Waterproof structure for deformation joint of top plate
By setting telescopic brackets, sealing components, elastic base plates and installation components in the waterproof structure of the deformation joint, the secondary processing needs caused by construction errors are solved, the construction cycle is shortened and the sealing effect is improved.
Patent Information
- Application Number
- CN202510388479.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-31
- Publication Date
- 2025-04-25
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
During the construction process, the existing deformed joint waterproof structures require secondary processing due to construction errors, resulting in a long construction cycle.
By setting up telescopic brackets, sealing components, elastic base plates and mounting components, flexible adjustment and sealing between the abutment plates and the main body are achieved, reducing the need for secondary processing.
The construction cycle of the deformed joint waterproof structure is shortened, the sealing effect between the abutment plate and the main body is improved, and the performance loss of the elastic base plate in use is reduced.
Smart Images

Figure CN119877729A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of building construction, and in particular to a waterproof structure of a top plate deformation joint. Background Art
[0002] At present, buildings often deform under the influence of external factors, resulting in cracks or even damage. The structural joints reserved for this situation are called deformation joints. Deformation joints are often reserved during the construction process. Deformation joints can absorb or buffer the stress caused by factors such as temperature difference, settlement and vibration, and reduce the deformation and cracking of buildings. The setting of deformation joints must meet the dual requirements of conforming to the deformation of the structure and sealing and waterproofing. According to different design concepts, deformation joints are divided into three types: expansion joints, settlement joints and seismic joints.
[0003] There are many existing methods for dealing with expansion joints. In most designs and constructions, waterstops are often embedded or finished expansion joint waterproof structures are used. After the embedded waterstop is constructed, the rubber waterstop is prone to lose its waterproof function due to excessive shear or axial deformation, poor protection, long-term use and aging, and because most cases are embedded in advance during construction and cannot be replaced, there is a lack of effective repair methods in the later stage; therefore, finished expansion joint waterproof structures are gradually widely used. Finished expansion joint waterproof structures are usually directly installed in the expansion joints, and can be replaced in time if they are damaged.
[0004] The above-mentioned existing technical solutions have the following defects: the finished expansion joint cover plates basically have fixed specifications, and due to construction errors during the construction of the expansion joints, the expansion joint structures of fixed specifications need to be processed twice before they can be used at the construction site, which prolongs the construction period of the expansion joint waterproof structure. Summary of the invention
[0005] In order to shorten the construction period of the deformation joint waterproof structure, the present application provides a top plate deformation joint waterproof structure.
[0006] The above technical objectives of this application are achieved through the following technical solutions: The top plate deformation joint waterproof structure comprises an abutment plate, a telescopic bracket and a cover arranged between the main bodies on both sides of the deformation joint, two abutment plates are arranged, the two abutment plates are respectively abutted with the main bodies on both sides of the deformation joint, the telescopic bracket is arranged between the two abutment plates, the telescopic bracket is used to push the two abutment plates to abut with the two main bodies respectively, the cover is arranged at the top end of the abutment plate, the cover is fixedly connected to the abutment plate, and the cover is used to cover the top end of the deformation joint; The telescopic bracket includes an upper plate, a lower plate, a connecting rod and an adjusting bolt. The upper plate and the lower plate are arranged in parallel. A plurality of connecting rods are provided. The plurality of connecting rods are divided into two groups. Two ends of one group of connecting rods are respectively hinged to the abutment plate and the upper plate, and two ends of the other group of connecting rods are respectively hinged to the abutment plate and the lower plate. One end of the adjusting bolt passes through the upper plate and is threadedly connected to the lower plate. The adjusting bolt is used to adjust the distance between the upper plate and the lower plate.
[0007] Furthermore, a sealing assembly is provided between the abutment plate and the main body, the sealing assembly comprising a sealing block and a sealing groove, the sealing groove is fixedly connected to the side wall of the main body, the sealing block is fixedly connected to the abutment plate, and the sealing block is plug-fitted to the sealing groove.
[0008] Furthermore, a groove is provided on one side of the sealing block far from the abutting plate, and an expansion rubber strip is fixedly connected in the groove. The expansion rubber strip is used to expand and close the gap between the sealing groove and the sealing block after encountering water.
