Quenching equipment for metal mold manufacturing

By designing an automated quenching equipment for metal mold manufacturing, the problems of workers being scalded by high temperatures and low water cooling treatment efficiency are solved, and efficient quenching process and recycling water resources are achieved.

CN119800041AInactive Publication Date: 2025-04-11YUHONGYAN TECH (SUZHOU) CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202510032203.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-09
Publication Date
2025-04-11
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In the process of metal mold manufacturing, the design of quenching equipment is difficult to effectively prevent workers from being scalded by high-temperature metal molds. At the same time, the existing quenching equipment has problems of low efficiency and waste of water resources in rapid water cooling treatment.

Method used

A quenching equipment for metal mold manufacturing is designed. The sealing plate is automatically pushed through the electric rod to open the front port of the quenching equipment to ensure that the worker keeps a distance from the metal mold. At the same time, the metal mold is automatically pushed into the cold water tank by using an electric cylinder for quenching, and the cold water is recycled through the water pump and filter.

Benefits of technology

It effectively avoids workers being scalded by high-temperature metal molds, improves the efficiency of the quenching process, significantly improves the hardness and wear resistance of the metal molds, extends the service life of the molds, and saves water resources.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119800041A_ABST
    Figure CN119800041A_ABST
Patent Text Reader

Abstract

The invention provides quenching equipment for metal mold manufacturing, and relates to the technical field of metal mold quenching. A rectangular groove is formed in the middle of the upper end of the equipment table, and fixing grooves are formed in the four corners of the outer end of the rectangular groove of the equipment table correspondingly. The distance is generated between a worker and the metal mold, the worker cannot be scalded by high temperature on the metal mold, meanwhile, the electric cylinder can automatically push the metal mold into the cold water pool for quenching, water in the cold water pool can be replaced at any time, and a metal material is rapidly cooled to be converted into martensite after being heated to an austenite area at the high temperature. The phase change enables the hardness of metal to be remarkably improved, and the problems that a metal mold on a movable plate needs to be placed in quenching equipment for machining, so that the distance between the metal mold and the metal mold needs to be kept, otherwise, the just machined metal mold can generate high temperature and easily scalds workers, and the metal mold needs to be quickly water-cooled for quenching after being manufactured; otherwise, the hardness of the metal mold is influenced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of metal mold quenching, in particular to quenching equipment for metal mold manufacturing. Background Art

[0002] Quenching is an important process in metal heat treatment, which aims to improve the hardness and strength of the heated metal material by rapidly cooling it (usually above its critical temperature). This process is particularly critical for the manufacture of metal molds, because the mold needs to withstand high temperature, high pressure and wear during operation, so its performance directly affects the quality and life of the finished product. In mold manufacturing, quenching is an important process in metal heat treatment, which mainly improves the hardness and strength of the metal material heated to a certain temperature by rapidly cooling it. Quenching can not only improve the hardness of the metal, but also improve its wear resistance and fatigue strength, thereby improving the mechanical properties of the material. This process usually involves heating the metal to its critical temperature (i.e., austenitizing temperature), at which temperature the metal's organizational structure changes to form an austenite phase, and then, through rapid cooling, usually using a cooling medium such as water, oil or gas, the temperature of the metal is rapidly reduced to transform it from austenite to martensite.

[0003] During the use of the quenching equipment, since the metal mold on the movable plate needs to be placed in the quenching equipment for processing, it is necessary to keep a distance from the metal mold, otherwise the metal mold that has just been processed will generate high temperature and easily scald the workers. After the metal mold is manufactured, it needs to be quickly water-cooled for quenching, otherwise it will affect the hardness of the metal mold. Summary of the invention

[0004] The disclosed embodiment relates to a quenching device for metal mold manufacturing. After the metal mold on the movable plate is pushed into the quenching device for manufacturing, the electric rod 203 can automatically push the sealing plate upwards, open the front end of the quenching device to facilitate the hook rod to pull out the bearing mesh frame. At this time, the worker is distanced from the metal mold, and the high temperature on the metal mold will not scald the worker. At the same time, the electric cylinder can also automatically push the metal mold into a cold water pool for quenching, and the water in the cold water pool can be replaced at any time. After the metal material is heated to the austenite zone at high temperature, it is rapidly cooled to transform it into martensite. This phase change significantly improves the hardness of the metal. Normally, the hardness of martensite is several levels higher than that of steel in its initial state. Water quenching has a high heat conduction efficiency and can quickly take away the heat from the surface of the metal workpiece. The quenching process can significantly improve the hardness of the metal mold, making it more wear-resistant during use. This hardness improvement can effectively extend the service life of the mold, reduce frequent repairs and replacements caused by wear, and thus reduce production costs.

