Comprehensive evaluation method, device and equipment for power facility construction planning and medium
By linking the equipment and communication protocols in the power facility construction planning book, the equipment to be replaced and the replacement equipment is found, the management inconvenience caused by different communication protocols of the power facility is solved, and the unified communication protocol and the convenience of operation and maintenance management are achieved.
Patent Information
- Application Number
- CN202411923588.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-25
- Publication Date
- 2025-03-28
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In the planning of power facilities construction, there are a large number of facilities that support different communication protocols, which makes it difficult to manage the unified power facilities and inconvenient to operate and maintain later.
By associating the equipment and communication protocols of the power facility construction plan, it is determined that the equipment that does not apply the communication protocol in the communication area is used as the equipment to be replaced, and the equipment that has the same function and uses the same communication protocol is searched from the power facility construction plan to calculate the comprehensive cost after replacement.
It realizes the unification of communication protocols in the power transmission system, facilitates the unified management of power facilities, and improves the convenience of later operation and maintenance management.
Smart Images

Figure CN119721636A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to power grid planning technology, and in particular to a comprehensive evaluation method, device, equipment and medium for power facility construction planning. Background Art
[0002] Grid planning, also known as transmission system planning, is based on load forecasting and power supply planning. Grid planning determines when, where and what type of transmission lines and the number of circuits to be built to achieve the required transmission capacity within the planning period and minimize the cost of the transmission system while meeting various technical indicators.
[0003] With the continuous development of smart grids, after the planning of power facility construction, there are a large number of power facilities that support different communication protocols. This is very inconvenient for the unified management of power facilities and easily brings inconvenience to the subsequent operation and maintenance management. Summary of the invention
[0004] The present invention provides a method, device, equipment and medium for comprehensive evaluation of electric power facility construction planning to improve the convenience of later operation and maintenance management.
[0005] In a first aspect, the present invention provides a comprehensive evaluation method for power facility construction planning, comprising:
[0006] Associating the equipment in the electric power facility construction plan with the communication protocols used by the equipment to obtain a communication equipment reference table;
[0007] For each communication protocol, determine the communication areas of all devices applying the communication protocol from the power grid planning plan;
[0008] Determine a device in the communication area that does not apply the communication protocol as a device to be replaced;
[0009] Searching the power facility construction plan for a device that has the same function as the device to be replaced and uses the communication protocol as a replaceable device;
[0010] Calculate the comprehensive cost of the power facility construction plan after replacing the equipment to be replaced with replaceable equipment.
[0011] Optionally, for each communication protocol, the communication areas of all devices applying the communication protocol are determined from the power grid planning plan, including:
[0012] The minimum circle covering method is adopted to calculate the minimum circle covering all the devices applying the communication protocol in the power grid planning plane as the communication area.
[0013] Optionally, searching the power facility construction plan for a device having the same function as the device to be replaced and using the communication protocol as a replaceable device includes:
[0014] Searching the power facility construction plan for a device that has the same function as the device to be replaced and uses the communication protocol as a backup replacement device;
[0015] Using the reliability index of the device to be replaced as a reference index, comparing the reliability index of the standby replacement device with the reference index;
[0016] A spare replacement device having a reliability index greater than the reference index is selected as the replaceable device.
[0017] Optionally, the comprehensive evaluation method for power facility construction planning also includes:
[0018] After determining that a device in the communication area that does not apply the communication protocol is a device to be replaced, a cable that is separately connected to the device to be replaced is determined as a control sample to be replaced.
[0019] Optionally, the comprehensive cost of the power facility construction plan includes the wiring cost generated by replacing the control sample to be replaced with the control sample of replaceable equipment.
[0020] Optionally, the calculation formula of the wiring cost is:
[0021]
[0022] Z2=A+B+C;
[0023] Z3=N1G I +N2G2+…+N n G n ;
[0024] Z = Z1 + Z2 + Z3;
[0025] Among them, Z is the wiring cost, Z1 is the cable cost, Z2 is the installation cost, Z3 is the wiring accessories cost, x is the difference between the x-coordinates of the two ends of the cable in the power grid planning plan, y is the difference between the y-coordinates of the two ends of the cable in the power grid planning plan, P is the cable unit price, A is the labor cost, B is the machinery cost, C is the transportation cost, N n is the number of the corresponding n-th cable accessories, G n The unit price of the nth cable accessory.
