Glass melting furnace brace structure and construction method thereof
By welding the pull-bar support on the original column of the glass melting kiln and installing the pull-bar, the problem of insufficient column height after transformation is solved, saving on transformation costs and safety of the transformation method is achieved.
Patent Information
- Application Number
- CN202411470612.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-21
- Publication Date
- 2025-04-08
AI Technical Summary
After the glass melting kiln was coldly modified, the original column height could not meet the requirements of laying double-stretch strips, resulting in increased costs and poor economicality during the transformation process.
By welding the pull-bar support at the upper end of the original melting section column, and using the original melting section column as the modified pull-bar fulcrum, the pull-bar is installed, and the pull-bar and the pull-bar support are fixed using a one-way thrust ball bearing and nut.
The problem of the original column height after the renovation cannot meet the layout of double-stretch strips, achieving a large reduction in transformation cost, and the transformation method is simple, safe and reliable.
Smart Images

Figure CN119774855A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of glass melting furnaces, and in particular to a glass melting furnace tie rod structure and a construction method thereof. Background Art
[0002] Glass melting furnace is a large thermal equipment. To ensure that the melting furnace remains stable and reliable during long-term hot operation, in addition to the reasonable configuration of refractory materials in various parts, a reasonable and safe steel structure must be matched with it. The large arch of the melting part of the horizontal flame glass melting furnace generally adopts a double-braced structure, which is mainly composed of a brace, a column, a one-way thrust ball bearing and a nut. The double-braced structure mainly resists the horizontal thrust generated by the large arch to maintain the thermal stability and safety of the large arch.
[0003] When a glass melting furnace is cold-modified after running for a period of time, there is often a requirement to increase the tonnage. The increase in the width of the tank will increase the height of the arch and the height of the breast wall. This causes the original column height to be unable to meet the requirements for arranging double tie bars. If new columns are made, it runs counter to the concept of rationality and economy in the transformation process. In view of the above-mentioned problems in the transformation process, the present invention aims to provide a glass melting furnace tie bar structure and a construction method thereof to solve the problem that the original column height after the transformation cannot meet the requirements for arranging double tie bars. Summary of the invention
[0004] The object of the present invention is to provide a glass melting furnace tie rod structure and a construction method thereof, so as to solve the above-mentioned technical problems.
[0005] The technical solution adopted by the present invention is as follows:
[0006] A glass melting furnace tie rod structure comprises a melting section column, a breast wall, a large arch, a tie rod, a nut, a one-way thrust ball bearing and a tie rod support, wherein the large arch and the breast wall are arranged between two melting section columns, the two ends of the large arch are connected to the two breast walls, the two breast walls are connected to the melting section columns, the upper ends of the two melting section columns are provided with the tie rod support, the two ends of the tie rod are connected to the two tie rod supports through the nut, the one-way thrust ball bearing is also arranged on the tie rod, and the one-way thrust ball bearing is located between the tie rod support and the nut.
[0007] Preferably, the brace support comprises a bottom plate, a vertical plate and a triangular plate, the vertical plate is arranged at one end of the base, and two triangular plates are arranged at the angle between the bottom plate and the vertical plate.
[0008] As a further preference, it further includes a rib plate, and the rib plate is arranged at the lower end of the bottom plate.
[0009] As a further preference, it further comprises a support plate, wherein the upper end of the bottom plate is provided with the support plate, the support plate is located between the two triangular plates, and the support plate is directly opposite to the vertical plate.
[0010] As a further preference, a mounting hole is provided on the vertical plate, and the upper surface of the support plate is flush with the plane where the lower inner wall of the mounting hole is located.
[0011] A construction method for a glass melting furnace tie rod structure, characterized in that it comprises the glass melting furnace tie rod structure, and the construction method comprises:
[0012] S1. First, weld and fix the tie rod support to the upper end of the melting part column;
[0013] S2, passing the end of the pull rod through the mounting hole on the vertical plate so that the lower surface of the pull rod abuts against the upper surface of the support plate;
[0014] S3. Install a one-way thrust ball bearing at the end of the tie rod, and then install the nut to lock and secure the tie rod and the tie rod support.
[0015] As a further preference, during the welding process of the brace support, first, fillet welds are made between the vertical plate and the flange of the melting part column, then fillet welds are made between the rib plate and the flange of the melting part column, and then fillet welds are made between the bottom plate and the web of the melting part column.
[0016] As a further preference, the height of the fillet weld between the vertical plate and the flange of the melting part column is 12 mm.
