In-plant implementation method and system for upgrading and reconstruction of intelligent substation monitoring system
By backing up, checking and upgrading the monitoring system data in the factory, combined with the consistency verification of the factory verification environment, the problem of the problem that the upgrade and transformation of the substation monitoring system is difficult to comprehensively test and verify during the power outage period, and efficient and reliable system upgrades and transformations are achieved.
Patent Information
- Application Number
- CN202411778805.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-05
- Publication Date
- 2025-03-28
AI Technical Summary
The upgrade and transformation of the substation monitoring system is difficult to conduct comprehensive testing and verification within a limited power outage time, which may lead to delays in technical transformation and quality problems, and even cause safety hazards.
By utilizing software and hardware resources and technical support in the factory, potential problems can be discovered and solved in advance, including backing up and verifying on-site monitoring system data, upgrading and transformation of the factory system in the factory, building a factory verification environment for consistency verification, and finally implementing it on-site.
The on-site power outage testing and testing time has been shortened, the efficiency and quality of the upgrade and transformation of the intelligent substation monitoring system has been improved, and the seamless upgrade and system safety has been ensured.
Smart Images

Figure CN119718778A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to a method and system for implementing upgrading and transformation of a monitoring system, and in particular to an in-plant implementation method and system for upgrading and transformation of a monitoring system for a smart substation. Background Art
[0002] The secondary equipment of the substation often needs system transformation and equipment update due to the service life or function upgrade requirements. Especially with the integration of advanced functions such as one-button sequential control, the upgrade and transformation of the monitoring system has become particularly urgent. In actual operation, most of them rely on on-site upgrades and manual point-to-point by engineering personnel, but it is often difficult for substations to apply for power outage time, and the power outage commissioning and acceptance cycle is short. If there are engineering parameter configuration errors, improper SCD model configuration, anti-error logic and sequential control ticket setting problems, or communication compatibility problems between new and old equipment during the precious power outage period, it may lead to technical transformation delays and quality problems, especially within the limited power outage time, it is impossible to carry out comprehensive point-to-point testing and functional verification, which may cause safety hazards after the substation is put back into operation. Therefore, there is an urgent need for an efficient and reliable monitoring system upgrade and transformation solution to solve these problems. Summary of the invention
[0003] Purpose of the invention: The purpose of the present invention is to provide an in-plant implementation method and system for upgrading and modifying the monitoring system of a smart substation, discover potential problems before the on-site upgrade and modification implementation stage, use the abundant software and hardware resources and technical support forces in the factory to solve the problems, shorten the on-site power outage commissioning and acceptance time, and improve the efficiency and quality of the upgrade and modification of the monitoring system of the smart substation.
[0004] Technical solution: The in-plant implementation method and system for upgrading and transforming the monitoring system of a smart substation described in the present invention include the following steps:
[0005] (1) Back up the substation on-site monitoring system data, verify the data, and generate an on-site major version mark;
[0006] (2) Restore the backed-up data to the same type and version of monitoring system in the factory, generate the old monitoring system data in the factory, verify the data, and generate the major version mark in the factory;
[0007] (3) Export the intermediate files of the old monitoring system in the factory and import them into the new monitoring system in the factory to upgrade the monitoring system;
[0008] (4) Build a factory verification environment to verify the consistency of monitoring system data before and after the upgrade;
[0009] (5) On-site implementation
[0010] Preferably, the step (1) specifically includes backing up the on-site monitoring system data, generating a file CRC check code for each data file, and performing a CRC fusion check based on each file CRC check code to generate an on-site major version mark.
[0011] Preferably, the step (2) specifically includes restoring the backup data to a monitoring system of the same type and version in the factory, generating a file CRC check code for each data file, and performing a CRC fusion check based on each file CRC check code to generate a major version mark in the factory.
[0012] Preferably, the intermediate files in step (3) include monitoring background intermediate files and gateway machine intermediate files; the monitoring background intermediate file types include database files and graphic files; the gateway machine intermediate file types include database files, channel files, and forwarding point table files.
[0013] Preferably, the step (4) verifies the monitoring system data before and after the upgrade and transformation, including offline static verification and online dynamic communication verification.
[0014] Preferably, the offline static verification method is: using a multi-source offline verification tool to perform consistency verification on the intermediate files of the new monitoring backend and the old monitoring backend, and the intermediate files of the new gateway machine and the old gateway machine respectively.
[0015] Preferably, the online dynamic communication verification includes monitoring background online dynamic communication verification and gateway machine online dynamic communication verification.
