Carbon emission and carbon reduction calculation method and system during highway maintenance and repair construction
By calculating the carbon emissions and carbon reductions of construction machinery, material transportation, construction materials and recycling materials during highway construction, the total direct carbon emissions during construction were obtained, which solved the problem of failure to effectively calculate and evaluate carbon emissions in the prior art, and achieved a comprehensive calculation of carbon emissions during construction and specific carbon reduction measures.
Patent Information
- Application Number
- CN202411841111.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-13
- Publication Date
- 2025-04-04
AI Technical Summary
The prior art has failed to effectively calculate and evaluate carbon emissions during highway construction, and lacks universal carbon reduction measures and benefits assessments.
A method for calculating carbon emissions and carbon reduction during highway construction is proposed. By calculating the carbon emissions and carbon reduction of construction machinery, material transportation, construction materials and recycling materials, the total direct carbon emissions during construction are obtained.
A comprehensive calculation of overall carbon emissions during highway construction has been achieved, multiple factors are taken into account, and specific carbon reduction measures and benefits are provided, which is universal.
Smart Images

Figure CN119761639A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of construction carbon emission, and in particular relates to a method and system for calculating carbon emission and carbon reduction during highway maintenance and repair construction. Background Art
[0002] The transportation industry is one of the three key areas of energy consumption. How to achieve low-carbon emission reduction in the transportation industry is an important issue in transportation. Therefore, it is of great significance to study the carbon emission calculation method, obtain the exact carbon emissions, study the scheme to reduce carbon emissions, and obtain the carbon reduction benefits to guide the green development during the construction of highways and promote sustainable development in the transition to a low-carbon economy. At present, there have been some studies on the carbon emissions of highways, but these studies mainly focus on the maintenance and construction of roads during operation, the emissions of maintenance building materials, and the carbon emissions of different types of vehicles on highways, but do not calculate the carbon emissions generated by the entire road during the construction process. Therefore, there is an urgent need for an assessment of the calculation method of carbon emissions generated by highways during construction.
[0003] At present, the research on carbon emissions during the operation period of highways mainly focuses on road operations or vehicle carbon emissions. At present, a more popular carbon emission accounting method is that some scholars have studied the carbon emission accounting method and emission reduction technology during the road construction period. Through the inventory-based accounting method, the input-output-based carbon emission accounting method, and the process analysis-based full life cycle evaluation method, technical support is provided for clarifying the carbon emissions during the road construction period and related carbon reduction measures. Although the final carbon emissions calculated by this method are more accurate, it can only be used to calculate carbon emissions when the road is clearly constructed. It is not a universal accounting method and does not take into account that many data cannot be obtained during the actual construction process. And under the condition of missing data, this carbon emission accounting method cannot be used. In addition, some scholars also use the full life cycle evaluation method to determine the emission boundaries and inventory analysis for the road maintenance and operation stages that are more difficult to calculate, determine the carbon emission calculation method for the maintenance projects in these two stages, and establish an asphalt pavement maintenance strategy optimization model with the goal of minimizing carbon emissions. However, this method is relatively general and cannot obtain the specific carbon emissions generated by fossil fuels or construction machinery. It can only perform overall optimization rather than local optimization. It is difficult to optimize carbon reduction during construction. Existing research results are mainly aimed at a certain category of carbon emissions, or more general carbon reduction plans. There is no universal carbon emission accounting method during road construction, nor are there more specific carbon reduction measures and integrated evaluation of their carbon reduction benefits. Summary of the invention
[0004] The purpose of the present invention is to solve the problem that the prior art fails to calculate the carbon emissions and carbon reductions generated during the construction of the entire highway to obtain the exact carbon emissions. A method and system for calculating carbon emissions and carbon reductions during highway maintenance and construction is proposed.