[0009] Furthermore, a sealing gasket is provided between the abutment plate and the main body, the sealing gasket is fixedly connected to the abutment plate, and the sealing gasket is used to seal the gap between the abutment plate and the main body.
[0010] Furthermore, an edge sealing plate is also provided at the top end of the abutting plate, the edge sealing plate is fixedly connected to the abutting plate, and the edge sealing plate abuts against the top end of the main body.
[0011] Furthermore, an elastic bottom plate is arranged between the two abutment plates, and the two ends of the elastic bottom plate are respectively fixedly connected to the two abutment plates. The elastic bottom plate is used to adapt to the movement between the two abutment plates. The two abutment plates are filled with polyurea grouting liquid, and the elastic bottom plate is used to support the polyurea grouting liquid.
[0012] Furthermore, an installation component is arranged between the elastic bottom plate and the abutment plate, and the installation component includes an installation groove, a clamping plate and a clamping bolt. An installation groove is opened on the opposite side of the two abutment plates, and a clamping plate is arranged in each installation groove. The clamping plate is slidably connected to the installation groove, and the clamping bolt passes through the side wall of the installation groove and is rotatably connected to the clamping plate. The clamping bolt is threadedly connected to the side wall of the installation groove, and the elastic bottom plate is inserted into the installation groove, and the elastic bottom plate is located on the side of the clamping plate away from the clamping bolt.
[0013] Furthermore, a support plate is provided between the cover and the abutment plate, one end of the support plate is fixedly connected to the abutment plate, and the other end abuts against the cover, and the cover is provided with a fixing bolt, which passes through the cover and is fixedly threadedly connected to the support plate.
[0014] Furthermore, a waterproof roll is laid on the top of the cover, and the waterproof roll is used to seal the gap between the fixing bolt and the cover.
[0015] Furthermore, a drainage plate is arranged at the bottom end of the cover, the drainage plate is fixedly connected to the cover, and structural adhesive is arranged between the waterproof material of the drainage plate body, and the structural adhesive is used to fill the gap between the drainage plate and the body.
[0016] In summary, this application has the following technical effects: By setting a telescopic bracket, the distance between the two abutment plates can be adjusted. Then, the distance between the two abutment plates can be adjusted at the construction site according to the actual width of the deformation joint after construction, so that both abutment plates abut against the main body, and it is no longer necessary to spend energy on secondary processing of the waterproof structure, thereby achieving the purpose of shortening the construction period of the deformation joint waterproof structure; By providing a sealing component, the sealing component is used to seal the gap between the abutment plate and the main body, thereby improving the sealing effect between the abutment plate and the main body; By setting up an elastic base plate and a mounting assembly, the elastic base plate can adapt to the change in the distance between the two abutting plates, and can select an elastic base plate of appropriate width according to the change range between the deformation joints, thereby avoiding excessive stretching of the elastic base plate, thereby reducing the performance of the elastic base plate when in use. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a structural schematic diagram of the top plate deformation joint waterproof structure of the present application; Figure 2 It is a structural schematic diagram of the telescopic bracket of the present application; Figure 3 yes Figure 2 A partial enlarged schematic diagram of part A; Figure 4 It is a schematic diagram showing the structure of fixing bolts and support plates without showing the waterproof membrane; Figure 5 yes Figure 4 A partial enlarged schematic diagram of part B.
[0018] In the figure, 1. abutment plate; 2. telescopic bracket; 21. upper plate; 22. lower plate; 23. connecting rod; 24. adjusting bolt; 3. cover; 4. sealing assembly; 41. sealing groove; 42. sealing block; 43. expansion rubber strip; 44. sealing gasket; 5. edge sealing plate; 6. elastic bottom plate; 7. installation assembly; 71. installation groove; 72. clamping plate; 73. clamping bolt; 8. support plate; 81. fixing bolt; 9. drainage plate; 91. structural adhesive; 10. waterproof membrane; 20. main body. DETAILED DESCRIPTION
[0019] The present application is further described in detail below in conjunction with the accompanying drawings.