[0005] In a first aspect of the present disclosure, a quenching device for metal mold manufacturing is provided, specifically comprising: an equipment table; a rectangular groove is provided in the middle of the upper end of the equipment table, and fixing grooves are provided at the four corners of the outer end of the rectangular groove of the equipment table; a tank groove is provided at the left end of the equipment table; a tank hole is provided at the right end of the equipment table; a groove is provided at the top of the equipment table; a quenching device is fixedly installed at the rear end of the equipment table, and a sealed small door is installed at the lower end of the side wall of the quenching device; A groove is provided at the top of the quenching equipment; symmetrical moving plates are slidably installed in the inner cavity of the quenching equipment; track grooves are provided at the opposite ends of the two moving plates; symmetrical limiting strips are fixedly installed at the opposite ends of the two moving plates, and three groups of penetrating fasteners are rotatably inserted on the limiting strips; a bearing net frame is installed in the middle of the limiting strips at both ends; a water pump is fixedly installed in the groove of the equipment table; A cold water pool is fixedly installed at the rectangular groove of the equipment platform, and through-holes are respectively opened at both ends of the cold water pool; a support frame is fixedly installed at the four fixed grooves of the equipment platform, and a through-hole is opened in the middle of the upper end of the support frame; ear plates are fixedly installed at the lower ends of the four corner side walls of the support frame, and through-bolts are respectively rotatably inserted in the middle of the four ear plates of the support frame, and a through-electric cylinder is fixedly installed at the round hole in the middle of the support frame, and a connecting frame is fixedly installed at the lower end of the electric cylinder; A guide rail frame is fixedly installed at the lower end of the connecting frame, and a notch block is fixedly installed at the front end of the guide rail frame. Four penetrating guide holes are opened on the guide rail frame, and mutually symmetrical positioning blocks are fixedly installed on the inner side wall of the guide rail frame. A hook rod is placed on the notch block of the guide rail frame, and a hook plate is fixedly installed at the rear end of the hook rod.

[0006] In at least some embodiments, a cooling tank is placed in the tank slot at the left end of the equipment platform, a pipe hole is opened at the right end of the cooling tank, and a penetrating collection tank is fixedly installed at the tank hole at the right end of the equipment platform.

[0007] In at least some embodiments, a supporting ring is fixedly mounted on the upper end of the inner side wall of the collection tank, and a filter screen is placed on the supporting ring.

[0008] In at least some embodiments, a sliding door is provided at the front end of the upper end of the quenching device, an anti-slip groove is provided in the middle of the front end of the quenching device, and an electric rod is fixedly installed in the groove at the top of the quenching device.

[0009] In at least some embodiments, a connecting rod is fixedly mounted on the upper end of the electric rod, a sealing plate is fixedly mounted on the lower end of the connecting rod, and an anti-slip strip is fixedly mounted on the bottom of the sealing plate.

[0010] In at least some embodiments, a baffle is fixedly mounted on the side wall at the lower end of the sealing plate, mutually symmetrical track bars are fixedly mounted on the side wall of the inner cavity of the quenching equipment, mutually symmetrical track plates are fixedly mounted on the front side wall of the quenching equipment, and a limiting plate is fixedly mounted on the front end of the track plate.

[0011] In at least some embodiments, a water suction pipe is fixedly connected to the left end of the water pump, and a drainage pipe is fixedly connected to the right end of the water pump.

[0012] In at least some embodiments, four vertically upward guide rods are fixedly installed at the bottom of the inner cavity of the cold water pool, and a retaining ring is rotatably installed on the upper end of the guide rod. A penetrating delivery pipe is fixedly installed at the pipe hole at the right end of the cold water pool.

