Safety protection system design and construction supervision system
By designing a safety prevention system, the problem of single methods of existing supervision solutions and poor management results in independent optimization are solved, multi-dimensional supervision and dynamic optimization management are achieved, and the supervision effect of safety prevention system design and construction is improved.
Patent Information
- Application Number
- CN202411899934.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-23
- Publication Date
- 2025-04-15
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing safety prevention system design and construction supervision plan is single, and it is impossible to effectively conduct design reliability supervision analysis and dynamic optimization management in different aspects, resulting in poor results in independent optimization management.
A safety prevention system design and construction supervision system is designed, including a safety prevention system design and construction local supervision module and an overall evaluation module. By monitoring, statistics and processing data from different dimensions, local construction data processing sequences are generated and uploaded to the implementation supervision platform in real time. According to the data combined with processing, data processing and analysis of reliable states in stages are carried out, and dynamic optimization management is carried out adaptively.
Multi-dimensional supervision of the design and construction of safety prevention systems has been achieved, the diversity and comprehensiveness of supervision methods have been improved, the effectiveness of independent optimization management has been enhanced, and the construction plan can be dynamically adjusted to improve safety.
Smart Images

Figure CN119831334A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of construction supervision, and in particular to a safety protection system design and construction supervision system. Background Art
[0002] Security system design and construction refers to a series of planning, design, installation and commissioning work carried out in buildings, facilities or other places to prevent and respond to possible security threats and risks.
[0003] When implementing the existing security system design and construction supervision plan, it is impossible to carry out different aspects of design reliability supervision analysis on the existing security system design and construction, and to dynamically optimize the existing security system design based on the results of supervision analysis in different aspects. This results in a single way of supervision on the design and construction of the security system, and poor results of autonomous optimization management. Summary of the invention
[0004] The purpose of the present invention is to provide a security system design and construction supervision system to solve the technical problems of the single security system design and construction supervision method and poor autonomous optimization management effect in the existing solutions.
[0005] The purpose of the present invention can be achieved through the following technical solutions:
[0006] A safety protection system design and construction supervision system, comprising:
[0007] The local supervision module for the design and construction of the security system is used to monitor, count and process data of the design and construction of the security system in different dimensions, and to process and combine the abnormal construction impact data of the corresponding dimensions for the monitoring and statistical processing data of different dimensions, obtain the local construction data processing sequence and upload it to the implementation supervision platform in real time;
[0008] Among them, the data of design item construction dimension is monitored, counted and processed for the design and construction of the security system, and the local construction status identification is obtained by the abnormal construction impact integration mark;
[0009] Also, data monitoring, statistics and processing of the design item quality inspection dimension of the security system design and construction are performed to obtain a local construction quality inspection mark obtained by the numerical mark of the total number of unqualified items, or a local construction quality inspection mark obtained by the abnormal quality inspection supervision value mark;
[0010] The local construction status identifications and local construction quality inspection identifications obtained by processing in different dimensions are sorted and combined to obtain a local construction data processing sequence;
[0011] The overall assessment module for the design and construction of security and protection systems is used to process and analyze the data of the stage-reliable status of the design and construction of security and protection systems according to the local construction data processing sequence obtained by the processing combination, and to adaptively and dynamically optimize the design and construction of security and protection systems according to the analysis results.
[0012] Preferably, data monitoring, statistics and processing are performed on the design and construction of the security system in terms of the design item construction dimension, and statistics are compiled on all the security design items that have been constructed according to the start construction time and the real-time construction time, as well as the design item construction time corresponding to different security design items;
[0013] The total number of construction items and the total construction time corresponding to all constructed safety design items are calculated by the formula Calculate and obtain the design item supervision value SJ of the design item standard construction corresponding to the safety prevention factor design construction; where NW and NW0 are the total number of completed constructions and the total number of completed standard constructions respectively; TW and TW0 are the total duration of completed constructions and the total duration of completed standard constructions respectively; Tw is the standard duration of construction error;
[0014] Data analysis is performed on the obtained design item supervision values to determine the local construction status corresponding to all constructed safety design items.
