Coal mine drilling pressure relief outburst prevention equipment based on gas extraction
By designing a drilling pressure relief and anti-protrusion equipment for coal mining, the deviation problem of existing equipment in drilling position and angle control is solved, the accuracy and efficiency of drilling is improved, and safety risks and production costs are reduced.
Patent Information
- Application Number
- CN202510035646.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-09
- Publication Date
- 2025-04-11
Smart Images

Figure CN119801395A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of coal mining, and in particular to a coal mine drilling pressure relief and outburst prevention device based on gas extraction. Background Art
[0002] Gas is a major safety hazard in the coal mining process. The drilling pressure relief and outburst prevention equipment can reduce the gas pressure and stress state in the coal body, reduce the risk of coal and gas outburst, provide safety protection for coal mining, and effectively prevent accidents such as gas explosions. In addition, through drilling pressure relief and gas extraction, the permeability of the coal seam can be improved, making the coal seam easier to mine, reducing the burden on the mine ventilation system, reducing ventilation costs, thereby improving mining efficiency and economic benefits. At the same time, gas is a clean and efficient energy source. Collecting and utilizing gas through gas extraction equipment can not only reduce environmental pollution, but also bring additional economic benefits to the enterprise.
[0003] When drilling to relieve pressure, the position, angle, depth and other parameters of the borehole are selected based on a detailed construction plan and geological conditions. Therefore, the position, angle and depth of each borehole should be precisely controlled. At the same time, due to the complexity of the construction plan and geological conditions, the position and angle of each borehole are diverse. The deviation angle of existing drilling equipment is 1.5°, and the deviation range is small, which cannot meet the drilling work at all angles and positions of the borehole. At the same time, due to the special nature of the tunnel, its surface is irregular, so there are deviations in the boreholes made according to the original parameters under this plane, which reduces mining efficiency and increases production costs.
[0004] Therefore, it is necessary to provide a coal mine drilling pressure relief and outburst prevention equipment based on gas extraction to solve the above problems. Summary of the invention
[0005] In view of the deficiencies of the prior art, the present invention provides the following technical solution, a coal mine drilling pressure relief and outburst prevention device based on gas extraction, comprising: Two traveling crawlers are arranged in a mirror image, and the two traveling crawlers are slidably assembled on both sides of the horizontal rotating disk, a drill rod angle adjustment assembly is fixedly assembled on the upper surface of the horizontal rotating disk, a drill rod pushing assembly is slidably assembled on the upper end of the drill rod angle adjustment assembly, and the drill rod pushing assembly is fixedly connected to the first drill rod fixture through two first telescopic rods arranged in parallel; Two drill rod racks are arranged in mirror image, placed on both sides of the drill rod angle adjustment assembly, and fixedly assembled on the upper surface of the horizontal rotating disk, and each drill rod rack is clamped with multiple drill rods; The drill rod transport assemblies are arranged in two mirror images, are placed on non-adjacent sides of the two drill rod racks, and are fixedly assembled on the upper surface of the horizontal rotating disk.
[0006] Further, as a preference, the horizontal rotating disk comprises: A fixed connecting frame, with two telescopic columns on both sides, and the other ends of the two telescopic columns on the same side are slidably arranged on the traveling crawler; A rotating connection seat is rotatably embedded in the fixed connection frame and the rotating connection seat is arranged on the output shaft of the driving motor, and the driving motor is fixedly embedded in the fixed connection frame; The universal horizontal plate is universally arranged above the rotating connection seat, and multiple rotating interfaces are fixedly assembled on the outer sides of the rotating connection seat and the universal horizontal plate, and the second telescopic rod is rotatably arranged on two rotating interfaces that are closer to the rotating connection seat and the universal horizontal plate.
[0007] Further, as a preference, a level sensor is embedded on the universal horizontal plate, and the level sensor detects the levelness of the universal horizontal plate, and adjusts the levelness of the universal horizontal plate by driving the second telescopic rod.
[0008] Further, as a preference, the drill rod angle adjustment assembly comprises: A fixed frame, fixedly assembled at the middle of the upper surface of the horizontal rotating disk, two third telescopic rods are rotatably arranged on both sides of the fixed frame, the other ends of the two third telescopic rods are rotatably arranged on the rotating block, and the rotating block is fixedly rotatably assembled on the fixed frame; A plurality of sliding blocks are provided, all of which are fixedly assembled on the upper surface of the rotating block, and a drill rod pushing assembly is slidably provided on the plurality of sliding blocks; The fourth telescopic rod is provided with two mirror images, one end of each of the fourth telescopic rods is respectively rotatably embedded in the fixed frame and located on the inner side of the rotating block, and the other end is rotatably provided at the lower end of the drill rod pushing assembly.
