root node, the estimated task offloading rate of the root node with each child node within the task offloading area, and the maximum task offloading rate of the child nodes.

[0106] The scheduling strategy for child nodes may include the rate of the single-hop link where the child node is located and the link scheduling factor.

[0107] In specific implementation, during the process of determining the scheduling strategy of the child nodes in each task offloading area by constructing the task backlog queue of the child nodes in each task offloading area, the electronic device can obtain the signal transmission parameters and buffer status of the child nodes in each task offloading area. Based on the signal transmission parameters and buffer status of each child node, a task backlog queue that meets the preset resource allocation target is constructed under preset resource allocation constraints. Then, according to the resource allocation strategy indicated by the task backlog queue, the scheduling strategy of the child nodes in each task offloading area is updated to obtain new upper-layer updated scheduling information.

[0108] For the ease of understanding of those skilled in the art, Figure 3 A flowchart illustrating the steps for updating the scheduling strategy of child nodes within each task's unloading area is provided. For example... Figure 3 As shown, this paper presents an optimization problem based on the physical layer signal transmission mechanism and the task backlog queue construction in the buffer area. The objective function of the optimization problem, i.e., the optimization objective, is to maximize the fair utility of each child node in the task offloading region. The constraints of the joint optimization problem include signal transmission reliability, physical layer transmission rate, and long-term average buffer queue stability of the system.

[0109] Thus, based on Lyapunov optimization theory and offset penalty optimization method, the optimization problem can be transformed into minimizing the upper bound of the Lyapunov penalty offset; then, based on the Lagrange gradient method, the minimization problem can be solved to obtain the scheduling strategy of each sub-node in the task unloading region.

[0110] In practical implementation, under the goal of ensuring fairness in child node scheduling, the resource allocation problem at the network and application layers can be modeled as maximizing the aggregate utility of nodes. The utility of a node depends on the rate and resource allocation of the users on that node. Thus, the goal of fair scheduling of child nodes can also be understood as the goal of resource allocation of child nodes. The optimization goal of the optimization problem—maximizing the fair utility of each child node within the task offloading region—can be understood as maximizing the aggregate utility of resource allocation of child nodes.

[0111] For the root node The optimization problem of the proposed task offloading scheduling method is constructed as follows:

[0112] ;

[0113] ;

[0114] ;

[0115] ;

[0116] ;

[0117] in, It refers to the weight parameters of the utility function based on proportional fairness (used as input parameters in the scheme initialization process). Represents the root node user Channel occupancy indicator, It is the root node's prediction and each child node's prediction. Task unloading rate, It is a child node Maximum task unloading rate. Considering users at the root node. The task offloading region OZ has multiple data transmission paths. The total data traffic on each link should not exceed the link capacity, as stated in the constraint: .

[0118] Introducing a task backlog queue for unloading tasks To satisfy the inequality constraints , This represents the maximum length of the task backlog queue. To satisfy the root node The maximum collision probability under the service quality requirements is defined as follows:

[0119] ;

[0120] in Each child node The actual rate. For all moments The queue satisfies ,and .

[0121] The utility function maximization problem under the aforementioned reliability constraints is solved using the Lyapunov optimization mechanism. The fair utility function is used as the penalty function, and the drift penalty (DPP) function between two consecutive time points is as follows:

[0122] ;

[0123] in For Lyapunov drift, Let be a non-negative constant representing the weight of the penalty function.

[0124] Using DPP optimization, the original optimization problem can be transformed into minimization. The upper limit. The upper bound satisfies:

[0125] ;

[0126] in It is a normal number.

[0127] To obtain the optimal solution to the optimization problem, the Lagrange function is introduced:

[0128] ;

[0129] in and is a Lagrange multiplier vector.

