A method and system for division of labor in structural design of production line of manufacturing equipment
By constructing a tree structure of manufacturing equipment structure design content and combining working time thresholds and knowledge complexity, module allocation is solved, and the problem of low division of labor for the entire production line of manufacturing equipment in the existing technology is solved, achieving more efficient design division of labor and progress controllability.
Patent Information
- Application Number
- CN202510020508.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-07
- Publication Date
- 2025-04-04
AI Technical Summary
The prior art is difficult to effectively divide the labor in structural design projects of the entire production line of manufacturing equipment, resulting in low design efficiency and only division of labor from the perspective of knowledge complexity without considering the workload, which may lead to uncontrollable project progress.
By constructing a tree structure of manufacturing equipment structure design content, the production line structure design content is split into a tree structure, and the working time threshold of the project division of labor task package is set. Combined with the knowledge complexity and workload, the module working hours and similarity are calculated, and the module allocation is performed until all modules are allocated to the project division of labor task package.
A reasonable division of labor in the manufacturing equipment production line structure design project is achieved, combining knowledge complexity and workload, design efficiency is improved and project progress is ensured.
Smart Images

Figure CN119761761A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of industrial design, and in particular to a method and system for division of labor in structural design of a manufacturing equipment production line. Background Art
[0002] It has become a consensus that reasonable division of labor can improve production efficiency, and this is also true in the field of intelligent manufacturing equipment design. Based on the design knowledge points of the manufacturing equipment design project, the entire design project is divided into design sub-projects with relatively simple knowledge, so that the knowledge complexity involved in a single design sub-project is reduced, thereby improving the design efficiency, such as "A method, system and storage medium for generating an industrial design process" (patent number: CN116204939A). This method divides labor from the perspective of knowledge complexity, which reduces the complexity of a single design sub-project to a certain extent and improves design efficiency. However, when faced with the structural design project of the entire production line of manufacturing equipment, this method cannot be well applied. And only dividing labor from the perspective of knowledge complexity without considering the workload may lead to uncontrollable overall project progress. Summary of the invention
[0003] In view of the above problems existing in the prior art, the present invention provides a method and system for designing a production line structure of manufacturing equipment.
[0004] To achieve the above object, the present invention provides the following technical solutions:
[0005] The present invention provides a method for designing a production line structure of manufacturing equipment, the method comprising:
[0006] S1. Construct a tree structure of manufacturing equipment structure design content consisting of module types, modules, design points, and knowledge points;
[0007] S2. According to the design content tree structure, split the manufacturing equipment production line structure design content into the tree structure;
[0008] S3. Set the working time threshold of the project division task package, calculate the sum of the working hours of all modules of the same module type, and compare and judge:
[0009] If the sum of the working hours of all modules in the same module type is less than or equal to the threshold, all modules in the module type are divided into the same project division task package;
[0010] If the sum of the working hours of all modules of the same module type is greater than the threshold, the similarity between each module of the module type and the whole composed of the remaining modules is calculated, and the module with the smallest similarity value is eliminated. The sum of the working hours of all the remaining modules is calculated and compared with the threshold until the sum of the working hours of all the remaining modules is less than or equal to the threshold. In this case, all the remaining modules are currently a project division task package;
[0011] For all modules eliminated in the above steps, the sum of working hours is calculated again, the threshold is determined, the module with the smallest similarity is eliminated, and the project division task package is formed, until all modules in the current module type are assigned to the project division task package;
[0012] S4. Perform step 3 for other module types of manufacturing equipment in sequence until all modules in all module types are allocated to the project division task package;
[0013] S5. Output the overall division of labor plan for the new manufacturing equipment production line design in the form of a division of labor plan tree structure.
[0014] Furthermore, in step S1, a manufacturing equipment structure design content tree structure consisting of module type, module, design key points, and knowledge points is constructed, specifically:
[0015] The module types are five types: fixtures for manufacturing equipment production lines, working systems and motion actuators, base plates, racks and appearance, and conveying systems;
[0016] The modules under each module type contain several key nodes in the design process, namely, the design points;
[0017] Each design point contains several knowledge points constructed from basic theory, experience, rules or standards, design requirement constraints, and other five different types of knowledge.
