Comprehensive pipeline construction management system based on BIM technology

Through the comprehensive pipeline construction management system based on BIM technology, the problem of difficulty in space conflict detection, construction monitoring and quality and safety control in traditional construction management is solved, dynamic management of the construction process and comprehensive quality and safety control are realized, and construction efficiency and quality are improved.

CN119863167AInactive Publication Date: 2025-04-22GUANGDONG CONSTR ENG DESIGN INST CO +1

Patent Information

Application Number
CN202411952347.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-27
Publication Date
2025-04-22
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Traditional pipeline construction management methods are difficult to carry out effective spatial conflict detection, construction process monitoring and quality and safety control, resulting in delays in construction progress, safety hazards, quality defects and cost overspending.

Method used

A comprehensive pipeline construction management system based on BIM technology is adopted, which includes BIM model creation module, pipeline construction planning module, real-time progress monitoring module, pipeline conflict detection and optimization module and quality and safety management module. Through the combination of these modules, dynamic management of the construction process and comprehensive quality and safety control are achieved.

Benefits of technology

The system can effectively avoid pipeline conflicts, optimize construction processes, improve construction efficiency and quality, reduce safety hazards and costs, and improve project management level.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119863167A_ABST
    Figure CN119863167A_ABST
Patent Text Reader

Abstract

The invention discloses a BIM technology-based comprehensive pipeline construction management system, which relates to the technical field of construction management and comprises a BIM model creation module, a pipeline construction planning module, a real-time progress monitoring module, a pipeline conflict detection and optimization module and a quality and safety management module. According to the comprehensive pipeline construction management system based on the BIM technology, multiple problems existing in traditional construction management can be effectively solved, through the functions of visual display, conflict detection and optimization, real-time progress monitoring, potential safety hazard inspection and the like of the BIM model, the system provides a comprehensive management tool for the construction process, and the construction efficiency is improved. The construction efficiency is improved, resource allocation is optimized, the construction quality and safety are greatly improved, finally, by means of the system, the overall management level of a project is remarkably improved, and the construction progress, quality and cost are more accurately and effectively controlled.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of construction management, and in particular to an integrated pipeline construction management system based on BIM technology. Background Art

[0002] With the continuous improvement of the construction efficiency and quality requirements of the construction industry, the traditional engineering management model can no longer meet the needs of modern projects. During the pipeline construction process, there are a series of problems such as pipeline conflicts, unreasonable construction sequence, and untimely scheduling of materials and personnel. These problems not only affect the construction progress, but may also lead to serious consequences such as safety hazards, quality defects and cost overruns. The traditional pipeline construction management method usually relies on two-dimensional design drawings, which makes it difficult to conduct effective spatial conflict detection, construction process monitoring and quality and safety control. Although there are some systems based on computer-aided design and project management software, these systems usually have single functions, cannot comprehensively consider various construction needs, and lack real-time progress and quality monitoring, and cannot effectively realize the dynamic management of the construction process. Summary of the invention

[0003] In order to solve the above technical problems, a comprehensive pipeline construction management system based on BIM technology is provided. This technical solution solves the above problems.

[0004] In order to achieve the above purpose, the technical solution adopted by the present invention is:

[0005] A comprehensive pipeline construction management system based on BIM technology, including:

[0006] BIM model creation module: obtain the design drawings of the engineering project, create a three-dimensional integrated pipeline model based on the design drawings, integrate different types of pipeline data, perform spatial layout and collision detection, and generate a BIM model by combining building information and construction information;

[0007] Pipeline construction planning module: The pipeline construction planning module is electrically connected to the BIM model creation module. The pipeline construction planning module is used to generate a detailed pipeline installation plan required in the construction process based on the BIM model, including construction sequence, material requirements and construction personnel scheduling information, so as to optimize the construction process;

[0008] Real-time progress monitoring module: The real-time progress monitoring module is electrically connected to the pipeline construction planning module. The real-time progress monitoring module is used to feed back the construction progress to the BIM model in real time based on the data interface of the on-site construction management system, dynamically update the construction status and perform visual display, and monitor the project progress and construction quality;

[0009] Pipeline conflict detection and optimization module: The pipeline conflict detection and optimization module is electrically connected to the real-time progress monitoring module. The pipeline conflict detection and optimization module is used to automatically detect the conflict between different pipeline systems, propose optimization solutions, and visualize them through the BIM model;

[0010] Quality and safety management module: The quality and safety management module is electrically connected to the pipeline conflict detection and optimization module. The quality and safety management module is used to combine the visualization function of the BIM model to conduct quality and safety hazard inspections on the construction site, record and feedback on on-site problems, and generate construction logs.

