High pier comprehensive maintenance device and use method thereof

By designing a comprehensive maintenance device for high bridge pier, including a spray system and a curtain system, the problems of uneven spraying, low efficiency, and high safety risks in the maintenance methods of the existing bridge lower structure are solved, and uniform and effective maintenance of the bridge pier is achieved, and maintenance efficiency and safety are improved.

CN119843572APending Publication Date: 2025-04-18CHINA RAILWAY SEVENTH GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510067012.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-16
Publication Date
2025-04-18

AI Technical Summary

Technical Problem

The existing bridge lower structure maintenance methods have problems such as uneven spraying, low efficiency, and high safety risks, which are difficult to meet the needs of modern bridge maintenance.

Method used

A comprehensive maintenance device for high bridge pier is designed, including a spray system and a curtain system. The spray system achieves uniform spraying of the piers through annular tracks and spray trucks. The curtain system uses a moisturizing and maintenance blanket and lifting mechanism to ensure that the moisture does not evaporate rapidly.

Benefits of technology

It realizes uniform and effective maintenance of bridge piers, improves maintenance efficiency, reduces safety risks, and facilitates repeated use of the device.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119843572A_ABST
    Figure CN119843572A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of pier maintenance, and particularly relates to a high pier comprehensive maintenance device and a using method thereof. The maintenance device comprises a spraying system and a curtain system. The spraying system comprises an annular rail which is arranged on the top of the supporting frame. A spraying vehicle moves on the annular track in a guiding manner, and a water spraying pipe is arranged on the spraying vehicle; a water tank is arranged on the bridge pier and is connected with a water spraying pipe on the spraying vehicle through a telescopic hose; the curtain system comprises a moisturizing and maintaining blanket, and the periphery of the pier is wrapped with the moisturizing and maintaining blanket in a surrounding mode. The top of the moisturizing maintenance blanket is fixed to the side face of the supporting frame. The curtain system further comprises a lifting mechanism, the lifting mechanism is used for driving the moisturizing and maintaining blanket to ascend or descend, and after the moisturizing and maintaining blanket completely descends, the periphery of the pier is completely wrapped with the moisturizing and maintaining blanket. According to the maintenance device, the bridge pier has a better maintenance effect, so that the maintenance efficiency is greatly improved, and the device is more convenient to recycle.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of bridge pier maintenance, and specifically relates to a high bridge pier comprehensive maintenance device and a use method thereof. Background Art

[0002] The substructure of a bridge generally includes piers, abutments and foundations. During the construction of existing bridge substructures, cast-in-place piers and abutments need to be maintained after the cement concrete has finally set. The surface of the concrete needs to be kept moist to ensure that the cement hydration and hardening process can proceed smoothly. If maintenance is not carried out in time, when the concrete surface loses water, the cement hydration reaction stops, and the surface dries and shrinks. Under the action of shrinkage stress, cracks will appear in the concrete structure, affecting the safety and normal use of the structure.

[0003] In the existing maintenance process, the traditional maintenance method of manual water spraying or sprinkling is generally adopted. The traditional manual operation mode will result in uneven spraying and inadequate spraying, and cannot achieve the effect of accurate and uniform spraying of the bridge piers. Maintenance omissions will inevitably occur, which is easy to leave safety hazards and affect the quality of the project. In summary, the traditional maintenance method has problems such as long maintenance cycle, low efficiency, and high safety risks, which can hardly meet the needs of modern bridge maintenance.

[0004] Therefore, it is necessary to provide an improved technical solution to address the above-mentioned deficiencies in the prior art. Invention content

[0005] The purpose of the present invention is to provide a high bridge pier comprehensive maintenance device and a method of using the same, so as to at least solve the above-mentioned problems existing in the prior art.