[0018] Furthermore, in the step S2, according to the design content tree structure, the new manufacturing equipment production line structure design content is split into the tree structure. Specifically, the modules that need to be designed for all equipment in the entire production line are classified and numbered by module type, and the design content is input into the algorithm to obtain the design points and knowledge points corresponding to each module.
[0019] Furthermore, the input of design content into the algorithm to obtain the design points and knowledge points corresponding to each module is to construct a design content-module type-design point-knowledge point mapping relationship database using annotated historical data, train a natural language processing algorithm model, and recommend the design points contained in each module that needs to be designed and the knowledge points corresponding to each design point.
[0020] Furthermore, in step S3, the sum of the working hours of all modules of the same type is calculated, specifically:
[0021] First, calculate the single module working hours, which is calculated by multiplying the working hours of the module type to which the module belongs by the module difficulty coefficient, where the difficulty coefficient is a function related to the number of design points, the total number of knowledge points, and the number of knowledge point types contained in the module;
[0022] Then calculate the sum of all module working hours in the same type of modules, where the sum of module working hours is the accumulation of all single module working hours minus repeated working hours;
[0023] The repetitive working hours are the ratio of the number of identical knowledge points involved in all modules under the current module type to the total number of knowledge points multiplied by the sum of the working hours of all modules.
[0024] Furthermore, in step S3, a working time threshold of the project division task package is set, and the working time threshold of the project division task package is 1 to 50 hours, preferably 2 to 12 hours.
[0025] Furthermore, in step S3, the similarity between each module in the module type and the whole composed of the remaining modules is calculated, and the similarity is the ratio of the number of the same knowledge point types between the current module and the whole composed of the remaining modules multiplied by the number of the same knowledge points possessed by the whole composed of the remaining modules multiplied by the number of the knowledge point types contained in the whole composed of the remaining modules multiplied by the total number of knowledge points, that is:
[0026]
[0027] The number of the same knowledge points between the current module and the rest of the modules.
[0028] The number of knowledge point types included in the whole composed of other modules;
[0029] The number of common knowledge points between the current module and the rest of the modules;
[0030] The total number of knowledge points in the whole composed of other modules.
[0031] Furthermore, in the step S5, the overall division of labor plan for the new manufacturing equipment production line design is output in the form of a division of labor plan tree structure, and the division of labor plan tree structure includes module type, project division of labor task package, module, and design points, wherein the project division of labor task package includes the working hours of the division of labor task package and the module numbers contained therein.
[0032] The present invention also provides a manufacturing equipment production line structure design division system, including the above method, the system includes an input module, a storage module, a calculation module, a combination module and an output module;
[0033] The input module is used to input the structural design content of the manufacturing equipment production line, the man-hour threshold of the project division task package, and the man-hour corresponding to the module type;
[0034] The storage module is used to store the constructed manufacturing equipment production line structure design content tree structure, the input new manufacturing equipment production line structure design content, and the input project division task package working time threshold;
[0035] The calculation module is used to calculate the module working hours, execute the natural language processing algorithm model, the similarity value of the module of the same module type and the whole composed of the remaining modules, and the working hours of the whole composed of the remaining modules;
[0036] The combination module is used to combine modules of the same module type;
[0037] The output module is used to output a new overall division of labor plan for manufacturing equipment production line design in the form of a division of labor plan tree structure.
[0038] Compared with the prior art, the present invention has the following beneficial effects:
[0039] The present invention provides a method and system for division of labor in structural design of a manufacturing equipment production line, which can couple knowledge complexity and workload, improve the rationality of division of labor in design projects of a manufacturing equipment production line, and thus further improve design efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0040] Figure 1 is a flow chart of the method of the present invention;
[0041] Figure 2 It is a tree structure diagram of manufacturing equipment production line design;
[0042] Figure 3 It is a tree structure diagram of the division of labor plan;
[0043] Figure 4 It is a system configuration diagram of the present invention. DETAILED DESCRIPTION
[0044] The present invention will be further described in detail below in conjunction with the accompanying drawings.