[0015] Preferably, if the design item supervision value is 0, it is indicated that the local construction status corresponding to all constructed safety design items is normal, and the value of the design item supervision value is marked as a local construction status identifier;
[0016] If the design item supervision value is not 0, it will prompt that the local construction status corresponding to all constructed safety design items is abnormal, and analyze whether NW-NW0 is 0;
[0017] If NW-NW0 is 0, the difference between the design item construction time corresponding to different constructed safety design items and the corresponding design item construction standard time is calculated and analyzed in turn.
[0018] Preferably, if the calculated difference is less than or equal to 0, the corresponding safety design item is marked as a normal construction design item; if the calculated difference is greater than 0, the corresponding safety design item is marked as an abnormal construction design item, and the abnormal construction impact value YS corresponding to the abnormal construction design item is calculated by the formula YS=SQ×(TX-TX0); wherein SQ is the design safety weight corresponding to the abnormal construction design item; TX and TX0 are the design item construction time and the design item construction standard time corresponding to the abnormal construction design item, respectively;
[0019] The abnormal construction impact values corresponding to all abnormal construction design items are summed up to obtain the abnormal construction impact integration degree YZ; and the value of the abnormal construction impact integration degree is marked as the local construction status identifier.
[0020] Preferably, if NW-NW0 is not 0, then the different constructed safety design items are traversed and matched with all corresponding standard safety design items in turn, and the unmatched standard safety design items are marked as unconstructed design items. At the same time, the differences between the construction durations of the design items corresponding to the different constructed safety design items and the corresponding standard construction durations of the design items are calculated and analyzed in turn to obtain the abnormal construction impact values YS corresponding to all abnormal construction design items, and the abnormal construction impact values corresponding to all abnormal construction design items and the standard construction durations of the design items corresponding to all unconstructed design items are compared through the formula Calculate and obtain the integration degree YZ of abnormal construction impact; where i is different abnormal construction design items, i=1, 2, 3, ..., N1; N1 is a positive integer; TXi and TXi0 are the design item construction time and design item standard construction time corresponding to different abnormal construction design items respectively; SQi is the design safety weight corresponding to different abnormal construction design items; j is different unconstructed design items, j=1, 2, 3, ..., N2; N2 is a positive integer; TXj0 is the design item standard construction time corresponding to different unconstructed design items; SQj is the design safety weight corresponding to different unconstructed design items; and the numerical value of the integration degree of abnormal construction impact is marked as the local construction status identifier.
[0021] Preferably, data monitoring, statistics and processing of the design item quality inspection dimension are performed on the design and construction of the security system, and the quality inspection results corresponding to all constructed safety design items are obtained, and the constructed safety design items are marked as qualified design items or unqualified design items according to the quality inspection results.
[0022] The total number of unqualified construction design items is counted and analyzed. If the total number of unqualified items is 0, it indicates that the safety design items are qualified as a whole, and the value of the total number of unqualified items is marked as a local construction quality inspection mark.
[0023] Preferably, if the total number of unqualified items is not 0, it indicates that the safety design items are partially qualified, and the formula Calculate and obtain the abnormal quality inspection and supervision value YJ corresponding to all unqualified construction design items; where k is a different unqualified construction design item, k = 1, 2, 3, ..., NY; NY is a positive integer; NY is the total number of all unqualified construction design items; SQk is the design safety weight corresponding to different unqualified construction design items;
[0024] The numerical value of the abnormal quality inspection supervision value obtained through processing is marked as a local construction quality inspection mark.
[0025] Preferably, a local construction data processing sequence is obtained and traversed for analysis;
[0026] If all elements in the local construction data processing sequence are 0, the existing security system design and construction will be maintained;
[0027] If there are elements in the local construction data processing sequence that are not 0, the elements in the local construction data processing sequence that are not 0 are subjected to data analysis through the stage abnormality identification function, and the stage abnormality identification BJ corresponding to the design and construction of the security system is output;
[0028] The stage abnormality flag contains a value of 0 or 1, indicating that the stage abnormality status corresponding to the design and construction of the security system is a stage mild abnormality or a stage severe abnormality.
