Steel lock plate connecting joint, shear wall structure, shear wall and mounting method of shear wall

By using steel lock plates to connect nodes in modular buildings, the problem of vertical connection of shear walls is solved, efficient construction technology and good structural stability are achieved, and the concept of modular building is in line with the concept of modular building.

CN119777502AActive Publication Date: 2025-04-08CHINA CONSTR FOURTH ENG DIV CORP LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411918193.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-25
Publication Date
2025-04-08
Estimated Expiration
2044-12-25

AI Technical Summary

Technical Problem

In modular buildings, vertical connection processing of shear walls is difficult, and the existing methods require on-site binding of steel bars and support formwork, resulting in low construction efficiency and inconsistent with the concept of modular buildings.

Method used

The steel lock plate is used to connect the nodes, including the embedded piece plate, the steel lock plate assembly, the first anchor rib group and the second anchor rib group. By setting the first plate and the second plate on the embedded piece plate to form a fitting cavity, and the anchor rib group is spaced apart in the vertical direction, the uniform distribution of the anchor force is ensured.

Benefits of technology

It realizes a reliable vertical connection between the shear walls between modules, has sufficient shear resistance and energy consumption, reduces on-site processes, improves construction efficiency, and realizes a construction process without supporting molds.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119777502A_ABST
    Figure CN119777502A_ABST
Patent Text Reader

Abstract

The invention discloses a steel lock plate connecting joint, a shear wall structure, a shear wall and a mounting method of the shear wall. The steel lock plate connecting joint comprises an embedded part plate, a steel lock plate assembly, a first anchor bar set and a second anchor bar set, and the first anchor bar set is configured to be pre-embedded in a first double-skin wall by a first preset depth; the second anchor bar group is configured to be pre-buried in the second double-skin wall by a second preset depth, and after the second anchor bar group vertically falls down, the anchor rods are inserted and fixed from the anchor bolt holes; the stress can be dispersed, so that the durability and the service life of the structure are improved; the steel lock plate connecting joints are added in the manufacturing process of the shear wall structure, when two shear wall structures are spliced, the vertical connection problem of shear walls between modules can be solved directly through the mode that the two steel lock plate connecting joints are buckled with each other, sufficient shear resistance and energy consumption are achieved, the risk of structural failure is reduced, and the service life of the shear wall structure is prolonged. The safety of the whole structure is improved, the formwork-free construction technology is achieved, and the concept of less operation on a modular building site is met.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention patent relates to the field of modular building engineering construction, and in particular to a steel lock plate connection node, a shear wall structure, a shear wall and an installation method thereof. Background Art

[0002] Prefabricated buildings have become an important direction for achieving green buildings and industrialization due to their short construction period and clean and environmentally friendly construction sites. Among them, modular buildings have become the mainstream direction of future development with their advantages of highly integrated decoration and electromechanical pipelines. Currently, modular buildings mainly include steel structure modular buildings and concrete modular buildings. Concrete modular building structures have price advantages and have become the mainstream development direction.

[0003] In modular shear wall buildings, due to the overlap of anchor steel bars in modular building shear walls, a vertical drop installation process is used during installation. This makes it difficult to handle the vertical joints of shear walls between different modules. A common practice is to tie steel bars on site and support formwork for partial concrete pouring. This method can ensure the reliability of the vertical connection of the shear wall, but some formwork still needs to be retained on site, which is contrary to the concept of modular building with less on-site work.

[0004] Therefore, a new connection node is needed to achieve on-site formwork-free construction and solve the vertical connection problem of shear walls between modules. Summary of the invention

[0005] In view of this, the present invention provides a steel lock plate connection node, a shear wall structure, a shear wall and an installation method thereof, which solve the vertical connection problem of the shear wall between modules, have sufficient shear resistance and energy dissipation effect, and can realize a formwork-free construction process.

[0006] To solve the above problems, in the first aspect, the present invention provides a steel locking plate connection node, including an embedded plate, a steel locking plate assembly, a first anchor bar group and a second anchor bar group. The embedded plate has a first side surface and a second side surface that are arranged opposite to each other; the steel locking plate assembly is arranged on the first side surface of the embedded plate, the steel locking plate assembly includes a first plate, a second plate, an anchor hole and an interlocking cavity, the first plate is vertically arranged on the embedded plate, and the first plate is arranged between the embedded plate and the second plate to form an interlocking cavity, the first plate is perpendicular to the second plate, and the first plate is provided with an anchor hole; the first anchor bar group is arranged on the second side surface of the embedded plate, the first anchor bar group includes a plurality of first anchor bars, and the plurality of first anchor bars are distributed on the second side surface at intervals in the vertical direction; the second anchor bar group is arranged on the second side surface of the embedded plate, the second anchor bar group is arranged opposite to the first anchor bar group, the second anchor bar group includes a plurality of second anchor bars, and the plurality of second anchor bars are distributed on the second side surface at intervals in the vertical direction, and the first anchor bars and the second anchor bars placed at the same height are arranged opposite to each other.