[0045] like Figure 1 As shown, the steps of a method for designing a production line structure of manufacturing equipment according to the present invention include:
[0046] S1. Construct a tree structure of manufacturing equipment structure design content consisting of module type, module, design key points, and knowledge points, such as Figure 2 As shown; specifically:
[0047] The module types are five types: jigs for manufacturing equipment production lines, working systems and action actuators, base plates, racks and appearance, and conveying systems;
[0048] The modules under each module type contain several key nodes in the design process, namely, the design points;
[0049] Each design point contains several knowledge points constructed from basic theory, experience, rules or standards, design requirement constraints, and other five different types of knowledge.
[0050] S2. According to the design content tree structure, the design content of the new manufacturing equipment production line structure is split into the tree structure; specifically, the modules that need to be designed for all equipment in the entire production line are classified and numbered according to module type, and the design content is input into the algorithm to obtain the design points and knowledge points corresponding to each module.
[0051] The method of inputting the design content into the algorithm to obtain the design points and knowledge points corresponding to each module is to use the labeled historical data to construct a design content-module type-design point-knowledge point mapping relationship database, train the natural language processing algorithm model, and recommend the design points contained in each module that needs to be designed and the knowledge points corresponding to each design point.
[0052] S3. Set the working time threshold of the project division task package, calculate the sum of the working hours of all modules of the same module type, compare and judge; specifically:
[0053] If the sum of the working hours of all modules in the same module type is less than or equal to a threshold, all modules in the module type are divided into the same project division task package; wherein, the calculation method of the sum of the working hours of all modules in the same type of modules is: first calculate the single module working hours, and the calculation method is to multiply the working hours of the module type to which the module belongs by the module difficulty coefficient, wherein the difficulty coefficient is a function related to the number of design points, the total number of knowledge points, and the number of knowledge point types contained in the module; then calculate the sum of the working hours of all modules in the same type of modules, and the sum of the module working hours is the accumulation of all single module working hours minus the repeated working hours; the repeated working hours are the ratio of the number of the same knowledge points involved in all modules under the current module type to the total number of knowledge points multiplied by the sum of the working hours of all modules; the threshold of the working hours of the project division task package is 1 to 50 hours, preferably 2 to 12 hours;
[0054] If the sum of the working hours of all modules in the same module type is greater than the threshold, then calculate the similarity between each module in the module type and the whole composed of the remaining modules, remove the module with the smallest similarity value, continue to calculate the sum of the working hours of all the remaining modules, and judge with the threshold until the sum of the working hours of all the remaining modules is less than or equal to the threshold, then all the remaining modules are currently a project division task package; wherein, the similarity is the ratio of the number of the same knowledge point types between the current module and the whole composed of the remaining modules multiplied by the number of the same knowledge points and the number of the knowledge point types contained in the whole composed of the remaining modules multiplied by the total number of knowledge points, that is:
[0055]
[0056] in: The number of the same knowledge points between the current module and the rest of the modules. The number of knowledge point types included in the whole composed of other modules; The number of common knowledge points between the current module and the rest of the modules; The total number of knowledge points in the whole composed of the remaining modules;
[0057] For all modules eliminated in the above steps, calculate the sum of working hours, threshold judgment, eliminate the module with the smallest similarity, and form a project division task package again, until all modules in the current module type are assigned to the project division task package. S4, perform step 3 operations for other module types of manufacturing equipment in sequence, until all modules in all module types are assigned to the project division task package;
[0058] S5. Output the overall division of labor plan for the new manufacturing equipment production line design in the form of a division of labor plan tree structure; Figure 3 As shown, the tree structure of the division of labor scheme includes module type, project division of labor task package, module, and design key points, wherein the project division of labor task package includes the working hours of the division of labor task package and the module numbers contained therein.
[0059] In order to implement the above method, the present invention also provides a Figure 4 The manufacturing equipment production line structure design division system shown includes an input module 1, a storage module 2, a calculation module 3, a combination module 4 and an output module 5;
[0060] The input module 1 is used to input the structural design content of the manufacturing equipment production line, the man-hour threshold of the project division task package, and the man-hour corresponding to the module type;
[0061] The storage module 2 is used to store the constructed manufacturing equipment production line structure design content tree structure, the input new manufacturing equipment production line structure design content, and the input project division task package working time threshold;
[0062] The calculation module 3 is used to calculate the module working hours, execute the natural language processing algorithm model, the similarity value of the module of the same module type and the whole composed of the remaining modules, and the working hours of the whole composed of the remaining modules;
[0063] The combination module 4 is used to combine modules of the same module type;
[0064] The output module 5 is used to output the overall division of labor plan for the new manufacturing equipment production line design in the form of a division of labor plan tree structure.