[0009] Further, as a preference, the drill rod pushing assembly comprises: A track bar is slidably arranged on the upper end of the drill rod angle adjustment assembly, and a limited position fixing block and a second drill rod fixture are respectively arranged at both ends of the track bar; A first track is slidably mounted on the upper end of the track bar, the first track is perpendicular to the sliding direction of the track bar, a sliding plate is slidably arranged on the first track, and sliding limiters are arranged at both ends of the first track; The drill rod driver is fixedly assembled on the upper surface of the sliding plate.
[0010] Further, as a preference, the first drill rod fixture comprises: A fixed carrier frame is rotatably mounted on one end of the two first telescopic rods, a driving connecting rod group is arranged on the side of the fixed carrier frame close to the first telescopic rods, and two clamping rotators with openings opposite to each other are arranged on the driving connecting rod group, and the two clamping rotators are rotatably arranged on the fixed carrier frame; A plurality of balance springs are provided, and all are fixedly assembled on the side of the fixed bearing frame away from the first telescopic rod.
[0011] Further, preferably, the two first telescopic rods do not always move synchronously.
[0012] Further, preferably, the drill pipe transport assembly comprises: A fixed beam is fixedly mounted on the upper surface of the horizontal rotating disk, and both ends of the fixed beam are fixedly mounted with vertically mounted supporting telescopic columns, and the upper end of each supporting telescopic column is fixedly mounted with a vertically mounted second track, the two second tracks are arranged in parallel and not parallel to the fixed beam, and a third track is vertically slidably mounted on the two second tracks, and a horizontal sliding plate is slidably mounted on the third track; A vertical telescopic column is vertically embedded on the horizontal sliding plate. An adjusting beam is rotatably provided at the lower end of the vertical telescopic column. Drill rod clamping claws are fixedly provided at both ends of the adjusting beam. A fifth telescopic rod is rotatably provided on the adjusting beam and the vertical telescopic column.
[0013] Compared with the prior art, the present invention has the following beneficial effects: In the present invention, the traveling crawler drives the entire device to move forward, and a tracking drive system is arranged inside the crawler, which can move the device to a designated position according to a planned path and automatically perform drilling work. The horizontal rotating disk can drive the various components thereon to rotate, so that the device can rotate in all directions, thereby facilitating the device to drill holes at drilling positions of various angles, and at the same time avoiding the situation where traditional equipment cannot turn in narrow areas and thus cannot effectively complete the drilling work. The arranged telescopic column can, if conditions in the tunnel permit, expand the distance between the two traveling crawlers, thereby making the lower plate of the device more stable.
[0014] In the present invention, the drill rod angle adjustment assembly can adjust the drill rod angle so that the drill rod axis coincides with the planned borehole axis, thereby effectively performing pressure relief work, and the drill rod angle adjustment assembly can adjust the relative position of the drill rod push assembly to a certain extent, so that the drill rod push assembly can be effectively extended, preventing the drilling position from being relatively far away, causing the drilling hole to shake and deviate, and then causing a safety accident.
[0015] In the present invention, the drill rod pushing assembly can rotate the drill rod so that the drill bit thereon can perform drilling work. At the same time, the drill rod pushing assembly can disassemble and assemble the drill rod, and with the assistance of the drill rod transport assembly, complete the extension and contraction of the entire drill rod group, thereby better serving the drilling work.
[0016] In the present invention, the position of the first drill rod holder can be adjusted by extending the first telescopic rod, so that it can be fixed at the drilling position, providing a support point for the drill rod to prevent it from shaking in the drilling hole, thereby causing the deviation of the drilling hole or even damaging the drill rod, while reducing the risk of coal and gas outbursts, providing safety protection for coal mining.