[0007] Different from the prior art, the above technical solution can provide better mechanical stability and bearing capacity by arranging the first plate and the second plate on the embedded plate to form an interlocking cavity. Especially when subjected to vertical and horizontal loads, the first anchor bar group and the second anchor bar group are spaced apart in the vertical direction and arranged relatively. Such a layout can ensure uniform distribution of anchoring force and improve the anchoring performance of the overall structure. The setting of the anchor hole makes it easy to install and fix the anchor bolts, simplifies the construction process, ensures the reliability of the vertical connection of the shear wall, reduces on-site processes, and improves construction efficiency.

[0008] In some embodiments, the first plate is eccentrically disposed on the embedded plate, and the anchor hole is disposed close to the second plate.

[0009] In some embodiments, the first plate has a first extension length; the first anchor bar has a first length, the first length is greater than the first extension length; and / or the second anchor bar has a second length, the second length is greater than the first extension length.

[0010] In a second aspect, the present invention further provides a shear wall structure, comprising a first double wall and a second double wall. The second double wall is arranged in parallel with the first double wall, and there is a building gap to be filled between the first double wall and the second double wall; a plurality of steel lock plate connection nodes are arranged in the building gap at intervals along the extension direction of the first double wall, and the steel lock plate connection nodes are the steel lock plate connection nodes described in the first aspect.

[0011] In some embodiments, the first anchor bar group is configured to be pre-buried in the first double skin wall at a first preset depth; the second anchor bar group is configured to be pre-buried in the second double skin wall at a second preset depth; the first plate is configured to protrude a preset distance beyond the outer edge of the first double skin wall so that the anchor hole is placed outside the first double skin wall.

[0012] In a third aspect, the present invention provides a shear wall, comprising a first shear wall and a second shear wall. The first shear wall is the shear wall structure described in the second aspect, the first shear wall has a first steel locking plate connection node, and the first steel locking plate connection node has a first interlocking cavity; the second shear wall is the shear wall structure described in the second aspect, the second shear wall has a second steel locking plate connection node, and the second steel locking plate connection node has a second interlocking cavity; the first shear wall and the second shear wall are configured to be nested and connected through the first steel locking plate connection node and the second steel locking plate connection node, and the first interlocking cavity and the second interlocking cavity at least partially overlap.

[0013] In some embodiments, the first steel locking plate connection node has a first anchor hole, the second steel locking plate connection node has a second anchor hole, the shear wall structure includes an anchor rod group, the anchor rod group includes multiple anchor rods, and each anchor rod sequentially passes through the first anchor hole and the second anchor hole located at the same height.

[0014] In a fourth aspect, the present invention provides a shear wall installation method, which is applicable to the shear wall described in the third aspect, wherein the first shear wall has a first building gap, and the second shear wall has a second building gap, and the shear wall installation method comprises:

[0015] Placing the first shear wall at a first preset position along the vertical direction so that the first engaging cavity is opened toward the first direction;

[0016] Move the second shear wall from top to bottom in the vertical direction to a second preset position, so that the second steel lock plate connection node is nested at the first steel lock plate connection node, the second embedding cavity is opened in a second direction, the second direction is opposite to the first direction, and the first embedding cavity and the second embedding cavity at least partially overlap;

[0017] Concrete is filled into the first building gap, the second building gap, the first embedding cavity and the second embedding cavity to obtain a shear wall.

[0018] In some embodiments, the first steel lock plate connection node has a first anchor bolt hole, the second steel lock plate connection node has a second anchor bolt hole, the shear wall further includes an anchor rod group, the anchor rod group includes a plurality of anchor rods, and each anchor rod sequentially penetrates the first anchor bolt hole and the second anchor bolt hole disposed at the same height;

[0019] Before the first building gap, the second building gap, the first embedding cavity and the second embedding cavity are filled with concrete to obtain the shear wall, the method further includes:

[0020] The anchor rod is sequentially passed through the first anchor bolt hole and the second anchor bolt hole which are arranged at the same height.