[0065] In one embodiment, a manufacturing equipment production line structure design division method and system are provided, which is used for the division of labor in the design of a notebook computer assembly production line, and the method includes the following steps:
[0066] S10, constructing a tree structure of manufacturing equipment structure design content consisting of module types, modules, design points, and knowledge points;
[0067] S11. Construct a tree structure of the content of the structural design of the production line of manufacturing equipment. The tree structure includes module types, modules, design points, and knowledge points. The module types are divided into: fixtures, working systems and action actuators, base plates, racks and appearance, and conveying systems; each module type contains several modules according to the actual project requirements, and each module contains several key nodes in the design process, namely design points. For example, the fixture design includes contour design, foolproof design, opening and closing method design, fixed structure design, etc. Each design point contains multiple knowledge points. For example, the opening and closing method includes the degree of opening and closing automation, opening and closing execution method, material selection, and interference considerations.
[0068] S20, splitting the new manufacturing equipment production line structure design content into the tree structure according to the design content tree structure;
[0069] S21. Collect and annotate the historical data of the structural design of the manufacturing equipment production line, and build a database of the mapping relationship between design content, module type, design key points and knowledge points;
[0070] S22. Build a natural language processing algorithm model, and use the constructed design content-module type-design key points-knowledge point mapping relationship database for training to obtain a trained algorithm model, so that the algorithm model can automatically map out the design points contained in each module to be designed and the knowledge points corresponding to each design point based on the input design content and the modules to be designed.
[0071] S23. Classify and number the modules that need to be designed for all equipment in the notebook computer assembly production line by module type; the production line contains 10 equipment. After splitting, the fixture module type contains 30 modules; the working system and action actuator type contains 25 modules, the base plate design module type contains 10 modules, the rack and appearance module type contains 10 modules, and the conveying system contains 11 modules. Each module is numbered.
[0072] S24. Input all modules that need to be designed for the notebook computer assembly production line and the corresponding design contents into the trained algorithm model, and calculate the design points contained in each module and the knowledge points corresponding to each design point.
[0073] S30, setting the working time threshold of the project division task package, calculating the sum of the working hours of all modules of the same module type, and comparing and judging;
[0074] S31. Set a working time threshold for the project division task package. To ensure the project progress, the threshold is generally 1 to 50 hours, preferably 2 to 12 hours. Here, the threshold is set to 12 hours.
[0075] S32, first calculate the single module working hours, the calculation method is to multiply the working hours of the module type to which the module belongs by the module difficulty coefficient, wherein the difficulty coefficient is a function related to the number of design points, the total number of knowledge points, and the number of knowledge point types contained in the module;
[0076] S321. Calculation function of building module difficulty:
[0077]
[0078] is the number of design points included in the module, is the total number of knowledge points contained in each design point in the module, The number of knowledge point types included in each design point in the module, , Q2, Q3 are weight values; generally
[0079]
[0080]
[0081] Here according to the setting =0.5, =0.3, =0.2, the number of design points, total number of knowledge points, and number of knowledge point types contained in each module are brought into the function to calculate the difficulty coefficient of each module respectively;
[0082] S322, construct a single module working time calculation formula and calculate the single module working time, the single module calculation formula is:
[0083]
[0084] in The working hours for the module type are 5 hours for fixture design in the 3C consumer electronics field, 6 hours for working system and action actuator design, 4 hours for base plate design, 5 hours for rack and appearance design, and 6 hours for conveyor system design. Substitute the working hours for each module type into the formula and calculate the working hours for each module separately.
[0085] S33, calculate the sum of the working hours of all modules in the same type of modules, the sum of the working hours of the modules is the sum of the working hours of all single modules minus the repeated working hours, the repeated working hours is the ratio of the number of the same knowledge points involved in all modules under the current module type to the total number of knowledge points multiplied by the sum of the working hours of all modules, the formula is:
[0086]
[0087] in is the total working time of the module, is the total number of modules included, For each single module working hours, is the number of the same knowledge points involved in all modules under the current module type, is the total number of knowledge points.