[0011] Preferably, the BIM model creation module specifically includes:

[0012] Design drawing data import unit: import design drawings of engineering projects from various sources, including CAD files, PDF drawings and traditional 2D design drawings;

[0013] Data format conversion and parsing unit: convert the format of the imported design drawings;

[0014] 3D modeling unit: Based on the building structure information in the design drawings, use BIM software to create a 3D geometric model of the building, including walls, floors, roofs, doors and windows, and convert different types of pipelines such as pipes, air ducts, power lines, and water supply and drainage pipes into a 3D integrated pipeline model according to the requirements in the design drawings;

[0015] Pipeline integration and spatial layout unit: classify and number various pipelines, and classify them according to the actual pipeline type and material, and carry out spatial layout of pipelines according to the actual situation of building space and structure;

[0016] Collision detection unit: Use the collision detection function of the BIM platform to automatically detect whether there are spatial conflicts between pipelines and between pipelines and building structures in the 3D integrated pipeline model;

[0017] Automatic identification and feedback unit: automatically identifies the conflicting locations and marks them in the BIM model;

[0018] Pipeline construction drawing generation unit: Based on the optimized three-dimensional integrated pipeline model, the system automatically generates pipeline construction drawings.

[0019] Preferably, the pipeline construction planning module specifically includes:

[0020] Construction task decomposition and pipeline element identification unit: extract all pipeline information from the BIM model, including the type, location, size, material, elevation and direction of the pipeline, identify the main pipeline system that needs to be installed, and the associated auxiliary components, and decompose the overall construction plan into different subtasks, including pipeline installation, equipment installation, welding, bracket installation, pipeline connection and pressure testing;

[0021] Construction sequence and logical relationship planning unit: Based on the spatial location of pipeline layout, construction period requirements and equipment installation requirements, determine the construction sequence of each pipeline installation, determine the dependency relationship between pipelines, plan the construction sequence through pipeline sequence information and node association information in the BIM model, and formulate a construction plan with the shortest construction period as the goal through the critical path optimization algorithm;

[0022] Material demand forecasting unit: automatically generates a material list based on the pipe type, material, size and quantity data in the BIM model, forecasts the procurement demand for each material based on the construction schedule, and schedules the procurement and distribution of materials in combination with the project schedule;

[0023] Construction personnel scheduling and resource optimization unit: Based on the specific tasks of pipeline construction, combined with the types of work and working hours required for each task, determine the number and allocation of construction personnel, arrange workers of different types of work, deploy personnel according to the progress and priority of construction tasks, calculate the working hours required for each task based on the workload, and arrange daily workload.

[0024] Preferably, the formulating of a reasonable construction plan by using the critical path optimization algorithm specifically includes:

[0025] Among them, the critical path method optimization algorithm formula is:

[0026]

[0027] Where M 总 The total time required for the entire project from start to finish, is the sum of the durations of the tasks on the critical path, i is the index of the task, m is 任 (i) represents the duration of the i-th task.

[0028] Preferably, the forecasting of procurement demand for various materials according to the construction schedule specifically includes:

[0029] According to the construction schedule, assuming that the project completes several tasks within a specified time period, the material demand within that time period is predicted, where the prediction formula is:

[0030]

[0031] In the formula, F j(t1, t2) is the demand for the jth type of material in the time period (t1, t2), n is the total number of construction tasks, h(i, t1, t2) is the construction volume of the i-th task completed in the time period (t1, t2), Q i Denotes the cost coefficient of the i-th task, D j represents the coefficient factor of the jth item, and n represents the total number of items involved in the calculation.

[0032] Preferably, the real-time progress monitoring module specifically includes:

[0033] Data collection and transmission unit: establish a data interface with the on-site construction management system to realize real-time data collection, obtain real-time construction progress data, and transmit the on-site data to the BIM model system in real time through the API;

[0034] BIM model dynamic update unit: dynamically updates the construction status in the BIM model according to real-time progress data, updates the quality information in the BIM model according to construction quality data, and displays the quality inspection results and defect information of each process;

[0035] 3D visualization display unit: visualize the construction progress through colors, icons and animations in the BIM model, and use the timeline function to display the changes in the construction progress;

[0036] Construction quality monitoring and feedback unit: dynamically updates the quality information in the BIM model based on the on-site quality inspection data, reflects the quality status in real time, displays the inspection results and problems of construction quality in the BIM model, and indicates areas with defects and areas that have not passed quality acceptance;

[0037] Automatic early warning and alarm mechanism unit: set thresholds for construction progress and quality monitoring. When progress lags behind or abnormal situations occur, the system automatically issues early warning notifications;

[0038] Progress analysis and report generation unit: compares planned progress with actual progress, generates progress deviation analysis reports, and provides an interactive user interface.