[0026] Optionally, the comprehensive evaluation method for power facility construction planning also includes:
[0027] After calculating the comprehensive cost of the power facility construction plan after replacing the equipment to be replaced with the replaceable equipment, ranking the comprehensive costs of the power facility construction plans to obtain a cost ranking;
[0028] The cost ranking is divided into gradients, and the gradient value of the comprehensive cost of each power facility construction plan is determined as an evaluation of the power facility construction plan.
[0029] In a second aspect, the present invention further provides a comprehensive evaluation device for electric power facility construction planning, comprising:
[0030] A protocol association module is used to associate the equipment in the power facility construction plan with the communication protocols used by the equipment to obtain a communication equipment reference table;
[0031] A communication area determination module, for determining, for each communication protocol, the communication areas of all devices applying the communication protocol from a power grid planning plan;
[0032] A to-be-replaced device determination module, used to determine a device in the communication area that does not apply the communication protocol as a to-be-replaced device;
[0033] A replaceable device determination module, used to search the electric power facility construction plan for a device having the same function as the device to be replaced and using the communication protocol as a replaceable device;
[0034] The cost calculation module is used to calculate the comprehensive cost of the power facility construction plan after the equipment to be replaced is replaced with replaceable equipment.
[0035] In a third aspect, the present invention further provides an electronic device, comprising:
[0036] one or more processors;
[0037] A storage device for storing one or more programs;
[0038] When the one or more programs are executed by the one or more processors, the one or more processors implement the comprehensive evaluation method for power facility construction planning as provided in the first aspect of the present invention.
[0039] In a fourth aspect, the present invention further provides a computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the comprehensive evaluation method for power facility construction planning as provided in the first aspect of the present invention.
[0040] The comprehensive evaluation method for electric power facility construction planning provided by the present invention associates the equipment in the electric power facility construction planning document with the communication protocol applied by the equipment to obtain a reference table of communication equipment. For each communication protocol, the communication area of all equipment applying the communication protocol is determined from the power grid planning plan, and the equipment in the communication area that does not apply the communication protocol is determined as the equipment to be replaced. Equipment with the same function as the equipment to be replaced and applying the communication protocol is searched from the electric power facility construction planning document as replaceable equipment, and the comprehensive cost of the electric power facility construction planning after replacing the equipment to be replaced with the replaceable equipment is calculated. By replacing the equipment to be replaced with different communication protocols with replaceable equipment with the same communication protocol and the same function, the communication protocol in the transmission system is unified, which is convenient for the unified management of electric power facilities and improves the convenience of later operation and maintenance management.
[0041] It should be understood that the contents described in this section are not intended to identify the key or important features of the embodiments of the present invention, nor are they intended to limit the scope of the present invention. Other features of the present invention will become easily understood through the following description. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0043] Figure 1 A flowchart of a comprehensive evaluation method for power facility construction planning provided by the present invention;
[0044] Figure 2 A schematic diagram of the structure of a comprehensive evaluation device for electric power facility construction planning provided by the present invention;
[0045] Figure 3 The present invention provides a schematic structural diagram of an electronic device.
[0046] The above drawings have shown clear embodiments of the present application, which will be described in more detail later. These drawings and text descriptions are not intended to limit the scope of the present application in any way, but to illustrate the concept of the present application to those skilled in the art by referring to specific embodiments. DETAILED DESCRIPTION
[0047] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.
[0048] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0049] Figure 1 This is a flow chart of a method for comprehensive evaluation of electric power facility construction planning provided by the present invention. This embodiment is applicable to situations where different electric power facilities support different communication protocols, which is not convenient for unified management of electric power facilities and easily brings inconvenience to later operation and maintenance management. The method can be executed by a comprehensive evaluation device for electric power facility construction planning provided by an embodiment of the present invention. The device can be implemented by software and / or hardware, and is usually configured in an electronic device, such as Figure 1 As shown in Figure 1, the comprehensive evaluation method for power facility construction planning includes the following steps:
[0050] S101. Associate the equipment in the electric power facility construction plan with the communication protocols used by the equipment to obtain a communication equipment reference table.