[0130] The multi-level optimization problem can be transformed into a minimization problem of the Lagrange function. The Lagrange dual problem can be represented as a convex problem:

[0131] ;

[0132] in:

[0133] ;

[0134] ;

[0135] ;

[0136] Using the Lagrange gradient method, for child nodes The link, the root node is in Rate of time allocation We can obtain:

[0137] ;

[0138] Based on nonlinear programming theory, the link rate scheduling algorithm for the root node belongs to the gradient algorithm in optimization theory. Therefore, when a suitable step size is selected, the algorithm is convergent, and the optimal solution to the optimization problem can be obtained through iterative loops.

[0139] In each iteration, time... The rate and link scheduling factor of each child node's single-hop link can be calculated using the following expressions:

[0140] ;

[0141] ;

[0142] At any moment Iterative Lagrange factor and for:

[0143] ;

[0144] .

[0145] Thus, the upper-level dynamic offloading scheduling method includes constructing the task backlog queue at the current moment, maximizing the fair reward function of the offloading task based on the Lyapunov algorithm, selecting appropriate child nodes and offloading rates in the task offloading region, and dynamically optimizing the offloading rate of the root node under the constraint of fair scheduling. This achieves the solution of the dynamic offloading strategy within the offloading region under the constraints of fair scheduling and queue stability, ensuring the stability of the backlog queue in the long-term evolution of nodes. Furthermore, this scheduling algorithm adopts the Lyapunov drift penalty optimization theory, which has low complexity and low overhead in terms of energy consumption, time, and computational resources.

[0146] For the purposes of understanding by those skilled in the art, Figure 4 A flowchart illustrating yet another task unloading and scheduling method is provided. For example... Figure 4 As shown, the task offloading scheduling method includes two aspects: physical layer offloading region decision mechanism and upper layer dynamic offloading scheduling.

[0147] (1) Physical layer unloading method:

[0148] The node receives the updated scheduling information from the upper layer, and based on the physical layer signal transmission mechanism, obtains channel state information and the node's signal strength, the number of nodes in the offload area, and buffer status data to calculate the transmission reliability of each single-hop link.

[0149] (2) Cloud-assisted upper-layer scheduling method:

[0150] This problem focuses on optimizing the physical layer signal transmission mechanism and buffer queue construction. The objective function of the optimization problem is to maximize the fair utility of each child node. The constraints of the joint optimization problem include user transmission reliability, physical layer transmission rate, and long-term average buffer queue stability. Based on Lyapunov optimization theory and offset penalty optimization method, the optimization problem is transformed into minimizing the upper bound of the Lyapunov penalty offset. The minimization problem is solved using the Lagrange gradient method to obtain the scheduling strategy for each child node, which is then reported to the cloud server.

[0151] The edge computing-based IoT service dynamic offloading method provided in this application can adapt well to the dynamic nature of task arrival and has low computational complexity.

[0152] Furthermore, this solution improves the scheduling mechanism, combines software algorithms to read the physical layer signal transmission status and run optimization algorithms, and guides the routing decisions and signal transmission of the lower layer through the upper-layer scheduling mechanism. It does not require adjustments to the hardware infrastructure and is practical.

[0153] Furthermore, this solution is primarily designed for multi-relay IoT and can be applied to various scenarios, including real-time control systems, large-scale IoT device and routing management, and IoT data transmission and processing in cloud-edge collaborative modes. This IoT scheduling algorithm has wide applications in real-time control, relay management, and data processing.

[0154] In another embodiment, such as Figure 5 As shown, a task offloading and scheduling method is provided. Taking the application of this method to an electronic device as an example, the method includes the following steps:

[0155] Step S502: Obtain the upper-layer update scheduling information of the physical layer in the multi-relay network.

[0156] Step S504: Based on the updated scheduling information from the upper layer, obtain the current network scale parameters of the multi-relay network.

[0157] Step S506: Determine the signal-to-noise ratio information of the destination node in each single-hop link based on the parameters related to signal transmission performance of each single-hop link segment.

[0158] Step S508: Obtain the target probability information of each single-hop link based on the signal-to-noise ratio value of the target node in each single-hop link segment.