[0039] Preferably, the progress analysis and report generation unit specifically includes:

[0040] Compare the planned progress with the actual progress, generate progress deviation analysis reports, put forward optimization suggestions, analyze construction quality based on real-time monitoring data, identify quality problem areas, and provide quality analysis reports;

[0041] It provides an interactive user interface, through which project managers, engineers and other personnel can view the progress and quality status of the project in real time, and check through the interactive function of the BIM model. The interface displays the overall progress of the project, the status of each construction stage, the completion status of the process and the quality problem areas, and archives the real-time progress and quality data.

[0042] Preferably, the pipeline conflict detection and optimization module specifically includes:

[0043] Data integration and synchronization unit: synchronizes the data of the real-time progress monitoring module with the pipeline conflict detection module, dynamically updates the pipeline model based on real-time data, imports pipeline data, including water pipes, electrical pipes, and HVAC pipes, and integrates pipeline data through the 3D pipeline system in the BIM model;

[0044] Pipeline conflict detection unit: Use the conflict detection engine of the BIM platform to automatically detect spatial conflicts, collisions and interferences between different pipeline systems, analyze the geometric shape, size, path and installation location of the pipeline, identify potential conflict areas, set conflict detection rules and standards, including minimum spacing, minimum distance between pipelines and walls and beams, and adjust detection sensitivity and conflict judgment thresholds;

[0045] Conflict visualization and feedback unit: Visually display the detected conflicts in the BIM model in the form of colors, annotations and prompts, so that designers and construction personnel can view the conflict location and type, and automatically generate a conflict report, listing the conflict information, including the conflicting pipelines, conflict types, conflict locations and impact levels;

[0046] Optimization scheme proposal and simulation unit: automatically propose pipeline optimization schemes based on conflict detection results.

[0047] Preferably, the conflict visualization and feedback unit specifically includes:

[0048] The pipeline optimization plan includes adjusting the pipeline position, changing the pipeline path, modifying the pipeline specifications, and adjusting the installation sequence;

[0049] Simulate the effect of the optimization plan in the BIM platform, evaluate whether the optimized pipeline layout solves the conflict, and verify whether the optimization plan meets the construction progress, quality requirements and cost control requirements;

[0050] Evaluate the effect of the optimization plan and select the best one. The evaluation indicators include cost, construction period, technical feasibility, construction difficulty and impact on the existing system;

[0051] Connect with the construction progress to ensure that the optimization plan is compatible with the real-time construction progress, and dynamically update the construction drawings, pipeline design drawings and construction plans in the BIM model;

[0052] As the construction progresses, the pipeline installation process is continuously conflict-checked and optimized. When pipeline design changes occur on site, the change information is fed back to the BIM model, conflict detection is re-performed, and a new optimization plan is automatically generated.

[0053] Preferably, the quality and safety management module specifically includes:

[0054] Safety hazard detection and inspection unit: Based on the BIM model, safety hazard detection is carried out in combination with the actual situation of the construction site, including high-altitude operations, pipeline conflicts and physical interference, equipment safety and personnel safety. Hazard inspection tools are used, and the analysis tools of the BIM platform are used to perform collision detection, spatial interference detection and dangerous area identification, automatically identify potential safety hazards, assign priorities to each hazard, and classify them according to the severity of the hazards;

[0055] Problem feedback and report generation unit: record the quality and safety issues detected on site in the system, generate construction logs and provide feedback. The feedback includes problem description, location, priority and handling suggestions.