[0017] In the present invention, the drill rod transport assembly will clamp the drill rod removed from the drill rod pushing assembly and place it on the corresponding drill rod rack, or clamp the drill rod to be installed and prevent it from being used for drilling on the drill rod pushing assembly, and the drill rod transport assembly will adjust the angle according to the actual situation of the drill rod pushing assembly when transporting the drill rod, thereby improving the drilling efficiency, and the drill rod transport assembly and the adjacent drill rod racks correspond to each other, and the two drill rod racks can carry drill rods of the same diameter or different diameters according to the actual situation. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of the structure of a coal mine drilling pressure relief and outburst prevention equipment based on gas extraction; Figure 2 It is a schematic diagram of the structure of a horizontal rotating disk; Figure 3 This is a schematic diagram of the drill rod angle adjustment assembly structure; Figure 4 This is a structural schematic diagram of the drill rod pushing assembly; Figure 5 It is a structural schematic diagram of a drill rod holder; Figure 6 It is a structural schematic diagram of the drill pipe transport assembly; In the figure: 1, traveling crawler; 2, horizontal rotating disk; 3, drill rod angle adjustment assembly; 4, drill rod pushing assembly; 5, first drill rod holder; 6, drill rod rack; 7, drill rod transport assembly; 8, first telescopic rod; 21, fixed connecting frame; 22, telescopic column; 23, universal horizontal disk; 24, rotating interface; 25, second telescopic rod; 26, rotating connecting seat; 31, fixed frame; 32, third telescopic rod; 33, rotating block; 34, sliding block; 35, fourth telescopic rod; 41, track The guide bar; 42, the limit fixing block; 43, the second drill rod fixture; 44, the first track; 45, the sliding plate; 46, the drill rod driver; 47, the sliding limiter; 51, the fixed bearing frame; 52, the driving connecting rod group; 53, the clamping rotator; 54, the balance spring; 71, the fixed beam; 72, the supporting telescopic column; 73, the second track; 74, the third track; 75, the horizontal sliding plate; 76, the vertical telescopic column; 77, the adjusting beam; 78, the drill rod clamping claw; 79, the fifth telescopic rod. DETAILED DESCRIPTION
[0019] The present invention will be described in detail below with reference to the accompanying drawings.
[0020] See also Figure 1 to Figure 6 The present invention provides a coal mine drilling pressure relief and outburst prevention device based on gas extraction, comprising: A traveling crawler 1 is provided with two mirror images, and the two traveling crawlers 1 are slidably assembled on both sides of a horizontal rotating disk 2, a drill rod angle adjustment assembly 3 is fixedly assembled on the upper surface of the horizontal rotating disk 2, a drill rod pushing assembly 4 is slidably assembled on the upper end of the drill rod angle adjustment assembly 3, and the drill rod pushing assembly 4 is fixedly connected to a first drill rod fixture 5 through two parallel first telescopic rods 8; one end of the drill rod pushing assembly 4 is fixedly assembled with two parallel first telescopic rods 8, and the other ends of the two first telescopic rods 8 are fixedly assembled with a first drill rod fixture 5; Drill rod racks 6, two of which are mirror-imaged and placed on both sides of the drill rod angle adjustment assembly 3 and fixedly assembled on the upper surface of the horizontal rotating disk 2, and each drill rod rack 6 is clamped with a plurality of drill rods; The drill rod transport assembly 7 is provided with two mirror images, which are placed on non-adjacent sides of the two drill rod racks 6 and fixedly assembled on the upper surface of the horizontal rotating disk 2; the drill rod transport assembly 7 places the drill rod on the drill rod rack 6 on the drill rod pushing assembly 4 or removes the drill rod from the drill rod pushing assembly 4 and places it on the drill rod rack 6.