[0029] Preferably, the subsequent implementation of the design and construction of the security system is dynamically optimized and managed according to the abnormal identification of the stage obtained by processing;
[0030] According to the stage abnormality mark with a value of 0 or 1, the subsequent implementation of the design and construction of the security system is respectively optimized locally or overall.
[0031] Preferably, the expression of the stage abnormality identification function is: Wherein, b and c are different calculation weight coefficients, and 0<b<c<1; BS and BZ are the local construction status identification and local construction quality inspection identification in the local construction data processing sequence; YB is the stage abnormal design value.
[0032] Compared with the existing solutions, the present invention achieves the following beneficial effects:
[0033] The present invention obtains abnormal supervision results corresponding to different dimensions by monitoring, counting, processing and calculating different safety design items from different dimensions, and obtains a local construction data processing sequence by sorting and combining the abnormal supervision results corresponding to different dimensions. It can not only realize the digital representation of the local abnormal construction impacts corresponding to different dimensions, but also provide reliable multi-dimensional supervision data support for the data analysis of the reliable status of the subsequent security system design and construction stage, thereby improving the diversity and comprehensiveness of the security system design and construction supervision methods.
[0034] The present invention processes and analyzes the data of the stage-reliable state of the design and construction of the security system through the local construction data processing sequence obtained by processing different aspects in the early stage, and adaptively performs dynamic optimization management of the design and construction of the security system according to the analysis results, thereby realizing the expanded utilization of the data processed in different aspects in the early stage, and at the same time, data analysis and dynamic optimization management can be performed from the overall stage dimension, thereby improving the autonomous optimization management effect of the design and construction supervision of the security system. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] The present invention will be further described below in conjunction with the accompanying drawings.
[0036] Figure 1 The present invention provides a module block diagram of a security system design construction supervision system.
[0037] Figure 2 A flowchart of the steps for designing a construction supervision system for a security system of the present invention.
[0038] Figure 3 A flowchart of the steps of performing data analysis on the obtained design item supervision values in the present invention. DETAILED DESCRIPTION
[0039] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0040] like Figure 1 to Figure 2 As shown, the present invention is a security system design and construction supervision system, including a security system design and construction local supervision module, a security system design and construction overall evaluation module and an implementation supervision platform;
[0041] The local supervision module for the design and construction of the security system is used to monitor, count and process data of the design and construction of the security system in different dimensions, and to process and combine the abnormal construction impact data of the corresponding dimensions for the monitoring and statistical processing data of different dimensions, obtain the local construction data processing sequence and upload it to the implementation supervision platform in real time; including:
[0042] Data monitoring, statistics and processing of design item construction dimensions for security system design and construction are carried out. Statistics of all security design items that have been constructed are calculated based on the start time of construction and the real-time construction time, as well as the construction time of the design items corresponding to different security design items;
[0043] Among them, the units corresponding to the start construction time and the real-time construction time are accurate to the hour;
[0044] The object of security system design can be a building. Security system design includes several different types of security design items, such as different types of security equipment. Specifically, infrared detectors or electronic fences are installed to prevent illegal intrusion, smoke sensors are installed to monitor the occurrence of smoke and fire, and emergency call buttons are set at important locations to quickly seek help in an emergency, etc.
