Free-form surface laminated ceramic tile roof supporting structure and construction method thereof
By adopting free-curved stacked design and on-site cold bending process in the terracotta roof support structure, the problem of difficulty in accurately installing the hyperbolic roof support structure in the prior art is solved, and efficient and precise installation is achieved to achieve a smooth transition free hyperbolic roof effect.
Patent Information
- Application Number
- CN202411980152.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-31
- Publication Date
- 2025-04-15
AI Technical Summary
The existing hyperbolic roof support structure using pre-pulled keels on site assembly is difficult to accurately control the installation position and installation accuracy of prefabricated keels according to structural design and structural deviation, resulting in the inability to realize the design plan for curved curtain wall roof.
The free-curved laminated terracotta tile roof support structure is adopted, including multiple purlin support, positioning purlin, main keel and secondary keel. The height, installation position and installation direction of the purlin support are analyzed through three-dimensional scanning and reverse parameterized modeling technology to ensure positioning accuracy. The unbending and prefabricated straight positioning purlins and keels are fitted with the terracotta installation positioning curve through on-site cold bending process, and are removably connected to the top of the purlin support.
It reduces the difficulty of profile processing, on-site wiring and installation, improves installation efficiency and installation accuracy, and realizes the exterior finishing effect of the free hyperbolic roof with smooth transition assembled straight strip profiles.
Smart Images

Figure CN119825088A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building decoration construction, and in particular to a free-form laminated ceramic tile roof supporting structure and a construction method thereof. Background Art
[0002] The main building of Jiaxing Nanhu Future Plaza adopts a large-span special-shaped spatial steel structure arch truss system with a white ceramic tile curved curtain wall roof, combined with green space on each floor, to form a staggered building complex.
[0003] Among them, the white ceramic tile curved curtain wall roof is a complex hyperbolic shape. The existing construction process is to use three-dimensional software to simulate the curved surface of the hyperbolic roof skin, and implement zoning construction. The supporting keels within each partition range are pre-bent in the factory, and the prefabricated supporting keels are transported to the site and installed in sequence according to the set position to achieve the fitting construction of the hyperbolic roof skin. However, the keel suitable for the prefabricated bending process has a small bending radius range, which is generally within ten radii, and the bending radius of different keels varies greatly. The white ceramic tile curved curtain wall roof has a large area and complex shape. The bending radius of the prefabricated keel is large and prone to rebound. The bending radius size reaches hundreds of types, which makes positioning and installation difficult. Moreover, in order to ensure a smooth hyperbolic exterior decoration effect, the radius difference between different prefabricated keels is small, which not only increases the processing difficulty of the prefabricated keel, but also makes it difficult to accurately control the installation position and installation accuracy of the prefabricated keel according to the structural design and structural deviation, resulting in the inability to realize the design of the curved curtain wall roof. Summary of the invention
[0004] In view of the problem that it is difficult to accurately control the installation position and installation accuracy of the prefabricated keel according to the structural design and structural deviation in the existing method of assembling the hyperbolic roof support structure on site by pre-bending the keel, the purpose of the present invention is to provide a free-form laminated ceramic tile roof support structure and a construction method thereof.
[0005] The technical solution adopted by the present invention to solve the technical problem is: a free-form laminated ceramic tile roof support structure, which comprises:
[0006] A plurality of purlin supports are arranged vertically and at intervals along the extension direction of the tile installation positioning curve and connected to the top of the main steel structure of the building;
[0007] Position the purlins, erect and thread them to the top of multiple purlin supports;
[0008] The main keel is staggered on the top of the positioning purlin and connected with the positioning purlin by bolts;
[0009] The secondary keel is arranged parallel to the positioning purlin and movably connected to the top of the main keel. A plurality of vertical and spaced support hangers are bolted to the secondary keel, and a plurality of ceramic tiles are detachably connected to the support hangers.