[0021] As a preferred embodiment, the travel crawler 1 drives the entire device to move forward, and a tracking drive system is arranged inside the crawler 1, which can move the device to a designated position according to a planned path for drilling work. The horizontal rotating disk 2 can drive the various components thereon to rotate, so that the device can rotate in all directions, thereby facilitating the device to drill holes at drilling positions of various angles, and at the same time avoiding the situation that traditional equipment cannot turn in narrow areas and thus cannot effectively complete the drilling work. The drill rod angle adjustment assembly 3 can adjust the drill rod angle on the drill rod pushing assembly 4 so that the drill rod axis coincides with the planned borehole axis, thereby effectively performing pressure relief work, and the drill rod angle adjustment assembly 3 can adjust the relative position of the drill rod pushing assembly 4 to a certain extent, so that the drill rod pushing assembly 4 can be effectively extended to prevent the drilling position from being relatively far away, causing the drilling hole to shake and deviate, and then causing a safety accident. The drill rod pushing assembly 4 can rotate the drill rod so that the drill bit on it can To carry out drilling work, at the same time, the drill rod pushing assembly 4 can disassemble and assemble the drill rod, and with the assistance of the drill rod transporting assembly 7, complete the installation and disassembly work of the entire drill rod group, so as to better serve the drilling work, the first drill rod fixture 5 can be adjusted in position by extending the first telescopic rod 8, so that it can be fixed at the drilling position, while further ensuring the drilling position of the drill rod, reducing the risk of coal and gas outburst, and providing safety protection for coal mining, the drill rod transporting assembly 7 will clamp the drill rod disassembled by the drill rod pushing assembly 4 and place it on the corresponding drill rod rack 6, or clamp the drill rod to be installed and place it on the drill rod pushing assembly 4 to carry out drilling work, and the drill rod transporting assembly 7 will adjust the angle according to the actual situation of the drill rod pushing assembly 4 when transporting the drill rod, so as to improve the drilling efficiency, and the drill rod transporting assembly 7 and the adjacent drill rod rack 6 correspond to each other, and the two drill rod racks 6 can carry drill rods of the same diameter or different diameters according to actual conditions.
[0022] Further, the horizontal rotating disk 2 comprises: A fixed connecting frame 21, two telescopic columns 22 are arranged on both sides thereof, and the other ends of the two telescopic columns 22 on the same side are slidably arranged on the traveling crawler 1; A rotating connection seat 26 is rotatably embedded in the fixed connection frame 21, and the rotating connection seat 26 is arranged on the output shaft of the driving motor, and the driving motor is fixedly embedded in the fixed connection frame 21; A universal horizontal plate 23 is universally arranged above the rotating connection seat 26, and multiple rotating interfaces 24 are fixedly assembled on the outer surfaces of the rotating connection seat 26 and the universal horizontal plate 23, and a second telescopic rod 25 is rotatably arranged on two rotating interfaces 24 on the rotating connection seat 26 and the universal horizontal plate 23 that are close to each other; As a preferred embodiment, the arrangement of the telescopic column 22 can expand the distance between the two traveling tracks 1 when the conditions in the tunnel permit, thereby making the lower plate of the device more stable, and the universal horizontal plate 23 and the rotating connecting seat 26 are universally arranged, so that the angle between the universal horizontal plate 23 and the upper surface of the fixed connecting frame 21 can be adjusted through the different telescopic lengths of the multiple second telescopic rods 25, so that the universal horizontal plate 23 can always maintain a horizontal state in the case of irregular tunnel ground, and the rotating connecting seat 26 can drive the universal horizontal plate 23 and the components thereon to rotate under the drive of its driving motor, so that the device can be adjusted in all directions, further improving the applicability of the device and improving the drilling efficiency.
[0023] Furthermore, a level sensor is embedded on the universal horizontal plate 23, and the level sensor detects the levelness of the universal horizontal plate, and adjusts the levelness of the universal horizontal plate 23 by driving the second telescopic rod 25; As a preferred embodiment, the horizontal sensor only works when the drilling work is about to start, and when the traveling track 1 drives the device to reach the specified position, according to the horizontal information of the horizontal sensor, the second telescopic rod 25 is driven to make the universal horizontal disk 23 level, and the traveling track 1 will adjust its position (after the universal horizontal disk 23 is adjusted, the center of gravity of the device will shift) until it reaches the specified position, thereby further ensuring the accuracy of the drilling position and reducing safety risks.
[0024] Further, the drill rod angle adjustment assembly 3 comprises: A fixed frame 31 is fixedly assembled at the middle of the upper surface of the horizontal rotating disk 2, two third telescopic rods 32 are rotatably arranged on both sides of the fixed frame 31, the other ends of the two third telescopic rods 32 are rotatably arranged on a rotating block 33, and the rotating block 33 is rotatably assembled on the fixed frame 31; There are multiple sliding blocks 34, all of which are fixedly assembled on the upper surface of the rotating block 33, and the drill rod pushing components 4 are slidably arranged on the multiple sliding blocks 34; The fourth telescopic rod 35 is provided in two mirror images, one end of each of the fourth telescopic rods 35 is respectively rotatably embedded in the fixing frame 31 and located inside the rotating block 33, and the other end is rotatably provided at the lower end of the drill rod pushing assembly 4; As a preferred embodiment, by extending or contracting the two third telescopic rods 32, the angle between the upper surface of the sliding block 34 and the upper surface of the universal horizontal disk 23 on the horizontal rotating disk 2 can be deflected, thereby adjusting the angle of the drill rod pushing assembly 4 until the central axis of the drill rod on the drill rod pushing assembly 4 coincides with the central axis of the planned borehole, and the sliding block 34 can make the drill rod pushing assembly 4 slide, and when the fourth telescopic rod 35 is extended or contracted, the drill rod pushing assembly 4 and the sliding block 34 slide in relative position, so that the fourth telescopic rod 35 drives the drill rod pushing assembly 4 to slide, thereby further ensuring the accuracy of the drill rod drilling work.