[0056] Compared with the prior art, the present invention has the following beneficial effects:

[0057] The present invention proposes an integrated pipeline construction management system based on BIM technology, which can effectively solve many problems existing in traditional construction management. Through the visualization of BIM models, conflict detection and optimization, real-time progress monitoring, and potential safety hazard inspection, the system provides a comprehensive management tool for the construction process, which not only improves construction efficiency and optimizes resource allocation, but also greatly improves construction quality and safety. Ultimately, with the help of this system, the overall management level of the project has been significantly improved, and the construction progress, quality, and cost have been more accurately and effectively controlled. BRIEF DESCRIPTION OF THE DRAWINGS

[0058] Figure 1 This is a schematic diagram of the architecture of an integrated pipeline construction management system based on BIM technology disclosed in an embodiment of the present invention. DETAILED DESCRIPTION

[0059] The following description is used to disclose the present invention so that those skilled in the art can implement the present invention. The preferred embodiments described below are only examples, and those skilled in the art may think of other obvious variations.

[0060] Reference Figure 1 As shown, a comprehensive pipeline construction management system based on BIM technology includes:

[0061] BIM model creation module:

[0062] Design drawing data import unit: import design drawings of engineering projects from various sources, including CAD files, PDF drawings and traditional 2D design drawings;

[0063] Data format conversion and parsing unit: convert the format of the imported design drawings;

[0064] 3D modeling unit: Based on the building structure information in the design drawings, use BIM software to create a 3D geometric model of the building, including walls, floors, roofs, doors and windows, and convert different types of pipelines such as pipes, air ducts, power lines, and water supply and drainage pipes into a 3D integrated pipeline model according to the requirements in the design drawings;

[0065] Pipeline integration and spatial layout unit: classify and number various pipelines, and classify them according to the actual pipeline type and material, and carry out spatial layout of pipelines according to the actual situation of building space and structure;

[0066] Collision detection unit: Use the collision detection function of the BIM platform to automatically detect whether there are spatial conflicts between pipelines and between pipelines and building structures in the 3D integrated pipeline model;

[0067] Automatic identification and feedback unit: automatically identifies the conflicting locations and marks them in the BIM model;

[0068] Pipeline construction drawing generation unit: Based on the optimized three-dimensional integrated pipeline model, the system automatically generates pipeline construction drawings.

[0069] Pipeline construction planning module:

[0070] Construction task decomposition and pipeline element identification unit: extract all pipeline information from the BIM model, including the type, location, size, material, elevation and direction of the pipeline, identify the main pipeline system that needs to be installed, and the associated auxiliary components, and decompose the overall construction plan into different subtasks, including pipeline installation, equipment installation, welding, bracket installation, pipeline connection and pressure testing;

[0071] Construction sequence and logical relationship planning unit: Based on the spatial location of pipeline layout, construction period requirements and equipment installation requirements, determine the construction sequence of each pipeline installation, determine the dependency relationship between pipelines, plan the construction sequence through pipeline sequence information and node association information in the BIM model, and formulate a construction plan with the shortest construction period as the goal through the critical path optimization algorithm;

[0072] Among them, the critical path method optimization algorithm formula is:

[0073]

[0074] Where M 总The total time required for the entire project from start to finish, is the sum of the durations of the tasks on the critical path, i is the index of the task, m is 任 (i) represents the duration of the i-th task;

[0075] Considering that the construction period is an important assessment indicator of the comprehensive pipeline construction project, the present invention also proposes another preferred optimization scheme to shorten the construction period.

[0076] Specifically, first determine whether the construction progress of the critical time node is lower than the preset threshold. If so, locate the critical pipeline nodes from the construction plan and dispatch additional personnel to install the critical pipeline nodes simultaneously. The above-mentioned critical time nodes refer to 50% of the pipeline material arrival time and / or construction period. The above-mentioned critical pipeline nodes refer to the construction of key nodes such as outlets, end wells, intersections, etc. The construction quality and progress of these key pipeline nodes are crucial to the success of the entire project. In turn, the construction progress of these key pipeline nodes will also affect the construction progress of other low-level nodes.

[0077] Material demand forecasting unit: automatically generates a material list based on the pipe type, material, size and quantity data in the BIM model, forecasts the procurement demand for each material based on the construction schedule, and schedules the procurement and distribution of materials in combination with the project schedule;

[0078] According to the construction schedule, assuming that the project completes several tasks within a specified time period, the material demand within that time period is predicted, where the prediction formula is:

[0079]

[0080] In the formula, F j (t1, t2) is the demand for the jth type of material in the time period (t1, t2), n is the total number of construction tasks, h(i, t1, t2) is the construction volume of the i-th task completed in the time period (t1, t2), Q i Denotes the cost coefficient of the i-th task, D j represents the coefficient factor of the jth item, and n represents the total number of items involved in the calculation;

[0081] Construction personnel scheduling and resource optimization unit: Based on the specific tasks of pipeline construction, combined with the types of work and working hours required for each task, determine the number and allocation of construction personnel, arrange workers of different types of work, deploy personnel according to the progress and priority of construction tasks, calculate the working hours required for each task based on the workload, and arrange daily workload.