[0005] The technical solution of the present invention is as follows: In the first aspect, a method for calculating direct carbon emissions and carbon reduction during highway construction comprises the following steps:
[0006] The carbon emissions of construction machinery are calculated based on the number of projects in the project content, the unit consumption of construction machinery and the carbon emission factor per unit unit;
[0007] Carbon emissions from material transportation are calculated based on the number of projects, material consumption, average material transportation distance, and carbon emission factors per unit turnover of transportation equipment.
[0008] The carbon emissions of construction materials are calculated based on the amount of construction materials used and the carbon dioxide emission factors of construction materials;
[0009] The carbon reduction of recycled materials is calculated based on the amount of recycled materials in the project content, the carbon emission factor of the recycled materials production process, the fossil fuel consumption and the carbon emission factor of fossil fuels;
[0010] The total direct carbon emissions during highway construction are calculated based on the carbon emissions from construction machinery, material transportation, construction materials and the carbon reduction from recycled materials.
[0011] The beneficial effects of the present invention are:
[0012] The present invention not only considers the carbon emissions of construction materials and facilities, but also takes into account the carbon reduction of construction machinery, material transportation, and recycled materials, thereby achieving a comprehensive calculation of the overall carbon emissions during the construction period.
[0013] Preferably, the calculation formula for the carbon emissions of the construction machinery is:
[0014]
[0015] Among them, E e represents the carbon emissions of construction machinery, A i Indicates the number of projects in the i-th project content, N e,i,j represents the consumption of the j-th type of construction machinery in the i-th project content, EF e,j It represents the carbon emission factor per unit shift of the j-th type of construction machinery, and n represents the total number of accounting items.
[0016] Preferably, the calculation formula for the carbon emissions from material transportation is:
[0017]
[0018] Among them, E cw represents the carbon emissions from material transportation, A i Indicates the number of projects in the i-th project content, N mik represents the unit-shift consumption of the kth material in the i-th project content, L k represents the average transportation distance of the kth material, EF t,p It represents the carbon emission factor per unit turnover of transport equipment, h represents the total number of materials, and m represents the total number of engineering contents.
[0019] As a preferred method, the average transportation distance L of the kth material k If unknown, the value is determined according to the following rules:
[0020] Average transportation distance of concrete materials L k1 =40km;
[0021] Average transportation distance L for sand, stone and other ground materials k2 =500km;
[0022] Average transportation distance of other materials L k3 =500km;
[0023] Average transportation distance L for intra-city transportation of prefabricated components k4 =40km;
[0024] Average transportation distance L of prefabricated components transported to different cities k5 =150km.
[0025] Preferably, the calculation formula of the carbon dioxide emission factor of the construction material is:
[0026]
[0027] Among them, EF l represents the carbon dioxide emission factor of the first type of construction material, CC l Indicates the carbon content per unit calorific value of the first type of construction material, OF l Expressed as the carbon oxidation rate of the first construction material, It represents the ratio of the relative molecular mass of carbon dioxide to carbon;
[0028] The calculation formula for the carbon emissions of construction materials is:
[0029] E f =EF l ×A l
[0030] Among them, E frepresents the carbon emissions of construction materials, A l Indicates the usage of the lth type of construction material.
[0031] Preferably, the calculation formula for the carbon reduction of the recycled materials is:
[0032]
[0033] Among them, E m Indicates the carbon reduction of recycled materials, B i Represents the amount of recycled materials in the i-th project content, N m′,i,g represents the quantity of the g-th type of recycled material in the i-th project content, EF m′,g represents the carbon emission factor of the production process of the g-th recycled material, S g,t represents the consumption of the tth fossil fuel in the transportation of the gth recycling material, EF t.g represents the carbon emission factor of the tth fossil fuel consumed in transporting the gth type of recycled material, m represents the total number of engineering contents, and m′ represents the total number of recycled materials.
[0034] Preferably, the calculation formula for the total direct carbon emissions during the highway construction period is:
[0035] E z =E e +E cw +E f -E m
[0036] Among them, E z represents the total direct carbon emissions during highway construction, E e represents the carbon emissions of construction machinery, E cw represents the carbon emissions from material transportation, E f represents the carbon emissions of construction materials, E m Indicates the carbon reduction from recycled materials.