[0025] Further, the drill rod pushing assembly 4 includes: A track bar 41 is slidably arranged on the upper end of the drill rod angle adjustment assembly 3, and is specifically slidably arranged on the sliding block 34 on the upper end of the drill rod angle adjustment assembly 3. A limited position fixing block 42 and a second drill rod fixture 43 are respectively arranged at both ends of the track bar 41; A first track 44 is slidably mounted on the upper end of the track bar 41. The first track 44 is perpendicular to the sliding direction of the track bar 41. A sliding plate 45 is slidably arranged on the first track 44. Meanwhile, sliding limiters 47 are arranged at both ends of the first track 44. The first track 44 includes a track plate and two guide rails. The track plate is slidably mounted on the upper end of the track bar 41. The track plate is provided with two slide rails. Both ends of the slide rails are provided with slide limiters 47. The slide plate 45 is slidably connected to the slide rails. A drill rod driver 46, fixedly mounted on the upper surface of the sliding plate 45; As a preferred embodiment, the limiting fixing block 42 can limit the position of the first track 44 and simultaneously fix two first telescopic rods 8 (one end of one of the first telescopic rods 8 is fixed to the upper end of the drill rod driver 46, and the other end is fixed to the first drill rod fixture 5, and one end of the other is fixed to the lower end of the drill rod driver 46 and passes through the track bar 41, and the other end is fixed to the first drill rod fixture 5), the second drill rod fixture 43 can fix the drill rod, and complete the disassembly and assembly of the drill rod under the action of the drill rod driver 46, and when working, the drill rod driver 46 is located in the middle section of the first track 44, and the drill rod transport assembly 7 on which side the drill rod driver 46 moves transports the drill rod.
[0026] Further, the first drill rod fixture 5 comprises: A fixed carrier frame 51 is rotatably mounted on one end of the two first telescopic rods 8. A driving connecting rod group 52 is provided on the fixed carrier frame 51 near the first telescopic rod 8. Two clamping rotators 53 with openings facing each other are provided on the driving connecting rod group 52. The two clamping rotators 53 are rotatably arranged on the fixed carrier frame 51. There are multiple balancing springs 54, all of which are fixedly mounted on the side of the fixed support frame 51 away from the first telescopic rod 8; As a preferred embodiment, the setting of the balance spring 54 can enable the fixed support frame 51 to be stably set on the tunnel wall where the drill hole is located, and keep the fixed support frame 51 vertical to the center axis of the drill hole. The driving connecting rod group 52 can drive the two clamping rotators 53 to clamp the drill rod, providing a support point for the drill rod to prevent it from shaking in the drill hole, thereby causing the drill hole to deviate or even damage the drill rod, and the clamping rotator 53 is provided with a ball (similar to a linear bearing) to fix the drill rod without limiting the drilling work of the drill rod. The setting of the fixed support frame 51 and the clamping rotator 53 can block the drill hole to a certain extent, reduce the risk of coal and gas outburst, and provide safety protection for coal mining.
[0027] Furthermore, the two first telescopic rods 8 do not always move synchronously; As a preferred embodiment, the two first telescopic rods 8 maintain a synchronous extension state in the initial state. When the two first telescopic rods 8 make the fixed support frame 51 contact the tunnel wall in the synchronous state, the two first telescopic rods 8 release the synchronization state, so that the fixed support frame 51 remains vertical to the center axis of the drilling hole.