[0088] S34. Construct a similarity calculation formula between each module and the rest of the modules in the same module type:
[0089]
[0090] The number of the same knowledge points between the current module and the rest of the modules.
[0091] The number of knowledge point types included in the whole composed of other modules;
[0092] The number of common knowledge points between the current module and the rest of the modules;
[0093] The total number of knowledge points in the whole composed of other modules.
[0094] S35. First, calculate the fixture design module type. The total working hours of all 30 modules is 187 hours, which is greater than the threshold of 12 hours. Then take out module 01 and calculate the similarity value of the whole composed of module 01 and modules 02 to 30. 0.78, and calculate the similarity value between each module and the rest of the modules, and obtain the similarity values respectively. , ··· ,in The similarity value is 0.32, which is the smallest value, and the module No. 23 in the fixture design is eliminated;
[0095] S36, the total working hours of the 29 modules except module No. 23 in the fixture module is calculated to be 182 hours, which is compared with the threshold value 12 and is greater than the threshold value, and step S35 is performed again until the sum of all remaining modules is less than the threshold value. At this time, the remaining modules are numbered 06, 13, and 19, and the remaining 3 modules are divided into a project division task package;
[0096] S38, remove modules 06, 13, and 19 that have been assigned to the project division task package in the above steps, calculate the total working hours of the remaining 27 modules, compare with the threshold, and repeat the above steps S35 to S36 until all modules in the current module type are assigned to the project division task package;
[0097] S40, performing step 3 for other module types of manufacturing equipment in sequence until modules in all module types are allocated to the project division task package;
[0098] S41, respectively perform steps S31 to S38 on the remaining working system and action actuator module types, base plate module types, rack and appearance module types, and conveying system module types, and assign all modules to the project division task package;
[0099] S50. Output the overall division of labor plan for the new manufacturing equipment production line design in the form of a division of labor plan tree structure;
[0100] S51, output the division of labor scheme in a tree structure of the division of labor scheme, the tree structure of the division of labor scheme includes module type, project division of labor task package, module, design key points, the project division of labor task package includes the working hours of the division of labor task package and the module number contained. For example, the scheme of this embodiment is divided into 43 project division of labor task packages, among which the fixture design type includes 13 project division of labor task packages, among which the project division of labor task package 01 includes fixture design modules numbered 06, 13, and 19, with a working time of 11 hours, among which the design key points included in the 06 module are profiling design, foolproof design, automatic opening and closing, electric module execution, and bolt fixing; the design key points under the 13 module are profiling design, foolproof design, automatic opening and closing, cylinder module, and bolt fixing; the design key points under the 19 module are profiling design, foolproof design, semi-dynamic opening and closing, cylinder module, and bolt fixing.
[0101] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modification, equivalent replacement and improvement made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A method for division of labor in structural design of a manufacturing equipment production line, characterized in that: The method comprises: S1. Construct a tree structure of manufacturing equipment structure design content consisting of module types, modules, design points, and knowledge points; S2. According to the design content tree structure, split the manufacturing equipment production line structure design content into the tree structure; S3. Set the working time threshold of the project division task package, calculate the sum of the working hours of all modules of the same module type, and compare and judge: If the sum of the working hours of all modules in the same module type is less than or equal to the threshold, all modules in the module type are divided into the same project division task package; If the sum of the working hours of all modules of the same module type is greater than the threshold, the similarity between each module of the module type and the whole composed of the remaining modules is calculated, and the module with the smallest similarity value is eliminated. The sum of the working hours of all the remaining modules is calculated and compared with the threshold until the sum of the working hours of all the remaining modules is less than or equal to the threshold. In this case, all the remaining modules are currently a project division task package; For all modules eliminated in the above steps, the sum of working hours is calculated again, the threshold is determined, the module with the smallest similarity is eliminated, and the project division task package is formed, until all modules in the current module type are assigned to the project division task package; S4. Perform step 3 for other module types of manufacturing equipment in sequence until all modules in all module types are allocated to the project division task package; S5. Output the overall division of labor plan for the new manufacturing equipment production line design in the form of a division of labor plan tree structure.