[0082] Real-time progress monitoring module:

[0083] Data collection and transmission unit: establish a data interface with the on-site construction management system to realize real-time data collection, obtain real-time construction progress data, and transmit the on-site data to the BIM model system in real time through the API;

[0084] BIM model dynamic update unit: dynamically updates the construction status in the BIM model according to real-time progress data, updates the quality information in the BIM model according to construction quality data, and displays the quality inspection results and defect information of each process;

[0085] 3D visualization display unit: visualize the construction progress through colors, icons and animations in the BIM model, and use the timeline function to display the changes in the construction progress;

[0086] Construction quality monitoring and feedback unit: dynamically updates the quality information in the BIM model based on the on-site quality inspection data, reflects the quality status in real time, displays the inspection results and problems of construction quality in the BIM model, and indicates areas with defects and areas that have not passed quality acceptance;

[0087] Automatic early warning and alarm mechanism unit: set thresholds for construction progress and quality monitoring. When progress lags behind or abnormal situations occur, the system automatically issues early warning notifications;

[0088] Progress analysis and report generation unit: compares the planned progress with the actual progress, generates a progress deviation analysis report, provides an interactive user interface, compares the planned progress with the actual progress, generates a progress deviation analysis report, makes optimization suggestions, analyzes the construction quality based on real-time monitoring data, identifies quality problem areas, and provides quality analysis reports. It provides an interactive user interface, and project managers, engineers, and other personnel can view the progress and quality status of the project in real time, and conduct investigations through the interactive functions of the BIM model. The interface displays the overall progress of the project, the status of each construction stage, the completion status of the process, and the quality problem areas, and archives the real-time progress and quality data.

[0089] Pipeline conflict detection and optimization module:

[0090] Data integration and synchronization unit: synchronizes the data of the real-time progress monitoring module with the pipeline conflict detection module, dynamically updates the pipeline model based on real-time data, imports pipeline data, including water pipes, electrical pipes, and HVAC pipes, and integrates pipeline data through the 3D pipeline system in the BIM model;

[0091] Pipeline conflict detection unit: Use the conflict detection engine of the BIM platform to automatically detect spatial conflicts, collisions and interferences between different pipeline systems, analyze the geometric shape, size, path and installation location of the pipeline, identify potential conflict areas, set conflict detection rules and standards, including minimum spacing, minimum distance between pipelines and walls and beams, and adjust detection sensitivity and conflict judgment thresholds;

[0092] Conflict visualization and feedback unit: Visually display the detected conflicts in the BIM model in the form of colors, annotations and prompts, so that designers and construction personnel can view the conflict location and type, and automatically generate a conflict report, listing the conflict information, including the conflicting pipelines, conflict types, conflict locations and impact levels;

[0093] Optimization scheme proposal and simulation unit: Based on the conflict detection results, pipeline optimization schemes are automatically proposed. The pipeline optimization schemes include adjusting pipeline positions, changing pipeline paths, modifying pipeline specifications, and adjusting installation sequences. The effects of the optimization schemes are simulated in the BIM platform to evaluate whether the optimized pipeline layout resolves conflicts, verify whether the optimization schemes meet the construction progress, quality requirements, and cost control requirements, evaluate the effects of the optimization schemes, and select the best optimization schemes. The evaluation indicators include cost, construction period, technical feasibility, construction difficulty, and impact on existing systems. The optimization schemes are connected with the construction progress to ensure that the optimization schemes are compatible with the real-time construction progress. The construction drawings, pipeline design drawings, and construction plans are dynamically updated in the BIM model. As the construction progresses, the pipeline installation process is continuously conflict-detected and optimized. When pipeline design changes occur on site, the change information is fed back to the BIM model, conflict detection is performed again, and a new optimization scheme is automatically generated.

[0094] Quality and safety management module:

[0095] Safety hazard detection and inspection unit: Based on the BIM model, safety hazard detection is carried out in combination with the actual situation of the construction site, including high-altitude operations, pipeline conflicts and physical interference, equipment safety and personnel safety. Hazard inspection tools are used, and the analysis tools of the BIM platform are used to perform collision detection, spatial interference detection and dangerous area identification, automatically identify potential safety hazards, assign priorities to each hazard, and classify them according to the severity of the hazards;

[0096] Problem feedback and report generation unit: record the quality and safety issues detected on site in the system, generate construction logs and provide feedback. The feedback includes problem description, location, priority and handling suggestions.