[0028] Further, the drill pipe transport assembly 7 comprises: A fixed beam 71 is fixedly mounted on the upper surface of the horizontal rotating disk 2, specifically fixed on the universal horizontal disk 23 of the horizontal rotating disk 2. Both ends of the fixed beam 71 are fixedly mounted with vertically arranged supporting telescopic columns 72. The upper end of each supporting telescopic column 72 is fixedly mounted with a vertically arranged second track 73. The two second tracks 73 are arranged in parallel and not parallel to the fixed beam 71. A third track 74 is vertically slidably arranged on the two second tracks 73. A horizontal sliding plate 75 is slidably arranged on the third track 74. A vertical telescopic column 76 is vertically embedded on the horizontal sliding plate 75, and an adjusting beam 77 is rotatably provided at the lower end of the vertical telescopic column 76. Drill rod clamping claws 78 are fixedly provided at both ends of the adjusting beam 77, and a fifth telescopic rod 79 is rotatably provided on the adjusting beam 77 and the vertical telescopic column 76; As a preferred embodiment, the telescopic arrangement of the supporting telescopic column 72 can allow the adjusting beam 77 to have sufficient space to adjust to be parallel to the drill rod pushing assembly 4 when the drill rod pushing assembly 4 is tilted at a large angle, thereby carrying out the drill rod transportation work, and during the daily movement of the device, the volume of the device can be reduced by contracting the supporting telescopic column 72, thereby adapting to the complex tunnel environment.
[0029] During the specific implementation, the following steps are included: planning the travel route of the device in advance according to the actual situation, and placing a sufficient number of drill rods of the same (different) diameter on the two drill rod racks 6 respectively, and moving to the designated position through the built-in tracking drive system of the travel crawler 1, and when the conditions in the tunnel permit, extending the telescopic column 22 to expand the distance between the two travel crawlers 1, and driving the second telescopic rod 25 to extend and retract to make the universal horizontal disk 23 horizontal through the horizontal information of the horizontal sensor, and then the travel crawler 1 will adjust its position repeatedly until it reaches the designated position, and the rotating connecting seat 26 can drive the universal horizontal disk 23 and the components thereon to rotate under the drive of its driving motor, and under the adjustment of the drill rod angle adjustment component 3, the drill rod axis coincides with the planned borehole axis, and the drill rod is adjusted according to the final angle of the drill rod pushing component 4 The transport assembly 7 makes the adjustment beam 77 parallel to the drill rod pushing assembly 4, and the two first telescopic rods 8 extend synchronously. When the two first telescopic rods 8 make the fixed carrier 51 contact the tunnel wall, the two first telescopic rods 8 are released from the synchronization state and extend respectively to make the fixed carrier 51 maintain a vertical state with the central axis of the borehole. The drill rod pushing assembly 4 pushes the drill rod and the drill bit to perform drilling work, and continuously replenishes the drill rod through the drill rod transport assembly 7 during work, so that the drill bit continues to drill, and after the drill bit passes the first drill rod fixture 5, the driving connecting rod group 52 will drive the two clamping rotators 53 to clamp the drill rod, providing a support point for the drill rod to prevent it from shaking in the borehole, thereby causing the borehole to deviate or even damage the drill rod, and then continue to continuously replenish the drill rod through the drill rod transport assembly 7, so that the drill bit continues to drill until the borehole pressure relief work is completed.
[0030] What is described above is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A coal mine drilling pressure relief and outburst prevention device based on gas extraction, characterized by: include: Two traveling crawlers (1) are arranged in a mirror image, and the two traveling crawlers (1) are slidably mounted on both sides of a horizontal rotating disk (2); a drill rod angle adjustment assembly (3) is fixedly mounted on the upper surface of the horizontal rotating disk (2); a drill rod pushing assembly (4) is slidably mounted on the upper end of the drill rod angle adjustment assembly (3); the drill rod pushing assembly (4) is fixedly connected to a first drill rod holder (5) via two first telescopic rods (8) arranged in parallel; Two drill rod racks (6) are arranged in mirror image, placed on both sides of the drill rod angle adjustment assembly (3), and fixedly mounted on the upper surface of the horizontal rotating disk (2), and each drill rod rack (6) is clamped with a plurality of drill rods; Two drill rod transport assemblies (7) are arranged in mirror image, placed on non-adjacent sides of the two drill rod racks (6), and fixedly assembled on the upper surface of the horizontal rotating disk (2).