[0021] Different from the prior art, the above technical solution has the following beneficial effects:

[0022] The first anchor bar group is configured to be embedded in the first double skin wall at a first preset depth; the second anchor bar group is configured to be embedded in the second double skin wall at a second preset depth, and after vertically dropping, the anchor rod is inserted from the anchor bolt hole to be fixed; by setting the first anchor bar group and the second anchor bar group on the embedded plate, the stress can be dispersed, thereby improving the durability and service life of the structure; after the fixing is completed, the concrete poured in the first building gap, the second building gap, and the first and second interlocking cavities can form an effective connection, which can solve the vertical connection problem of the shear wall between modules, has sufficient shear resistance and energy dissipation, and the design of the structure takes into account the transmission and distribution of force. Through reasonable layout and structural design, the risk of structural failure can be reduced and the safety of the overall structure can be improved. At the same time, a formwork-free construction process can be realized, which is in line with the concept of less work on site in modular buildings. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0024] Figure 1 It is a schematic diagram of the steel lock plate connection node;

[0025] Figure 2 It is a schematic diagram of the steel lock plate connection node in the connected state;

[0026] Figure 3 It is a schematic diagram of the shear wall structure described in the first embodiment without pouring the first double skin wall and the second double skin wall;

[0027] Figure 4 It is a schematic diagram of pouring the first double skin wall of the shear wall structure described in the first embodiment;

[0028] Figure 5 It is a schematic diagram of pouring the second double skin wall of the shear wall structure described in the first embodiment;

[0029] Figure 6 is a schematic diagram of the shear wall structure described in the first embodiment;

[0030] Figure 7 is a first connection schematic diagram of the shear wall structure described in the second embodiment;

[0031] Figure 8 is a second connection schematic diagram of the shear wall structure described in the second embodiment;

[0032] Fig. 9 is a third connection schematic diagram of the shear wall structure described in the second embodiment;

[0033] Fig.10 It is a schematic diagram of a unit building module.

[0034] Reference numerals:

[0035] 1. Steel lock plate connection node;

[0036] 11. Embedded plate;

[0037] 12. First plate;

[0038] 121, anchor bolt hole;

[0039] 122. Chimeric cavity;

[0040] 13. Second plate;

[0041] 14. The first anchor bar group;

[0042] 15. The second anchor bar group;

[0043] 2. Shear wall structure;

[0044] 21. The first double skin wall;

[0045] 22. The second double skin wall;

[0046] 3. The first shear wall;

[0047] 31. First steel lock plate connection node;

[0048] 32. First building gap;

[0049] 4. Second shear wall;

[0050] 41. Second steel lock plate connection node;

[0051] 42. Second building void;

[0052] 5. Anchor rod;

[0053] 6. Unit building module;

[0054] 61. Vertical connection nodes.

[0055] a. First direction;

[0056] b. Second direction. DETAILED DESCRIPTION

[0057] The present invention will be further described in detail below in conjunction with the accompanying drawings and examples. It is particularly noted that the following examples are only used to illustrate the present invention, but are not intended to limit the scope of the present invention. Similarly, the following examples are only partial embodiments of the present invention rather than all embodiments, and all other embodiments obtained by those of ordinary skill in the art without creative work are within the scope of protection of the present invention.

[0058] The present invention provides a steel lock plate connection node based on a modular shear wall structure, which can realize a formwork-free construction process, can solve the vertical connection problem of shear walls between modules, and has sufficient shear resistance and energy dissipation effect.

[0059] See also Figure 1 and Figure 2In a first aspect, the present embodiment provides a steel locking plate connection node 1, comprising an embedded plate 11, a steel locking plate assembly, a first anchor bar group 14 and a second anchor bar group 15. The embedded plate 11 has a first side surface and a second side surface which are arranged opposite to each other; the steel locking plate assembly is arranged on the first side surface of the embedded plate 11, and the steel locking plate assembly includes a first plate 12, a second plate 13, an anchor hole 121 and an interlocking cavity 122, the first plate 12 is vertically arranged on the embedded plate 11, and the first plate 12 is arranged between the embedded plate 11 and the second plate 13 to form the interlocking cavity 122, the first plate 12 is perpendicular to the second plate 13, and the first plate 12 is provided with an anchor hole 121; the first anchor bar group 14 is arranged on the second side surface of the embedded plate 11, the first anchor bar group 14 includes a plurality of first anchor bars, and the plurality of first anchor bars are distributed on the second side surface at intervals in the vertical direction; the second anchor bar group 15 is arranged on the second side surface of the embedded plate 11, the second anchor bar group 15 is arranged opposite to the first anchor bar group 14, the second anchor bar group 15 includes a plurality of second anchor bars, and the plurality of second anchor bars are distributed on the second side surface at intervals in the vertical direction, and the first anchor bars and the second anchor bars which are placed at the same height are arranged opposite to each other.