[0051] In the embodiments of the present invention, the equipment (power equipment) includes but is not limited to smart meters, Hall current sensors, Hall voltage sensors, substation automation systems, distribution automation systems, energy management systems and communication network equipment. As a communication analysis, taking smart meters as an example, smart meters (such as DTSD1352-C model electric energy meters) communicate with the main station through the DL / T 645 protocol to realize functions such as remote meter reading. Depending on the model of the smart meter, the smart meter can also communicate remotely through the MODBUS protocol, DLMS / COSEM protocol, IEC 61850 protocol, Zigbee protocol, and LoRaWAN protocol.
[0052] To achieve a refined analysis of the power facility construction plan, the equipment in the power facility construction plan is associated with the communication protocols applied by the equipment to obtain a communication equipment reference table. In addition, the power equipment in the power facility construction plan is classified according to functions.
[0053] S102. For each communication protocol, determine the communication area of all the equipment applying the communication protocol from the power grid planning floor plan.
[0054] In an embodiment of the present invention, for each communication protocol, determine the communication area of all the equipment applying the communication protocol from the power grid planning floor plan, and the communication area may be the smallest area covering all the equipment applying the communication protocol.
[0055] Exemplarily, in an embodiment of the present invention, the minimum circle covering method is used to calculate the minimum circle covering all the equipment applying the communication protocol in the power grid planning floor plan as the communication area. The minimum circle covering is an algorithm problem in mathematics, which studies how to find the minimum circle that can cover a group of points on a plane.
[0056] Exemplarily, taking the incremental method in the minimum circle covering method as an example, all the equipment applying the communication protocol is regarded as points in the power grid planning floor plan, and the specific algorithm is as follows:
[0057] 1. Randomly arrange all the points.
[0058] 2. Initially, randomly find two points, denoted as P1 and P2, and obtain an initial circle with P1P2 as the diameter, denoted as C2 (Ci represents the minimum circle containing the first i points).
[0059] 3. Add points in sequence. Let the current point be Pi. If Pi is inside the current circle Ci-1, then Ci = Ci-1 (indicating that the minimum circle has been found); otherwise, go to step 4.
[0060] 4. Construct a new circle Ci with P1Pi as the diameter.
[0061] 5. Find a point Pj (j < i) that is not in Ci, and construct a new circle Cj with PiPj as the diameter.
[0062] 6. Find a point Pk (k < j < i) that is not in Cj. Then Pi, Pj, and Pk must be on the boundary of an updated circle. Now we can determine that there are three points (Pi, Pj, Pk) on the boundary of an updated circle. Since three points determine a circle, Pi, Pj, and Pk form a new circle, which must be able to cover the first i points. In this way, loop until the minimum circle covering all the points is found.
[0063] S103. Determine the equipment that does not apply the communication protocol within the communication area as the equipment to be replaced.
[0064] In the embodiment of the present invention, after determining the smallest circle covering all devices applying the communication protocol as the communication area, devices in the communication area that do not apply the communication protocol are determined as devices to be replaced.
[0065] S104. Search the power facility construction plan for equipment that has the same functions as the equipment to be replaced and uses the same communication protocol as the equipment to be replaced as replaceable equipment.
[0066] In an embodiment of the present invention, a device having the same function as the device to be replaced and applying the communication protocol is searched for as a replaceable device in the power facility construction plan, and the device to be replaced is replaced with the replaceable device. In this way, the communication protocol in the power transmission system is unified, which facilitates the unified management of power facilities and improves the convenience of subsequent operation and maintenance management.
[0067] Illustratively, in some embodiments of the present invention, according to the equipment function classification in the aforementioned embodiments, equipment with the same function as the equipment to be replaced and applying the communication protocol is searched from the power facility construction plan as a backup replacement equipment, and the reliability index of the equipment to be replaced is used as a reference index. The reliability index of the backup replacement equipment is compared with the reference index, and the backup replacement equipment with a reliability index greater than the reference index is selected as the replaceable equipment, thereby ensuring the allowable reliability of the replaced equipment.
[0068] After determining the devices in the communication area that do not apply the communication protocol as the devices to be replaced, the cables that are separately connected to the devices to be replaced are determined as the control samples to be replaced.
[0069] S105. Calculate the comprehensive cost of the power facility construction plan after replacing the equipment to be replaced with replaceable equipment.
[0070] In an embodiment of the present invention, the comprehensive cost of the power facility construction plan after replacing the equipment to be replaced with the replaceable equipment is calculated. Exemplarily, the comprehensive cost of the power facility construction plan includes multiple components, such as the material cost, transportation cost, installation cost, and accessory cost of the equipment, and the material cost, installation cost, and accessory cost of the cable, which are not limited in this embodiment of the present invention.