[0037] The beneficial effects of the above preferred solution are:
[0038] 1. The above preferred solution quantifies the carbon emissions of various factors in the construction process through formula calculation, making the calculation process simpler and faster.
[0039] 2. The relevant factors involved in the present invention are all independent of the construction mileage, and therefore can be applied to all expressways, with strong universality.
[0040] In the second aspect, a direct carbon emission and carbon reduction calculation system during highway construction includes:
[0041] The construction machinery carbon emission calculation module is used to calculate the construction machinery carbon emission based on the number of projects in the project content, the unit consumption of construction machinery and the unit carbon emission factor;
[0042] The carbon emission calculation module for material transportation is used to calculate the carbon emission of material transportation based on the number of projects in the project content, the material consumption per shift, the average transportation distance of materials, and the carbon emission factor of the unit turnover of transportation equipment;
[0043] A construction material carbon emission calculation module is used to calculate the construction material carbon emission based on the construction material usage and the carbon dioxide emission factor of the construction material;
[0044] A module for calculating the carbon reduction of recycled materials, which is used to calculate the carbon reduction of recycled materials based on the amount of recycled materials in the project content, the carbon emission factor of the recycled materials production process, the fossil fuel consumption and the carbon emission factor of fossil fuels;
[0045] The module for calculating the total direct carbon emissions is used to calculate the total direct carbon emissions during highway construction based on the carbon emissions of construction machinery, carbon emissions of material transportation, carbon emissions of construction materials, and carbon reductions from recycled materials.
[0046] In a third aspect, an electronic device is provided, characterized in that it comprises: at least one processor; and a memory communicatively connected to the at least one processor; wherein the memory stores instructions executable by the at least one processor, and the instructions are executed by the at least one processor so that the at least one processor executes the method described in the first aspect.
[0047] In a fourth aspect, a non-transitory computer-readable storage medium storing computer instructions is provided, wherein the computer instructions are used to cause a computer to execute the method described in the first aspect. BRIEF DESCRIPTION OF THE DRAWINGS
[0048] Figure 1 Shown is a flow chart of a method for calculating direct carbon emissions and carbon reductions during highway construction.
[0049] Figure 2 Shown is a schematic diagram of the carbon emission factors, usage and carbon emissions of the main materials for pavement maintenance in a highway expansion project.
[0050] Figure 3 Shown is a schematic diagram of the carbon emission factors, usage and carbon emissions of construction machinery used in road maintenance work in a highway expansion project. DETAILED DESCRIPTION
[0051] Now, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings. It should be understood that the embodiments shown and described in the accompanying drawings are only exemplary and are intended to explain the principles and spirit of the present invention, rather than to limit the scope of the present invention.
[0052] Embodiment 1:
[0053] like Figure 1 As shown, a method for calculating direct carbon emissions and carbon reduction during highway construction includes the following steps:
[0054] S1. Calculate the carbon emissions of construction machinery based on the number of projects in the project content, the unit consumption of construction machinery and the unit carbon emission factor;
[0055] S2. Calculate the carbon emission of material transportation based on the number of projects, material consumption, average distance of material transportation and carbon emission factor of unit turnover of transportation equipment;
[0056] S3. Calculate the carbon emissions of construction materials based on the amount of construction materials used and the carbon dioxide emission factors of construction materials;
[0057] S4. Calculate the carbon reduction of recycled materials based on the amount of recycled materials in the project content, the carbon emission factor of the recycled materials production process, the fossil fuel consumption and the carbon emission factor of fossil fuels;
[0058] S5. The total direct carbon emissions during highway construction are calculated based on the carbon emissions from construction machinery, material transportation, construction materials and carbon reduction from recycled materials.