[0045] Different safety design items are pre-set with a corresponding design item construction standard duration and design safety weight. The design safety weight is used to digitally and differentially represent the design safety importance corresponding to the corresponding safety design item. The specific values of the design safety weights corresponding to different safety design items can be determined by professional and technical personnel in this field based on work experience and work requirements, or can be determined based on the degree of negative impact caused by the history of the corresponding safety design item;
[0046] The total number of construction items and the total construction time corresponding to all constructed safety design items are calculated by the formula Calculate and obtain the design item supervision value SJ of the design item standard construction corresponding to the safety prevention factor design construction; where NW and NW0 are the total number of constructions and the total number of standard constructions respectively; TW and TW0 are the total construction time and the total standard construction time respectively; Tw is the standard construction error time; the total number of standard constructions and the total standard construction time are determined according to the standard design data between the start construction time and the real-time construction time; the standard construction error time can be obtained by summing up the single standard time corresponding to a single safety design item, and the one-way standard time corresponding to different safety design items can be determined by professional and technical personnel in this field according to their work experience, or can be determined according to the existing construction design requirements corresponding to different safety design items;
[0047] It should be noted that the design item supervision value is used to calculate the monitoring data corresponding to all constructed safety design items from the design item construction dimension, so as to digitally represent the local construction status corresponding to the constructed safety design items;
[0048] like Figure 3 As shown, data analysis is performed on the obtained design item supervision values to determine the local construction status corresponding to all constructed safety design items;
[0049] If the design item supervision value is 0, it indicates that the local construction status corresponding to all constructed safety design items is normal, and the value of the design item supervision value is marked as the local construction status identifier;
[0050] If the design item supervision value is not 0, it will prompt that the local construction status corresponding to all constructed safety design items is abnormal, and analyze whether NW-NW0 is 0;
[0051] In an embodiment of the present invention, by performing data analysis on the obtained design item supervision values, it is possible to obtain the local construction status corresponding to all constructed safety design items, and provide reliable supervision processing data support for the abnormal construction impact analysis corresponding to all abnormal construction design items.
[0052] If NW-NW0 is 0, the difference between the design item construction time corresponding to different constructed safety design items and the corresponding design item construction standard time is calculated and analyzed in turn;
[0053] If the calculated difference is less than or equal to 0, the safety design item is marked as a normal construction design item; if the calculated difference is greater than 0, the safety design item is marked as an abnormal construction design item, and the abnormal construction impact value YS corresponding to the abnormal construction design item is calculated by the formula YS=SQ×(TX-TX0); where SQ is the design safety weight corresponding to the abnormal construction design item; TX and TX0 are the design item construction time and the design item standard construction time corresponding to the abnormal construction design item, respectively;
[0054] It should be noted that the abnormal construction impact value is used to calculate the abnormal data corresponding to different aspects of the abnormal construction design item, so as to digitally represent the abnormal construction impact corresponding to the abnormal construction design item;
[0055] The abnormal construction impact values corresponding to all abnormal construction design items are summed up to obtain the abnormal construction impact integration degree YZ; and the value of the abnormal construction impact integration degree is marked as a local construction status identifier;
[0056] If NW-NW0 is not 0, then the different constructed safety design items are traversed and matched with all the corresponding standard safety design items in turn, and the unmatched standard safety design items are marked as unconstructed design items. At the same time, the difference between the construction time of the design items corresponding to the different constructed safety design items and the corresponding standard construction time of the design items is calculated and analyzed in turn to obtain the abnormal construction impact value YS corresponding to all abnormal construction design items, and the abnormal construction impact value corresponding to all abnormal construction design items and the standard construction time of the design items corresponding to all unconstructed design items are compared through the formula Calculate and obtain the integration degree YZ of abnormal construction impact; where i is different abnormal construction design items, i=1, 2, 3, ..., N1; N1 is a positive integer; TXi and TXi0 are the design item construction time and design item standard construction time corresponding to different abnormal construction design items respectively; SQi is the design safety weight corresponding to different abnormal construction design items; j is different unconstructed design items, j=1, 2, 3, ..., N2; N2 is a positive integer; TXj0 is the design item standard construction time corresponding to different unconstructed design items; SQj is the design safety weight corresponding to different unconstructed design items; and mark the value of the integration degree of abnormal construction impact as the local construction status identifier;
[0057] It should be noted that the abnormal construction impact integration degree is used to calculate the monitoring and processing data corresponding to all abnormal construction design items and all unconstructed design items to digitally represent all abnormal construction impacts;
[0058] In the embodiment of the present invention, by further performing data processing and integrated calculation on the impact of abnormal construction in different aspects on the abnormal construction obtained in the previous analysis, the corresponding integration degree of the impact of abnormal construction is obtained, which can provide reliable design item construction dimension processing data support for the data analysis of the reliable status of the subsequent security system design and construction stage.
[0059] Also, data monitoring, statistics and processing of the quality inspection dimension of the design items of the security system design and construction are carried out to obtain the quality inspection results corresponding to all constructed safety design items, and mark the constructed safety design items as qualified design items or unqualified design items according to the quality inspection results;
[0060] The quality inspection corresponding to different constructed safety design items can be implemented and recorded by professional construction quality inspection personnel. The specific quality inspection requirements and contents can be customized according to the actual application scenarios.