[0017] The above technical solution has the following advantages or beneficial effects:
[0018] In the present invention, by arranging the cooperation between the pull rod support and the pull rod, the problem that the height of the original melting part column cannot meet the requirements of arranging double pull rods is solved, the original melting part column is reused, and a large cost saving of transformation is achieved. It has good economic benefits, and the transformation method is simple, convenient, safe and reliable, and can be promoted to other glass melting furnace transformation projects. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a partial structural schematic diagram of the glass melting furnace tie rod structure in the present invention;
[0020] Figure 2 yes Figure 1 The enlarged view of point A in the middle;
[0021] Figure 3 This is a schematic diagram of the structure of the brace support in the present invention. Figure 1 ;
[0022] Figure 4 This is a schematic diagram of the structure of the brace support in the present invention. Figure 2 .
[0023] In the figure: 1, melting section column; 2, breast wall; 3, large arch; 4, tie rod; 5, nut; 6, one-way thrust ball bearing; 7, tie rod support; 71, bottom plate; 72, vertical plate; 73, triangular plate; 74, rib plate; 75, support plate; 76, mounting hole. DETAILED DESCRIPTION
[0024] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0025] In the description of the present invention, it should be noted that, if the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. appear, the orientation or position relationship indicated is based on the orientation or position relationship shown in the drawings, which is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, if the terms "first", "second", "third" appear, they are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.
[0026] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected" and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0027] Figure 1 It is a partial structural schematic diagram of the glass melting furnace tie rod structure in the present invention; Figure 2 yes Figure 1 The enlarged view of point A in the middle; Figure 3 This is a schematic diagram of the structure of the brace support in the present invention. Figure 1 ; Figure 4 This is a schematic diagram of the structure of the brace support in the present invention. Figure 2 , see Figures 1 to 4As shown, a preferred embodiment is shown, which shows a glass melting furnace tie rod structure, including a melting part column 1, a breast wall 2, a large crown 3, a tie rod 4, a nut 5, a one-way thrust ball bearing 6 and a tie rod support 7. A large crown 3 and a breast wall 2 are provided between the two melting part columns 1. The two ends of the large crown 3 are connected to the two breast walls 2, and the two breast walls 2 are connected to the melting part column 1. The upper ends of the two melting part columns 1 are provided with a tie rod support 7. The two ends of the tie rod 4 are connected to the two tie rod supports 7 through nuts 5. A one-way thrust ball bearing 6 is also provided on the tie rod 4, and the one-way thrust ball bearing 6 is located between the tie rod support 7 and the nut 5. When a glass melting furnace is cold-modified, there is often a requirement to increase the tonnage. Generally, the purpose of increasing the melting capacity is achieved by increasing the pool width and the length of the melting part. The increase in the pool width will increase the height of the large crown 3, and the height of the breast wall 2 will also increase accordingly. This results in that the original melting part column 1 cannot meet the requirement of arranging double tie bars. In this embodiment, the upper tie bars of the original melting part column 1 are used as the modified lower tie bars, and tie bar supports 7 are welded on the top of the original melting part column 1 to install the upper tie bars, thereby solving the problem that the original column height cannot meet the requirement of arranging double tie bars after modification, and the original column is reused, thus achieving a significant reduction in modification cost.
[0028] Furthermore, as a preferred embodiment, the brace support 7 includes a bottom plate 71, a vertical plate 72 and a triangular plate 73. The vertical plate 72 is provided at one end of the base, and two triangular plates 73 are provided at the angle between the bottom plate 71 and the vertical plate 72. It also includes a rib plate 74, which is provided at the lower end of the bottom plate 71, and a support plate 75, which is provided at the upper end of the bottom plate 71. The support plate 75 is located between the two triangular plates 73, and the support plate 75 is directly opposite to the vertical plate 72. The vertical plate 72 and the support plate 75 are used to support the brace 4, and the bottom plate 71, the vertical plate 72, the triangular plate 73, the rib plate 74 and the support plate 75 can be integrally formed or welded.
[0029] Further, as a preferred embodiment, a mounting hole 76 is provided on the vertical plate 72, and the upper surface of the support plate 75 is flush with the plane where the lower inner wall of the mounting hole 76 is located. The mounting hole 76 runs through the vertical plate 72, and the mounting hole 76 is used to install the end of the pull rod 4. The end of the pull rod 4 can pass through the mounting hole 76, and then the lower surface of the pull rod 4 will be supported on the upper surface of the support plate 75, so as to support the pull rod 4.