[0010] The free-form laminated ceramic tile roof support structure of the present invention comprises a plurality of purlin supports arranged along the extension direction of the ceramic tile installation positioning curve and connected to the top of the building main body steel structure, positioning purlins erected and threadedly connected to the tops of the plurality of purlin supports, main keels arranged in an interlaced manner and bolted to the tops of the positioning purlins, and secondary keels arranged in parallel with the positioning purlins and movably connected to the tops of the main keels; since the height, installation position and installation direction of the purlin supports are determined by using three-dimensional scanning and reverse parameterized modeling technology The analysis shows that the accuracy of the positioning of the purlin supports is guaranteed. The straight positioning purlins and keels that are not prefabricated without bending are fitted with the ceramic tile installation positioning curve through the on-site cold bending process, and are detachably connected to the top of the purlin supports in turn, so that the ceramic tile finish can be connected to the main steel structure of the building along the ceramic tile installation positioning curve, which reduces the difficulty of profile processing, on-site layout and installation, improves the installation efficiency and installation accuracy, and realizes the architectural exterior finishing effect of assembling straight strip profiles into a free hyperbolic roof with a smooth transition.
[0011] Furthermore, the purlin support includes a support rod, an outer sleeve and a base. The support rod is vertically arranged and fixedly connected to the top of the main steel structure of the building. The base is connected to one end of the outer sleeve, and the other end of the outer sleeve is sleeved and connected to the support rod.
[0012] Furthermore, one end of the support rod passes through the insulation layer and is welded to the main steel structure of the building. The side wall of the outer sleeve is provided with multiple through holes. The outer sleeve is sleeved on the support rod and welded to it; or, the outer sleeve and the vertical pole have corresponding oblong holes in their setting positions, and the screw rod passes through the oblong holes of the outer sleeve and the vertical pole and is locked and fixed by a nut.
[0013] Furthermore, the positioning purlin includes a base plate and two side plates, the two side plates are parallel, spaced apart and fixed to the top of the base plate, the two side plates are provided with a plurality of pairs of bolt holes corresponding in position and number, the spacing between the two side plates matches the size of the ribs of the main keel, so that the ribs of the main keel can be embedded between the two side plates of the positioning purlin, and a plurality of bolts pass through the corresponding bolt holes of the side plates and the main keel in sequence and are locked and fixed by nuts.
[0014] Furthermore, it also includes a waterproof layer, which covers the exposed part of the support rod and the connecting part between the support rod and the insulation layer and the base. The waterproof layer includes a layer of polyurethane sealant sealed at the connection between the insulation layer and the support rod, as well as a waterproof reinforcement layer and a polyurethane spray waterproof surface layer arranged from the inside to the outside.
[0015] In addition, the present invention also provides a construction method of a free-form laminated ceramic tile roof support structure, the steps of which are as follows:
[0016] S1: Determine the center coordinates of the disk at the intersection of the roof rods according to the three-dimensional model of the main steel structure of the building, determine the ceramic tile installation positioning curve according to the three-dimensional model of the free-form ceramic tile roof, establish a longitudinal section with the ceramic tile installation positioning curve as the path, and the intersection line of the longitudinal section and the three-dimensional model of the main steel structure of the building is the installation reference line for positioning the purlin. Select several points on the installation reference line at intervals as the installation points of the purlin support, calculate the positioning coordinates of both ends of each purlin support, and determine the installation direction of each purlin support according to the extension direction of the ceramic tile installation positioning curve;
[0017] S2: According to the data obtained in step S1, the center of the disk of the main steel structure of the building is positioned, and the installation points of the two ends of the purlin support are obtained in combination with the positioning of the disk center. According to the installation points obtained by the positioning, multiple purlin supports are sequentially installed on the top of the main steel structure of the building along the extension direction of the ceramic tile installation positioning curve, and the positioning purlin is erected on the top of the multiple purlin supports. The positioning purlin between two adjacent purlin supports is the purlin adjustment section. One end of the purlin adjustment section is bolted to the purlin support located on one side thereof. Then, add a purlin support between the two purlin supports, perform cold bending construction on the purlin adjustment section, adjust the height of the added purlin support, bolt the middle part of the purlin adjustment section to the added purlin support, and finally, bolt the other end of the purlin adjustment section to another purlin support, so that the curvature of the cold-bent purlin adjustment section is consistent with the curvature of the corresponding ceramic tile installation positioning curve, repeat this step, cold-bend the positioning purlin section by section along the extension direction of the ceramic tile installation positioning curve and bolt it to the top of the purlin support;
[0018] S3: The main keels are staggered and bolted to the top of the positioning purlins, the secondary keels are cold-bent section by section and bolted to the top of the main keels, so that the curvature of the secondary keels and the ceramic tile installation positioning curve are consistent, multiple support hangers are installed at intervals on the top of the secondary keels, and the ceramic tiles are connected to the support hangers.