[0060] In this embodiment, the embedded plate 11 refers to a metal plate pre-embedded in concrete for subsequent connection with other steel structures, namely, the first plate 12, the second plate 13, the first anchor bar group 14 and the second anchor bar group 15; the first plate 12 and the second plate 13 are two main components in the steel locking plate assembly, which are arranged vertically to form a U-shaped structure with the embedded plate 11, namely, a fitting cavity. Anchor holes 121 are provided on the first plate 12, and the anchor holes 121 are used for the subsequent fixing process of the anchor rod 5, as described below. It can be understood that the anchor holes 121 can be arranged close to one side of the second plate 13 for easy splicing. The provision of the anchor holes 121 allows the anchor rod 5 to be easily installed and fixed, simplifying the construction process.

[0061] The first anchor bar group 14 and the second anchor bar group 15 are distributed at intervals along the vertical direction on the other side of the embedded plate. For the convenience of distinction, the two sides of the embedded plate 11 are recorded as the first side and the second side. The first plate 12 and the second plate 13 are distributed on the first side, and the first anchor bar group 14 and the second anchor bar group 15 are distributed on the second side and are arranged opposite to each other. Specifically, the first anchor bar group 14 includes a plurality of first anchor bars, and the first anchor bars are distributed at intervals along the vertical direction on the second side, such as Figure 1 and Figure 2 As shown, the second anchor bar group 15 includes a plurality of second anchor bars, and the second anchor bars are distributed at intervals on the second side surface along the vertical direction. Figure 1 and Figure 2 As shown, it can be understood that the first anchor bar and the second anchor bar can be set in one-to-one correspondence based on the set height, so that the uniform distribution of the anchoring force can be achieved and the anchoring performance of the overall structure can be improved.

[0062] When in use, the first anchor bar group 14, the second anchor bar group 15 and the embedded plate 11 are all pre-embedded in the shear wall structure 2. After pouring concrete to form the double wall described later, the steel locking plate assembly can be directly fixed in the building gap of the shear wall structure 2 to facilitate further splicing and use.

[0063] In this embodiment, the first anchor bar group 14 is configured to be embedded in the first double skin wall 21 at a first preset depth; the second anchor bar group 15 is configured to be embedded in the second double skin wall 22 at a second preset depth. By arranging the first anchor bar group 14 and the second anchor bar group 15 on the embedded plate, stress can be dispersed, thereby improving the durability and service life of the structure; it has sufficient shear resistance and energy dissipation, takes into account the transmission and distribution of force, reduces the risk of structural failure, and improves the safety of the overall structure. It is convenient to realize the construction process of the shear wall in the splicing process without formwork, which is in line with the concept of less work on the modular building site.

[0064] See also Figure 1 and Figure 2 In this embodiment, the first plate 12 is eccentrically disposed on the embedded plate 11 , and the anchor hole 121 is disposed close to the second plate 13 .

[0065] In this embodiment, the eccentric setting of the first plate 12 can keep the center of gravity of the entire steel lock plate connection node 1 at the geometric center, which can improve the connection strength of the entire steel lock plate connection node 1. At the same time, the eccentric setting of the first plate 12 is convenient for the subsequent splicing of two steel lock plate connection nodes 1. The middle interlocking cavity can have a larger area overlap to pour concrete and ensure the stress strength of the two steel lock plate connection nodes 1 after pouring. By arranging the first plate 12 and the second plate 13 on the embedded plate 11 and forming the interlocking cavity 122, such a structural design can provide better mechanical stability and bearing capacity when bearing vertical and horizontal loads.

[0066] In this embodiment, the anchor hole 121 is arranged close to the second plate 13. When the two steel lock plate connection nodes 1 are subsequently spliced, the space area occupied by the anchor rod 5 connection can be reduced, and the steel lock plate connection node 1 can be placed as much as possible between the building gap enclosed by the first double skin wall 21 and the second double skin wall 22, thereby improving the connection strength when the two shear wall structures 2 are spliced, and reducing the influence of the vertical connection node 61 at the connection point on the overall connection structure.

[0067] See also Figure 1 In this embodiment, the first plate 12 has a first extension length; the first anchor bar has a first length, which is greater than the first extension length; the second anchor bar has a second length, which is greater than the first extension length.