2. A method for designing a manufacturing equipment production line structure according to claim 1, characterized in that: In step S1, a manufacturing equipment structure design content tree structure consisting of module type, module, design key points, and knowledge points is constructed, specifically: The module types are five types: fixtures for manufacturing equipment production lines, working systems and motion actuators, base plates, racks and appearance, and conveying systems; The modules under each module type contain several key nodes in the design process, namely, the design points; Each design point contains several knowledge points constructed from basic theory, experience, rules or standards, design requirement constraints, and other five different types of knowledge.
3. A method for designing a manufacturing equipment production line structure according to claim 1, characterized in that: In the step S2, according to the design content tree structure, the new manufacturing equipment production line structure design content is split into the tree structure. Specifically, the modules that need to be designed for all equipment in the entire production line are classified and numbered by module type, and the design content is input into the algorithm to obtain the design points and knowledge points corresponding to each module.
4. A method for division of labor in structural design of a manufacturing equipment production line according to claim 3, characterized in that: The method of inputting the design content into the algorithm to obtain the design points and knowledge points corresponding to each module is to use the labeled historical data to construct a design content-module type-design point-knowledge point mapping relationship database, train the natural language processing algorithm model, and recommend the design points contained in each module that needs to be designed and the knowledge points corresponding to each design point.
5. A method for division of labor in structural design of a manufacturing equipment production line according to claim 1, characterized in that: In step S3, the sum of the working hours of all modules of the same type is calculated, specifically: First, calculate the single module working hours, which is calculated by multiplying the working hours of the module type to which the module belongs by the module difficulty coefficient, where the difficulty coefficient is a function related to the number of design points, the total number of knowledge points, and the number of knowledge point types contained in the module; Then calculate the sum of all module working hours in the same type of modules, where the sum of module working hours is the accumulation of all single module working hours minus repeated working hours; The repetitive working hours are the ratio of the number of identical knowledge points involved in all modules under the current module type to the total number of knowledge points multiplied by the sum of the working hours of all modules.
6. A method for division of labor in structural design of a manufacturing equipment production line according to claim 1, characterized in that: In the step S3, a working time threshold of the project division task package is set, and the working time threshold of the project division task package is 1 to 50 hours.
7. A method for division of labor in structural design of a manufacturing equipment production line according to claim 1, characterized in that: In step S3, the similarity between each module in the module type and the whole composed of the remaining modules is calculated. The similarity is the ratio of the number of the same knowledge point types between the current module and the whole composed of the remaining modules multiplied by the number of the same knowledge points and the number of the knowledge point types contained in the whole composed of the remaining modules multiplied by the total number of knowledge points, that is: ; The number of the same knowledge points between the current module and the rest of the modules. The number of knowledge point types included in the whole composed of other modules; The number of common knowledge points between the current module and the rest of the modules; The total number of knowledge points in the whole composed of other modules.
8. A method for division of labor in structural design of a manufacturing equipment production line according to claim 1, characterized in that: In step S5, the overall division of labor plan for the new manufacturing equipment production line design is output in the form of a division of labor plan tree structure, wherein the division of labor plan tree structure includes module type, project division of labor task package, module, and design key points, wherein the project division of labor task package includes the working hours of the division of labor task package and the module numbers contained therein.
9. A manufacturing equipment production line structure design division system, comprising any method of claims 1-8, characterized in that: The system comprises an input module (1), a storage module (2), a calculation module (3), a combination module (4) and an output module (5); The input module (1) is used to input the structural design content of the manufacturing equipment production line, the working time threshold of the project division task package, and the working time corresponding to the module type; The storage module (2) is used to store the constructed manufacturing equipment production line structure design content tree structure, the input new manufacturing equipment production line structure design content, and the input project division task package working time threshold; The calculation module (3) is used to calculate the module working hours, execute the natural language processing algorithm model, the similarity value of the module of the same module type and the whole composed of the remaining modules, and the working hours of the whole composed of the remaining modules; The combination module (4) is used to combine modules of the same module type; The output module (5) is used to output a new overall division of labor plan for the design of a manufacturing equipment production line in the form of a division of labor plan tree structure.