Drilling device and method for rock and soil construction reconnaissance

By designing adjustable fixed components and hydraulic cylinder system, the shaking and inclination problems of drilling equipment for geotechnical construction surveys when used in potholes and slopes is solved, and the stability and accuracy of drilling surveys are achieved.

CN119878022AActive Publication Date: 2025-04-25BEIJING INST OF GEOLOGY & MINERAL EXPLORATION +1
View PDF 12 Cites 0 Cited by

Patent Information

Application Number
CN202510346740.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-03-24
Publication Date
2025-04-25
Estimated Expiration
2045-03-24

AI Technical Summary

Technical Problem

When used in potholes and slopes, existing drilling devices for geotechnical construction surveys are prone to shaking and inclination, resulting in skewed drill rods, affecting the quality of exploration holes and the accuracy of survey results.

Method used

A drilling device for geotechnical construction survey is designed, using adjustable fixing components, including a third screw, connecting shell, slider and anchor nails. The stable fixing and horizontal adjustment of the device is achieved through the adjustment head and hydraulic cylinder to ensure the correct position and stability of the drilling components.

Benefits of technology

It effectively avoids the shake and inclination of the device when used in potholes and slopes, ensures the stability and accuracy of drilling surveys, and improves the quality of survey results.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119878022A_ABST
    Figure CN119878022A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of rock mass engineering investigation, in particular to a drilling device and method for rock and soil construction investigation, the drilling device comprises a support frame, a connecting frame is arranged at the top of the support frame, a first moving frame is arranged on the connecting frame, a drilling assembly is arranged at the bottom of the first moving frame, and a fixing assembly is arranged on the support frame. The device has the beneficial effects that when the position needing drilling exploration is located on the side slope, different fixing assemblies can be adjusted according to the inclination angle of the side slope, so that the levelness of the supporting frame is guaranteed, deflection during drilling exploration is avoided, the quality of exploration drilling holes is guaranteed, and the accuracy of exploration results is guaranteed; when there are many pits in the position needing to be drilled and explored, it can be ensured that anchoring nails in different positions can be inserted into all positions of the ground with uneven horizontal heights to fix the device, and therefore the device is prevented from shaking or inclining, the stability of the device during drilling and exploration is ensured, and the drilling and exploration effect is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of rock mass engineering investigation, and in particular to a drilling device and method for rock and soil construction investigation. Background Art

[0002] Geotechnical engineering is about solving rock and soil engineering problems, including foundations, slopes and underground engineering. Geotechnical engineering surveys often require drilling to obtain geological information.

[0003] Rock exploration is the process of detailed investigation and analysis of underground rocks to obtain information about the properties, composition, structure and characteristics of the rocks. Key technologies include drilling technology, geophysical exploration, etc. The main features of these technologies and methods include: Drilling technology: By drilling underground, rock samples are obtained for laboratory analysis to understand the physical properties, chemical composition and pore characteristics of the rocks; Geophysical exploration: By measuring underground physical field parameters such as seismic wave propagation speed, electromagnetic field changes, gravity and magnetic field characteristics, etc., the properties and structure of the rocks can be inferred; In summary, the comprehensive application of rock exploration technologies and methods can provide comprehensive rock information and provide important basis for geological research, mineral resource exploration, engineering construction and environmental assessment.

[0004] A drilling device and drilling process for geotechnical engineering investigation disclosed in Chinese patent CN112324355A, wherein the drilling device includes a frame, a drill rod and a plurality of legs, the drill rod and the legs are connected to the frame for lifting and lowering, a first driving member for driving the drill rod to rotate is connected to the frame, and a linkage mechanism for driving the legs to lift and lower is also connected to the frame.

[0005] However, compared with the prior art and the comparative scheme, it can be seen that the drilling device still has the following problems during actual use: When there are many potholes on the rock surface where the device is placed, the device will shake and tilt. When the part that needs to be drilled for exploration is located in a non-horizontal position such as a slope, it is not convenient to adjust the drilling device horizontally, which can easily lead to the drill rod being skewed. The skewed drill rod can easily lead to poor drilling quality of the exploration hole, which can ultimately affect the accuracy of the exploration results. Summary of the invention

[0006] The purpose of the present invention is to provide a drilling device and method for geotechnical construction investigation in order to solve the above-mentioned problems.