[0159] Step S510: Determine the signal transmission reliability information of the physical layer based on the target probability information of each single-hop link segment.

[0160] Step S512: For any single-hop link, if the transmission reliability of any single-hop link does not meet the preset conditions, obtain the task offloading area of ​​the root node in any single-hop link after the update.

[0161] Step S514: Obtain the signal transmission parameters and buffer status of the child nodes in the unloading area of ​​each task.

[0162] Step S516: Based on the signal transmission parameters and buffer status of each child node, construct a task backlog queue that meets the preset resource allocation target under preset resource allocation constraints.

[0163] Step S518: Update the scheduling strategy of the child nodes in each task unloading area according to the resource allocation strategy indicated by the task backlog queue.

[0164] It should be noted that the specific limitations of the above steps can be found in the specific limitations of a task unloading and scheduling method described above.

[0165] It should be understood that although the steps in the flowcharts of the embodiments described above are shown sequentially according to the arrows, these steps are not necessarily executed in the order indicated by the arrows. Unless explicitly stated herein, there is no strict order restriction on the execution of these steps, and they can be executed in other orders. Moreover, at least some steps in the flowcharts of the embodiments described above may include multiple steps or multiple stages. These steps or stages are not necessarily completed at the same time, but can be executed at different times. The execution order of these steps or stages is not necessarily sequential, but can be performed alternately or in turn with other steps or at least some of the steps or stages of other steps.

[0166] Based on the same inventive concept, this application also provides a task offloading and scheduling apparatus for implementing the task offloading and scheduling method described above. The solution provided by this apparatus is similar to the implementation described in the above method; therefore, the specific limitations in one or more task offloading and scheduling apparatus embodiments provided below can be found in the limitations of the task offloading and scheduling method described above, and will not be repeated here.

[0167] In one exemplary embodiment, such as Figure 6 As shown, a task offloading and scheduling device is provided, including: an acquisition module 610, a region determination module 620, and a strategy determination module 630, wherein:

[0168] The acquisition module 610 is used to acquire signal transmission reliability information of the physical layer in a multi-relay network; the signal transmission reliability information is used to record the transmission reliability of multiple single-hop links in the physical layer; the multiple single-hop links are used to realize communication between the source node and the destination node of the multi-relay network.

[0169] The region determination module 620 is used to determine the task offloading region of the root node in each segment of the single-hop link based on the signal transmission reliability information of the physical layer; the task offloading region includes child nodes whose signal strength meets a preset signal strength threshold; the signal strength is the strength of the signal transmitted by the root node received by the child node.

[0170] The strategy determination module 630 is used to determine the scheduling strategy of the sub-nodes in each task unloading area by constructing a task backlog queue for the sub-nodes in each task unloading area.

[0171] In one embodiment, the acquisition module 610 is specifically used to acquire upper-layer update scheduling information of the physical layer in the multi-relay network; obtain the current network scale parameters of the multi-relay network based on the upper-layer update scheduling information; the network scale parameters include parameters related to signal transmission performance of each segment of the single-hop link; and determine the signal transmission reliability information of the physical layer based on the network scale parameters.

[0172] In one embodiment, the acquisition module 610 is specifically used to determine the signal-to-noise ratio (SNR) information of the destination node in each segment of the single-hop link based on the parameters associated with the signal transmission performance of each segment of the single-hop link; and to obtain the signal transmission reliability information of the physical layer based on the SNR information of the destination node in each segment of the single-hop link.

[0173] In one embodiment, the signal-to-noise ratio (SNR) information includes a SNR value. The acquisition module 610 is specifically used to acquire target probability information for each segment of the single-hop link based on the SNR value of the destination node in each segment of the single-hop link. The target probability information is used to characterize the probability that the SNR value of the destination node in the single-hop link is greater than a preset SNR threshold. Based on the target probability information of each segment of the single-hop link, the signal transmission reliability information of the physical layer is determined.