[0097] In summary, the advantages of the present invention are:

[0098] BIM technology can realize visual management of the entire construction process, especially in the process of pipeline installation. The BIM model can clearly display the spatial location, size and material information of each pipeline, thereby helping the construction team to accurately plan the pipeline layout, avoid errors and omissions in construction, and improve the accuracy of construction;

[0099] Through the pipeline construction planning module of the integrated pipeline construction management system, the construction tasks can be decomposed and scheduled in detail, the construction sequence and resource allocation can be optimized, unnecessary construction processes and waste can be reduced, the rational use of materials and personnel resources can be ensured, and the construction costs can be minimized;

[0100] The real-time progress monitoring module, combined with the data interface of the on-site construction management system, can obtain construction progress information in real time, dynamically update the BIM model, and display the construction status and quality of each process. Through progress deviation analysis and quality monitoring feedback, the system can promptly identify possible progress delays or quality problems in the construction process, helping project managers to adjust the construction plan in a timely manner to avoid construction delays and quality problems.

[0101] The pipeline conflict detection and optimization module can automatically detect spatial conflicts between pipeline systems and between pipelines and building structures, and provide visual feedback through the BIM platform to provide designers and construction personnel with clear conflict locations and solutions. This module can not only perform conflict detection before construction to avoid later rework caused by design defects, but also adjust pipeline layout according to real-time progress during construction to ensure smooth pipeline installation;

[0102] The quality and safety management module uses the BIM model in combination with the actual situation of the construction site to conduct comprehensive safety hazard detection, and can generate construction logs to record on-site problems in a timely manner, helping the construction team to discover potential safety risks and quality problems. The automatic early warning and alarm mechanism can provide real-time prompts of possible safety hazards or quality defects during the construction process, avoiding accidents and ensuring the safety of construction personnel and construction quality.

[0103] The pipeline construction management system based on BIM technology can integrate various construction data and design drawings, and provide a unified platform for collaborative work among various departments. Project managers, designers, construction teams, material suppliers and other personnel can achieve real-time communication and collaboration by sharing BIM models, thereby improving the management efficiency of the entire project;

[0104] Through accurate planning and real-time monitoring of the pipeline construction process, different construction plans can be simulated in the BIM platform, and the cost, construction period, technical feasibility, etc. of each plan can be evaluated to help managers select the best construction plan. In addition, the system can automatically generate various reports and analysis reports to facilitate managers to fully control the progress, quality and cost of the project.

[0105] Based on the visualization function of the BIM model, the entire construction process will become more transparent. Each stage and each task of the project can be viewed and tracked in detail through the BIM system, and construction personnel and managers can monitor and adjust more efficiently. Through this transparent management, problems that arise during the construction process can be quickly discovered and solved in a timely manner, reducing the risks caused by information lag or poor communication.

[0106] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The above embodiments and descriptions only describe the principles of the present invention. The present invention may be subject to various changes and improvements without departing from the spirit and scope of the present invention. These changes and improvements fall within the scope of the present invention. The scope of protection claimed by the present invention is defined by the attached claims and their equivalents.

Claims

1. A comprehensive pipeline construction management system based on BIM technology, characterized in that: include: BIM model creation module: obtain the design drawings of the engineering project, create a three-dimensional integrated pipeline model based on the design drawings, integrate different types of pipeline data, perform spatial layout and collision detection, and generate a BIM model by combining building information and construction information; Pipeline construction planning module: The pipeline construction planning module is electrically connected to the BIM model creation module. The pipeline construction planning module is used to generate a detailed pipeline installation plan required in the construction process based on the BIM model, including construction sequence, material requirements and construction personnel scheduling information, so as to optimize the construction process; Real-time progress monitoring module: The real-time progress monitoring module is electrically connected to the pipeline construction planning module. The real-time progress monitoring module is used to feed back the construction progress to the BIM model in real time based on the data interface of the on-site construction management system, dynamically update the construction status and perform visual display, and monitor the project progress and construction quality; Pipeline conflict detection and optimization module: The pipeline conflict detection and optimization module is electrically connected to the real-time progress monitoring module. The pipeline conflict detection and optimization module is used to automatically detect the conflict between different pipeline systems, propose optimization solutions, and visualize them through the BIM model; Quality and safety management module: The quality and safety management module is electrically connected to the pipeline conflict detection and optimization module. The quality and safety management module is used to combine the visualization function of the BIM model to conduct quality and safety hazard inspections on the construction site, record and feedback on on-site problems, and generate construction logs.