[0013] The present invention provides a quenching device for metal mold manufacturing, which has the following beneficial effects: When the quenching equipment in the present invention is in use, the metal mold on the movable plate is pushed into the quenching equipment for manufacturing. After completion, the electric rod 203 can automatically push the sealing plate upwards, open the front end of the quenching equipment to facilitate the hook rod to pull out the bearing mesh frame. At this time, the worker is distanced from the metal mold, and the high temperature on the metal mold will not scald the worker. At the same time, the electric cylinder can also automatically push the metal mold into the cold water pool for quenching, and the water in the cold water pool can be replaced at any time. After the metal material is heated to the austenite zone at high temperature, it is rapidly cooled to transform it into martensite. This phase change significantly improves the hardness of the metal. Under normal circumstances, the hardness of martensite is several levels higher than that of steel in its initial state. Water quenching has a high heat conduction efficiency and can quickly take away the heat from the surface of the metal workpiece. The quenching process can significantly improve the hardness of the metal mold, making it more wear-resistant during use. This hardness improvement can effectively extend the service life of the mold, reduce frequent repairs and replacements caused by wear, and thus reduce production costs.

[0014] In addition, use the electric rod to push the connecting rod and the sealing plate upward, then the mouth of the front end of the quenching equipment will open, use the hook plate on the hook rod to hook the front end of the bearing mesh frame and pull it forward, and at the same time the moving plate will slide forward and move out of the quenching equipment. At this time, the track groove on the moving plate will slide on the track plate, and then continue to slide forward to the receiving track frame. It will stop moving forward due to the obstruction of the positioning block, and the sealing plate can also open and close automatically, so that workers can stay away from high-temperature metal molds to avoid being scalded by the high temperature on the metal molds.

[0015] In addition, the water in the cold water pool is discharged into the collection tank through the delivery pipe, and the quenched cold water will fall on the filter net. At this time, the filter net will block and limit the debris in the water, so that the water in the collection tank can be used again after filtering, thereby saving the waste of water resources. Then start the water pump and use the suction pipe to pump up the cold water in the cooling tank, and then deliver it into the cold water pool from the drain pipe, so that the cold water in the cold water pool can continue to quench the metal mold.

[0016] By using the electric cylinder to push the connecting frame and the guide rail frame downward, the metal mold on the load-bearing mesh frame will also move downward. When the metal mold enters the cold water pool, the cold water in the cold water pool will quench the metal mold. Quenching can significantly improve the hardness and wear resistance of the mold material, so that it can still maintain a good shape and performance under high load conditions. The mold with strong wear resistance can withstand wear during long-term use, reduce frequent replacement and repair, and effectively extend the service life. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solution of the embodiment of the present invention, the drawings of the embodiment are briefly introduced below.

[0018] The drawings described below are only related to some embodiments of the present invention, but are not intended to limit the present invention.

[0019] In the attached picture: Figure 1 The schematic diagram of the upper left front axial structure of the present application is shown; Figure 2 The schematic diagram of the upper right rear axial structure of the present application is shown; Figure 3 A schematic diagram of the partially disassembled structure of the equipment table, water pump and cold water tank of the present application is shown; Figure 4 It shows the partial disassembly of the quenching equipment and the schematic diagram of the moving plate part of the present application; Figure 5 A schematic diagram of the disassembled structure of the quenching equipment part and the moving plate part of the present application is shown; Figure 6 A schematic diagram of the structure of the movable plate and the connecting frame of the present application is shown; Figure 7 A schematic diagram of the structure of the moving plate and the cold water pool of the present application is shown; Figure 8 A schematic diagram of the structure of the water pump, cold water tank and support frame of the present application is shown; Fig. 9 A schematic diagram of the explosion structure of the present application is shown.