[0019] The construction method of the free-form surface laminated ceramic tile roof support structure of the present invention comprises the following steps: firstly, determining a ceramic tile installation positioning curve according to a three-dimensional model of the free-form surface ceramic tile roof, establishing a longitudinal section with the ceramic tile installation positioning curve as a path, and the intersection line between the longitudinal section and the three-dimensional model of the building main body steel structure is used as an installation reference line for positioning purlins, selecting a plurality of points on the installation reference line at intervals as installation points of purlin supports, calculating the positioning coordinates of both ends of each purlin support, and determining the installation direction of each purlin support according to the extension direction of the ceramic tile installation positioning curve; and The installation points obtained by the lofting are sequentially installed on the top of the main steel structure of the building along the extension direction of the ceramic tile installation positioning curve. One end of the purlin adjustment section is bolted to a purlin support, and a purlin support is added between the two purlin supports. The purlin adjustment section is cold-bent and its middle part is bolted to the added purlin support. Finally, the other end of the purlin adjustment section is bolted to another purlin support, so that the curvature of the cold-bent purlin adjustment section is consistent with the curvature of the corresponding ceramic tile installation positioning curve. This is repeated along the extension direction of the ceramic tile installation positioning curve. The positioning purlins are cold-bent section by section and bolted to the top of the purlin supports, the main keels are staggered and bolted to the top of the positioning purlins, and the secondary keels are cold-bent section by section and bolted to the top of the main keels, so that the curvature of the secondary keels and the ceramic tile installation positioning curve are consistent; the construction method accurately calculates the positioning coordinates of the two ends of the positioning purlin according to the three-dimensional model of the main steel structure of the building and the free ceramic tile roof, and accurately lays out the actual measured points at the construction site, first fixes the two adjacent purlin supports according to the measured points, and then fixes the two adjacent purlin supports between the two adjacent purlin supports. An additional purlin support is added, and the purlin adjustment section is cold-bent on-site and bolted to three purlin supports in sequence, so that the curvature of the positioning purlin is consistent with the corresponding ceramic tile installation positioning curve. The unbent prefabricated straight strip profile is fitted into a smooth free curve shape on-site using the three-point arc method, so that the ceramic tile facing can be connected to the main steel structure of the building along the ceramic tile installation positioning curve, reducing the difficulty of profile processing, on-site layout and installation, improving the installation efficiency and installation accuracy of the free-form roof support structure, and realizing the decorative effect of the free-form ceramic tile roof.
[0020] Furthermore, in step S2, the spacing between two adjacent purlin supports is determined according to the deflection of the positioning purlin, the load allowed to be applied during the cold bending construction of the positioning purlin is calculated, and whether the installation position and height of the additional purlin supports are reasonable is determined according to the profile deflection and the allowable load. If reasonable, the additional purlin supports are positioned according to the calculated data; if unreasonable, the spacing and installation position of the two adjacent purlin supports are adjusted until the calculated results meet the requirements of the profile deflection and the load.