[0006] In order to achieve the above object, the present invention provides the following technical solutions:

[0007] A comprehensive maintenance device for high bridge piers, the maintenance device comprising a spray system and a curtain system;

[0008] The spray system comprises an annular track, which is arranged on the top of a support frame, and the support frame is detachably fixed on the top of the pier;

[0009] A spray vehicle is guided and moved on the circular track, and a water spray pipe is arranged on the spray vehicle, and the water spray pipe sprays water toward the outer surface of the bridge pier;

[0010] A water tank is provided on the bridge pier, and the water tank is connected to the water spray pipe on the spray vehicle through a telescopic hose, and the water tank is used to supply water to the water spray pipe through the telescopic hose;

[0011] The curtain system includes a moisture-retaining maintenance blanket, which surrounds and wraps around the periphery of the bridge pier;

[0012] The top of the moisturizing and curing blanket is fixed to the side of the supporting frame;

[0013] The curtain system also includes a lifting mechanism, which is used to drive the moisturizing maintenance blanket to rise or fall. When the moisturizing maintenance blanket is completely fallen, the moisturizing maintenance blanket is completely wrapped around the periphery of the bridge pier.

[0014] As described above, in the comprehensive maintenance device for high bridge piers, preferably, the moisture-retaining maintenance blanket comprises a plastic film on the outer layer and a water-absorbing layer on the inner layer, and the water-absorbing layer is made of a water-absorbing material prepolymer implanted in a non-woven fabric.

[0015] As described above, in the comprehensive maintenance device for high bridge piers, preferably, a plurality of fixing rings are provided on the moisturizing maintenance blanket, and the fixing rings are arranged on the outer surface of the moisturizing maintenance blanket; a support rod extending outward is provided on the side of the support frame, and the fixing ring on the top of the moisturizing maintenance blanket is fixed on the support rod.

[0016] In the above-mentioned high bridge pier comprehensive maintenance device, preferably, the lifting mechanism includes a driving source of multiple lifting ropes, and the multiple lifting ropes are evenly distributed around the circumference of the moisturizing maintenance blanket;

[0017] One end of the lifting rope is fixed to the bottom of the moisturizing and curing blanket, and the other end is fixed to the rotation output end of the driving source.

[0018] In the above-mentioned comprehensive maintenance device for high bridge piers, preferably, the lifting rope passes through a plurality of fixing rings arranged along one lifting rope in sequence.

[0019] The high bridge pier comprehensive maintenance device as described above, preferably, the maintenance device further comprises a tightening rope, the tightening rope is spirally wound around the periphery of the moisturizing maintenance blanket;

[0020] One end of the tightening rope is fixed to the bottom of the moisturizing and curing blanket, and the other end of the tightening rope is fixed to the spraying vehicle.

[0021] In the above-mentioned high bridge pier comprehensive maintenance device, preferably, a plurality of the fixing rings are arranged on the periphery of the moisturizing maintenance blanket along a spiral track;

[0022] The tightening rope passes through a plurality of fixing rings arranged on the periphery of the moisture-retaining maintenance blanket in sequence.

[0023] In the above-mentioned high bridge pier comprehensive maintenance device, preferably, the driving source is a winch, one end of the multiple lifting ropes are connected to the rotation output end of the winch, and the winch drives the multiple lifting ropes to rise or fall synchronously.

[0024] In the above-mentioned high bridge pier comprehensive maintenance device, preferably, the driving source is a motor, an I-shaped wheel is provided at the output end of the motor, one end of a plurality of lifting ropes is fixed on the I-shaped wheel, and the I-shaped wheel is driven to rotate to drive the plurality of lifting ropes to rise or fall synchronously.

[0025] The present application also provides a method for using a high bridge pier comprehensive maintenance device, the method for using is the method for using the above-mentioned high bridge pier comprehensive maintenance device, the method for using comprises:

[0026] Step 1, installing the maintenance device on the top of the pier;

[0027] Step 2, start the driving source to drive the lifting rope to descend, so that the moisturizing maintenance blanket is wrapped around the periphery of the bridge pier after being completely lowered;

[0028] Step 3: Start the spray truck and guide it along the circular track to drive the water spray pipe to spray water evenly toward the outer surface of the pier. At the same time, the spray truck drives a part of the tightening rope to wrap around the support frame, and the tightening rope is gradually tightened to make the moisturizing maintenance blanket close to the outer periphery of the pier.