[0020] Reference numerals list Equipment table; 101, cooling tank; 102, collecting tank; 103, supporting ring; 104, filter; 2, quenching equipment; 201, sliding door; 202, anti-slip groove; 203, electric rod; 204, connecting rod; 205, sealing plate; 206, anti-slip strip; 207, retaining bar; 208, track bar; 209, track plate; 210, limiting plate; 3, moving plate; 301, track groove; 302, limiting bar; 303, bearing net frame; 4, water pump; 401, suction pipe; 402, drainage pipe; 5, cold water pool; 501, guide rod; 502, retaining ring; 503, conveying pipe; 6, supporting frame; 601, electric cylinder; 602, connecting frame; 603, guide track frame; 604, guide hole; 605, positioning block; 606, hook rod. DETAILED DESCRIPTION

[0021] In order to make the purpose, technical solution and advantages of the embodiment of the present invention clearer, the technical solution of the embodiment of the present invention will be clearly and completely described below in conjunction with the accompanying drawings of the embodiment of the present invention. Obviously, the described embodiment is a part of the embodiment of the present invention, not all of the embodiments. Based on the described embodiment of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0022] Example 1: Please refer to Figures 1 to 9 : The present invention provides a quenching device for metal mold manufacturing, comprising: an equipment table 1; a rectangular groove is provided in the middle of the upper end of the equipment table 1, and fixed grooves are respectively provided at the four corners of the outer end of the rectangular groove of the equipment table 1; a tank groove is provided at the left end of the equipment table 1; a tank hole is provided at the right end of the equipment table 1; a groove is provided at the top of the equipment table 1; a quenching device 2 is fixedly installed at the rear end of the equipment table 1, and a sealed small door is installed at the lower end of the side wall of the quenching device 2; the small door on the quenching device 2 is opened to fill coal, and garbage in the quenching device 2 can also be cleaned; the top of the quenching device 2 is opened A groove is provided; symmetrical moving plates 3 are slidably installed in the inner cavity of the quenching equipment 2; the two moving plates 3 are respectively provided with a track groove 301 at one end facing away from each other; the track groove 301 on the moving plate 3 is slidably installed on the track bar 208, and when the metal mold on the bearing net frame 303 is heated, the hook plate on the hook rod 606 is hooked on the front end of the bearing net frame 303 and pulled forward, and at the same time, the moving plate 3 will also slide forward and move out of the quenching equipment 2, and then the track groove 301 on the moving plate 3 will slide on the track plate 209, and then continue to slide forward to the receiving guide The track frame 603 will stop moving forward when it is blocked by the positioning block 605. The two opposite ends of the two movable plates 3 are fixedly installed with mutually symmetrical limiting bars 302, and three sets of penetrating fasteners are rotatably inserted on the limiting bars 302; the fasteners on the limiting bars 302 are rotatably inserted on the bearing net frame 303, and the bearing net frame 303 is fixedly installed on the two movable plates 3 so that it will not fall off. The bearing net frame 303 is installed in the middle of the limiting bars 302 at both ends; a metal mold is placed on the bearing net frame 303, and a metal mold is fixedly installed in the groove of the equipment table 1. Water pump 4; a cold water pool 5 is fixedly installed at the rectangular groove of the equipment table 1, and two ends of the cold water pool 5 are respectively provided with penetrating pipe holes; a support frame 6 is fixedly installed at the four fixed grooves of the equipment table 1, and a penetrating circular hole is opened in the middle of the upper end of the support frame 6; ear plates are respectively fixedly installed at the lower ends of the four corner side walls of the support frame 6, and penetrating bolts are respectively rotatably inserted in the middle of the four ear plates of the support frame 6, and the bolts on the ear plates of the support frame 6 are rotatably inserted on the equipment table 1, so as to firmly restrict the ear plates and the support frame 6 to prevent the support frame 6 from shaking and tilting when being touched.

[0023] Among them, a cooling tank 101 is placed in the tank slot at the left end of the equipment table 1, and cold water is injected into the cold water pool 5 for a long time. A pipe hole is opened at the right end of the cooling tank 101. A penetrating collection tank 102 is fixedly installed at the tank hole at the right end of the equipment table 1. The right end of the delivery pipe 503 is inserted into the collection tank 102. After the cold water in the cold water pool 5 frequently quenches the metal mold, the water temperature in the cold water pool 5 will increase. At this time, the water in the cold water pool 5 is discharged into the collection tank 102 through the delivery pipe 503. The quenched cold water will fall on the filter 104, and the filter 104 will block and limit the debris in the water to prevent the debris from entering the inner cavity of the collection tank 102. The water in the collection tank 102 can be used again after cooling and filtering. A supporting ring 103 is fixedly installed on the upper end of the inner wall of the collection tank 102, and the filter 104 is placed on the supporting ring 103. The filter 104 can be disassembled by grabbing it and lifting it up, and then the debris on the filter 104 can be cleaned.