[0174] In one embodiment, for any single-hop link segment, the signal-to-noise ratio (SNR) information of the destination node in the single-hop link segment includes the SNR information of the destination node in the single-hop link segment on the subcarriers allocated in the single-hop link segment; the parameters related to the signal transmission performance of the single-hop link segment include at least the current task offloading region identifier of the root node in the single-hop link segment, the current scheduling indication information of the single-hop link segment, the channel gain of the sub-channel of the single-hop link segment, the interference signal of the destination node in the single-hop link segment from other single-hop links, and the transmit signal power of the root node in the single-hop link segment.

[0175] In one embodiment, the region determination module 620 is specifically used to, for any single-hop link, when the transmission reliability of the single-hop link does not meet a preset condition, obtain the updated task offloading region of the root node in the single-hop link; wherein, when the transmission reliability of the single-hop link does not meet the preset condition, the root node in the single-hop link is used to select a new root node from the relay nodes in the multi-relay network to form a new single-hop link for the destination node in the single-hop link, and then update the current task offloading region.

[0176] In one embodiment, the strategy determination module 630 is specifically used to obtain the signal transmission parameters and buffer states of the child nodes in each task unloading area; construct the task backlog queue that satisfies the preset resource allocation target under preset resource allocation constraints based on the signal transmission parameters and buffer states of each child node; the resource allocation target is to maximize the resource allocation aggregation utility of the corresponding child nodes in the task unloading area; and update the scheduling strategy of the child nodes in each task unloading area according to the resource allocation strategy indicated by the task backlog queue.

[0177] Each module in the aforementioned task offloading and scheduling device can be implemented entirely or partially through software, hardware, or a combination thereof. These modules can be embedded in the processor of the electronic device in hardware form or independent of it, or stored in the memory of the electronic device in software form, so that the processor can call and execute the operations corresponding to each module.

[0178] In one exemplary embodiment, an electronic device is provided, which may be a server, and its internal structure diagram may be as follows: Figure 7As shown, this electronic device includes a processor, memory, input / output (I / O) interfaces, and a communication interface. The processor, memory, and I / O interfaces are connected via a system bus, and the communication interface is also connected to the system bus via the I / O interfaces. The processor provides computing and control capabilities. The memory includes non-volatile storage media and internal memory. The non-volatile storage media stores the operating system, computer programs, and a database. The internal memory provides the environment for the operation of the operating system and computer programs stored in the non-volatile storage media. The database stores node identification data. The I / O interfaces are used for exchanging information between the processor and external devices. The communication interface is used for communicating with external terminals via a network connection. When the computer program is executed by the processor, it implements a task offloading and scheduling method.

[0179] Those skilled in the art will understand that Figure 7 The structure shown is merely a block diagram of a portion of the structure related to the present application and does not constitute a limitation on the electronic device to which the present application is applied. The specific electronic device may include more or fewer components than shown in the figure, or combine certain components, or have different component arrangements.

[0180] In one embodiment, an electronic device is also provided, including a memory and a processor, wherein the memory stores a computer program, and the processor executes the computer program to implement the steps in the above-described method embodiments.

[0181] In one embodiment, a computer-readable storage medium is provided having a computer program stored thereon that, when executed by a processor, implements the steps in the above method embodiments.

[0182] In one embodiment, a computer program product is provided, including a computer program that, when executed by a processor, implements the steps in the above method embodiments.

[0183] It should be noted that the user information (including but not limited to user device information, user personal information, etc.) and data (including but not limited to data used for analysis, data stored, data displayed, etc.) involved in this application are all information and data authorized by the user or fully authorized by all parties, and the collection, use and processing of the relevant data must comply with relevant regulations.