[0068] In this embodiment, the first extension length can be understood as the distance between the second plate 13 and the first side of the embedded plate 11, the first length of the first anchor bar can be understood as the distance between the free end of the first anchor bar and the second side of the embedded plate 11, and similarly, the second length of the second anchor bar can be understood as the distance between the free end of the second anchor bar and the second side of the embedded plate 11, and the first anchor bar and the second anchor bar can have the same length. In this embodiment, by setting the first length of the first anchor bar and the second length of the second anchor bar to be greater than the first extension length of the first plate 12, the first anchor bar and the second anchor bar can provide sufficient tensile strength to the first plate 12 and the second plate 13, thereby avoiding the rollover problem of the first plate 12 and the second plate 13 on the embedded plate 11, thereby improving the anchoring force and making the connection more secure. During the construction process, the first length of the first anchor bar and the second length of the second anchor bar can be adjusted according to the actual structural conditions to ensure the best anchoring effect and improve the flexibility of construction.

[0069] See also Figures 3 to 6 In a second aspect, the present invention provides a shear wall structure 2, comprising a first double wall 21 and a second double wall 22. The second double wall 22 is arranged in parallel with the first double wall 21, and there is a building gap to be filled between the first double wall 21 and the second double wall 22; a plurality of steel lock plate connection nodes 1 are arranged in the building gap at intervals along the extension direction of the first double wall 21, and the steel lock plate connection nodes 1 are the steel lock plate connection nodes 1 described in the first aspect.

[0070] In this embodiment, the first double wall 21 and the second double wall 22 are two parallel walls in the shear wall structure 2, with a building gap in the middle to be filled with concrete. A plurality of steel locking plate connection nodes 1 are arranged at intervals in the building gap along the extension direction of the first double wall 21 to achieve effective connection between the double walls, thereby improving the overall stability and bearing capacity of the shear wall.

[0071] Specifically, the first double skin wall 21 and the second double skin wall 22 can be made by laying steel bars and reinforcement cages, and then pouring concrete or other building materials, such as Figures 3 to 6 , showing the manufacturing process of the first double skin wall 21, the second double skin wall 22 and the steel lock plate connection node 1. It should be noted that in this process, there is a building gap between the first double skin wall 21 and the second double skin wall 22, and the building gap is used for the subsequent shear wall manufacturing.

[0072] In this embodiment, the embedded plate 11, the first anchor bar group 14, and the second anchor bar group 15 are all arranged at a certain distance inside the edges of the first double skin wall 21 and the second double skin wall 22, and part of the structure of the first plate 12 protrudes out of the edges of the first double skin wall 21 and the second double skin wall 22 to facilitate the anchor hole 121 to protrude to the outside, and the second plate 13 is completely placed outside the edges of the first double skin wall 21 and the second double skin wall 22, thus forming a structure in which part of the mosaic cavity protrudes out, which is convenient for the subsequent splicing of the two shear wall structures 2.

[0073] See also Figure 1 and Figure 5 In some embodiments, the first anchor bar group 14 is configured to be pre-buried in the first double skin wall 21 at a first preset depth; the second anchor bar group 15 is configured to be pre-buried in the second double skin wall 22 at a second preset depth; the first plate 12 is configured to protrude a preset distance from the outer edge of the first double skin wall 21 so that the anchor hole 121 is placed outside the first double skin wall 21.

[0074] In this embodiment, the first anchor bar group 14 can be pre-buried at a first preset depth in the first double skin wall 21, and the second anchor bar group 15 can be pre-buried at a second preset depth in the second double skin wall 22, wherein the first preset depth and the second preset depth are adjusted according to actual needs, thereby improving the flexibility of the structural design; the first plate 12 is designed to protrude a preset distance from the outer edge of the first double skin wall 21, so that the anchor hole 121 is located outside the first double skin wall 21, which helps to fix the anchor rod 5.

[0075] See also Figures 7 to 9 In a third aspect, the present embodiment provides a shear wall, which includes a first shear wall 3 and a second shear wall 4. The first shear wall 3 is the shear wall structure 2 of the second aspect, and the first shear wall 3 has a first steel locking plate connection node 31, and the first steel locking plate connection node 31 has a first interlocking cavity; the second shear wall 4 is the shear wall structure 2 of the second aspect, and the second shear wall 4 has a second steel locking plate connection node 41, and the second steel locking plate connection node 41 has a second interlocking cavity; the first shear wall 3 and the second shear wall 4 are configured to be nested and connected through the first steel locking plate connection node 31 and the second steel locking plate connection node 41, and the first interlocking cavity and the second interlocking cavity at least partially overlap.

[0076] In this embodiment, the shear wall is also called a wind-resistant wall or an earthquake-resistant wall or a structural wall. It is a wall in a house or structure that mainly bears horizontal loads caused by wind loads or earthquakes, and is usually a reinforced concrete structure. In this embodiment, the specific structural form of how two shear walls are assembled into one shear wall is shown, and the fourth aspect describes a specific method of how two shear walls are assembled into one shear wall.