[0024] Among them, a sliding door 201 is provided at the front end of the upper end of the quenching equipment 2, and a sealing plate 205 is slidably installed at the sliding door 201. An anti-slip groove 202 is provided in the middle part of the front end of the quenching equipment 2, and an electric rod 203 is fixedly installed in the groove at the top of the quenching equipment 2. A connecting rod 204 is fixedly installed on the upper end of the electric rod 203, and a sealing plate 205 is fixedly installed on the lower end of the connecting rod 204. The electric rod 203 is used to push the connecting rod 204 and the sealing plate 205 upward, and then the mouth of the front end of the quenching equipment 2 will be opened, so that the bearing net frame 303 in the quenching equipment 2 can be conveniently entered or pulled out, and the connecting rod 204 and the sealing plate 205 are pulled downward by the electric rod 203, and the anti-slip strip 206 will be inserted into the anti-slip groove 202, and the sealing plate 205 is used to close the front end of the quenching equipment 2, and the anti-slip strip 206 is fixedly installed on the bottom of the sealing plate 205. 206 is inserted in the anti-slip groove 202, and a baffle 207 is fixedly installed on the side wall at the lower end of the sealing plate 205. During the upward movement of the sealing plate 205, the baffle 207 is blocked by the front end of the quenching equipment 2 and cannot continue to move upward, so that the supporting net frame 303 can enter or be pulled out of the quenching equipment 2. Mutually symmetrical track bars 208 are fixedly installed on the side walls of the inner cavity of the quenching equipment 2, and mutually symmetrical track plates 209 are fixedly installed on the front side walls of the quenching equipment 2. A limiting plate 210 is fixedly installed at the front end of the track plate 209, and the bottom of the limiting plate 210 is in contact with the top side wall of the connecting track frame 603. During the upward movement of the connecting track frame 603, it is blocked and restricted by the limiting plate 210, and the connecting track frame 603 will stop moving upward. At this time, the connecting track frame 603 will be on the same horizontal line with the track plate 209, so that the movable plate 3 can slide back and forth conveniently.

[0025] The left end of the water pump 4 is fixedly connected with a water pumping pipe 401, which penetrates the pipe hole at the right end of the cooling tank 101. The right end of the water pump 4 is fixedly connected with a drain pipe 402, which penetrates the pipe hole at the left end of the cold water pool 5. The water pump 4 is started to pump the cold water in the cooling tank 101 with the water pumping pipe 401, and then transported into the cold water pool 5 from the drain pipe 402, so that the cold water in the cold water pool 5 can quench the metal mold entering. Four vertically upward guide rods 5 are fixedly installed at the bottom of the inner cavity of the cold water pool 5. 01, the guide hole 604 on the connecting track frame 603 is slidably mounted in the guide rod 501. When the connecting track frame 603 slides up and down, the guide hole 604 on the connecting track frame 603 is restricted by the guide rod 501, and the connecting track frame 603 can only slide up and down to prevent the connecting track frame 603 from being offset when sliding up and down. A retaining ring 502 is rotatably installed on the upper end of the guide rod 501, and the retaining ring 502 is attached to the side wall of the connecting track frame 603. A through-conveying pipe 503 is fixedly installed at the pipe hole at the right end of the cold water pool 5.

[0026] Among them, a penetrating electric cylinder 601 is fixedly installed at the circular hole in the middle of the support frame 6, and a connecting frame 602 is fixedly installed at the lower end of the electric cylinder 601, and a receiving track frame 603 is fixedly installed at the lower end of the connecting frame 602, and a notch block is fixedly installed at the front end of the receiving track frame 603. When the metal mold on the movable plate 3 and the bearing net frame 303 slides onto the receiving track frame 603, the electric cylinder 601 is used to push the connecting frame 602 and the receiving track frame 603 downward. At this time, the metal mold on the bearing net frame 303 will also move downward. When the metal mold enters the cold water pool 5, the cold water in the cold water pool 5 will quench the metal mold. Four penetrating guide holes 604 are opened on the receiving track frame 603, and mutually symmetrical positioning blocks 605 are fixedly installed on the inner side wall of the receiving track frame 603. A hook rod 606 is placed on the notch block of the receiving track frame 603, and a hook plate is fixedly installed at the rear end of the hook rod 606.