2. A coal mine drilling pressure relief and outburst prevention device based on gas extraction according to claim 1, characterized in that: The horizontal rotating disk (2) comprises: A fixed connecting frame (21) is provided with two telescopic columns (22) on both sides thereof, and the other ends of the two telescopic columns (22) on the same side are slidably arranged on the traveling crawler (1); A rotating connection seat (26) is rotatably mounted on the fixed connection frame (21), and the rotating connection seat (26) is arranged on the output shaft of the driving motor, and the driving motor is fixedly mounted on the fixed connection frame (21); The universal horizontal plate (23) is universally arranged on the rotating connection seat (26), and a plurality of rotating interfaces (24) are fixedly mounted on the outer surfaces of the rotating connection seat (26) and the universal horizontal plate (23), and a second telescopic rod (25) is rotatably arranged on two rotating interfaces (24) on the rotating connection seat (26) and the universal horizontal plate (23) that are closer in distance.
3. A coal mine drilling pressure relief and outburst prevention device based on gas extraction according to claim 2, characterized in that: A level sensor is embedded on the universal horizontal plate (23), and the level sensor detects the levelness of the universal horizontal plate (23), and adjusts the levelness of the universal horizontal plate (23) by driving the second telescopic rod (25).
4. The coal mine drilling pressure relief and outburst prevention equipment based on gas extraction according to claim 1 is characterized by: The drill rod angle adjustment assembly (3) comprises: A fixed frame (31) is fixedly mounted on the middle part of the upper surface of the horizontal rotating disk (2), two third telescopic rods (32) are rotatably mounted on both sides of the fixed frame (31), the other ends of the two third telescopic rods (32) are rotatably mounted on a rotating block (33), and the rotating block (33) is fixedly rotatably mounted on the fixed frame (31); A plurality of sliding blocks (34) are provided, each of which is fixedly mounted on the upper surface of the rotating block (33), and a drill rod pushing assembly (4) is slidably provided on the plurality of sliding blocks (34); Two fourth telescopic rods (35) are arranged in mirror image, one end of each fourth telescopic rod (35) is rotatably embedded in the fixed frame and located inside the rotating block, and the other end is rotatably arranged at the lower end of the drill rod pushing assembly (4).
5. The coal mine drilling pressure relief and outburst prevention equipment based on gas extraction according to claim 1 is characterized by: The drill rod pushing assembly (4) comprises: A track bar (41) is slidably arranged on the upper end of the drill rod angle adjustment assembly (3), and a limit fixing block (42) and a second drill rod fixture (43) are respectively arranged at both ends of the track bar (41); A first track (44) is slidably mounted on the upper end of the track bar (41), the first track (44) being perpendicular to the sliding direction of the track bar (41), and a sliding plate (45) is slidably arranged on the first track (44), and sliding limiters (47) are arranged at both ends of the first track (44); The drill rod driver (46) is fixedly mounted on the upper surface of the sliding plate (45).
6. A coal mine drilling pressure relief and outburst prevention device based on gas extraction according to claim 1, characterized in that: The first drill rod fixture (5) comprises: A fixed bearing frame (51) is fixedly mounted on one end of the two first telescopic rods (8); a driving connecting rod group (52) is provided on a side of the fixed bearing frame (51) close to the first telescopic rods (8); two clamping rotators (53) are provided on the driving connecting rod group (52) with openings arranged opposite to each other; the two clamping rotators (53) are rotatably arranged on the fixed bearing frame (51); A plurality of balance springs (54) are provided, all of which are fixedly mounted on a side of the fixed support frame (51) away from the first telescopic rod (8).
7. A coal mine drilling pressure relief and outburst prevention device based on gas extraction according to claim 6, characterized in that: The two first telescopic rods (8) do not always move synchronously.
8. The coal mine drilling pressure relief and outburst prevention equipment based on gas extraction according to claim 1 is characterized by: The drill pipe transport assembly (7) comprises: A fixed beam (71) is rotatably mounted on the upper surface of the horizontal rotating disk (2); both ends of the fixed beam (71) are fixedly mounted with vertically mounted supporting telescopic columns (72); the upper end of each supporting telescopic column (72) is fixedly mounted with a vertically mounted second track (73); the two second tracks (73) are arranged in parallel and not parallel to the fixed beam (71); a third track (74) is vertically slidably mounted on the two second tracks (73); a horizontal sliding plate (75) is slidably mounted on the third track (74); A vertical telescopic column (76) is vertically embedded in the horizontal sliding plate (75), an adjusting beam (77) is rotatably provided at the lower end of the vertical telescopic column (76), drill rod clamping claws (78) are fixedly provided at both ends of the adjusting beam (77), and a fifth telescopic rod (79) is rotatably provided on the adjusting beam (77) and the vertical telescopic column (76).