[0020] Reference Figure 1 and Figure 2The waterproof structure of the top plate deformation joint provided in this embodiment includes an abutment plate 1, a telescopic bracket 2 and a cover 3 arranged between the main bodies 20 on both sides of the deformation joint. Two abutment plates 1 are provided, and the two abutment plates 1 are respectively abutted with the main bodies 20 on both sides of the deformation joint. The telescopic bracket 2 is arranged between the two abutment plates 1. The telescopic bracket 2 is used to push the two abutment plates 1 to abut with the two main bodies 20 respectively. The cover 3 is arranged at the top end of the abutment plate 1. The cover 3 is fixedly connected to the abutment plate 1, and the cover 3 is used to cover the top end of the deformation joint; the telescopic bracket 2 includes an upper plate 21, a lower plate 22, a connecting rod 23 and an adjusting bolt 24, the upper plate 21 and the lower plate 22 are arranged in parallel, and a plurality of connecting rods 23 are arranged, and the plurality of connecting rods 23 are divided into two groups, one group of connecting rods 23 is evenly distributed on both sides of the upper plate 21, and the two ends of the connecting rods 23 are respectively hinged to the abutting plate 1 and the upper plate 21, and the other group of connecting rods 23 is evenly distributed on both sides of the lower plate 22, and the two ends of the connecting rods 23 are respectively hinged to the abutting plate 1 and the lower plate 22, one end of the adjusting bolt 24 passes through the upper plate 21 and is threadedly connected to the lower plate 22, the adjusting bolt 24 is rotatably connected to the upper plate 21, and the adjusting bolt 24 is used to adjust the distance between the upper plate 21 and the lower plate 22.
[0021] Reference Figure 2 and Figure 3 A sealing assembly 4 is provided between the abutment plate 1 and the main body 20. The sealing assembly 4 includes a sealing block 42 and a sealing groove 41. The sealing groove 41 is fixedly connected to the side wall of the main body 20. In this embodiment, considering that the general distance of the deformation joint is small, the sealing groove 41 is pre-buried in the main body 20 of the deformation joint in advance, so that the sealing groove 41 is fixed in the main body 20 together with the concrete. The sealing block 42 is fixedly connected to the abutment plate 1, and the sealing block 42 is plugged into the sealing groove 41; a groove is provided on one side of the sealing block 42 far from the abutment plate 1, and an expansion joint is fixedly connected in the groove. The rubber strip 43 is used for expanding and sealing the gap between the sealing groove 41 and the sealing block 42 after it comes into contact with water; a sealing gasket 44 is provided between the abutment plate 1 and the main body 20, and the sealing gasket 44 is fixedly connected to the abutment plate 1. The sealing gasket 44 is used to seal the gap between the abutment plate 1 and the main body 20. In this embodiment, the sealing gasket 44 is divided into several parts by the sealing block 42, that is, the sealing gasket 44 is also provided between adjacent sealing blocks 42; a side sealing plate 5 is also provided at the top end of the abutment plate 1, and the side sealing plate 5 is fixedly connected to the abutment plate 1, and the side sealing plate 5 abuts against the top end of the main body 20.
[0022] Reference Figure 4 and Figure 5An elastic bottom plate 6 is arranged between the two abutment plates 1, and the two ends of the elastic bottom plate 6 are respectively fixedly connected to the two abutment plates 1. The elastic bottom plate 6 is used to adapt to the movement between the two abutment plates 1. The two abutment plates 1 are filled with polyurea grouting liquid, and the elastic bottom plate 6 is used to support the polyurea grouting liquid; a mounting assembly 7 is arranged between the elastic bottom plate 6 and the abutment plate 1, and the mounting assembly 7 includes a mounting groove 71, a clamping plate 72 and a clamping bolt 73. An mounting groove 71 is opened on the opposite side of the two abutment plates 1, and a clamping plate 72 is arranged in each mounting groove 71. The clamping plate 72 is slidably connected with the mounting groove 71, and the clamping bolt 73 passes through the side wall of the mounting groove 71 and is rotatably connected with the clamping plate 72. The clamping bolt 73 is threadedly connected with the side wall of the mounting groove 71, and the elastic bottom plate 6 is inserted in the mounting groove 71, and the elastic bottom plate 6 is located on the side of the clamping plate 72 away from the clamping bolt 73.