[0027] Embodiment 2, based on embodiment 1, as Figure 1 and Fig. 9 As shown, ear plates are fixedly installed at the lower ends of the four corner side walls of the support frame 6, and through bolts are rotatably inserted in the middle of the four ear plates of the support frame 6. The ear plates and bolts are removed, and then the lower end of the support frame 6 is fixedly welded to the equipment table 1 to firmly restrict the support frame 6. In this way, the support frame 6 will not fall over when touched, avoiding the loosening of the bolts after long-term use, making it impossible to continue to fix the support frame 6, and also saving the cost of parts.

[0028] The working principle of this embodiment is as follows: when in use, the track groove 301 on the movable plate 3 is slidably installed on the track bar 208. When the metal mold on the bearing mesh frame 303 is heated, the electric rod 203 is used to push the connecting rod 204 and the sealing plate 205 upwards. At this time, the mouth of the front end of the quenching equipment 2 will be opened, and the hook plate on the hook rod 606 is hooked on the front end of the bearing mesh frame 303 and pulled forward. At the same time, the movable plate 3 will also slide forward and move out of the quenching equipment 2. At this time, the track groove 301 on the movable plate 3 will slide on the track plate 209, and then continue to slide forward to the receiving track frame 603. It will stop moving forward due to the obstruction of the positioning block 605, and then the electric cylinder 601 is used to push the connecting frame 602 and the receiving track frame 603 downwards. The metal mold on the supporting mesh frame 303 will also move downward. When the metal mold enters the cold water pool 5, the cold water in the cold water pool 5 will quench the metal mold. The water pump 4 is started to pump the cold water in the cooling tank 101 with the pumping pipe 401, and then the cold water is transported into the cold water pool 5 from the drain pipe 402, so that the cold water in the cold water pool 5 can quench the entering metal mold. After the cold water in the cold water pool 5 frequently quenches the metal mold, the water temperature in the cold water pool 5 will increase. At this time, the water in the cold water pool 5 is discharged into the collection tank 102 through the delivery pipe 503, and the quenched cold water will fall on the filter screen 104. At this time, the filter screen 104 will block and limit the debris in the water to prevent the debris from entering the inner cavity of the collection tank 102.

[0029] In this article, there are a few points to note: 1. The drawings of the embodiments of the present disclosure only involve structures related to the embodiments of the present disclosure, and other structures may refer to general designs.

[0030] 2. In the absence of conflict, the embodiments of the present disclosure and the features therein may be combined with each other to obtain new embodiments.

[0031] The above are only specific embodiments of the present disclosure, but the protection scope of the present disclosure is not limited thereto. Any technician familiar with the technical field can easily think of changes or substitutions within the technical scope disclosed in the present disclosure, which should be included in the protection scope of the present disclosure. Therefore, the protection scope of the present disclosure should be based on the protection scope of the claims.

Claims

1. Quenching equipment for metal mold manufacturing, including: An equipment platform (1); a rectangular groove is provided in the middle of the upper end of the equipment platform (1), and fixed grooves are provided at the four corners of the outer end of the rectangular groove of the equipment platform (1); a tank groove is provided at the left end of the equipment platform (1); a tank hole is provided at the right end of the equipment platform (1); a groove is provided at the top of the equipment platform (1); a quenching device (2) is fixedly installed at the rear end of the equipment platform (1), and a sealed small door is installed at the lower end of the side wall of the quenching device (2); a groove is provided at the top of the quenching device (2); it is characterized in that mutually symmetrical moving plates (3) are slidably installed in the inner cavity of the quenching device (2); the two moving plates (3) are respectively provided with track grooves (301) at the opposite ends; the two moving plates (3) are opposite to each other. The ends of the equipment platform (1) are fixedly mounted with symmetrical limiting bars (302), and three groups of penetrating fasteners are rotatably inserted on the limiting bars (302); a bearing net frame (303) is installed in the middle of the limiting bars (302) at both ends; a water pump (4) is fixedly mounted at the groove of the equipment platform (1); a cold water pool (5) is fixedly mounted at the rectangular groove of the equipment platform (1), and penetrating pipe holes are respectively provided at both ends of the cold water pool (5); a support frame (6) is fixedly mounted at the four fixed grooves of the equipment platform (1), and a penetrating circular hole is provided in the middle of the upper end of the support frame (6); ear plates are fixedly mounted at the lower ends of the four corner side walls of the support frame (6), and penetrating bolts are rotatably inserted in the middle of the four ear plates of the support frame (6).