[0016] Preferably, the monitoring background online dynamic communication verification method is: construct an interval layer device simulation tool, parse the old monitoring background SCD, establish a 61850 connection between the interval layer device simulation tool and the new monitoring background, and generate online the full-station data point change record, full-station remote control record, graphic data point change record, and graphic remote control record of the monitoring background and the interval layer simulation end, and perform consistency verification on each pair of record files.
[0017] Preferably, the online dynamic communication verification method of the gateway machine is: constructing an interval layer device simulation tool, parsing the old monitoring background SCD, establishing 61850 connections between the interval layer device simulation tool and the new gateway machine and the old gateway machine respectively, constructing a simulation master station, connecting the new gateway machine and the old gateway machine with the simulation master station, and generating online data point change records of the new gateway machine and the interval layer simulation end, as well as the simulation master station record files and remote control record files of the new gateway machine and the old gateway machine, and performing consistency verification on each pair of record files.
[0018] Preferably, the step (5) is specifically to select, during the on-site implementation stage, to replace the new machine after the factory upgrade or to only restore the monitoring system data backup after the factory upgrade to the site.
[0019] The present invention also provides an in-plant implementation system for upgrading and transforming a monitoring system of a smart substation, comprising:
[0020] Backup tool module: used to back up monitoring system data;
[0021] Recovery tool module: used to restore the backed-up data to the monitoring system;
[0022] Export tool module: used to export monitoring system data;
[0023] Import tool module: used to monitor the import of system data;
[0024] Verification tool module: used for data verification of new and old monitoring systems, including bay layer device simulation module, dispatching master station simulation module, monitoring system transmission module, and multi-source offline verification tool;
[0025] Data point change recording module: used to record the received telesignaling and telemetry during the online dynamic communication verification process.
[0026] Beneficial effects: Compared with the prior art, the present invention has the following significant advantages: before the on-site commissioning stage of the upgrade and renovation project, the abundant software and hardware resources and technical support forces in the factory are utilized to discover and solve potential problems in advance, simplify on-site work, achieve seamless upgrades, shorten the on-site power outage commissioning acceptance time, and improve the efficiency and quality of the upgrade work of the smart substation monitoring system. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 Schematic diagram of the overall architecture of the method of the present invention.
[0028] Figure 2 This is the in-factory verification diagram of the monitoring background described in the present invention.
[0029] Figure 3 This is a factory verification diagram of the gateway machine described in the present invention. DETAILED DESCRIPTION
[0030] The technical solution of the present invention is further described below in conjunction with the accompanying drawings.
[0031] like Figure 1 As shown, a method for upgrading and transforming a monitoring system of a smart substation in a factory includes the following steps:
[0032] (1) Back up the substation on-site monitoring system data, verify the data, and generate an on-site major version mark;
[0033] (2) Restore the backed-up data to the same type and version of monitoring system in the factory, generate the old monitoring system data in the factory, verify the data, and generate the major version mark in the factory;
[0034] (3) Export the intermediate files of the old monitoring system in the factory and import them into the new monitoring system in the factory to upgrade the monitoring system;
[0035] (4) Build a factory verification environment to verify the consistency of monitoring system data before and after the upgrade;
[0036] (5) On-site implementation
[0037] The following is a detailed description of each step in the in-plant implementation method for upgrading and transforming the monitoring system of smart substations:
[0038] Backup substation on-site monitoring system data:
[0039] The backup tool module in this system automatically discovers and marks key data based on the data structure and file path templates provided by the manufacturer to ensure the comprehensiveness and accuracy of the backup process. The graphical user interface (GUI) of the backup tool module is implemented, allowing operators to intuitively select specific data sets for backup and monitor the backup progress and status in real time. Real-time verification is performed on the backup data to ensure the integrity and accuracy of the data during the backup process. The CRC algorithm generates a unique checksum value for each file, which is then aggregated to form a large version mark. After the backup is completed, the backup tool module stores the checksum value together with the backup data, and uses AES-256 to encrypt the stored data to enhance data security.
[0040] Factory recovery:
[0041] Use the recovery tool module in this system to restore the backup data to the same type and version of the monitoring system machine in the factory. After the recovery process is completed, use the CRC check algorithm to check the recovered data again and generate the major version mark again. Verify the consistency of the data by comparing the major version mark generated by the on-site backup and the factory recovery. If the check values match, it is confirmed that the data copy process is correct. In addition, the backup tool module records the logs of the backup and recovery operations in detail, including the operation time, operator, operation results and any abnormal information, to facilitate problem tracking and subsequent audits, to ensure the efficiency, security and reliability of the step of "copying the on-site monitoring system data to the factory", and to provide reliable data protection for the upgrade of the smart substation monitoring system.