[0021] Furthermore, in step S2, the purlin support includes a support rod, an outer sleeve and a base, the support rod is vertically arranged and fixedly connected to the top of the main steel structure of the building, the base is connected to one end of the outer sleeve, and the other end of the outer sleeve is sleeved and connected to the support rod. After the support rod is fixed to the top of the main steel structure of the building, the relative distance between the outer sleeve and the support rod is adjusted so that the connecting line between the top ends of two adjacent purlin supports and the additional purlin support is consistent with the curvature of the ceramic tile installation positioning curve. After the relative position of the outer sleeve and the support rod is determined, the two are welded together or locked and fixed by through bolts. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a schematic diagram of the connection nodes between the purlin support and the main steel structure and keel of the building in one embodiment of the free-form laminated ceramic tile roof support structure of the present invention;
[0023] Figure 2 It is a structural schematic diagram of another connection node between the purlin support and the main steel structure and keel of the building in one embodiment of the present invention.
[0024] The numbers in the figure are as follows:
[0025] Main steel structure of the building 1; insulation layer 2; galvanized corrugated steel plate 2a; trough-filled rock wool 2b; waterproof and heat-insulating foam bricks 2c; asphalt waterproof membrane 2d; main keel 5; secondary keel 6; supporting hanger 7; ceramic tile 8; purlin support 10; support rod 11; outer sleeve 12; through hole 12a; base 14; polyurethane sealant 25; waterproof reinforcement layer 26; polyurethane spray waterproof surface layer 27; positioning purlin 30; base plate 31; side plate 32. DETAILED DESCRIPTION
[0026] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that the drawings are all in very simplified form and use non-precise proportions, which are only used to conveniently and clearly assist in explaining the purpose of the embodiments of the present invention. For the convenience of description, the "upper" and "lower" described below are consistent with the upper and lower directions of the drawings, but this cannot be a limitation of the technical solution of the present invention.
[0027] Combination Figure 1 and Figure 2 The free-form laminated tile roof support structure of the present invention comprises:
[0028] A plurality of purlin supports 10 are arranged vertically and spaced apart along the extension direction of the tile installation positioning curve, and connected to the top of the main steel structure 1 of the building;
[0029] Positioning purlins 30, erected and threadedly connected to the tops of a plurality of purlin supports 10;
[0030] The main keel 5 is staggered on the top of the positioning purlin 30 and is bolted to the positioning purlin 30;
[0031] The secondary keel 6 is arranged parallel to the positioning purlin 30 and movably connected to the top of the main keel 5. A plurality of vertical and spaced support hangers 7 are bolted to the secondary keel 6. A plurality of ceramic tiles 8 are detachably connected to the support hangers 7.
[0032] The free-form laminated ceramic tile roof support structure of the present invention comprises a plurality of purlin supports 10 arranged along the extension direction of the ceramic tile installation positioning curve and connected to the top of the building main body steel structure 1, a positioning purlin 30 erected and threadedly connected to the top of the plurality of purlin supports 10, a main keel 5 staggered and bolted to the top of the positioning purlin 30, and a secondary keel 6 arranged parallel to the positioning purlin 30 and movably connected to the top of the main keel 5; since the height, installation position and installation direction of the purlin supports 10 are determined by three-dimensional scanning and reverse parameterization, the purlin supports 10 are provided with a plurality of purlin supports 10, and ... The modeling technology analysis shows that the accuracy of the positioning of the purlin support 10 is guaranteed, and the straight positioning purlin 30 and the keel that are not prefabricated by bending are fitted with the ceramic tile installation positioning curve through the on-site cold bending process, and are detachably connected to the top of the purlin support 10 in turn, so that the ceramic tile facing can be connected to the main steel structure 1 of the building along the ceramic tile installation positioning curve, which reduces the difficulty of profile processing, on-site layout and installation, improves the installation efficiency and installation accuracy, and realizes the architectural exterior finishing effect of assembling straight strip profiles into a free hyperbolic roof with a smooth transition.