[0059] In this embodiment, the calculation formula for the carbon emissions of the construction machinery is:
[0060]
[0061] Among them, E e Indicates the carbon emissions of construction machinery in kilograms of carbon dioxide (kgCO 2 ), A i Indicates the number of projects in the i-th project content, N e,i,j It represents the consumption of the j-th type of construction machinery in the i-th project content, in units of machine shifts, EF e,j represents the carbon emission factor per unit shift of the j-th type of construction machinery, in kilograms of carbon dioxide per shift (kgC0 2 / shift), n represents the total number of accounting items.
[0062] In this embodiment, the calculation formula for the carbon emissions from material transportation is:
[0063]
[0064] Among them, E cw Indicates the carbon emissions of material transportation in kilograms of carbon dioxide (kgCO 2 ), A i Indicates the number of projects in the i-th project content, N mik Indicates the consumption of the kth material in the i-th project content, in kilograms (kg) or cubic meters (m 3 ), L k It represents the average transportation distance of the kth material, in kilometers (km), EF t,p The carbon emission factor per unit turnover of transport equipment is expressed in kgCO2 / (tons·km) (kgCO 2 / (t·km)), h represents the total number of materials, and m represents the total number of engineering contents.
[0065] In this embodiment, the on-site transportation distance of each material (equipment) is L k The actual transportation distance should be used. If the average transportation distance of the kth material is L k If unknown, the value is determined according to the following rules:
[0066] Average transportation distance of concrete materials L k1 =40km;
[0067] Average transportation distance L for sand, stone and other ground materials k2 =500km;
[0068] Average transportation distance of other materials L k3 =500km;
[0069] Average transportation distance L for intra-city transportation of prefabricated components k4 =40km;
[0070] Average transportation distance L of prefabricated components transported to different cities k5 =150km.
[0071] In this embodiment, the calculation formula of the carbon dioxide emission factor of the construction material is:
[0072]
[0073] Among them, EF l It represents the carbon dioxide emission factor of the first type of construction material, in kgCO2 / GJ (kgCO2 / GJ), CC l Indicates the carbon content per unit calorific value of the first type of construction material, in tons of carbon / gigajoule (tC / GJ), OF l It is expressed as the carbon oxidation rate of the first construction material, expressed in %, It represents the ratio of the relative molecular mass of carbon dioxide to carbon;
[0074] The calculation formula for the carbon emissions of construction materials is:
[0075] E f =EF l ×A l
[0076] Among them, E f Indicates the carbon emissions of construction materials in kilograms of carbon dioxide (kgCO 2 ), A l Indicates the usage of the lth type of construction material.
[0077] In this embodiment, the calculation formula for the carbon reduction of the recycled materials is:
[0078]
[0079] Among them, E m Indicates the carbon reduction of recycled materials, in kilograms of carbon dioxide (kgCO 2 ), B i Represents the amount of recycled materials in the i-th project content, N m′,i,g represents the quantity of the g-th type of recycled material in the i-th project content, EF m′,g It represents the carbon emission factor of the production process of the g-th recycled material, in kg CO2 / kg or kg CO2 / cubic meter (kgC0 2 / kg, kgC0 2 / m 3 ), the carbon emission factor of the material production process should use the material carbon footprint data audited by a third party, S g,t represents the consumption of the tth fossil fuel in the transportation of the gth type of recycled material, in tons (t), EF t.g The carbon emission factor of the tth fossil fuel consumed in transporting the gth type of recycled material, in kgCO2 / (ton) (kgCO 2 / (t)), m represents the total number of engineering contents, and m′ represents the total number of recycled materials.
[0080] In this embodiment, the calculation formula for the total amount of direct carbon emissions during the highway construction period is:
[0081] E z =E e +E cw +E f -E m
[0082] Among them, E zIt represents the total direct carbon emissions during highway construction, in kilograms of carbon dioxide (kgCO 2 ), E e represents the carbon emissions of construction machinery, E cw represents the carbon emissions from material transportation, E f represents the carbon emissions of construction materials, E m Indicates the carbon reduction from recycled materials.