[0061] The total number of unqualified construction design items is counted and analyzed. If the total number of unqualified items is 0, it indicates that the safety design items are qualified as a whole, and the value of the total number of unqualified items is marked as a local construction quality inspection mark;
[0062] If the total number of unqualified items is not 0, it indicates that the safety design items are partially qualified and the formula Calculate and obtain the abnormal quality inspection and supervision value YJ corresponding to all unqualified construction design items; where k is a different unqualified construction design item, k = 1, 2, 3, ..., NY; NY is a positive integer; NY is the total number of all unqualified construction design items; SQk is the design safety weight corresponding to different unqualified construction design items;
[0063] It should be noted that the abnormal quality inspection supervision value is used to calculate the abnormal data corresponding to all unqualified construction design items obtained by quality inspection, so as to digitally represent the impact of local construction quality inspection;
[0064] Mark the value of the abnormal quality inspection supervision value obtained through processing as a local construction quality inspection mark;
[0065] The local construction status identifications and local construction quality inspection identifications obtained by processing in different dimensions are sorted and combined to obtain a local construction data processing sequence;
[0066] In the embodiment of the present invention, different safety design items are monitored, counted, processed and calculated from different dimensions to obtain abnormal supervision results corresponding to different dimensions. By sorting and combining the abnormal supervision results corresponding to different dimensions, a local construction data processing sequence is obtained. This can not only realize the digital representation of the local abnormal construction impacts corresponding to different dimensions, but also provide reliable multi-dimensional supervision data support for the data analysis of the reliable status of the subsequent security system design and construction stage, thereby improving the diversity and comprehensiveness of the security system design and construction supervision methods.
[0067] The overall assessment module for the design and construction of security and protection systems is used to process and analyze the data of the stage reliability status of the design and construction of security and protection systems according to the local construction data processing sequence obtained by the processing combination, and to adaptively and dynamically optimize the design and construction of security and protection systems according to the analysis results; including:
[0068] Obtain local construction data processing sequence and traverse and analyze;
[0069] If all elements in the local construction data processing sequence are 0, the existing security system design and construction will be maintained;
[0070] If there are elements in the local construction data processing sequence that are not 0, the elements in the local construction data processing sequence that are not 0 are subjected to data analysis through the stage abnormality identification function, and the stage abnormality identification BJ corresponding to the design and construction of the security system is output;
[0071] Among them, the expression of the stage anomaly recognition function is: Wherein, b and c are different calculation weight coefficients, and 0<b<c<1, and the specific values of b and c are not limited and can be determined according to the actual construction design requirement data of the actual application scenario; BS and BZ are the local construction status identification and local construction quality inspection identification in the local construction data processing sequence; YB is the stage abnormal design value, which can be determined by the median of all historical stage abnormal values, or can be determined by professional and technical personnel in this field according to the construction design requirement data;
[0072] It should be noted that the stage abnormality identification is used to analyze the local construction abnormality data obtained by processing different dimensions in the early stage to digitally represent the stage abnormality status corresponding to the design and construction of the security system;
[0073] The stage abnormality flag contains a value of 0 or 1, indicating that the stage abnormality state corresponding to the design and construction of the security system is a stage mild abnormality or a stage severe abnormality;
[0074] Dynamically optimize the subsequent implementation of the security system design and construction based on the abnormal identification of the obtained stage;
[0075] According to the abnormal stage mark with a value of 0 or 1, the subsequent implementation of the design and construction of the security system is respectively optimized locally or overall;
[0076] Among them, local optimization management is carried out for the subsequent implementation of the design and construction of the security system. Specifically, it can be targeted optimization and supervision of the construction progress of the design items or the construction specifications of the design items;
[0077] Overall optimization management can specifically involve targeted optimization and supervision of all aspects. There is no restriction on the specific content of optimization and supervision, which can be customized according to the actual application requirements of the actual application scenario.