[0071] For example, in some embodiments of the present invention, the comprehensive cost of power facility construction planning also includes the wiring cost generated by replacing the control sample to be replaced with the control sample of the replaceable equipment. The calculation formula of the wiring cost is:
[0072]
[0073] Z2=A+B+C;
[0074] Z3=N1G I +N2G2+…+Nn G n ;
[0075] Z = Z1 + Z2 + Z3;
[0076] Among them, Z is the wiring cost, Z1 is the cable cost, Z2 is the installation cost, Z3 is the wiring accessories cost, x is the difference between the x-coordinates of the two ends of the cable in the power grid planning plan, y is the difference between the y-coordinates of the two ends of the cable in the power grid planning plan, P is the cable unit price, A is the labor cost, B is the machinery cost, C is the transportation cost, N n is the number of the corresponding n-th cable accessories, G n The price of the nth cable accessory, including but not limited to cable connectors, terminal heads, fixings and protective tubes.
[0077] In some embodiments of the present invention, after calculating the comprehensive cost of the power facility construction plan after replacing the equipment to be replaced with replaceable equipment, the comprehensive costs of the power facility construction plans are ranked to obtain a cost ranking, and the cost ranking is gradient-divided to determine the gradient value of the comprehensive cost of each power facility construction plan as an evaluation of the power facility construction plan.
[0078] The comprehensive evaluation method for electric power facility construction planning provided by the present invention associates the equipment in the electric power facility construction planning document with the communication protocol applied by the equipment to obtain a reference table of communication equipment. For each communication protocol, the communication area of all equipment applying the communication protocol is determined from the power grid planning plan, and the equipment in the communication area that does not apply the communication protocol is determined as the equipment to be replaced. Equipment with the same function as the equipment to be replaced and applying the communication protocol is searched from the electric power facility construction planning document as replaceable equipment, and the comprehensive cost of the electric power facility construction planning after replacing the equipment to be replaced with the replaceable equipment is calculated. By replacing the equipment to be replaced with different communication protocols with replaceable equipment with the same communication protocol and the same function, the communication protocol in the transmission system is unified, which is convenient for the unified management of electric power facilities and improves the convenience of later operation and maintenance management.
[0079] Figure 2 A schematic diagram of a comprehensive evaluation device for power facility construction planning provided by the present invention is shown in FIG. Figure 2 As shown, the comprehensive evaluation device for power facility construction planning includes:
[0080] The protocol association module 201 is used to associate the equipment in the power facility construction plan with the communication protocols used by the equipment to obtain a communication equipment reference table;
[0081] A communication area determination module 202, for determining, for each communication protocol, the communication areas of all devices applying the communication protocol from the power grid planning plan;
[0082] A to-be-replaced device determination module 203, configured to determine a device in the communication area that does not apply the communication protocol as a to-be-replaced device;
[0083] A replaceable device determination module 204, configured to search the electric power facility construction plan for a device having the same function as the device to be replaced and using the communication protocol as a replaceable device;
[0084] The cost calculation module 205 is used to calculate the comprehensive cost of the power facility construction plan after the equipment to be replaced is replaced with replaceable equipment.
[0085] In some embodiments of the present invention, the communication area determination module 202 includes:
[0086] The minimum circle solving submodule is used to use the minimum circle covering method to calculate the minimum circle covering all devices applying the communication protocol in the power grid planning plan as the communication area.
[0087] In some embodiments of the present invention, the replaceable device determination module 204 includes:
[0088] A spare replacement device search submodule is used to search the power facility construction plan for a device that has the same function as the device to be replaced and uses the communication protocol as a spare replacement device;
[0089] An index comparison submodule, used to use the reliability index of the device to be replaced as a reference index, and compare the reliability index of the standby replacement device with the reference index;
[0090] The replaceable device determination submodule is used to select a spare replacement device whose reliability index is greater than the reference index as a replaceable device.
[0091] In some embodiments of the present invention, the comprehensive evaluation device for electric power facility construction planning further includes:
[0092] The module for determining the control samples to be replaced is used to determine, after determining the device in the communication area that does not apply the communication protocol as the device to be replaced, a cable separately connected to the device to be replaced as the control sample to be replaced.