[0033] like Figure 1 and Figure 2 As shown, the purlin support 10 includes a support rod 11, an outer sleeve 12 and a base 14. The support rod 11 is vertically arranged and fixed to the top of the main steel structure 1 of the building. The base 14 is connected to one end of the outer sleeve 12, and the other end of the outer sleeve 12 is sleeved and connected to the support rod 11. The purlin support 10 adopts a sleeve connection mode of the support rod 11 and the outer sleeve 12, which is convenient for construction personnel to adjust the height of the purlin support 10 according to the on-site installation requirements. The height of the purlin support 10 is determined according to the relative height between the ceramic tile installation curve and the main steel structure 1 of the building, so that the height of the purlin support 10 meets the construction requirements of the ceramic tile installation curve.
[0034] like Figure 1 As shown, one end of the support rod 11 passes through the insulation layer 2 and is welded to the main steel structure 1 of the building. The side wall of the outer sleeve 12 is provided with multiple through holes 12a. The outer sleeve 12 is sleeved on the support rod 11 and connected with it by plug welding; or, the outer sleeve 12 and the vertical pole are set at corresponding oblong holes, and the screw passes through the oblong holes of the outer sleeve 12 and the vertical pole and is locked and fixed by a nut. The setting of the oblong holes makes it easy for construction personnel to flexibly adjust the actual height of the purlin support 10 according to on-site installation requirements.
[0035] like Figure 2As shown, the positioning purlin 30 includes a base plate 31 and two side plates 32. The two side plates 32 are parallel, spaced apart and fixed to the top of the base plate 31. The two side plates 32 are provided with a plurality of pairs of bolt holes corresponding in position and number. The spacing between the two side plates 32 matches the size of the ribs of the main keel 5, so that the ribs of the main keel 5 can be embedded between the two side plates 32 of the positioning purlin 30. A plurality of bolts sequentially penetrate the bolt holes corresponding to the side plates 32 and the main keel 5 and are locked and fixed by nuts, thereby realizing a detachable connection between the main keel 5 and the positioning purlin 30. The installation and removal are convenient and quick.
[0036] like Figure 1 As shown, the insulation layer 2 includes, from bottom to top, galvanized corrugated steel plate 2a, glass fiber veneer, trough-filled rock wool 2b, 100 mm thick SBS special composite veneer waterproof insulation foam brick 2c, 4 mm thick SBS modified asphalt waterproof membrane 2d, and 2 mm thick polyurethane spray waterproof surface layer 27.
[0037] like Figure 1 As shown, the free-form laminated ceramic tile 8 roof support structure also includes a waterproof layer, which covers the exposed part of the support rod 11 and the connecting part between the support rod 11, the insulation layer 2 and the base 14. The waterproof layer includes a layer of polyurethane sealant 25 sealed at the connection between the insulation layer 2 and the support rod 11, and a polymer modified asphalt waterproof reinforcement layer 26 and a 2mm thick polyurethane spray waterproof surface layer 27 arranged from the inside to the outside.