[0023] Reference Figure 2 and Figure 4 A support plate 8 is arranged between the cover 3 and the abutment plate 1, one end of the support plate 8 is fixedly connected to the abutment plate 1, and the other end abuts against the cover 3, and a fixing bolt 81 is arranged on the cover 3, and the fixing bolt 81 passes through the cover 3 and is fixedly threadedly connected with the support plate 8; a waterproof coiled material 10 is laid on the top of the cover 3, and the waterproof coiled material 10 is used to seal the gap between the fixing bolt 81 and the cover 3; a drain plate 9 is arranged at the bottom end of the cover 3, and the drain plate 9 is fixedly connected to the cover 3, and a structural adhesive 91 is arranged between the waterproof material of the main body 20 of the drain plate 9, and the structural adhesive 91 is used to fill the gap between the drain plate 9 and the main body 20.
[0024] The implementation principle of the deformation joint waterproof structure of the top plate of the embodiment of the present application is as follows: when using the deformation joint waterproof structure, first select an elastic bottom plate 6 of a suitable width according to the width of the deformation joint at the construction site, insert the elastic bottom plate 6 between the clamping plate 72 and the side wall of the installation groove 71, and then rotate the clamping bolt 73 to push the clamping plate 72 to slide in the installation groove 71, and the clamping plate 72 and the side wall of the installation groove 71 jointly clamp the elastic bottom plate 6 to fix the elastic bottom plate 6 in the installation groove 71; then move the abutment plate 1 into the deformation joint, and then rotate the adjusting bolt 24 to drive the upper plate 21 and the lower plate 22 to approach each other, so that the upper plate 21 and the lower plate 22 simultaneously drive the support rod to rotate, so that the support rod pushes the two abutment plates 1 away from each other, and the abutment plate 1 drives the sealing block 42 to be inserted into the sealing groove 41, and at the same time uses the expansion rubber strip 43 to close the gap between the sealing block 42 and the sealing groove 41. When the sealing block 42 is inserted into the sealing groove 41, the abutment plate 1 drives the sealing gasket 44 to abut the side wall of the main body 20; at this time, the polyurea grouting liquid is injected between the two abutment plates 1, so that after the polyurea grouting liquid solidifies, the cover 3 is moved to the top of the support plate 8, and the fixing bolts 81 are passed through the cover 3 and threadedly connected with the support plate 8, so that the position of the cover 3 and the abutment plate 1 is fixed. At this time, the drainage plate 9 is located on the side wall of the main body 20, and the gap between the drainage plate 9 and the main body 20 is sealed with structural adhesive 91. The distance between the two abutment plates 1 can be adjusted by setting the telescopic bracket 2, and then the distance between the two abutment plates 1 can be adjusted at the construction site according to the actual width of the deformation joint after construction, so that the two abutment plates 1 are both abutted with the main body 20, and it is no longer necessary to spend energy on secondary processing of the waterproof structure, thereby achieving the purpose of shortening the construction period of the deformation joint waterproof structure.
[0025] This specific embodiment is merely an explanation of the present application and is not a limitation of the present application. After reading this specification, those skilled in the art may make modifications to the present embodiment without any creative contribution as needed, but such modifications are protected by the patent law as long as they are within the scope of the claims of the present application.
Claims
1. The waterproof structure of the top plate deformation joint is characterized by: The invention comprises an abutment plate (1), a telescopic bracket (2) and a cover (3) arranged between the main bodies (20) on both sides of the deformation joint, wherein two abutment plates (1) are arranged, and the two abutment plates (1) are respectively abutted against the main bodies (20) on both sides of the deformation joint, the telescopic bracket (2) is arranged between the two abutment plates (1), and the telescopic bracket (2) is used to push the two abutment plates (1) to respectively abut against the two main bodies (20), and the cover (3) is arranged at the top end of the abutment plate (1), and the cover (3) is fixedly connected to the abutment plate (1), and the cover (3) is used to cover the top end of the deformation joint; The telescopic bracket (2) comprises an upper plate (21), a lower plate (22), a connecting rod (23) and an adjusting bolt (24); the upper plate (21) and the lower plate (22) are arranged in parallel; a plurality of connecting rods (23) are arranged; the plurality of connecting rods (23) are divided into two groups; two ends of one group of connecting rods (23) are respectively hinged to the abutting plate (1) and the upper plate (21); two ends of the other group of connecting rods (23) are respectively hinged to the abutting plate (1) and the lower plate (22); one end of the adjusting bolt (24) passes through the upper plate (21) and is threadedly connected to the lower plate (22); the adjusting bolt (24) is used to adjust the distance between the upper plate (21) and the lower plate (22).