[0093] In some embodiments of the present invention, the comprehensive cost of the power facility construction plan includes the wiring cost generated by replacing the control sample to be replaced with the control sample of replaceable equipment.
[0094] In some embodiments of the present invention, the calculation formula of the wiring cost is:
[0095]
[0096] Z2=A+B+C;
[0097] Z3=N1G I +N2G2+…+N n G n ;
[0098] Z = Z1 + Z2 + Z3;
[0099] Among them, Z is the wiring cost, Z1 is the cable cost, Z2 is the installation cost, Z3 is the wiring accessories cost, x is the difference between the x-coordinates of the two ends of the cable in the power grid planning plan, y is the difference between the y-coordinates of the two ends of the cable in the power grid planning plan, P is the cable unit price, A is the labor cost, B is the machinery cost, C is the transportation cost, N n is the number of the corresponding n-th cable accessories, G n The unit price of the nth cable accessory.
[0100] In some embodiments of the present invention, the comprehensive evaluation device for electric power facility construction planning further includes:
[0101] A cost ranking module, for ranking the comprehensive costs of the power facility construction plans after the equipment to be replaced is replaced with the replaceable equipment, to obtain a cost ranking;
[0102] The gradient division module is used to perform gradient division on the cost ranking and determine the gradient value of the comprehensive cost of each power facility construction plan as an evaluation of the power facility construction plan.
[0103] The above-mentioned comprehensive evaluation device for electric power facility construction planning can execute the comprehensive evaluation method for electric power facility construction planning provided by the aforementioned embodiment of the present invention, and has corresponding functional modules and beneficial effects for executing the comprehensive evaluation method for electric power facility construction planning.
[0104] Figure 3 A schematic diagram of the structure of an electronic device provided by the present invention. The electronic device is intended to represent various forms of digital computers, such as laptop computers, desktop computers, workstations, personal digital assistants, servers, blade servers, mainframe computers, and other suitable computers. The electronic device may also represent various forms of mobile devices, such as personal digital processing, cellular phones, smart phones, wearable devices (such as helmets, glasses, watches, etc.) and other similar computing devices. The components shown herein, their connections and relationships, and their functions are merely examples and are not intended to limit the implementation of the present invention described and / or required herein.
[0105] like Figure 3As shown, the electronic device includes at least one processor 11, and a memory connected to the at least one processor 11, such as a read-only memory (ROM) 12, a random access memory (RAM) 13, etc., wherein the memory stores a computer program that can be executed by at least one processor, and the processor 11 can perform various appropriate actions and processes according to the computer program stored in the read-only memory (ROM) 12 or the computer program loaded from the storage unit 18 to the random access memory (RAM) 13. In the RAM 13, various programs and data required for the operation of the electronic device can also be stored. The processor 11, the ROM 12, and the RAM 13 are connected to each other through a bus 14. An input / output (I / O) interface 15 is also connected to the bus 14.
[0106] A number of components in the electronic device are connected to the I / O interface 15, including: an input unit 16, such as a keyboard, a mouse, etc.; an output unit 17, such as various types of displays, speakers, etc.; a storage unit 18, such as a disk, an optical disk, etc.; and a communication unit 19, such as a network card, a modem, a wireless communication transceiver, etc. The communication unit 19 allows the electronic device to exchange information / data with other devices through a computer network such as the Internet and / or various telecommunication networks.
[0107] The processor 11 may be a variety of general and / or special processing components with processing and computing capabilities. Some examples of the processor 11 include, but are not limited to, a central processing unit (CPU), a graphics processing unit (GPU), various special artificial intelligence (AI) computing chips, various processors running machine learning model algorithms, digital signal processors (DSPs), and any appropriate processors, controllers, microcontrollers, etc. The processor 11 executes the various methods and processes described above, such as a comprehensive evaluation method for power facility construction planning.
[0108] In some embodiments, the comprehensive evaluation method for the construction planning of electric power facilities may be implemented as a computer program, which is tangibly contained in a computer-readable storage medium, such as a storage unit 18. In some embodiments, part or all of the computer program may be loaded and / or installed on an electronic device via the ROM 12 and / or the communication unit 19. When the computer program is loaded into the RAM 13 and executed by the processor 11, one or more steps of the comprehensive evaluation method for the construction planning of electric power facilities described above may be performed. Alternatively, in other embodiments, the processor 11 may be configured to execute the comprehensive evaluation method for the construction planning of electric power facilities by any other appropriate means (e.g., by means of firmware).