2. According to claim 1, a comprehensive pipeline construction management system based on BIM technology is characterized in that: The BIM model creation module specifically includes: Design drawing data import unit: import design drawings of engineering projects from various sources, including CAD files, PDF drawings and traditional 2D design drawings; Data format conversion and parsing unit: convert the format of the imported design drawings; 3D modeling unit: Based on the building structure information in the design drawings, use BIM software to create a 3D geometric model of the building, including walls, floors, roofs, doors and windows, and convert different types of pipelines such as pipes, air ducts, power lines, and water supply and drainage pipes into a 3D integrated pipeline model according to the requirements in the design drawings; Pipeline integration and spatial layout unit: classify and number various pipelines, and classify them according to the actual pipeline type and material, and carry out spatial layout of pipelines according to the actual situation of building space and structure; Collision detection unit: Use the collision detection function of the BIM platform to automatically detect whether there are spatial conflicts between pipelines and between pipelines and building structures in the 3D integrated pipeline model; Automatic identification and feedback unit: automatically identifies the conflicting locations and marks them in the BIM model; Pipeline construction drawing generation unit: Based on the optimized three-dimensional integrated pipeline model, the system automatically generates pipeline construction drawings.

3. According to claim 2, a comprehensive pipeline construction management system based on BIM technology is characterized in that: The pipeline construction planning module specifically includes: Construction task decomposition and pipeline element identification unit: extract all pipeline information from the BIM model and decompose the overall construction plan into different subtasks; Construction sequence and logical relationship planning unit: Based on the spatial location of pipeline layout, construction period requirements and equipment installation requirements, determine the construction sequence of each pipeline installation, and formulate a reasonable construction plan through the critical path optimization algorithm; Material demand forecasting unit: automatically generates a material list based on the pipe type, material, size and quantity data in the BIM model, forecasts the procurement demand for each material based on the construction schedule, and schedules the procurement and distribution of materials in combination with the project schedule; Construction personnel scheduling and resource optimization unit: Based on the specific tasks of pipeline construction, combined with the types of work and working hours required for each task, determine the number and allocation of construction personnel, arrange workers of different types of work, deploy personnel according to the progress and priority of construction tasks, calculate the working hours required for each task based on the workload, and arrange daily workload.

4. The integrated pipeline construction management system based on BIM technology according to claim 3 is characterized in that: The construction plan with the shortest construction period as the goal is to formulate a construction plan through the critical path method optimization algorithm. include: Among them, the critical path method optimization algorithm formula is: Where M 总 The total time required for the entire project from start to finish, is the sum of the durations of the tasks on the critical path, i is the index of the task, m is 任 (i) represents the duration of the i-th task.

5. The integrated pipeline construction management system based on BIM technology according to claim 4 is characterized in that: According to the construction schedule, the forecast of procurement demand for various materials includes: According to the construction schedule, assuming that the project completes several tasks within a specified time period, the material demand within that time period is predicted, where the prediction formula is: In the formula, F j (t1, t2) is the demand for the jth type of material in the time period (t1, t2), n is the total number of construction tasks involved, h(i, t1, t 2) is the construction volume of the ith task completed in the time period (t1, t2), Q i Denotes the cost coefficient of the i-th task, D j represents the coefficient factor of the jth item, and n represents the total number of items involved in the calculation.

6. The integrated pipeline construction management system based on BIM technology according to claim 5 is characterized in that: The real-time progress monitoring module specifically includes: Data collection and transmission unit: establish a data interface with the on-site construction management system to realize real-time data collection, obtain real-time construction progress data, and transmit the on-site data to the BIM model system in real time through the API; BIM model dynamic update unit: dynamically updates the construction status in the BIM model according to real-time progress data, updates the quality information in the BIM model according to construction quality data, and displays the quality inspection results and defect information of each process; 3D visualization display unit: visualize the construction progress through colors, icons and animations in the BIM model, and use the timeline function to display the changes in the construction progress; Construction quality monitoring and feedback unit: dynamically updates the quality information in the BIM model based on the on-site quality inspection data, reflects the quality status in real time, displays the inspection results and problems of construction quality in the BIM model, and indicates areas with defects and areas that have not passed quality acceptance; Automatic early warning and alarm mechanism unit: set thresholds for construction progress and quality monitoring. When progress lags behind or abnormal situations occur, the system automatically issues early warning notifications; Progress analysis and report generation unit: compares planned progress with actual progress, generates progress deviation analysis reports, and provides an interactive user interface.