[0042] In-plant upgrades:
[0043] Abstract and refine the functions of mainstream monitoring systems, and define a set of intermediate file standards that are compatible with information fields of monitoring systems of various versions and even manufacturers, and are used to export old systems and import new systems. By running the export tool module in the system, the one-click export operation of the old monitoring system data is realized to generate intermediate files. These intermediate files are copied to the new version of the monitoring system machine in the factory. Run the import tool module to complete the one-click import operation, thereby realizing the upgrade and transformation of the monitoring system. The import and export tools of the intermediate files are specifically mapped and customized by the manufacturer of the monitoring system according to the specific release version, and integrated into this system as a sub-function module.
[0044] Among them, the monitoring background intermediate file types include database intermediate files and graphic intermediate files. The database intermediate file contains primary equipment, calculation telesignaling, five-defense rules, operation tickets and operation terms, etc. The data in the file is separated by tabs. It specifically includes the device group table / interval table record DevGroup.txt, the logical node table record LogicNodeRecords.txt, the telesignaling table record YxRecords.txt, the telemetry table record YcRecords.txt, the gear table record DwRecords.txt, the primary equipment record DevRecords.txt, etc. Taking the device group table / interval table record as an example, five information fields are defined, including OID, device group name, interval name, virtual device existence, and device group alias. Interval records are matched by interval names, and those without interval names are updated by name matching to generate OID mapping; taking the logical node table record as an example, eight columns are defined, including OID, logical node name, IED name, whether to protect the node, number of telesignals, number of telemetry, number of remote controls, and device type number. Logical node records are matched by IED names, and those without IED names are updated by name matching to generate OID mapping; taking the telesignal table record as an example, 18 columns are defined, including OID, telesignal name, logical node telesignal, remote control number, terminal information, inversion, telesignal linkage REF, telesignal processing flag, direct transmission alarm level, direct transmission alarm name, device type name index number, telesignal logical node name index number, remote control logical node name index number, device name index number, measuring point name index number, dual telesignal discrimination time, logical node dual-position telesignal, and telesignal status. Telesignal records are matched by reference, and those without reference are updated by name matching to generate OID mapping. The graphic intermediate file format is a G format file, and the file content includes information such as the position of the graphic element (x, y), the reference of the graphic element associated signal, the graphic element associated signal ID, signal description, remote control reference, and the signal associated with the remote control.
[0045] The types of intermediate files of the gateway machine specifically include database intermediate files, channel intermediate files, and forwarding point table intermediate files. The contents of the database intermediate files include plant station information, voltage level, interval information, primary equipment, secondary equipment, telemetry, telesignaling, remote control and other information. The contents of the channel intermediate files include the address of the master and substation, the IP address of the AB network, the monitoring retention parameters and other information; in the forwarding point table intermediate file, telesignaling includes the forwarding table serial number, the name of the secondary equipment, the signal name, the upload type, etc.; remote control includes the forwarding table serial number, the name of the secondary equipment, and the signal name; telemetry includes the forwarding table serial number, the name of the secondary equipment, and the name of the telemetry signal.
[0046] In-factory verification:
[0047] Build a verification environment to fully verify the upgraded monitoring system to ensure the consistency of monitoring system information data before and after the upgrade and the reliability of the new system functions. The verification tool modules in this system include the bay layer device simulation module (supporting IEC61850, DL / T860 (CMS) protocol simulation), the dispatching master station simulation module (supporting 104 and extended protocol simulation), the monitoring system transmission module, and the multi-source offline verification tool. Perform offline static verification and online dynamic communication verification on the monitoring background and gateway machine respectively.
[0048] Offline static verification of the monitoring background: When upgrading and renovating within the factory, the new and old monitoring backgrounds export intermediate files respectively, including database intermediate files and graphic intermediate files. The content of the database intermediate file includes plant information, voltage level, interval information, primary equipment, secondary equipment, telemetry, telesignaling, remote control and other information; the content of the graphic intermediate file includes the position of the graphic element (x, y), the reference of the graphic element associated signal, the graphic element associated signal ID, signal description, remote control reference, and the signal associated with the remote control. Use the multi-source offline verification tool to perform consistency verification on the database intermediate files and graphic intermediate files of the new and old monitoring backgrounds respectively. If the consistency verification is correct, it means that the database information before and after the upgrade of the monitoring background is correct and the screen measurement point association is correct. If it is inconsistent, the corresponding consistency verification result file is output.