[0109] Various implementations of the systems and techniques described above herein can be implemented in digital electronic circuit systems, integrated circuit systems, field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), load programmable logic devices (CPLDs), computer hardware, firmware, software, and / or combinations thereof. These various implementations can include: being implemented in one or more computer programs that can be executed and / or interpreted on a programmable system including at least one programmable processor, which can be a special purpose or general purpose programmable processor that can receive data and instructions from a storage system, at least one input device, and at least one output device, and transmit data and instructions to the storage system, the at least one input device, and the at least one output device.
[0110] Computer programs for implementing the methods of the present invention may be written in any combination of one or more programming languages. These computer programs may be provided to a processor of a general-purpose computer, a special-purpose computer, or other programmable data processing device, so that when the computer program is executed by the processor, the functions / operations specified in the flow chart and / or block diagram are implemented. The computer program may be executed entirely on the machine, partially on the machine, partially on the machine and partially on a remote machine as a stand-alone software package, or entirely on a remote machine or server.
[0111] In the context of the present invention, a computer-readable storage medium may be a tangible medium that may contain or store a computer program for use by or in combination with an instruction execution system, device or equipment. A computer-readable storage medium may include, but is not limited to, electronic, magnetic, optical, electromagnetic, infrared, or semiconductor systems, devices or equipment, or any suitable combination of the foregoing. Alternatively, a computer-readable storage medium may be a machine-readable signal medium. A more specific example of a machine-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.
[0112] To provide interaction with a user, the systems and techniques described herein may be implemented on an electronic device having: a display device (e.g., a CRT (cathode ray tube) or LCD (liquid crystal display) monitor) for displaying information to the user; and a keyboard and a pointing device (e.g., a mouse or trackball) through which the user can provide input to the electronic device. Other types of devices may also be used to provide interaction with the user; for example, the feedback provided to the user may be any form of sensory feedback (e.g., visual feedback, auditory feedback, or tactile feedback); and input from the user may be received in any form (including acoustic input, voice input, or tactile input).
[0113] The systems and techniques described herein may be implemented in a computing system that includes backend components (e.g., as a data server), or a computing system that includes middleware components (e.g., an application server), or a computing system that includes frontend components (e.g., a user computer with a graphical user interface or a web browser through which a user can interact with implementations of the systems and techniques described herein), or a computing system that includes any combination of such backend components, middleware components, or frontend components. The components of the system may be interconnected by any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include: a local area network (LAN), a wide area network (WAN), a blockchain network, and the Internet.
[0114] A computing system may include a client and a server. The client and the server are generally remote from each other and usually interact through a communication network. The client and server relationship is generated by computer programs running on the corresponding computers and having a client-server relationship with each other. The server may be a cloud server, also known as a cloud computing server or cloud host, which is a host product in the cloud computing service system to solve the defects of difficult management and weak business scalability in traditional physical hosts and VPS services.
[0115] An embodiment of the present invention also provides a computer program product, including a computer program, which, when executed by a processor, implements the comprehensive evaluation method for power facility construction planning provided in any embodiment of the present application.
[0116] In the process of implementation, the computer program product can be written in one or more programming languages or a combination thereof to perform the computer program code of the present invention, including object-oriented programming languages, such as Java, Smalltalk, C++, and conventional procedural programming languages, such as "C" language or similar programming languages. The program code can be executed entirely on the user's computer, partially on the user's computer, as a separate software package, partially on the user's computer and partially on a remote computer, or entirely on a remote computer or server. In the case of a remote computer, the remote computer can be connected to the user's computer through any type of network, including a local area network (LAN) or a wide area network (WAN), or can be connected to an external computer (for example, using an Internet service provider to connect through the Internet).
[0117] It should be understood that the various forms of processes shown above can be used to reorder, add or delete steps. For example, the steps described in the present invention can be executed in parallel, sequentially or in different orders, as long as the desired results of the technical solution of the present invention can be achieved, and this document does not limit this.