2. The waterproof structure of top plate deformation joint according to claim 1, characterized in that: A sealing assembly (4) is provided between the abutment plate (1) and the main body (20), the sealing assembly (4) comprising a sealing block (42) and a sealing groove (41), the sealing groove (41) being fixedly connected to the main body (20), the sealing block (42) being fixedly connected to the abutment plate (1), and the sealing block (42) and the sealing groove (41) being plug-fitted.
3. The waterproof structure of top plate deformation joint according to claim 2, characterized in that: The sealing block (42) is provided with a groove on one side far from the contact plate (1), and an expansion rubber strip (43) is fixedly connected in the groove. The expansion rubber strip (43) is used to expand and seal the gap between the sealing groove (41) and the sealing block (42) when it encounters water.
4. The roof expansion joint waterproof structure according to claim 2, characterized in that: A sealing gasket (44) is provided between the abutment plate (1) and the main body (20); the sealing gasket (44) is fixedly connected to the abutment plate (1); and the sealing gasket (44) is used to seal the gap between the abutment plate (1) and the main body (20).
5. The waterproof structure of top plate deformation joint according to claim 4, characterized in that: The top end of the abutment plate (1) is also provided with an edge sealing plate (5), the edge sealing plate (5) is fixedly connected to the abutment plate (1), and the edge sealing plate (5) abuts against the top end of the main body (20).
6. The roof expansion joint waterproof structure according to claim 1, characterized in that: An elastic bottom plate (6) is provided between the two abutment plates (1), the two ends of the elastic bottom plate (6) are respectively fixedly connected to the two abutment plates (1), the elastic bottom plate (6) is used to adapt to the movement between the two abutment plates (1), the space between the two abutment plates (1) is filled with polyurea grouting liquid, and the elastic bottom plate (6) is used to support the polyurea grouting liquid.
7. The roof expansion joint waterproof structure according to claim 6, characterized in that: A mounting assembly (7) is provided between the elastic bottom plate (6) and the abutment plate (1), and the mounting assembly (7) comprises a mounting groove (71), a clamping plate (72) and a clamping bolt (73). An mounting groove (71) is provided on one side opposite to the two abutment plates (1), and a clamping plate (72) is provided in each mounting groove (71). The clamping plate (72) is slidably connected to the mounting groove (71), and the clamping bolt (73) passes through the side wall of the mounting groove (71) and is rotatably connected to the clamping plate (72). The clamping bolt (73) is threadedly connected to the side wall of the mounting groove (71), and the elastic bottom plate (6) is inserted into the mounting groove (71). The elastic bottom plate (6) is located on the side of the clamping plate (72) away from the clamping bolt (73).
8. The waterproof structure of top plate deformation joint according to claim 1, characterized in that: A support plate (8) is provided between the sealing cover (3) and the abutment plate (1); one end of the support plate (8) is fixedly connected to the abutment plate (1) and the other end abuts against the sealing cover (3); the sealing cover (3) is provided with a fixing bolt (81) which passes through the sealing cover (3) and is fixedly threadedly connected to the support plate (8).
9. The waterproof structure of top plate deformation joint according to claim 8, characterized in that: A waterproof coiled material (10) is laid on the top of the sealing cover (3), and the waterproof coiled material (10) is used to seal the gap between the fixing bolt (81) and the sealing cover (3).
10. The roof expansion joint waterproof structure according to claim 9, characterized in that: A drainage plate (9) is arranged at the bottom end of the cover (3), the drainage plate (9) is fixedly connected to the cover (3), and a structural adhesive (91) is arranged between the waterproof material of the drainage plate (9) and the main body (20), and the structural adhesive (91) is used to fill the gap between the drainage plate (9) and the main body (20).
Citation Information
Patent Citations
Deformation joint sealing waterproof structure and construction method thereof
CN113216423A
Building expansion joint waterproof structure
CN214402217U
Building deformation joint structure
CN215594438U
Deformation joint structure of house building
CN216689826U
Waterproof structure of expansion joint
CN218346445U