2. The quenching equipment for metal mold manufacturing according to claim 1, characterized in that: A cooling tank (101) is placed in the tank slot at the left end of the equipment platform (1), and a pipe hole is opened at the right end of the cooling tank (101). A penetrating collecting tank (102) is fixedly installed at the tank hole at the right end of the equipment platform (1).

3. The quenching equipment for metal mold manufacturing according to claim 2, characterized in that: A supporting ring (103) is fixedly mounted on the upper end of the inner wall of the collection tank (102), and a filter screen (104) is placed on the supporting ring (103).

4. The quenching equipment for metal mold manufacturing according to claim 1, characterized in that: A sliding door (201) is provided at the front end of the upper end of the quenching device (2), an anti-slip groove (202) is provided in the middle of the front end of the quenching device (2), and an electric rod (203) is fixedly mounted in the groove at the top end of the quenching device (2).

5. The quenching equipment for metal mold manufacturing according to claim 4, characterized in that: A connecting rod (204) is fixedly mounted on the upper end of the electric rod (203), a sealing plate (205) is fixedly mounted on the lower end of the connecting rod (204), and an anti-slip strip (206) is fixedly mounted on the bottom of the sealing plate (205).

6. The quenching equipment for metal mold manufacturing according to claim 5, characterized in that: A stop bar (207) is fixedly mounted on the side wall at the lower end of the sealing plate (205), mutually symmetrical track bars (208) are fixedly mounted on the side wall of the inner cavity of the quenching device (2), mutually symmetrical track plates (209) are fixedly mounted on the front side wall of the quenching device (2), and a limit plate (210) is fixedly mounted on the front end of the track plate (209).

7. The quenching equipment for metal mold manufacturing according to claim 1, characterized in that: The left end of the water pump (4) is fixedly connected to a water suction pipe (401), and the right end of the water pump (4) is fixedly connected to a drainage pipe (402).

8. The quenching equipment for metal mold manufacturing according to claim 1, characterized in that: Four vertically upward guide rods (501) are fixedly installed at the bottom of the inner cavity of the cold water pool (5), and a retaining ring (502) is rotatably installed on the upper end of the guide rod (501). A conveying pipe (503) is fixedly installed at the pipe hole at the right end of the cold water pool (5).

9. The quenching equipment for metal mold manufacturing according to claim 1, characterized in that: An electric cylinder (601) is fixedly mounted at the circular hole in the middle of the support frame (6), a connecting frame (602) is fixedly mounted at the lower end of the electric cylinder (601), a guide rail frame (603) is fixedly mounted at the lower end of the connecting frame (602), and a notch block is fixedly mounted at the front end of the guide rail frame (603).

10. The quenching equipment for metal mold manufacturing according to claim 9, characterized in that: The guide rail frame (603) is provided with four penetrating guide holes (604), and mutually symmetrical positioning blocks (605) are fixedly mounted on the inner side wall of the guide rail frame (603). A hook rod (606) is placed on the notch block of the guide rail frame (603), and a hook plate is fixedly mounted on the rear end of the hook rod (606).

Citation Information

Patent Citations

  • Small -size work piece quenching device with filtering mechanism

    CN208649388U

  • Quenching bath for steel processing

    CN220300794U

  • Die machining quenching equipment

    CN220665380U

  • A mold manufacturing quenching device

    CN221028543U

  • Quenching cooling device for screw production

    CN221094218U