[0118] The above specific implementations do not constitute a limitation on the protection scope of the present invention. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions can be made according to design requirements and other factors. Any modification, equivalent substitution and improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A comprehensive evaluation method for power facility construction planning, characterized in that: include: Associating the equipment in the electric power facility construction plan with the communication protocols used by the equipment to obtain a communication equipment reference table; For each communication protocol, determine the communication areas of all devices applying the communication protocol from the power grid planning plan; Determine a device in the communication area that does not apply the communication protocol as a device to be replaced; Searching the power facility construction plan for a device that has the same function as the device to be replaced and uses the communication protocol as a replaceable device; Calculate the comprehensive cost of the power facility construction plan after replacing the equipment to be replaced with replaceable equipment.
2. The comprehensive evaluation method for electric power facility construction planning according to claim 1 is characterized in that: For each communication protocol, determine the communication areas of all devices that apply the communication protocol from the power grid planning plan, including: The minimum circle covering method is adopted to calculate the minimum circle covering all the devices applying the communication protocol in the power grid planning plane as the communication area.
3. The comprehensive evaluation method for electric power facility construction planning according to claim 1 is characterized in that: Searching the power facility construction plan for a device that has the same function as the device to be replaced and uses the communication protocol as a replaceable device, including: Searching the power facility construction plan for a device that has the same function as the device to be replaced and uses the communication protocol as a backup replacement device; Using the reliability index of the device to be replaced as a reference index, comparing the reliability index of the standby replacement device with the reference index; A spare replacement device having a reliability index greater than the reference index is selected as the replaceable device.
4. The comprehensive evaluation method for electric power facility construction planning according to claim 1 is characterized in that: Also includes: After determining that a device in the communication area that does not apply the communication protocol is a device to be replaced, a cable that is separately connected to the device to be replaced is determined as a control sample to be replaced.
5. The comprehensive evaluation method for electric power facility construction planning according to claim 4 is characterized in that: The comprehensive cost of the power facility construction plan includes the wiring cost generated by replacing the control samples to be replaced with control samples of replaceable equipment.
6. The comprehensive evaluation method for electric power facility construction planning according to claim 5 is characterized in that: The calculation formula of the wiring cost is: Z2=A+B+C; Z3=N1G I +N2G2+…+N n G n ; Z = Z1 + Z2 + Z3; Among them, Z is the wiring cost, Z1 is the cable cost, Z2 is the installation cost, Z3 is the wiring accessories cost, x is the difference between the x-coordinates of the two ends of the cable in the power grid planning plan, y is the difference between the y-coordinates of the two ends of the cable in the power grid planning plan, P is the cable unit price, A is the labor cost, B is the machinery cost, C is the transportation cost, N n is the number of the corresponding n-th cable accessories, G n The unit price of the nth cable accessory.
7. The comprehensive evaluation method for electric power facility construction planning according to claim 1 is characterized in that: Also includes: After calculating the comprehensive cost of the power facility construction plan after replacing the equipment to be replaced with the replaceable equipment, ranking the comprehensive costs of the power facility construction plans to obtain a cost ranking; The cost ranking is divided into gradients, and the gradient value of the comprehensive cost of each power facility construction plan is determined as an evaluation of the power facility construction plan.
8. A comprehensive evaluation device for power facility construction planning, characterized in that: include: A protocol association module is used to associate the equipment in the power facility construction plan with the communication protocols used by the equipment to obtain a communication equipment reference table; A communication area determination module, for determining, for each communication protocol, the communication areas of all devices applying the communication protocol from a power grid planning plan; A to-be-replaced device determination module, used to determine a device in the communication area that does not apply the communication protocol as a to-be-replaced device; A replaceable device determination module, used to search the electric power facility construction plan for a device having the same function as the device to be replaced and using the communication protocol as a replaceable device; The cost calculation module is used to calculate the comprehensive cost of the power facility construction plan after the equipment to be replaced is replaced with replaceable equipment.
9. An electronic device, characterized in that: include: one or more processors; A storage device for storing one or more programs; When the one or more programs are executed by the one or more processors, the one or more processors implement the comprehensive evaluation method for power facility construction planning as described in any one of claims 1-7.
10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by a processor, the comprehensive evaluation method for power facility construction planning as described in any one of claims 1-7 is implemented.
Citation Information
Patent Citations
Network security protection method and system based on WSN protocol, and computer program
CN109451519A
Micro-service management method and device based on unified management platform and computer device
CN110138741A
Deep learning model unified application method and device, server and storage medium
CN115878096A
Communication connection establishment method, terminal device, storage medium and chip system
CN116744472A