[0078] In the embodiment of the present invention, the local construction data processing sequence obtained by processing different aspects in the early stage is used to process and analyze the data of the stage reliable state of the design and construction of the security system, and the design and construction of the security system is adaptively dynamically optimized and managed according to the analysis results, thereby realizing the expanded utilization of the data processed in different aspects in the early stage, and at the same time, data analysis and dynamic optimization management can be performed from the overall stage dimension, thereby improving the autonomous optimization management effect of the design and construction supervision of the security system.
[0079] In addition, the formulas involved in the above are all dimensionless and numerical calculations. They are a formula that is closest to the actual situation obtained by collecting a large amount of data and simulating it with simulation software.
[0080] In the several embodiments provided by the present invention, it should be understood that the disclosed system can be implemented in other ways. For example, the above-described embodiments of the invention are only illustrative, for example, the division of modules is only a logical function division, and there may be other division methods in actual implementation.
[0081] The modules described as separate components may or may not be physically separated, and the components shown as modules may or may not be physical modules, and may be located in one place or distributed on multiple network modules. Some or all of the modules may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0082] In addition, each functional module in each embodiment of the present invention may be integrated into one processing module, or each module may exist physically separately, or two or more modules may be integrated into one module. The above-mentioned integrated module may be implemented in the form of hardware or in the form of hardware plus software functional modules.
[0083] It is obvious to a person skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the essential characteristics of the present invention.
[0084] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the spirit and scope of the technical solution of the present invention.
Claims
1. A security system design and construction supervision system, characterized in that: include: The local supervision module for the design and construction of the security system is used to monitor, count and process data of the design and construction of the security system in different dimensions, and to process and combine the abnormal construction impact data of the corresponding dimensions for the monitoring and statistical processing data of different dimensions, obtain the local construction data processing sequence and upload it to the implementation supervision platform in real time; Among them, the data of design item construction dimension is monitored, counted and processed for the design and construction of the security system, and the local construction status identification is obtained by the abnormal construction impact integration mark; Also, data monitoring, statistics and processing of the design item quality inspection dimension of the security system design and construction are performed to obtain a local construction quality inspection mark obtained by the numerical mark of the total number of unqualified items, or a local construction quality inspection mark obtained by the abnormal quality inspection supervision value mark; The local construction status identifications and local construction quality inspection identifications obtained by processing in different dimensions are sorted and combined to obtain a local construction data processing sequence; The overall assessment module for the design and construction of security and protection systems is used to process and analyze the data of the stage-reliable status of the design and construction of security and protection systems according to the local construction data processing sequence obtained by the processing combination, and to adaptively and dynamically optimize the design and construction of security and protection systems according to the analysis results.
2. A security system design and construction supervision system according to claim 1, characterized in that: Data monitoring, statistics and processing of design item construction dimensions for security system design and construction are carried out. Statistics of all security design items that have been constructed are calculated based on the start time of construction and the real-time construction time, as well as the construction time of the design items corresponding to different security design items; The total number of construction items and the total construction time corresponding to all constructed safety design items are calculated by the formula Calculate and obtain the design item supervision value SJ of the design item standard construction corresponding to the safety prevention factor design construction; where NW and NW0 are the total number of completed constructions and the total number of completed standard constructions respectively; TW and TW0 are the total duration of completed constructions and the total duration of completed standard constructions respectively; Tw is the standard duration of construction error; Data analysis is performed on the obtained design item supervision values to determine the local construction status corresponding to all constructed safety design items.
3. A security system design and construction supervision system according to claim 2, characterized in that: If the design item supervision value is 0, it indicates that the local construction status corresponding to all constructed safety design items is normal, and the value of the design item supervision value is marked as the local construction status identifier; If the design item supervision value is not 0, it will prompt that the local construction status corresponding to all constructed safety design items is abnormal, and analyze whether NW-NW0 is 0; If NW-NW0 is 0, the difference between the design item construction time corresponding to different constructed safety design items and the corresponding design item construction standard time is calculated and analyzed in turn.