[0049] Offline static verification of gateway machines: When upgrading and modifying within the factory, the new and old gateway machines export intermediate files respectively, including database intermediate files, channel intermediate files, and forwarding point table intermediate files. The content of the database intermediate file includes plant station information, voltage level, interval information, primary equipment, secondary equipment, telemetry, telesignaling, remote control and other information; the content of the channel intermediate file includes the address of the master and substation, the IP address of the AB network, the monitoring retention parameters and other information; the content of the forwarding point table intermediate file includes the forwarding table sequence number, the name of the secondary equipment, the signal name, the upload type, etc. Use the multi-source offline verification tool to perform consistency verification on the database intermediate files, channel intermediate files, and forwarding point table intermediate files of the new and old gateway machines respectively. If the consistency verification is correct, it means that the database information, channel information, and forwarding table data before and after the gateway machine upgrade are correct. If they are inconsistent, the corresponding consistency verification result file is output.
[0050] Monitoring background online dynamic communication verification: Figure 2 As shown in the figure, in the online dynamic communication verification, the bay layer simulation tool imports the SCD of the old monitoring background to simulate the 61850 server functions of the bay layer devices such as protection and measurement and control devices, and can support the simulation of 300 or more IEDs (calculated based on 500kV smart substations). The bay layer device simulation tool parses the telesignaling and telemetry in the "background database intermediate file" as the point source, automatically triggers the telesignaling and telemetry change value, and exports the "simulation end full station data point change record" after all triggers are completed. The new monitoring background uses the data point change record module to automatically record the received telesignaling and telemetry, and exports the "background end full station data point change record" after the trigger is completed. The new monitoring background parses the remote control data in the "database intermediate file" and triggers batch sequential remote control. After all remote control commands are triggered, the "background end full station remote control record" is exported; the simulation system responds to the remote control command triggered by the new monitoring background, and exports the "simulation end full station remote control record" after receiving. Similarly, the "simulation end graphic data change record", "background end graphic data change record", "background end graphic remote control record", and "simulation end graphic remote control record" are generated. Run the multi-source offline verification tool of this system to perform consistency verification on the above pairs of record files. If the consistency verification is correct, the telemetry, telesignaling and remote control after upgrading the monitoring background will complete the communication verification. If it is inconsistent, the corresponding consistency verification result file will be output.
[0051] Online dynamic communication verification of the gateway machine: Under the premise that the offline verification of the intermediate files exported by the new and old monitoring systems is consistent, run the interval layer device simulation tool constructed by the present invention to parse the old monitoring background SCD. The interval layer device simulation tool will establish 61850 connections with the new and old gateway machines respectively, and the new and old gateway machines will be connected to the simulation master station constructed by the present invention respectively, and the data point change records of the new gateway machine and the interval layer simulation end will be generated online respectively, as well as the simulation master station record files and remote control record files corresponding to the new and old gateway machines. Figure 3As shown, the interval layer device simulation tool parses the telesignaling and telemetry in the "database intermediate file" as the point source, automatically triggers the telesignaling and telemetry change value, and exports the "simulation end data point change record" after all triggers are completed. The new gateway uses the data point change record module provided by this system to automatically record the received telesignaling and telemetry, and exports the "gateway end data point change record" after the trigger is completed. Then the new and old gateways are tested in a black box to verify the data consistency between the two. The interval layer device simulation tool parses the transfer table intermediate file of the new gateway, selects the telesignaling and telemetry as the point source, automatically triggers the telesignaling and telemetry change value, and sends the change data to the simulation master station. The simulation master station runs the data point change record module provided by this system to automatically record the received telesignaling and telemetry, and exports the simulation master station record file A and simulation master station record file B after all triggers are completed. Then the new gateway is tested in a black box for the remote control function. The simulation master station A parses the remote control data in the transfer table intermediate file as the point source, and automatically triggers the remote control to send the remote control to the old gateway. The interval layer device simulation tool responds to the received remote control and exports the remote control record file A after all remote control triggers are completed, and generates the remote control record file B in the same way. Run the multi-source offline verification tool provided by this system to perform consistency verification on each pair of record files mentioned above. If the consistency verification is correct, the telemetry and telesignaling remote control after the gateway machine is upgraded will complete the communication verification. If they are inconsistent, the corresponding consistency verification result file will be output. In addition, in the online verification of the gateway machine remote control, it is necessary to compare the transfer table intermediate file with the remote control record file to detect the problem of missed remote control sent by the master station. If the number of remote controls and IDs are consistent, it means that the dynamic remote control verification of the gateway machine has covered all remote control points in the transfer table intermediate file.