[0083] The method for calculating direct carbon emissions and carbon reduction during highway construction proposed in the present invention directly uses the calorific value of known materials to calculate the carbon emission factor of the materials, thereby obtaining the carbon emissions of construction materials; the carbon emissions of construction machinery are obtained through the simple and easily available data such as the number of projects in the project content, the unit-shift consumption of construction machinery, and the carbon emission factor per unit-shift; the carbon emissions of material (equipment) transportation are obtained through the number of projects in the project content, the unit-shift consumption of materials (equipment), the average transportation distance of materials (equipment), and the carbon emission factor per unit turnover of transportation equipment; the carbon reduction of recycled materials is obtained through the number of recycled materials, the carbon emission factor of the recycled material production process, the fossil fuel consumption, and the carbon emission factor of fossil fuels; all relevant factors involved in the calculation process are simple and easy to obtain in actual construction, which simplifies the calculation of carbon emissions in the construction process, so that more people can intuitively understand the importance of carbon reduction, and the relevant factors involved in the calculation are independent of the construction mileage, and can be applied to all highways, with universal applicability, such as Figure 2 and Figure 3 Shown are the carbon emission factors and usage of the main materials and construction machinery in a road maintenance project in a highway expansion project, as well as the total carbon emissions calculated by the direct carbon emissions and carbon reduction calculation method during highway construction proposed in the present invention.
[0084] Embodiment 2:
[0085] Based on Example 1, this embodiment provides a system for calculating direct carbon emissions and carbon reduction during highway construction, which is used to implement the method for calculating direct carbon emissions and carbon reduction during highway construction as described in Example 1. The system includes:
[0086] The construction machinery carbon emission calculation module is used to calculate the construction machinery carbon emission based on the number of projects in the project content, the unit consumption of construction machinery and the unit carbon emission factor;
[0087] The carbon emission calculation module for material transportation is used to calculate the carbon emission of material transportation based on the number of projects in the project content, the material consumption per shift, the average transportation distance of materials, and the carbon emission factor of the unit turnover of transportation equipment;
[0088] A construction material carbon emission calculation module is used to calculate the construction material carbon emission based on the construction material usage and the carbon dioxide emission factor of the construction material;
[0089] A module for calculating the carbon reduction of recycled materials, which is used to calculate the carbon reduction of recycled materials based on the amount of recycled materials in the project content, the carbon emission factor of the recycled materials production process, the fossil fuel consumption and the carbon emission factor of fossil fuels;
[0090] The module for calculating the total direct carbon emissions is used to calculate the total direct carbon emissions during highway construction based on the carbon emissions of construction machinery, carbon emissions of material transportation, carbon emissions of construction materials, and carbon reductions from recycled materials.
[0091] In this embodiment, an electronic device, a readable storage medium, and a computer program product are also provided.
[0092] The electronic device includes: at least one processor; and a memory communicatively connected to the at least one processor; wherein the memory stores instructions executable by the at least one processor, and the instructions are executed by the at least one processor so that the at least one processor can execute the method for calculating direct carbon emissions and carbon reductions during highway construction as described in Example 1.
[0093] In this embodiment, the readable storage medium may be a non-transitory computer-readable storage medium storing computer instructions, wherein the computer instructions are used to enable a computer to execute the method for calculating direct carbon emissions and carbon reductions during highway construction as described in Example 1.
[0094] In this embodiment, the computer program product includes a computer program, which, when executed by a processor, implements the method for calculating direct carbon emissions and carbon reduction during highway construction as described in Example 1.
[0095] The program code for implementing the method of the present invention can be written in any combination of one or more programming languages. These program codes can be provided to a processor or controller of a general-purpose computer, a special-purpose computer or other programmable data processing device, so that the program code, when executed by the processor or controller, enables the functions / operations specified in the flow chart and / or block diagram to be implemented. The program code can be executed entirely on the machine, partially on the machine, partially on the machine as a stand-alone software package and partially on a remote machine, or entirely on a remote machine or server.