7. The integrated pipeline construction management system based on BIM technology according to claim 6 is characterized in that: The progress analysis and report generation unit specifically includes: Compare the planned progress with the actual progress, generate progress deviation analysis reports, put forward optimization suggestions, analyze construction quality based on real-time monitoring data, identify quality problem areas, and provide quality analysis reports; Provides an interactive user interface and archives real-time progress and quality data.

8. The integrated pipeline construction management system based on BIM technology according to claim 7 is characterized in that: The pipeline conflict detection and optimization module specifically includes: Data integration and synchronization unit: synchronizes the data of the real-time progress monitoring module with the pipeline conflict detection module, dynamically updates the pipeline model based on real-time data, imports pipeline data, including water pipes, electrical pipes, and HVAC pipes, and integrates pipeline data through the 3D pipeline system in the BIM model; Pipeline conflict detection unit: Use the conflict detection engine of the BIM platform to automatically detect spatial conflicts, collisions and interferences between different pipeline systems, analyze the geometric shape, size, path and installation location of the pipeline, identify potential conflict areas, set conflict detection rules and standards, including minimum spacing, minimum distance between pipelines and walls and beams, and adjust detection sensitivity and conflict judgment thresholds; Conflict visualization and feedback unit: Visually display the detected conflicts in the BIM model in the form of colors, annotations and prompts, so that designers and construction personnel can view the conflict location and type, and automatically generate a conflict report, listing the conflict information, including the conflicting pipelines, conflict types, conflict locations and impact levels; Optimization scheme proposal and simulation unit: automatically propose pipeline optimization schemes based on conflict detection results.

9. The integrated pipeline construction management system based on BIM technology according to claim 8 is characterized in that: The conflict visualization and feedback unit specifically includes: The pipeline optimization plan includes adjusting the pipeline position, changing the pipeline path, modifying the pipeline specifications, and adjusting the installation sequence; Simulate the effect of the optimization plan in the BIM platform, evaluate whether the optimized pipeline layout solves the conflict, and verify whether the optimization plan meets the construction progress, quality requirements and cost control requirements; Evaluate the effect of the optimization plan and select the best one. The evaluation indicators include cost, construction period, technical feasibility, construction difficulty and impact on the existing system; Connect with the construction progress to ensure that the optimization plan is compatible with the real-time construction progress, and dynamically update the construction drawings, pipeline design drawings and construction plans in the BIM model; As the construction progresses, the pipeline installation process is continuously conflict-checked and optimized. When pipeline design changes occur on site, the change information is fed back to the BIM model, conflict detection is re-performed, and a new optimization plan is automatically generated.

10. The integrated pipeline construction management system based on BIM technology according to claim 9 is characterized in that: The quality and safety management module specifically includes: Safety hazard detection and inspection unit: Based on the BIM model, safety hazard detection is carried out in combination with the actual situation of the construction site. Hazard inspection tools are used, and the analysis tools of the BIM platform are used to perform collision detection, spatial interference detection and dangerous area identification, automatically identify potential safety hazards, assign priorities to each hazard, and classify them according to the severity of the hazards; Problem feedback and report generation unit: record the quality and safety issues detected on site in the system, generate construction logs and provide feedback. The feedback includes problem description, location, priority and handling suggestions.

Citation Information

Patent Citations

  • BIMbased metro construction method

    CN106202723A

  • Bridge construction organization method based on three-dimensional digital technology

    CN116596483A

  • Building engineering construction optimization system based on BIM

    CN117421808A

  • BIM-based building construction management system and method

    CN118536716A

  • Engineering project construction process control system supported by BIM

    CN118644059A

Cited By

  • Construction optimization method and system based on BIM model

    CN120197910A

  • Resource allocation optimization method and system for gas pipeline refitting construction project

    CN120387798A

  • A method and system for optimizing resource allocation in gas pipeline modification construction projects

    CN120387798B

  • Electromechanical pipeline conflict detection and adjustment method and system based on BIM model

    CN120781430A

  • Municipal road construction method and system based on BIM

    CN120930236A