[0007] The present invention achieves the above-mentioned purpose through the following technical solutions: A drilling device for geotechnical construction survey comprises a support frame, a connecting frame is arranged on the top of the support frame, a first moving frame is arranged on the connecting frame, a drilling assembly is arranged at the bottom of the first moving frame, and a fixing assembly is arranged on the support frame; The fixing assembly includes a third screw, an adjusting head is provided at one end of the third screw, an end of the third screw away from the adjusting head is rotatably connected to a connecting shell, a first sliding member is provided inside the connecting shell, connecting balls are provided on both sides of the first sliding member, a second sliding member is provided on the side of the connecting shell away from the third screw, a connecting column is slidably connected to the second sliding member, one end of the connecting column located inside the connecting shell is in contact with the connecting ball, a limiting plate is provided on the end of the connecting column located outside the connecting shell, an elastic member is provided on the limiting plate, and an anchor nail is provided on the side of the limiting plate away from the connecting column.

[0008] Preferably: a rotating frame is arranged on the supporting frame, a hydraulic cylinder, a first limiting sliding rod and a fixing bolt are arranged on the rotating frame, and a limiting block is arranged at one end of the first limiting sliding rod away from the rotating frame.

[0009] Preferably: the connecting frame is arranged at the output end of the hydraulic cylinder, the connecting frame is provided with a first driving member, the output end of the first driving member is provided with a first screw, the first screw is rotatably connected to the connecting frame, a slide groove is provided on the connecting frame, the position of the slide groove corresponds to the position of the first screw, a second limiting slide rod is provided at the bottom of the connecting frame, a first connecting hole is provided on the connecting frame, and the connecting frame is slidably connected to the first limiting slide rod through the first connecting hole.

[0010] Preferably: a connecting screw hole and a second connecting hole are provided on the first movable frame, the first movable frame is threadedly connected to the first screw rod through the connecting screw hole, the first movable frame is slidably connected to the second limiting sliding rod through the second connecting hole, a second driving member is provided on one side of the first movable frame, a second screw rod is provided at the output end of the second driving member, the second screw rod is rotatably connected to the first movable frame, the axis of the second screw rod is perpendicular to the axis of the first screw rod, the second movable frame is threadedly connected to the second screw rod, and the second movable frame is slidably connected to the first movable frame.

[0011] Preferably: the drilling assembly includes a third driving member, the third driving member is fixedly mounted on the second mobile frame, a coupling is provided at the output end of the third driving member, a drill rod is connected to the output end of the third driving member via the coupling, and a drill bit is provided at one end of the drill rod away from the coupling.

[0012] Preferably: the third screw is threadedly connected to the support frame.

[0013] Preferably, the cross section of the first sliding member is an inverted triangle, and the two connecting balls are in contact with two surfaces of the bottom of the first sliding member respectively.

[0014] Preferably, the elastic member is arranged between the limiting plate and the second sliding member.

[0015] Preferably, the number of the connecting ball, the second sliding member, the connecting column, the limiting plate, the elastic member and the anchoring nail are two each.

[0016] A method for using a drilling device for geotechnical construction investigation comprises the following steps: S1: When the location to be drilled and surveyed is located on a slope, the third screw is rotated by the adjusting head, the third screw drives the connecting shell to move, the connecting shell drives the connecting column through the second sliding member, the connecting column drives the anchor nail to move through the limit plate, and the anchor nail is inserted into the ground to fix the device; S2: Adjust different fixing components according to the inclination angle of the slope to ensure the level of the support frame, thereby avoiding the situation where the drill rod is skewed during the drilling and survey of the drilling component, ensuring the quality of the survey borehole, and thus ensuring the accuracy of the drilling and survey results; S3: before drilling and surveying, start the first driving member and the second driving member, the first driving member drives the first moving frame to move through the first screw, the second driving member drives the second moving frame to move through the second screw, and the second moving frame drives the drilling assembly to move, so as to adjust the position of the drilling assembly; S4: When the drilling assembly moves to a position where drilling and investigation is required, the first driving member and the second driving member are turned off, and the third driving member is started. The third driving member drives the drill rod through the coupling, and the drill rod drives the drill bit to rotate; S5: At the same time, the hydraulic cylinder is started, and the hydraulic cylinder drives the first moving frame through the connecting frame, and the first moving frame drives the drilling assembly to move downward, and the rotating drill bit performs drilling and exploration; S6: When there are many potholes in the location to be drilled for investigation, two different anchoring nails on the same fixing assembly are respectively inserted into different locations on the ground. Since the potholes on the ground are not evenly distributed, the ground levels at the locations where the different anchoring nails are located are not the same; S7: After the limit plate on the anchor nail at a relatively high level contacts the ground, the limit plate pushes the connecting ball upward through the connecting column, and the connecting ball pushes the connecting ball corresponding to the relatively low level position downward through the first sliding member; S8: The connecting ball corresponding to the position with a relatively low horizontal height pushes the connecting column corresponding to the position with a relatively low horizontal height, and the connecting column corresponding to the position with a relatively low horizontal height drives the anchor nail corresponding to the position with a relatively low horizontal height to move downward through the limit plate, and is inserted into the ground at the position with a relatively low horizontal height, ensuring that the anchor nails at different positions can be inserted into the ground to fix the device, thereby avoiding shaking or tilting of the device when used in places with many potholes, ensuring the stability of the device during drilling and investigation, and thus ensuring the effect of drilling and investigation.