[0038] Combine the following Figure 1 and Figure 2 The construction method of the free-form laminated ceramic tile roof support structure of the present invention is described, and the specific steps are as follows:
[0039] S1: Determine the center coordinates of the disk at the intersection of the roof rods according to the three-dimensional model of the building main steel structure 1, determine the ceramic tile installation positioning curve according to the three-dimensional model of the free-form ceramic tile roof, establish a longitudinal section with the ceramic tile installation positioning curve as the path, and the intersection line of the longitudinal section and the three-dimensional model of the building main steel structure 1 is the installation reference line for positioning the purlin 30, select several points on the installation reference line at intervals as the installation points of the purlin support 10, calculate the positioning coordinates of both ends of each purlin support 10, and determine the installation direction of each purlin support 10 according to the extension direction of the ceramic tile installation positioning curve;
[0040] S2: According to the data obtained in step S1, the center of the disk of the main steel structure 1 of the building is lofted using a total station, and the installation points of the two ends of the purlin support 10 are obtained in combination with the lofting of the disk center. According to the installation points obtained by the lofting, multiple purlin supports 10 are sequentially installed on the top of the main steel structure 1 of the building along the extension direction of the ceramic tile installation positioning curve, and the positioning purlins 30 are erected on the top of the multiple purlin supports 10. There is a corresponding section of positioning purlin 30 between every two adjacent purlin supports 10, and two adjacent purlin supports 10 are purlin support one, and the space between the two purlin supports one is the purlin adjustment section , bolt one end of the purlin adjustment section to the purlin support one located on one side thereof, then install the purlin support two between the two purlin support one, perform cold bending construction on the purlin adjustment section, and adjust the height of the purlin support two, bolt the middle part of the purlin adjustment section to the purlin support two, and finally, bolt the other end of the purlin adjustment section to another purlin support one, so that the curvature of the cold-bent purlin adjustment section is consistent with the curvature of the corresponding ceramic tile installation positioning curve, repeat this step, cold-bend the positioning purlin 30 section by section along the extension direction of the ceramic tile installation positioning curve and bolt it to the top of the purlin support 10;
[0041] S3: The main keels 5 are staggered and bolted to the top of the positioning purlins 30, and the secondary keels 6 are cold-bent section by section and bolted to the top of the main keel 5, so that the curvature of the secondary keel 6 is consistent with the ceramic tile installation positioning curve, and multiple support hangers 7 are installed at intervals on the top of the secondary keel 6, and the ceramic tile 8 is connected to the support hangers 7.
[0042] The construction method of the free-form laminated ceramic tile roof support structure of the present invention comprises the following steps: first, determining a ceramic tile installation positioning curve according to a three-dimensional model of the free-form ceramic tile roof, establishing a longitudinal section with the ceramic tile installation positioning curve as a path, and the intersection line between the longitudinal section and the three-dimensional model of the building main body steel structure 1 is used as an installation reference line for positioning the purlin 30, selecting a plurality of points on the installation reference line at intervals as installation points of the purlin support 10, calculating the positioning coordinates of both ends of each purlin support 10, and determining the installation direction of each purlin support 10 according to the extension direction of the ceramic tile installation positioning curve; and obtaining the installation coordinates of the purlin support 10 according to the projection direction of the purlin support 10 according to the projection direction of the purlin support 10. The installation points are sequentially installed on the top of the main steel structure 1 of the building along the extension direction of the ceramic tile installation positioning curve, one end of the purlin adjustment section is bolted to a purlin support 10, and a purlin support 10 is added between the two purlin supports 10. The purlin adjustment section is cold-bent and the middle part is bolted to the added purlin support 10, and finally the other end of the purlin adjustment section is bolted to another purlin support 10, so that the curvature of the cold-bent purlin adjustment section is consistent with the curvature of the corresponding ceramic tile installation positioning curve, and this is repeated, and the purlin adjustment section is gradually adjusted along the extension direction of the ceramic tile installation positioning curve. The positioning purlin 30 is cold-bent and bolted to the top of the purlin support 10, the main keel 5 is staggered and bolted to the top of the positioning purlin 30, and the secondary keel 6 is cold-bent section by section and bolted to the top of the main keel 5, so that the curvature of the secondary keel 6 is consistent with the ceramic tile installation positioning curve; the construction method accurately calculates the positioning coordinates of the two ends of the positioning purlin 30 according to the three-dimensional model of the building main steel structure 1 and the free ceramic tile roof, and accurately lays out the actual measured point position at the construction site, first fixes two adjacent purlin supports 10 according to the measured point position, and fixes the two adjacent purlin supports 10 at the two adjacent purlin supports 10. A purlin support 10 is added between 10, and the purlin adjustment section is cold-bent on-site and bolted to the three purlin supports 10 in sequence, so that the curvature of the positioning purlin 30 is consistent with the corresponding ceramic tile installation positioning curve. The three-point arc method is used to fit the unbent prefabricated straight strip profile into a smooth free curve shape on-site, so that the ceramic tile facing can be connected to the main steel structure 1 of the building along the ceramic tile installation positioning curve, reducing the difficulty of profile processing, on-site layout and installation, improving the installation efficiency and installation accuracy of the free-form roof support structure, and realizing the decorative effect of the free-form ceramic tile roof.