[0077] For ease of description, in this embodiment, the two shear walls are respectively recorded as the first shear wall 3 and the second shear wall 4, wherein the first shear wall 3 and the second shear wall 4 both refer to the shear wall structure 2 described in the second aspect. The first shear wall 3 and the second shear wall 4 are connected by a first steel locking plate connection node 31 and a second steel locking plate connection node 41. The specific connecting structure can be combined with Figure 2 , Figures 7 to 9 For understanding, further interlocking methods can be understood by referring to the fourth aspect described later. For ease of expression, the interlocking cavity of the first steel lock plate connection node 31 is recorded as the first interlocking cavity, and the interlocking cavity of the second steel lock plate connection node 41 is recorded as the second interlocking cavity. The first interlocking cavity and the second interlocking cavity are partially overlapped by interlocking the first steel lock plate connection node 31 and the second steel lock plate connection node 41. The partial overlap of the first interlocking cavity and the second interlocking cavity can make the concrete be poured to the overlapping area of ​​the first interlocking cavity and the second interlocking cavity simultaneously during the process of pouring the first shear wall 3 and the second shear wall 4, so that the first shear wall 3 and the second shear wall 4 can be connected. The force wall 4 is fused into a whole. During this process, the engagement of the first steel locking plate connection node 31 and the second steel locking plate connection node 41 can provide rigid connection and support for the first shear wall 3 and the second shear wall 4, thereby improving the structural stiffness and stability of the vertical connection node 61. At the same time, the first steel locking plate connection node 31 and the second steel locking plate connection node 41 can also provide vertical guidance for the first shear wall 3 and the second shear wall 4 during the splicing process, avoiding displacement during the splicing process, and facilitating the splicing process of the first shear wall 3 and the second shear wall 4.

[0078] In this embodiment, the first steel lock plate connection node 31 and the second steel lock plate connection node 41 are nested and connected, so that the first embedding cavity and the second embedding cavity at least partially overlap. The nested connection method simplifies the construction process and reduces the workload of on-site welding or bolt connection. At the same time, the vertical connection node 61 formed has a good bearing capacity, has better integrity, and improves overall neatness and aesthetics.

[0079] See also Figure 7 and Figure 8 In this embodiment, the first steel locking plate connection node 31 has a first anchor hole, the second steel locking plate connection node 41 has a second anchor hole, and the shear wall structure 2 also includes an anchor rod group, which includes a plurality of anchor rods 5, and each anchor rod 5 sequentially penetrates the first anchor hole and the second anchor hole arranged at the same height.

[0080] For ease of description, the anchor hole of the first steel lock plate connection node 31 is recorded as the first anchor hole, and the anchor hole of the second steel lock plate connection node 41 is recorded as the second anchor hole. The first anchor hole and the second anchor hole are coaxial when the first and second fitting cavities are fitted together. Figure 7 and Figure 8As shown, the anchor rod 5 can pass through the first anchor bolt hole and the second anchor bolt hole to keep the first steel locking plate connection node 31 and the second steel locking plate connection node 41 relatively fixed in the vertical direction.

[0081] In this embodiment, the anchor rod 5 is a component in an engineering structure, which is mainly used to fix soil or rock to increase the stability of the structure. The anchor rod 5 can be a solid steel rod or other rods, which are specifically set according to actual needs. The anchor rod group includes a plurality of anchor rods 5, each anchor rod 5 corresponds to a first anchor hole and a second anchor hole at the same height, and each anchor rod 5 in the anchor rod group can play a role in fixing and reinforcing. After the first shear wall 3 and the second shear wall 4 are nested and connected, the two are further spliced ​​together to form a whole through the anchor rod group, which significantly enhances the connection strength between the first shear wall 3 and the second shear wall 4, and improves the overall stability and bearing capacity of the structure.

[0082] See also Figures 3 to 7 In a fourth aspect, the present invention provides a shear wall installation method, which is applicable to the shear wall of the third aspect, wherein the first shear wall has a first building gap, and the second shear wall has a second building gap, and the shear wall installation method comprises:

[0083] Placing the first shear wall at a first preset position along the vertical direction so that the first engaging cavity is opened toward the first direction a;

[0084] Move the second shear wall from top to bottom in the vertical direction to a second preset position, so that the second steel lock plate connection node is nested at the first steel lock plate connection node, the second embedding cavity is opened toward the second direction b, the second direction b is opposite to the first direction a, and the first embedding cavity and the second embedding cavity at least partially overlap;

[0085] Concrete is filled into the first building gap, the second building gap, the first embedding cavity and the second embedding cavity to obtain a shear wall.