[0017] Compared with the prior art, the present invention has the following beneficial effects: When the location where drilling and exploration is required is on a slope, different fixing components can be adjusted according to the inclination angle of the slope to ensure the level of the support frame, thereby avoiding the drilling and exploration from being skewed, ensuring the quality of the exploration borehole, and ensuring the accuracy of the exploration results. When there are many potholes at the location where drilling and exploration is required, it can ensure that the anchor nails at different positions can be inserted into various parts of the ground with uneven horizontal heights to fix the device, thereby avoiding shaking or tilting of the device when used in a place with many potholes, ensuring the stability of the device during drilling and exploration, and thus ensuring the effect of drilling and exploration.

[0018] The parts not involved in the device are the same as those in the prior art or can be implemented by using the prior art. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0020] Figure 1 It is a structural schematic diagram of a first state of an embodiment of the present invention; Figure 2 It is a structural schematic diagram of the second state of an embodiment of the present invention; Figure 3 This is a schematic diagram of the structure of an embodiment of the present invention when drilling and exploring on an inclined working surface such as a slope; Figure 4 It is a schematic structural diagram of a support frame according to an embodiment of the present invention; Figure 5 It is a structural schematic diagram of a connecting frame from a first viewing angle according to an embodiment of the present invention; Figure 6 It is a structural schematic diagram of a connecting frame according to an embodiment of the present invention from a second viewing angle; Figure 7 It is a schematic structural diagram of a first mobile frame according to an embodiment of the present invention; Figure 8 It is a structural schematic diagram of a drilling assembly according to an embodiment of the present invention; Fig. 9 It is a structural schematic diagram of a first state of a fixing assembly according to an embodiment of the present invention; Fig.10 It is a cross-sectional structural schematic diagram of a first state of a fixing assembly according to an embodiment of the present invention; Fig.11 for Fig.10 A schematic diagram of the structure enlargement at the center A; Fig.12It is a structural schematic diagram of the second state of the fixing assembly of an embodiment of the present invention; Fig.13 for Fig.12 A magnified schematic diagram of the structure at point B in the middle.

[0021] The following are the descriptions of the reference numerals: 1. Support frame; 101. Rotating frame; 102. Hydraulic cylinder; 103. First limit slide bar; 104. Fixing bolt; 105. Limit block; 2. Connecting frame; 201. First driving member; 202. First screw rod; 203. Slide groove; 204. Second limit slide bar; 205. First connecting hole; 3. First moving frame; 301. Connecting screw hole; 302. Second connecting hole; 303. Second driving member; 304. Two screw rods; 305, second movable frame; 4, drilling assembly; 401, third driving member; 402, coupling; 403, drill rod; 404, drill bit; 5, fixing assembly; 501, third screw rod; 502, adjusting head; 503, connecting shell; 504, first sliding member; 505, connecting ball; 506, second sliding member; 507, connecting column; 508, limit plate; 509, elastic member; 510, anchor nail. DETAILED DESCRIPTION

[0022] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood by specific circumstances.

[0023] The present invention will be further described below in conjunction with the accompanying drawings: Embodiment 1

[0024] like Figures 1 to 3 As shown, a drilling device for geotechnical construction investigation includes a support frame 1, a connecting frame 2 is arranged on the top of the support frame 1, a first movable frame 3 is arranged on the connecting frame 2, a drilling assembly 4 is arranged at the bottom of the first movable frame 3, and a fixed assembly 5 is arranged on the support frame 1. The number of the fixed assemblies 5 is plural and distributed in a circular array on the support frame 1.

[0025] like Figure 4 As shown, a rotating frame 101 is arranged on the support frame 1 , and a hydraulic cylinder 102 , a first limiting slide bar 103 and a fixing bolt 104 are arranged on the rotating frame 101 . A limiting block 105 is arranged at one end of the first limiting slide bar 103 away from the rotating frame 101 .