[0029] Step 4: After the spraying maintenance is completed, the spraying vehicle returns to the starting position to loosen the tightening rope;

[0030] Step 5, start the driving source again to drive the lifting rope to rise, so that the moisturizing curing blanket rises and folds back; so as to facilitate the transportation and reuse of the curing device;

[0031] Step 6, transporting the maintenance device to the next pier to be maintained, and repeating the above maintenance steps.

[0032] Beneficial effects:

[0033] When the maintenance device is installed on the top of the pier, the lifting mechanism is first started to completely lower the moisturizing maintenance blanket so that the moisturizing maintenance blanket surrounds the periphery of the pier, thereby preventing the moisture on the pier surface from evaporating quickly after spraying maintenance on the pier surface, thereby achieving a better spraying maintenance effect, ensuring the maintenance intensity of the pier, and thus improving the maintenance efficiency as much as possible.

[0034] After the moisturizing maintenance blanket is put into place, start the spray truck and guide it along the circular track. At this time, the water pipe on the spray truck sprays water to the pier from the gap between the moisturizing maintenance blanket and the pier. The water flows along the outer surface of the pier from the top to the bottom, thereby realizing the spray maintenance of the pier and greatly improving the maintenance efficiency.

[0035] When the maintenance of a pier is completed, the lifting mechanism is started again to lift the moisturizing maintenance blanket upward, so that the moisturizing maintenance blanket can be folded and contracted for easy transportation; when the moisturizing maintenance blanket is contracted into place, the entire maintenance device is installed on the next pier to repeat the above maintenance work; the moisturizing maintenance blanket can be used repeatedly, and the wrapping and folding operations of the moisturizing maintenance blanket on the pier body are relatively simple, and the maintenance device is more convenient for repeated use.

[0036] The spray vehicle is guided and moved along the circular track to drive the tightening rope to be gradually tightened, so that the moisturizing maintenance blanket fits on the bridge pier, so that the bridge pier has a better maintenance effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] The drawings constituting part of the present application are used to provide a further understanding of the invention. The exemplary embodiments and descriptions of the invention are used to explain the invention and do not constitute an improper limitation on the invention. Among them:

[0038] Figure 1 A front view of a maintenance device installed on a bridge pier in accordance with an embodiment of the present invention;

[0039] Figure 2 A top view of a maintenance device installed on a bridge pier in accordance with an embodiment of the present invention;

[0040] Figure 3 A schematic diagram of a moisture-retaining maintenance blanket after lowering according to an embodiment of the present invention;

[0041] Figure 4 A schematic diagram of a tightened moisture-retaining maintenance blanket according to an embodiment of the present invention.

[0042] In the figure: 1. Bridge pier; 2. Tightening rope; 3. Moisturizing maintenance blanket; 4. Fixing ring; 5. Lifting rope; 6. Circular track; 7. Support frame; 8. Driving source; 9. Water tank; 10. Telescopic hose; 11. Spray truck; 12. Water spray pipe. DETAILED DESCRIPTION

[0043] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field belong to the scope of protection of the present invention.

[0044] In the description of the present invention, the terms "longitudinal", "lateral", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and do not require that the present invention must be constructed and operated in a specific direction. Therefore, they cannot be understood as limitations on the present invention. The terms "connected" and "connected" used in the present invention should be understood in a broad sense. For example, they can be fixedly connected or detachably connected; they can be directly connected or indirectly connected through intermediate components. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.

[0045] The present invention will be described in detail below with reference to the accompanying drawings and in combination with the embodiments. It should be noted that the embodiments and features in the embodiments of the present invention can be combined with each other without conflict.