[0086] In this embodiment, the first shear wall 3 and the second shear wall 4 are both the shear wall structures described in the second aspect. Based on this, the first shear wall 3 has a building void and the second shear wall 4 has a building void. For ease of distinction, the building void of the first shear wall 3 is recorded as the first building void 32, and the building void of the second shear wall 4 is recorded as the second building void 42.

[0087] Specifically, the first shear wall 3 is placed in a first preset position along the vertical direction. The first preset position is an area reserved in advance for constructing the shear wall. This step requires ensuring that the first shear wall 3 remains arranged in the vertical direction so that the first interlocking cavity is opened toward the first direction a.

[0088] Similarly, the second shear wall 4 is placed in the second preset position along the vertical direction. The second preset position is adjacent to the first preset position. During the placement process, the second shear wall 4 needs to be lowered in a top-down manner so that the opening of the second fitting cavity faces the second direction b, and the first steel lock plate connection node 31 and the second steel lock plate connection node 41 form Figure 7 The chimeric structure shown.

[0089] On this basis, concrete is filled into the first building void 32, the second building void 42, the first interlocking cavity and the second interlocking cavity, and after necessary curing processes, a complete shear wall can be obtained.

[0090] The steps shown in this embodiment can realize the simple installation of the first shear wall 3 and the second shear wall 4 on site, minimize the difficulty and steps of assembling the shear walls on site, and at the same time ensure the structural rigidity and stability of the first shear wall 3 and the second shear wall 4 after assembly.

[0091] See also Figure 8 and Fig. 9 In this embodiment, the first steel lock plate connection node has a first anchor bolt hole, the second steel lock plate connection node has a second anchor bolt hole, the shear wall further includes an anchor rod group, the anchor rod group includes a plurality of anchor rods, and each anchor rod sequentially penetrates the first anchor bolt hole and the second anchor bolt hole disposed at the same height;

[0092] Before the first building gap, the second building gap, the first embedding cavity and the second embedding cavity are filled with concrete to obtain the shear wall, the method further includes:

[0093] The anchor rod is sequentially passed through the first anchor bolt hole and the second anchor bolt hole which are arranged at the same height.

[0094] In this embodiment, the through connection of the anchor rod 5 enhances the connection strength between the two first shear walls 3 and the second shear wall 4, and the load is dispersed and transferred through the anchor rod 5, thereby improving the stability of the entire structure.

[0095] See also Fig.10 , Fig.10 This is the assembly diagram of the modular building of this system, which mainly includes unit building modules 6, vertical connection nodes 61, and horizontal connection nodes. The modular building is mainly stacked by unit building modules 6, and the unit building modules 6 are effectively connected through the vertical connection nodes 61 and the horizontal connection nodes to form a modular building.

[0096] The splicing process of the vertical connection node 61 involves the splicing process of the aforementioned first shear wall 3 and the second shear wall 4. By using the aforementioned first shear wall 3, the second shear wall 4 and the corresponding installation method, the current situation that the vertical connection node 61 needs to support the template is solved, the on-site construction is convenient and simple, the module installation efficiency is improved, and the steel bar binding steps are reduced; at the same time, the convenience and feasibility of unit module processing are ensured, the connection node is safe and reliable, the construction cost is reduced, and environmental pollution is reduced, which meets the requirements of sustainable development.

[0097] By adopting the above technical solution, the present invention has the following beneficial effects compared with the prior art:

[0098] The first anchor bar group 14 is configured to be embedded in the first double wall 3 at a first preset depth; the second anchor bar group 15 is configured to be embedded in the second double wall 4 at a second preset depth, and after vertically dropping, the anchor rod 5 is inserted and fixed from the first anchor bolt hole and the second anchor bolt hole; by arranging the first anchor bar group 14 and the second anchor bar group 15 on the embedded plate 11, the stress can be dispersed, thereby improving the durability and service life of the structure; after the fixing is completed, the concrete poured in the first building gap 32, the second building gap 42 and the first interlocking cavity and the second interlocking cavity can form an effective connection, which can solve the vertical connection problem of the shear walls between modules, has sufficient shear resistance and energy dissipation, takes into account the transmission and distribution of force, reduces the risk of structural failure through reasonable layout and structural design, improves the safety of the overall structure, realizes a formwork-free construction process, and conforms to the concept of less work on site in modular buildings.