[0043] In step S2, the spacing between two adjacent purlin supports 10-1 is determined according to the deflection of the positioning purlin 30, the load allowed to be applied during the cold bending construction of the positioning purlin 30 is calculated, and whether the installation position and height of the additional purlin support 2 are reasonable is determined according to the profile deflection and the allowable applied load. If reasonable, the purlin support 2 will be installed according to the calculated data; if unreasonable, the spacing and installation position of the purlin support 1 will be adjusted until the calculation results meet the requirements of the profile deflection and load.
[0044] In the step S2, the purlin support 10 includes a support rod 11, an outer sleeve 12 and a base 14. The support rod 11 is vertically arranged and fixedly connected to the top of the main steel structure 1 of the building. The base 14 is connected to one end of the outer sleeve 12. The other end of the outer sleeve 12 is sleeved and connected to the support rod 11. After the support rod 11 is fixed to the top of the main steel structure 1 of the building, the relative distance between the outer sleeve 12 and the support rod 11 is adjusted so that the top connection line of two purlin supports 1 and one purlin support 2 is consistent with the curvature of the installation positioning curve of the ceramic tile 8. After the relative position of the outer sleeve 12 and the support rod 11 is determined, the two are welded and connected, or locked and fixed by through bolts.
[0045] The above description is only a description of the preferred embodiments of the present invention, and is not intended to limit the scope of the present invention. Any changes or modifications made by a person skilled in the art in the field of the present invention based on the above disclosure shall fall within the scope of the claims.
Claims
1. A free-form laminated ceramic tile roof support structure, characterized in that: include: A plurality of purlin supports are arranged vertically and at intervals along the extension direction of the tile installation positioning curve and connected to the top of the main steel structure of the building; Position the purlins, erect and thread them to the top of multiple purlin supports; The main keel is staggered on the top of the positioning purlin and connected with the positioning purlin by bolts; The secondary keel is arranged parallel to the positioning purlin and movably connected to the top of the main keel. A plurality of vertical and spaced support hangers are bolted to the secondary keel, and a plurality of ceramic tiles are detachably connected to the support hangers.
2. The free-form laminated ceramic tile roof support structure according to claim 1, characterized in that: The purlin support comprises a support rod, an outer sleeve and a base. The support rod is vertically arranged and fixedly connected to the top of the main steel structure of the building. The base is connected to one end of the outer sleeve, and the other end of the outer sleeve is sleeved and connected to the support rod.
3. The free-form laminated ceramic tile roof support structure according to claim 2, characterized in that: One end of the support rod passes through the insulation layer and is welded to the main steel structure of the building. The side wall of the outer sleeve is provided with multiple through holes. The outer sleeve is sleeved on the support rod and welded to it; or, the outer sleeve and the vertical pole have corresponding oblong holes in their setting positions, and the screw rod passes through the oblong holes of the outer sleeve and the vertical pole and is locked and fixed by a nut.
4. The free-form laminated ceramic tile roof support structure according to claim 1, characterized in that: The positioning purlin includes a base plate and two side plates. The two side plates are parallel, spaced apart and fixed to the top of the base plate. The two side plates are provided with a plurality of pairs of bolt holes corresponding in position and number. The spacing between the two side plates matches the size of the ribs of the main keel, so that the ribs of the main keel can be embedded between the two side plates of the positioning purlin. A plurality of bolts pass through the corresponding bolt holes of the side plates and the main keel in sequence and are locked and fixed by nuts.