[0046] According to the specific embodiments of the present invention, Figure 1-4 As shown, the present invention provides a comprehensive maintenance device for high bridge piers, the maintenance device includes a spray system and a curtain system;

[0047] The spray system includes an annular track 6, which is arranged on the top of a support frame 7, and the support frame 7 is detachably fixed on the top of the pier 1;

[0048] A spraying vehicle 11 is guided and moved on the circular track 6, and a water spraying pipe 12 is arranged on the spraying vehicle 11, and the water spraying pipe 12 sprays water toward the outer surface of the bridge pier 1;

[0049] A water tank 9 is provided on the bridge pier 1, and the water tank 9 is connected to a water spray pipe 12 on a spray truck 11 through a telescopic hose 10. The water tank 9 is used to supply water to the water spray pipe 12 through the telescopic hose 10. In this embodiment, a water pump is provided in the water tank 9, and water pumped by the water pump is transferred to the water spray pipe 12 through the telescopic hose 10, so that the water spray pipe 12 sprays water onto the surface of the bridge pier 1.

[0050] In other embodiments, the water pump may also be arranged on the spray truck 11, in which case the telescopic hose 10 connects the water tank 9 with the water pumping end, and the water spray pipe 12 is connected to the water discharge end of the water pump.

[0051] The curtain system includes a moisture-retaining maintenance blanket 3, which surrounds and wraps around the outer periphery of the bridge pier 1;

[0052] The top of the moisturizing and curing blanket 3 is fixed to the side of the supporting frame 7;

[0053] The curtain system also includes a lifting mechanism, which is used to drive the moisturizing maintenance blanket 3 to rise or fall. When the moisturizing maintenance blanket 3 is completely fallen, the moisturizing maintenance blanket 3 is completely wrapped around the periphery of the pier 1.

[0054] After the maintenance device is installed on the top of the pier 1, the lifting mechanism is first started to completely lower the moisturizing maintenance blanket 3 so that the moisturizing maintenance blanket 3 surrounds and wraps around the periphery of the pier 1, thereby preventing the moisture on the surface of the pier 1 from being evaporated quickly after the surface of the pier 1 is sprayed and maintained, thereby achieving a better spray maintenance effect, ensuring the maintenance strength of the pier 1, and thus improving the maintenance efficiency as much as possible.

[0055] After the moisturizing maintenance blanket 3 is put into place, the spray truck 11 is started and guided to move along the circular track 6. At this time, the water spray pipe 12 on the spray truck 11 sprays water to the pier 1 from the gap between the moisturizing maintenance blanket 3 and the pier 1. The water flows along the outer surface of the pier 1 from the top to the bottom, thereby realizing the spray maintenance of the pier 1 and greatly improving the maintenance efficiency.

[0056] After the maintenance of a pier 1 is completed, the lifting mechanism is started again to lift the moisturizing maintenance blanket 3 upwards, so that the moisturizing maintenance blanket 3 can be folded and contracted for easy transportation; when the moisturizing maintenance blanket 3 is contracted into place, the entire maintenance device is installed on the next pier 1 to repeat the above maintenance work; the moisturizing maintenance blanket 3 can be used repeatedly, and the wrapping and folding operations of the moisturizing maintenance blanket 3 on the pier body are relatively simple, that is, the maintenance device of the present application is more convenient for repeated use.

[0057] The moisturizing and curing blanket 3 comprises a plastic film on the outer layer and a water-absorbing layer on the inner layer. The water-absorbing layer is made of a water-absorbing material prepolymer implanted in a non-woven fabric.

[0058] In one embodiment of the present application, in the moisturizing maintenance blanket 3, the plastic film prevents the evaporation of water too quickly, and the water-absorbing layer made of a water-absorbing material prepolymer implanted in a non-woven fabric has good water absorption. After spraying, the water-absorbing layer is filled with water and adheres closely to the surface of the pier 1, thereby achieving a better maintenance effect for the pier 1.

[0059] Specifically, the moisturizing maintenance blanket 3 is a new type of polymer concrete water-saving maintenance moisturizing film; the moisturizing film uses a plastic film as a carrier, and through the prepolymerization method, the water-absorbing material prepolymer is implanted into a special non-woven fabric, wherein the water-absorbing material is a water-absorbing resin, and the water-absorbing resin is integrated with the special non-woven fabric and the impermeable plastic film, and adheres to the polymer that can absorb 200 times its own weight of water. That is, the moisturizing maintenance blanket 3 can not only prevent rapid evaporation of water, but also has good water absorption, which is beneficial to improving maintenance efficiency.