[0099] The above descriptions are only some embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Any equivalent device or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A steel lock plate connection node, characterized in that: include: An embedded plate, the embedded plate having a first side surface and a second side surface that are arranged opposite to each other; A steel lock plate assembly is arranged on the first side of the embedded plate, the steel lock plate assembly includes a first plate, a second plate, an anchor hole and a fitting cavity, the first plate is vertically arranged on the embedded plate, and the first plate is arranged between the embedded plate and the second plate to form the fitting cavity, the first plate is vertical to the second plate, and the anchor hole is arranged on the first plate; A first anchor bar group is arranged on the second side surface of the embedded plate, wherein the first anchor bar group includes a plurality of first anchor bars, and the plurality of first anchor bars are distributed on the second side surface at intervals along a vertical direction; A second anchor bar group is arranged on the second side surface of the embedded plate. The second anchor bar group is arranged opposite to the first anchor bar group. The second anchor bar group includes a plurality of second anchor bars. The plurality of second anchor bars are distributed on the second side surface at intervals in the vertical direction. The first anchor bar and the second anchor bar are arranged opposite to each other at the same height.

2. The steel lock plate connection node according to claim 1, characterized in that: The first plate member is eccentrically disposed on the embedded member plate, and the anchor bolt hole is disposed close to the second plate member.

3. The steel lock plate connection node according to claim 1 or 2, characterized in that: The first plate has a first extension length; The first anchor bar has a first length, the first length being greater than the first extension length; And / or, the second anchor bar has a second length, and the second length is greater than the first extension length.

4. A shear wall structure, characterized in that: include: The first double skin wall; A second double wall is arranged in parallel with the first double wall, and a building gap to be filled is provided between the first double wall and the second double wall; A plurality of steel lock plate connection nodes are arranged at intervals in the building gap along the extension direction of the first double skin wall, and the steel lock plate connection nodes are the steel lock plate connection nodes described in any one of claims 1 to 3.

5. The shear wall structure according to claim 4, characterized in that: The first anchor bar group is configured to be embedded in the first double skin wall at a first preset depth; The second anchor bar group is configured to be embedded in the second double skin wall at a second preset depth; The first plate is configured to protrude a preset distance from an outer edge of the first double skin wall so that the anchor hole is located outside the first double skin wall.

6. A shear wall, characterized in that: include: A first shear wall, wherein the first shear wall is the shear wall structure according to claim 4 or 5, the first shear wall has a first steel locking plate connection node, and the first steel locking plate connection node has a first fitting cavity; A second shear wall, wherein the second shear wall is the shear wall structure according to claim 4 or 5, the second shear wall has a second steel locking plate connection node, and the second steel locking plate connection node has a second fitting cavity; The first shear wall and the second shear wall are configured to be nested and connected through the first steel locking plate connection node and the second steel locking plate connection node, and the first mosaic cavity and the second mosaic cavity at least partially overlap.

7. The shear wall according to claim 6, characterized in that: The first steel locking plate connection node has a first anchor bolt hole, the second steel locking plate connection node has a second anchor bolt hole, and the shear wall structure further includes: The anchor rod group includes a plurality of anchor rods, each of which sequentially penetrates the first anchor bolt hole and the second anchor bolt hole which are arranged at the same height.

8. A shear wall installation method, characterized in that: Applicable to the shear wall according to claim 6 or 7, the first shear wall has a first building gap, the second shear wall has a second building gap, and the installation method comprises: Placing the first shear wall at a first preset position along a vertical direction so that the first engaging cavity opens toward a first direction; Move the second shear wall from top to bottom in the vertical direction to a second preset position, so that the second steel lock plate connection node is nested at the first steel lock plate connection node, the second embedding cavity is opened in a second direction, the second direction is opposite to the first direction, and the first embedding cavity and the second embedding cavity at least partially overlap; The shear wall is obtained by filling the first building gap, the second building gap, the first embedding cavity and the second embedding cavity with concrete.

9. The shear wall installation method according to claim 8, characterized in that: The first steel lock plate connection node has a first anchor bolt hole, the second steel lock plate connection node has a second anchor bolt hole, the shear wall further includes an anchor rod group, the anchor rod group includes a plurality of anchor rods, each of the anchor rods sequentially penetrates the first anchor bolt hole and the second anchor bolt hole disposed at the same height; Before the first building gap, the second building gap, the first embedding cavity and the second embedding cavity are filled with concrete to obtain the shear wall, the method further includes: The anchor rod is sequentially passed through the first anchor bolt hole and the second anchor bolt hole which are arranged at the same height.

Citation Information

Patent Citations

  • Laminated board type shearing wall with exposure of fastened steel bars and connecting method

    CN104328846A

  • Connection joint for steel pipe beam combined shear wall and steel beam

    CN110565802A

  • Fabricated concrete shear wall and floor support plate dry type connection joint and construction method thereof

    CN114232811A

  • Wallboard connected node

    CN205444555U

  • Steel concrete composite structure and construction method of steel concrete composite structure

    JP2018188851A