[0096] In the context of the present invention, a machine-readable medium may be a tangible medium that may contain or store a program for use by or in conjunction with an instruction execution system, device, or equipment. A machine-readable medium may be a machine-readable signal medium or a machine-readable storage medium. A machine-readable medium may include, but is not limited to, electronic, magnetic, optical, electromagnetic, infrared, or semiconductor systems, devices, or equipment, or any suitable combination of the foregoing. A more specific example of a machine-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.
[0097] To provide interaction with a user, the systems and techniques described herein can be implemented on a computer having: a display device (e.g., a CRT (cathode ray tube) or LCD (liquid crystal display) monitor) for displaying information to the user; and a keyboard and pointing device (e.g., a mouse or trackball) through which the user can provide input to the computer. Other types of devices can also be used to provide interaction with the user; for example, the feedback provided to the user can be any form of sensory feedback (e.g., visual feedback, auditory feedback, or tactile feedback); and input from the user can be received in any form (including acoustic input, voice input, or tactile input).
[0098] The systems and techniques described herein may be implemented in a computing system that includes back-end components (e.g., as a data server), or a computing system that includes middleware components (e.g., an application server), or a computing system that includes front-end components (e.g., a user computer with a graphical user interface or a web browser through which a user can interact with implementations of the systems and techniques described herein), or a computing system that includes any combination of such back-end components, middleware components, or front-end components. The components of the system may be interconnected by any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include: a local area network (LAN), a wide area network (WAN), and the Internet.
[0099] A computer system may include a client and a server. The client and the server are generally remote from each other and usually interact through a communication network. The relationship of client and server is generated by computer programs running on respective computers and having a client-server relationship with each other. The server may be a cloud server, a server of a distributed system, or a server combined with a blockchain.
[0100] Those skilled in the art will appreciate that the embodiments described herein are intended to help readers understand the principles of the present invention, and should be understood that the protection scope of the present invention is not limited to such specific statements and embodiments. Those skilled in the art can make various other specific variations and combinations that do not deviate from the essence of the present invention based on the technical revelations disclosed by the present invention, and these variations and combinations are still within the protection scope of the present invention.
Claims
1. A method for calculating direct carbon emissions and carbon reduction during highway construction, characterized in that: The following steps are involved: The carbon emissions of construction machinery are calculated based on the number of projects in the project content, the unit consumption of construction machinery and the carbon emission factor per unit unit; Carbon emissions from material transportation are calculated based on the number of projects, material consumption, average material transportation distance, and carbon emission factors per unit turnover of transportation equipment. The carbon emissions of construction materials are calculated based on the amount of construction materials used and the carbon dioxide emission factors of construction materials; The carbon reduction of recycled materials is calculated based on the amount of recycled materials in the project content, the carbon emission factor of the recycled materials production process, the fossil fuel consumption and the carbon emission factor of fossil fuels; The total direct carbon emissions during highway construction are calculated based on the carbon emissions from construction machinery, material transportation, construction materials and the carbon reduction from recycled materials.
2. The method for calculating direct carbon emissions and carbon reduction during highway construction according to claim 1 is characterized in that: The calculation formula for the carbon emissions of construction machinery is: Among them, E e represents the carbon emissions of construction machinery, A i Indicates the number of projects in the i-th project content, N e,i,j represents the consumption of the j-th type of construction machinery in the i-th project content, EF e,j It represents the carbon emission factor per unit shift of the j-th type of construction machinery, and n represents the total number of accounting items.
3. The method for calculating direct carbon emissions and carbon reduction during highway construction according to claim 1 is characterized in that: The calculation formula for the carbon emissions from material transportation is: Among them, E cw represents the carbon emissions from material transportation, A i Indicates the number of projects in the i-th project content, N mik represents the unit-shift consumption of the kth material in the i-th project content, L k represents the average transportation distance of the kth material, EF t,p It represents the carbon emission factor per unit turnover of transport equipment, h represents the total number of materials, and m represents the total number of engineering contents.