[0060] A plurality of fixing rings 4 are arranged on the moisturizing and curing blanket 3 , and the fixing rings 4 are arranged on the outer surface of the moisturizing and curing blanket 3 .

[0061] In one embodiment of the present application, a fixing ring 4 is provided on the moisturizing maintenance blanket 3 so that the force on the moisturizing maintenance blanket 3 is more evenly applied and it is convenient to fix the moisturizing maintenance blanket 3 on the support rod on the side of the support frame 7 through the fixing ring 4 on the top.

[0062] The side of the support frame 7 is provided with a support rod extending outward, and the fixing ring 4 on the top of the moisturizing maintenance blanket 3 is fixed on the support rod. By arranging a support rod extending outside the pier 1 on the support frame 7, and fixing the top of the moisturizing maintenance blanket 3 on the support rod on the side of the support frame 7, a gap is formed between the moisturizing maintenance blanket 3 and the periphery of the pier 1, so that the water spray pipe 12 can spray the outer surface of the pier 1 from the gap between the moisturizing maintenance blanket 3 and the periphery of the pier 1 for maintenance.

[0063] The lifting mechanism includes a driving source 8 and a plurality of lifting ropes 5, and the plurality of lifting ropes 5 are evenly distributed around the moisturizing and curing blanket 3; one end of the lifting rope 5 is fixed to the bottom of the moisturizing and curing blanket 3, and the other end is fixed to the rotating output end of the driving source 8. In one embodiment of the present application, the output end is driven to rotate by the driving source 8, so that the lifting rope 5 is wound around the output end of the driving source 8, so that the lifting rope 5 is retracted, thereby driving the moisturizing and curing blanket 3 to fold upward and rise; or the lifting rope 5 is released from the output end of the driving source 8, so that the lifting rope 5 is lowered, thereby driving the moisturizing and curing blanket 3 to be lowered. Multiple lifting ropes 5 are arranged around the moisturizing and curing blanket 3 so that the force during the rising and falling process of the moisturizing and curing blanket 3 is more uniform.

[0064] In this embodiment, the driving source 8 is arranged on the top of the pier 1, and the water tank 9 is supported by a bracket to avoid interference between the lifting rope 5 and the water tank 9. In other embodiments, the driving source 8 can also be arranged above the water tank 9, and the water tank 9 can be arranged at the center of the top of the pier 1.

[0065] The lifting rope 5 passes through a plurality of fixing rings 4 arranged along one lifting rope 5 in sequence. In one embodiment of the present application, only the bottom end of the lifting rope 5 is fixed to the bottom end of the moisturizing and curing blanket 3, and the lifting rope 5 only passes through the fixing ring 4 arranged on the periphery of the moisturizing and curing blanket 3; when the lifting rope 5 is lowered, the fixing ring 4 on the moisturizing and curing blanket 3 is guided along the lifting rope 5, so that the lowering process of the moisturizing and curing blanket 3 is more uniform and stable; when the lifting rope 5 is retracted, the fixing ring 4 on the moisturizing and curing blanket 3 is folded along the lifting rope 5, so that the moisturizing and curing blanket 3 can be folded evenly, thereby making it more convenient to transport and install the curing device.

[0066] The maintenance device also includes a tightening rope 2, which is spirally wound around the outer periphery of the moisturizing maintenance blanket 3; one end of the tightening rope 2 is fixed to the bottom of the moisturizing maintenance blanket 3, and the other end of the tightening rope 2 is fixed to the spraying vehicle 11. In one embodiment of the present application, the spraying vehicle 11 is guided and moved along the circular track 6 to drive the tightening rope 2 to be gradually tightened, so that the moisturizing maintenance blanket 3 is attached to the bridge pier 1, so that the bridge pier 1 has a better maintenance effect.