[0184] Those skilled in the art will understand that all or part of the processes in the methods of the above embodiments can be implemented by a computer program instructing related hardware. The computer program can be stored in a non-volatile computer-readable storage medium, and when executed, it can include the processes of the embodiments of the above methods. Any references to memory, databases, or other media used in the embodiments provided in this application can include at least one of non-volatile memory and volatile memory. Non-volatile memory can include read-only memory (ROM), magnetic tape, floppy disk, flash memory, optical memory, high-density embedded non-volatile memory, resistive random access memory (ReRAM), magnetic random access memory (MRAM), ferroelectric random access memory (FRAM), phase change memory (PCM), graphene memory, etc. Volatile memory can include random access memory (RAM) or external cache memory, etc. By way of illustration and not limitation, RAM can take many forms, such as Static Random Access Memory (SRAM) or Dynamic Random Access Memory (DRAM). The databases involved in the embodiments provided in this application may include at least one type of relational database and non-relational database. Non-relational databases may include, but are not limited to, blockchain-based distributed databases. The processors involved in the embodiments provided in this application may be general-purpose processors, central processing units, graphics processing units, digital signal processors, programmable logic devices, quantum computing-based data processing logic devices, artificial intelligence (AI) processors, etc., and are not limited to these.

[0185] The technical features of the above embodiments can be combined in any way. For the sake of brevity, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this application.

[0186] The embodiments described above are merely illustrative of several implementation methods of this application, and while the descriptions are specific and detailed, they should not be construed as limiting the scope of this patent application. It should be noted that those skilled in the art can make various modifications and improvements without departing from the concept of this application, and these all fall within the protection scope of this application. Therefore, the protection scope of this application should be determined by the appended claims.

Claims

1. A task offloading and scheduling method, characterized in that, The method includes: Obtain reliable signal transmission information of the physical layer in a multi-relay network; the reliable signal transmission information is used to record the transmission reliability of multiple single-hop links in the physical layer; the multiple single-hop links are used to realize communication between the source node and the destination node of the multi-relay network; Based on the signal transmission reliability information of the physical layer, the task offloading area of ​​the root node in each segment of the single-hop link is determined; the task offloading area includes child nodes whose signal strength meets a preset signal strength threshold; the signal strength is the strength of the signal transmitted by the root node received by the child node; By constructing task backlog queues for child nodes within each task offloading region, the scheduling strategy for child nodes within each task offloading region is determined, including: under preset resource allocation constraints, constructing task backlog queues for child nodes within each task offloading region that satisfy preset resource allocation targets; the preset resource allocation constraints include signal transmission reliability, physical layer transmission rate, and long-term average task backlog queue stability; the long-term average task backlog queue stability includes inequality constraints. , for Real-time task backlog queue T represents the maximum length of the task backlog queue and time. The resource allocation objective is to maximize the fair utility of the child nodes within the corresponding task unloading area. The scheduling strategy of each child node within the task unloading area is updated according to the resource allocation strategy indicated by the task backlog queue.

2. The method according to claim 1, characterized in that, The acquisition of physical layer signal transmission information in a multi-relay network includes: Obtain the upper-layer update scheduling information of the physical layer in the multi-relay network; Based on the upper-layer update scheduling information, the current network size parameters of the multi-relay network are obtained; the network size parameters include parameters related to signal transmission performance of each segment of the single-hop link. Based on the network scale parameters, the signal transmission reliability information of the physical layer is determined.

3. The method according to claim 2, characterized in that, Determining the signal transmission reliability information of the physical layer based on the network scale parameters includes: Based on the parameters related to signal transmission performance of each segment of the single-hop link, determine the signal-to-noise ratio information of the destination node in each segment of the single-hop link; Based on the signal-to-noise ratio information of the destination node in each segment of the single-hop link, the signal transmission reliability information of the physical layer is obtained.

4. The method according to claim 3, characterized in that, The signal-to-noise ratio (SNR) information includes SNR values. Obtaining the physical layer's signal transmission reliability information based on the SNR information of the destination node in each segment of the single-hop link includes: Based on the signal-to-noise ratio (SNR) value of the destination node in each segment of the single-hop link, the target probability information of each segment of the single-hop link is obtained; the target probability information is used to characterize the probability that the SNR value of the destination node in the single-hop link is greater than a preset SNR threshold. Based on the target probability information of each single-hop link, the signal transmission reliability information of the physical layer is determined.