5. The free-form laminated ceramic tile roof support structure according to claim 1, characterized in that: It also includes a waterproof layer, which covers the exposed part of the support rod and the connecting part between the support rod and the insulation layer and the base. The waterproof layer includes a layer of polyurethane sealant sealed at the connection between the insulation layer and the support rod, as well as a waterproof reinforcement layer and a polyurethane spray waterproof surface layer arranged from the inside to the outside.
6. The construction method of the free-form laminated ceramic tile roof support structure according to any one of claims 1 to 5, characterized in that: Here are the steps: S1: Determine the center coordinates of the disk at the intersection of the roof rods according to the three-dimensional model of the main steel structure of the building, determine the ceramic tile installation positioning curve according to the three-dimensional model of the free-form ceramic tile roof, establish a longitudinal section with the ceramic tile installation positioning curve as the path, and the intersection line of the longitudinal section and the three-dimensional model of the main steel structure of the building is the installation reference line for positioning the purlin. Select several points on the installation reference line at intervals as the installation points of the purlin support, calculate the positioning coordinates of both ends of each purlin support, and determine the installation direction of each purlin support according to the extension direction of the ceramic tile installation positioning curve; S2: According to the data obtained in step S1, the center of the disk of the main steel structure of the building is positioned, and the installation points of the two ends of the purlin support are obtained in combination with the positioning of the disk center. According to the installation points obtained by the positioning, multiple purlin supports are sequentially installed on the top of the main steel structure of the building along the extension direction of the ceramic tile installation positioning curve, and the positioning purlin is erected on the top of the multiple purlin supports. The positioning purlin between two adjacent purlin supports is the purlin adjustment section. One end of the purlin adjustment section is bolted to the purlin support located on one side thereof. Then, add a purlin support between the two purlin supports, perform cold bending construction on the purlin adjustment section, adjust the height of the added purlin support, bolt the middle part of the purlin adjustment section to the added purlin support, and finally, bolt the other end of the purlin adjustment section to another purlin support, so that the curvature of the cold-bent purlin adjustment section is consistent with the curvature of the corresponding ceramic tile installation positioning curve, repeat this step, cold-bend the positioning purlin section by section along the extension direction of the ceramic tile installation positioning curve and bolt it to the top of the purlin support; S3: The main keels are staggered and bolted to the top of the positioning purlins, the secondary keels are cold-bent section by section and bolted to the top of the main keels, so that the curvature of the secondary keels and the ceramic tile installation positioning curve are consistent, multiple support hangers are installed at intervals on the top of the secondary keels, and the ceramic tiles are connected to the support hangers.
7. The construction method of the free-form laminated ceramic tile roof support structure according to claim 6, characterized in that: In step S2, the spacing between two adjacent purlin supports is determined according to the deflection of the positioning purlin, the load allowed to be applied during the cold bending construction of the positioning purlin is calculated, and whether the installation position and height of the additional purlin supports are reasonable is determined according to the profile deflection and the allowable load. If reasonable, the additional purlin supports are positioned according to the calculated data; if unreasonable, the spacing and installation position of the two adjacent purlin supports are adjusted until the calculation results meet the requirements of the profile deflection and the load.
8. The construction method of the free-form laminated ceramic tile roof support structure according to claim 6, characterized in that: In step S2, the purlin support includes a support rod, an outer sleeve and a base. The support rod is vertically arranged and fixedly connected to the top of the main steel structure of the building. The base is connected to one end of the outer sleeve. The other end of the outer sleeve is sleeved and connected to the support rod. After the support rod is fixed to the top of the main steel structure of the building, the relative distance between the outer sleeve and the support rod is adjusted so that the connecting line between the top ends of two adjacent purlin supports and the additional purlin support is consistent with the curvature of the ceramic tile installation positioning curve. After the relative position of the outer sleeve and the support rod is determined, the two are welded together or locked and fixed by through bolts.