[0067] A plurality of fixing rings 4 are arranged on the periphery of the moisturizing and curing blanket 3 along a spiral track; the tightening rope 2 passes through the plurality of fixing rings 4 arranged on the periphery of the moisturizing and curing blanket 3 in sequence.

[0068] In one embodiment of the present application, the fixing ring 4 on the moisture-retaining maintenance blanket 3 is arranged along a spiral trajectory, so that the tightening rope 2 can pass through multiple fixing rings 4 in sequence. Then, after the tightening rope 2 is gradually tightened, the moisture-retaining maintenance blanket 3 can be more evenly attached to the periphery of the pier 1.

[0069] The driving source 8 is a winch, one end of each of the plurality of lifting ropes 5 is connected to the rotation output end of the winch, and the winch drives the plurality of lifting ropes 5 to rise or fall synchronously.

[0070] The driving source 8 is a motor, and an I-shaped wheel is provided at the output end of the motor. One end of the plurality of lifting ropes 5 is fixed on the I-shaped wheel, and the I-shaped wheel is driven to rotate to drive the plurality of lifting ropes 5 to rise or fall synchronously.

[0071] The present application also provides a method for using the comprehensive maintenance device for high bridge piers 1. The method for using is the method for using the comprehensive maintenance device for high bridge piers 1 described above. The method for using includes:

[0072] Step 1, installing the maintenance device on the top of the pier 1;

[0073] Step 2, start the driving source 8 to drive the lifting rope 5 to descend, so that the moisturizing maintenance blanket 3 is wrapped around the periphery of the pier 1 after being completely lowered; so as to better avoid excessive evaporation of water during the maintenance process, thereby achieving better maintenance effect.

[0074] Step 3, start the spraying vehicle 11, guide the spraying vehicle 11 along the circular track 6, drive the water spraying pipe 12 to spray water evenly toward the outer surface of the pier 1; at the same time, the spraying vehicle 11 drives a part of the tightening rope 2 to be wound around the support frame 7, and the tightening rope 2 is gradually tightened, so that the moisturizing maintenance blanket 3 is closely attached to the outer periphery of the pier 1; in order to reduce the gap between the moisturizing maintenance blanket 3 and the pier 1, so as to achieve a better maintenance effect, in the process of gradually tightening the tightening rope 2, the water spraying pipe 12 synchronously sprays water evenly toward the outer surface of the pier 1 , so that the water flows gradually from the top of the pier 1 to the bottom of the pier 1; and after the tightening rope 2 is fully tightened, the part of the moisturizing maintenance blanket 3 where the tightening rope 2 is set is close to the pier 1. Since the tightening rope 2 is spirally set, after the moisturizing maintenance blanket 3 is tightened on the pier 1, a spiral gap channel is reserved between the moisturizing maintenance blanket 3 and the pier 1; at this time, the spraying vehicle 11 continues to spray, and the water will flow from the top of the pier 1 to the bottom of the pier 1 along the spiral gap channel, so that the pier 1 is evenly sprayed and maintained;

[0075] Step 4: After the spraying maintenance is completed, the spraying vehicle 11 returns to the starting position to loosen the tightening rope 2;

[0076] Step 5, start the driving source 8 again to drive the lifting rope 5 to rise, so that the moisturizing curing blanket 3 rises and folds back; so as to facilitate the transportation and reuse of the curing device;

[0077] Step 6, transport the maintenance device to the next pier 1 to be maintained, and repeat the above maintenance steps.

[0078] It should be understood that the above description is merely exemplary and the embodiments of the present application do not limit this.

[0079] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention are within the scope of protection of the pending claims of the present invention.

Claims

1. A high bridge pier comprehensive maintenance device, characterized in that: The maintenance device includes a spray system and a curtain system; The spray system comprises an annular track, which is arranged on the top of a support frame, and the support frame is detachably fixed on the top of the pier; A spray vehicle is guided and moved on the circular track, and a water spray pipe is arranged on the spray vehicle, and the water spray pipe sprays water toward the outer surface of the bridge pier; A water tank is provided on the bridge pier, and the water tank is connected to the water spray pipe on the spray vehicle through a telescopic hose, and the water tank is used to supply water to the water spray pipe through the telescopic hose; The curtain system includes a moisture-retaining maintenance blanket, which surrounds and wraps around the periphery of the bridge pier; The top of the moisturizing and curing blanket is fixed to the side of the supporting frame; The curtain system also includes a lifting mechanism, which is used to drive the moisturizing maintenance blanket to rise or fall. When the moisturizing maintenance blanket is completely fallen, the moisturizing maintenance blanket is completely wrapped around the periphery of the bridge pier.