5. The method according to claim 3, characterized in that, For any single-hop link segment, the signal-to-noise ratio (SNR) information of the destination node in the single-hop link segment is included on the subcarriers allocated in the single-hop link segment. The parameters associated with signal transmission performance of any single-hop link segment include at least the current task offloading region identifier of the root node in the single-hop link segment, the current scheduling indication information of the single-hop link segment, the channel gain of the sub-channel of the single-hop link segment, the interference signal of other single-hop links to the destination node in the single-hop link segment, and the transmission signal power of the root node in the single-hop link segment.

6. The method according to claim 1, characterized in that, The step of determining the task offloading area of ​​the root node in each segment of the single-hop link based on the signal transmission reliability information of the physical layer includes: For any single-hop link segment, if the transmission reliability of the single-hop link segment does not meet the preset conditions, obtain the task offloading area of ​​the root node in the single-hop link segment after the update. Wherein, if the transmission reliability of any single-hop link does not meet the preset conditions, the root node in any single-hop link is used to select a new root node from the relay nodes in the multi-relay network to form a new single-hop link for the destination node in any single-hop link, and then update the current task offloading area.

7. The method according to claim 1, characterized in that, The step of constructing a task backlog queue for child nodes within each task unloading area that satisfies a preset resource allocation target under preset resource allocation constraints includes: Obtain the signal transmission parameters and buffer status of the child nodes within each task unloading area; Based on the signal transmission parameters of each child node and the buffer state, a task backlog queue that satisfies the preset resource allocation target is constructed under preset resource allocation constraints.

8. A task offloading and scheduling device, characterized in that, The device includes: The acquisition module is used to acquire signal transmission reliability information of the physical layer in a multi-relay network; the signal transmission reliability information is used to record the transmission reliability of multiple single-hop links in the physical layer; the multiple single-hop links are used to realize communication between the source node and the destination node of the multi-relay network; The region determination module is used to determine the task offloading region of the root node in each segment of the single-hop link based on the signal transmission reliability information of the physical layer; the task offloading region includes child nodes whose signal strength meets a preset signal strength threshold; the signal strength is the strength of the signal transmitted by the root node received by the child node; The strategy determination module is used to determine the scheduling strategy of the sub-nodes in each task unloading area by constructing the task backlog queue of the sub-nodes in each task unloading area. The strategy determination module is specifically used to construct task backlog queues for child nodes within each task offloading area that satisfy preset resource allocation targets, under preset resource allocation constraints. The preset resource allocation constraints include signal transmission reliability, physical layer transmission rate, and long-term average task backlog queue stability. The long-term average task backlog queue stability includes inequality constraints. , for Real-time task backlog queue T represents the maximum length of the task backlog queue and time. The resource allocation objective is to maximize the fair utility of the child nodes within the corresponding task unloading area. The scheduling strategy of each child node within the task unloading area is updated according to the resource allocation strategy indicated by the task backlog queue.

9. An electronic device comprising a memory and a processor, wherein the memory stores a computer program, characterized in that, When the processor executes the computer program, it implements the steps of the method according to any one of claims 1 to 7.

10. A computer-readable storage medium having a computer program stored thereon, characterized in that, When the computer program is executed by a processor, it implements the steps of the method according to any one of claims 1 to 7.

11. A computer program product, comprising a computer program, characterized in that, When the computer program is executed by a processor, it implements the steps of the method according to any one of claims 1 to 7.

Citation Information

Patent Citations

  • Method for relay selection and subchannel allocation in OFDM system

    CN101388692A

  • Real-time resource scheduling method for spatial data relay network

    CN116886175A

  • Rapid selection method for V2V task unloading node set of Internet of Vehicles

    CN117278970A