[0052] On-site implementation:
[0053] After the factory verification of the new monitoring system is completed, all import, export, transmission, and verification tools for factory upgrades and factory verification need to be deleted to ensure the purity of the new system restored on site and avoid misoperation after the system is connected to the network. During the on-site implementation phase, choose to replace the new machine upgraded in the factory or only restore its data backup to the site according to the upgrade requirements. If the latter is selected, the backup and recovery steps will be repeated, and the integrity and consistency of the data during the copy process will be ensured by comparing the major version mark, thereby achieving a seamless upgrade of the on-site monitoring system.
Claims
1. A method for upgrading and transforming a monitoring system of a smart substation in a factory, characterized in that: The following steps are involved: (1) Back up the substation on-site monitoring system data, verify the data, and generate an on-site major version mark; (2) Restore the backed-up data to the same type and version of monitoring system in the factory to form the old monitoring system data in the factory, verify the data, and generate the major version mark in the factory; (3) Export the intermediate files of the old monitoring system in the factory and import them into the new monitoring system in the factory to upgrade the monitoring system; (4) Build a factory verification environment to verify the consistency of monitoring system data before and after the upgrade; (5) On-site implementation 2. According to claim 1, a method for upgrading and transforming a monitoring system of a smart substation is implemented in a factory, characterized in that: The step (1) specifically backs up the on-site monitoring system data, generates a file CRC check code for each data file, and performs a CRC fusion check based on the CRC check code of each file to generate an on-site major version mark.
3. According to claim 1, a method for upgrading and transforming a monitoring system of a smart substation is implemented in a factory, characterized in that: The step (2) specifically includes restoring the backup data to the same type and version monitoring system in the factory, generating a file CRC check code for each data file, and performing a CRC fusion check based on the CRC check code of each file to generate a major version mark in the factory.
4. The method for implementing the upgrade and transformation of the monitoring system of a smart substation in a factory according to claim 1, characterized in that: The intermediate files in step (3) include monitoring background intermediate files and gateway machine intermediate files; the monitoring background intermediate file types include database files and graphic files; the gateway machine intermediate file types include database files, channel files, and forwarding point table files.
5. The method for upgrading and transforming a monitoring system of a smart substation in a factory according to claim 1, characterized in that: The step (4) verifies the monitoring system data before and after the upgrade and transformation, including offline static verification and online dynamic communication verification.
6. The method for implementing the upgrade and transformation of the monitoring system of a smart substation in a factory according to claim 5, characterized in that: The offline static verification method is: using a multi-source offline verification tool to perform consistency verification on the intermediate files of the new monitoring backend and the old monitoring backend, and the intermediate files of the new gateway machine and the old gateway machine respectively.
7. The method for upgrading and transforming the monitoring system of a smart substation in a factory according to claim 5, characterized in that: The online dynamic communication verification includes the online dynamic communication verification of the monitoring background and the online dynamic communication verification of the gateway.
8. The method for upgrading and transforming the monitoring system of a smart substation in a factory according to claim 7, characterized in that: The monitoring background online dynamic communication verification and validation method is as follows: construct an interval layer device simulation tool, parse the old monitoring background SCD, establish a 61850 connection between the interval layer device simulation tool and the new monitoring background, and respectively generate online the full-station data point change records, full-station remote control records, graphic data point change records, and graphic remote control records for the monitoring background and the interval layer simulation end, and perform consistency verification on each pair of record files.
9. The method for implementing the upgrade and transformation of the monitoring system of a smart substation in a factory according to claim 7, characterized in that: The online dynamic communication verification and validation method of the gateway machine is as follows: construct an interval layer device simulation tool, parse the old monitoring background SCD, establish 61850 connections between the interval layer device simulation tool and the new gateway machine and the old gateway machine respectively, construct a simulation master station, connect the new gateway machine and the old gateway machine to the simulation master station, generate data point change records of the new gateway machine and the interval layer simulation end online, as well as the simulation master station record files and remote control record files of the new gateway machine and the old gateway machine respectively, and perform consistency verification on each pair of record files.
10. The method for upgrading and transforming a monitoring system of a smart substation in a factory according to claim 1, characterized in that: The step (5) specifically involves, during the on-site implementation phase, selecting to replace the new machine after the factory upgrade or only restoring the monitoring system data backup after the factory upgrade to the on-site.
11. An in-plant implementation system for upgrading and transforming a smart substation monitoring system, characterized in that: include: Backup tool module: used to back up monitoring system data; Recovery tool module: used to restore the backed-up data to the monitoring system; Export tool module: used to export monitoring system data; Import tool module: used to monitor the import of system data; Verification tool module: used for data verification of new and old monitoring systems, including bay layer device simulation module, dispatching master station simulation module, monitoring system transmission module, and multi-source offline verification tool; Data point change recording module: used to record the received telesignaling and telemetry during the online dynamic communication verification process.