2. The high bridge pier comprehensive maintenance device according to claim 1 is characterized in that: The moisture-retaining maintenance blanket comprises a plastic film on the outer layer and a water-absorbing layer on the inner layer. The water-absorbing layer is made of a water-absorbing material prepolymer implanted in a non-woven fabric.

3. The high bridge pier comprehensive maintenance device according to claim 2 is characterized in that: The moisturizing maintenance blanket is provided with a plurality of fixing rings, and the fixing rings are arranged on the outer surface of the moisturizing maintenance blanket; the side of the support frame is provided with a supporting rod extending outward, and the fixing ring on the top of the moisturizing maintenance blanket is fixed on the supporting rod.

4. The high bridge pier comprehensive maintenance device according to claim 3 is characterized in that: The lifting mechanism includes a driving source and a plurality of lifting ropes, and the plurality of lifting ropes are evenly distributed in the circumference of the moisturizing and curing blanket; One end of the lifting rope is fixed to the bottom of the moisturizing and curing blanket, and the other end is fixed to the rotation output end of the driving source.

5. The high bridge pier comprehensive maintenance device according to claim 4 is characterized in that: The lifting cord passes through a plurality of fixing rings arranged along one lifting cord in sequence.

6. The high bridge pier comprehensive maintenance device according to claim 4 is characterized in that: The maintenance device also includes a tightening rope, which is spirally wound around the periphery of the moisturizing maintenance blanket; One end of the tightening rope is fixed to the bottom of the moisturizing and curing blanket, and the other end of the tightening rope is fixed to the spraying vehicle.

7. The high bridge pier comprehensive maintenance device according to claim 6 is characterized in that: A plurality of the fixing rings are arranged on the periphery of the moisturizing and curing blanket along a spiral track; The tightening rope passes through a plurality of fixing rings arranged on the periphery of the moisture-retaining maintenance blanket in sequence.

8. The high bridge pier comprehensive maintenance device according to claim 4 is characterized in that: The driving source is a winch, one end of each of the plurality of lifting ropes is connected to the rotation output end of the winch, and the winch drives the plurality of lifting ropes to rise or fall synchronously.

9. The high bridge pier comprehensive maintenance device according to claim 4, characterized in that: The driving source is a motor, and an I-shaped wheel is arranged at the output end of the motor. One end of a plurality of lifting ropes is fixed on the I-shaped wheel, and the I-shaped wheel is driven to rotate to drive the plurality of lifting ropes to rise or fall synchronously.

10. A method for using a high bridge pier comprehensive maintenance device, characterized in that: The method of use is the method of use of the high bridge pier comprehensive maintenance device according to claim 7, and the method of use comprises: Step 1, installing the maintenance device on the top of the pier; Step 2, start the driving source to drive the lifting rope to descend, so that the moisturizing maintenance blanket is wrapped around the periphery of the bridge pier after being completely lowered; Step 3: Start the spray truck and guide it along the circular track to drive the water spray pipe to spray water evenly toward the outer surface of the pier. At the same time, the spray truck drives a part of the tightening rope to wrap around the support frame, and the tightening rope is gradually tightened to make the moisturizing maintenance blanket close to the outer periphery of the pier. Step 4: After the spraying maintenance is completed, the spraying vehicle returns to the starting position to loosen the tightening rope; Step 5, start the driving source again to drive the lifting rope to rise, so that the moisturizing curing blanket rises and folds back; so as to facilitate the transportation and reuse of the curing device; Step 6, transporting the maintenance device to the next pier to be maintained, and repeating the above maintenance steps.