4. A security system design and construction supervision system according to claim 3, characterized in that: If the calculated difference is less than or equal to 0, the corresponding safety design item is marked as a normal construction design item; If the calculated difference is greater than 0, the corresponding safety design item is marked as an abnormal construction design item, and the abnormal construction impact value YS corresponding to the abnormal construction design item is calculated by the formula YS=SQ×(TX-TX0); where SQ is the design safety weight corresponding to the abnormal construction design item; TX and TX0 are the design item construction time and the design item construction standard time corresponding to the abnormal construction design item, respectively; The abnormal construction impact values corresponding to all abnormal construction design items are summed up to obtain the abnormal construction impact integration degree YZ; The numerical value of the abnormal construction affecting the integration degree is marked as the local construction status identifier.
5. A security system design and construction supervision system according to claim 4, characterized in that: If NW-NW0 is not 0, then the different constructed safety design items are traversed and matched with all the corresponding standard safety design items in turn, and the unmatched standard safety design items are marked as unconstructed design items. At the same time, the difference between the construction time of the design items corresponding to the different constructed safety design items and the corresponding standard construction time of the design items is calculated and analyzed in turn to obtain the abnormal construction impact value YS corresponding to all abnormal construction design items, and the abnormal construction impact value corresponding to all abnormal construction design items and the standard construction time of the design items corresponding to all unconstructed design items are compared through the formula Calculate and obtain the integration degree YZ of abnormal construction impact; where i is different abnormal construction design items, i = 1, 2, 3, ..., N1; N1 is a positive integer; TXi and TXi0 are respectively the design item construction time and the design item construction standard time corresponding to different abnormal construction design items; SQi is the design safety weight corresponding to different abnormal construction design items; j is different unconstructed design items, j = 1, 2, 3, ..., N2; N2 is a positive integer; TXj0 is the design item construction standard time corresponding to different unconstructed design items; SQj is the design safety weight corresponding to different unconstructed design items; The numerical value of the abnormal construction affecting the integration degree is marked as the local construction status identifier.
6. A security system design and construction supervision system according to claim 5, characterized in that: Conduct data monitoring, statistics and processing on the quality inspection dimension of design items for the design and construction of security protection systems, obtain the quality inspection results corresponding to all constructed safety design items, and mark the constructed safety design items as qualified design items or unqualified design items according to the quality inspection results; The total number of unqualified construction design items is counted and analyzed. If the total number of unqualified items is 0, it indicates that the safety design items are qualified as a whole, and the value of the total number of unqualified items is marked as a local construction quality inspection mark.
7. A security system design and construction supervision system according to claim 6, characterized in that: If the total number of unqualified items is not 0, it indicates that the safety design items are partially qualified and the formula Calculate and obtain the abnormal quality inspection and supervision value YJ corresponding to all unqualified construction design items; where k is a different unqualified construction design item, k = 1, 2, 3, ..., NY; NY is a positive integer; NY is the total number of all unqualified construction design items; SQk is the design safety weight corresponding to different unqualified construction design items; The numerical value of the abnormal quality inspection supervision value obtained through processing is marked as a local construction quality inspection mark.
8. A security system design and construction supervision system according to claim 7, characterized in that: Obtain local construction data processing sequence and traverse and analyze; If all elements in the local construction data processing sequence are 0, the existing security system design and construction will be maintained; If there are elements in the local construction data processing sequence that are not 0, the elements in the local construction data processing sequence that are not 0 are subjected to data analysis through the stage abnormality identification function, and the stage abnormality identification BJ corresponding to the design and construction of the security system is output; The stage abnormality flag contains a value of 0 or 1, indicating that the stage abnormality status corresponding to the design and construction of the security system is a stage mild abnormality or a stage severe abnormality.
9. A security system design and construction supervision system according to claim 8, characterized in that: Dynamically optimize the subsequent implementation of the security system design and construction based on the abnormal identification of the obtained stage; According to the stage abnormality mark with a value of 0 or 1, the subsequent implementation of the design and construction of the security system is respectively optimized locally or overall.
10. A security system design and construction supervision system according to claim 8, characterized in that: The expression of the stage anomaly recognition function is: Wherein, b and c are different calculation weight coefficients, and 0<b<c<1; BS and BZ are the local construction status identification and local construction quality inspection identification in the local construction data processing sequence; YB is the stage abnormal design value.