[0030] By providing the one-way thrust ball bearing 6 and the nut 5 , the brace 4 and the brace support 7 can be fixed together.
[0031] On the basis of the above embodiments, the present invention also has the following preferred construction method:
[0032] A construction method for a glass melting furnace tie rod structure, the construction method comprising:
[0033] S1. First, weld and fix the tie rod support 7 to the upper end of the melting part column 1; during the welding process of the tie rod support 7, first, fillet weld the vertical plate 72 and the flange of the melting part column 1, then fillet weld the rib plate 74 and the flange of the melting part column 1, and then fillet weld the bottom plate 71 and the web of the melting part column 1.
[0034] S2, passing the end of the pull bar 4 through the mounting hole 76 on the vertical plate 72, so that the lower surface of the pull bar 4 abuts against the upper surface of the support plate 75;
[0035] S3. Install a one-way thrust ball bearing 6 at the end of the tie rod 4, and then install a nut 5 to lock and fix the tie rod 4 and the tie rod support 7.
[0036] Among them, the weld height of the fillet weld between the vertical plate 72 and the flange of the melting part column 1 is 12 mm, the weld height of the fillet weld between the rib plate 74 and the flange of the melting part column 1 is 12 mm, and the weld height of the fillet weld between the bottom plate 71 and the web of the melting part column 1 is 12 mm, which effectively enhances the connection strength between the tie rod support 7 and the melting part column 1.
[0037] In this embodiment, the brace support 7 and the support plate 75 are used to support the brace 4 to prevent the brace 4 from sagging due to its own gravity and affecting the installation. The non-verticality between the vertical plate 72 and the bottom plate 71 of the brace support 7 is not greater than 0.5 mm. Figure 3 and Figure 4 The surface with the symbol "▽" indicates the processed surface, and the surface unevenness is no more than 1mm.
[0038] The above description is only a preferred embodiment of the present invention, and does not limit the implementation mode and protection scope of the present invention. For those skilled in the art, it should be aware that all solutions obtained by equivalent substitutions and obvious changes made using the description and illustrations of the present invention should be included in the protection scope of the present invention.
Claims
1. A glass melting furnace pull rod structure, characterized in that: It includes a melting part column, a breast wall, a large arch, a tie rod, a nut, a one-way thrust ball bearing and a tie rod support. The large arch and the breast wall are arranged between the two melting part columns. The two ends of the large arch are connected to the two breast walls. The two breast walls are connected to the melting part columns. The upper ends of the two melting part columns are provided with the tie rod support. The two ends of the tie rod are connected to the two tie rod supports through the nut. The one-way thrust ball bearing is also arranged on the tie rod. The one-way thrust ball bearing is located between the tie rod support and the nut.
2. The glass melting furnace tie rod structure according to claim 1, characterized in that: The brace support comprises a bottom plate, a vertical plate and a triangular plate. The vertical plate is arranged at one end of the base, and two triangular plates are arranged at the angle between the bottom plate and the vertical plate.
3. The glass melting furnace tie rod structure according to claim 2, characterized in that: It also includes a rib plate, which is arranged at the lower end of the bottom plate.
4. The glass melting furnace tie rod structure according to claim 2, characterized in that: It also includes a support plate, which is arranged on the upper end of the bottom plate, and is located between the two triangular plates, and is directly opposite to the vertical plate.
5. The glass melting furnace tie rod structure according to claim 4, characterized in that: The vertical plate is provided with a mounting hole, and the upper surface of the support plate is flush with the plane where the lower inner wall of the mounting hole is located.
6. A construction method for a glass melting furnace tie rod structure, characterized in that: The glass melting furnace tie rod structure comprising any one of claims 1 to 5, wherein the construction method comprises: S1. First, weld and fix the rod support to the upper end of the melting part column; S2, passing the end of the pull rod through the mounting hole on the vertical plate so that the lower surface of the pull rod abuts against the upper surface of the support plate; S3. Install a one-way thrust ball bearing at the end of the tie rod, and then install the nut to lock and secure the tie rod and the tie rod support.
7. The construction method of the glass melting furnace tie rod structure according to claim 6, characterized in that: During the welding process of the brace support, first, fillet weld the vertical plate and the flange of the melting part column, then fillet weld the rib plate and the flange of the melting part column, and then fillet weld the bottom plate and the web of the melting part column.
8. The construction method of the glass melting furnace tie rod structure according to claim 7, characterized in that: The height of the fillet weld between the vertical plate and the flange of the melting part column is 12mm.