4. The method for calculating direct carbon emissions and carbon reduction during highway construction according to claim 3 is characterized in that: The average transportation distance of the kth material is L k If unknown, the value is determined according to the following rules: Average transportation distance of concrete materials L k1 =40km; Average transportation distance L for sand, stone and other ground materials k2 =500km; Average transportation distance of other materials L k3 =500km; Average transportation distance L for intra-city transportation of prefabricated components k4 =40km; Average transportation distance L of prefabricated components transported to different cities k5 =150km.
5. The method for calculating direct carbon emissions and carbon reduction during highway construction according to claim 1 is characterized in that: The calculation formula for the carbon dioxide emission factor of the construction materials is: Among them, EF l represents the carbon dioxide emission factor of the first type of construction material, CC l Indicates the carbon content per unit calorific value of the first type of construction material, OF l Expressed as the carbon oxidation rate of the first construction material, It represents the ratio of the relative molecular mass of carbon dioxide to carbon; The calculation formula for the carbon emissions of construction materials is: E f =EF l ×A l Among them, E f represents the carbon emissions of construction materials, A l Indicates the usage of the lth type of construction material.
6. The method for calculating direct carbon emissions and carbon reduction during highway construction according to claim 1 is characterized in that: The calculation formula for the carbon reduction of recycled materials is: Among them, E m Indicates the carbon reduction of recycled materials, B i Represents the amount of recycled materials in the i-th project content, N m′,i,g represents the quantity of the g-th type of recycled material in the i-th project content, EF m′,g represents the carbon emission factor of the production process of the g-th recycled material, S g,t represents the consumption of the tth fossil fuel in the transportation of the gth recycling material, EF t.g represents the carbon emission factor of the tth fossil fuel consumed in transporting the gth type of recycled material, m represents the total number of engineering contents, and m′ represents the total number of recycled materials.
7. The method for calculating direct carbon emissions and carbon reduction during highway construction according to claim 1 is characterized in that: The calculation formula for the total direct carbon emissions during the construction of the expressway is: AND z =And e +E cw +E f -AND m Among them, E z represents the total direct carbon emissions during highway construction, E e represents the carbon emissions of construction machinery, E cw represents the carbon emissions from material transportation, E f represents the carbon emissions of construction materials, E m Indicates the carbon reduction from recycled materials.
8. A system for calculating direct carbon emissions and carbon reduction during highway construction, characterized in that: include: The construction machinery carbon emission calculation module is used to calculate the construction machinery carbon emission based on the number of projects in the project content, the unit consumption of construction machinery and the unit carbon emission factor; The carbon emission calculation module for material transportation is used to calculate the carbon emission of material transportation based on the number of projects in the project content, the material consumption per shift, the average transportation distance of materials, and the carbon emission factor of the unit turnover of transportation equipment; A construction material carbon emission calculation module is used to calculate the construction material carbon emission based on the construction material usage and the carbon dioxide emission factor of the construction material; A module for calculating the carbon reduction of recycled materials, which is used to calculate the carbon reduction of recycled materials based on the amount of recycled materials in the project content, the carbon emission factor of the recycled materials production process, the fossil fuel consumption and the carbon emission factor of fossil fuels; The module for calculating the total direct carbon emissions is used to calculate the total direct carbon emissions during highway construction based on the carbon emissions of construction machinery, carbon emissions of material transportation, carbon emissions of construction materials, and carbon reductions from recycled materials.
9. An electronic device, characterized in that: include: at least one processor; and a memory communicatively connected to the at least one processor; wherein the memory stores instructions executable by the at least one processor, and the instructions are executed by the at least one processor so that the at least one processor executes the method described in any one of claims 1-7.
10. A non-transitory computer-readable storage medium storing computer instructions, characterized in that: The computer instructions are used to enable a computer to execute the method according to any one of claims 1-7.
Citation Information
Cited By
Carbon reduction performance evaluation method and system in railway construction process