[0026] like Figures 1 to 6As shown, the connecting frame 2 is arranged at the output end of the hydraulic cylinder 102, and a first driving member 201 is arranged on the connecting frame 2. A first screw 202 is arranged at the output end of the first driving member 201, and the first screw 202 is rotatably connected to the connecting frame 2. A slide groove 203 is provided on the connecting frame 2, and the position of the slide groove 203 corresponds to the position of the first screw 202. A second limiting slide bar 204 is provided at the bottom of the connecting frame 2, and a first connecting hole 205 is provided on the connecting frame 2. The connecting frame 2 is slidably connected to the first limiting slide bar 103 through the first connecting hole 205.

[0027] like Figures 1 to 3 , Figures 5 to 7 As shown, a connecting screw hole 301 and a second connecting hole 302 are provided on the first movable frame 3, the first movable frame 3 is threadedly connected to the first screw rod 202 through the connecting screw hole 301, the first movable frame 3 is slidably connected to the second limiting slide rod 204 through the second connecting hole 302, a second driving member 303 is provided on one side of the first movable frame 3, a second screw rod 304 is provided on the output end of the second driving member 303, the second screw rod 304 is rotatably connected to the first movable frame 3, the axis of the second screw rod 304 is perpendicular to the axis of the first screw rod 202, a second movable frame 305 is threadedly connected to the second screw rod 304, and the second movable frame 305 is slidably connected to the first movable frame 3.

[0028] like Figure 1 , Figure 7 and Figure 8 As shown, the drilling assembly 4 includes a third driving member 401, a coupling 402, a drill rod 403 and a drill bit 404. The third driving member 401 is fixedly mounted on the second movable frame 305. The output end of the third driving member 401 is provided with a coupling 402. The output end of the third driving member 401 is connected to the drill rod 403 through the coupling 402. The drill bit 404 is provided at one end of the drill rod 403 away from the coupling 402. There are multiple drill rods 403. When in use, multiple drill rods 403 are connected in sequence. The drill bit 404 is arranged on the lowest drill rod 403. The number of drill rods 403 can be adjusted according to the required drilling depth.

[0029] like Figure 1 , Figures 9 to 13As shown, the fixing assembly 5 includes a third screw 501, an adjusting head 502, a connecting shell 503, a first sliding member 504, a connecting ball 505, a second sliding member 506, a connecting column 507, a limiting plate 508, an elastic member 509 and an anchoring nail 510. The third screw 501 is threadedly connected to the support frame 1, and an adjusting head 502 is provided at one end of the third screw 501. The end of the third screw 501 away from the adjusting head 502 is rotatably connected to the connecting shell 503. The first sliding member 504 is provided inside the connecting shell 503. Both sides of the first sliding member 504 are provided with connecting balls 505. The cross-section of the first sliding member 504 is an inverted triangle. The two connecting balls 505 are respectively connected to the two bottom portions of the first sliding member 504. The two surfaces are in contact with each other, and a second sliding member 506 is provided on the side of the connecting shell 503 away from the third screw rod 501, and a connecting column 507 is slidably connected to the second sliding member 506. The end of the connecting column 507 located inside the connecting shell 503 is in contact with the connecting ball 505, and a limiting plate 508 is provided on the end of the connecting column 507 located outside the connecting shell 503, and an elastic member 509 is provided on the limiting plate 508, and the elastic member 509 is arranged between the limiting plate 508 and the second sliding member 506. An anchoring nail 510 is provided on the side of the limiting plate 508 away from the connecting column 507, and the number of the connecting ball 505, the second sliding member 506, the connecting column 507, the limiting plate 508, the elastic member 509 and the anchoring nail 510 are all two.

[0030] A method for using a drilling device for geotechnical construction investigation comprises the following steps: S1: When the location to be drilled and surveyed is located on a slope, the third screw 501 is rotated by the adjusting head 502, and the third screw 501 drives the connecting shell 503 to move, and the connecting shell 503 drives the connecting column 507 through the second sliding member 506, and the connecting column 507 drives the anchoring nail 510 to move through the limiting plate 508, and the anchoring nail 510 is inserted into the ground to fix the device; S2: adjusting different fixing components 5 according to the inclination angle of the slope to ensure the level of the support frame 1, thereby avoiding the situation where the drill rod 403 is skewed when the drilling component 4 performs drilling survey, ensuring the quality of the survey borehole, and thus ensuring the accuracy of the drilling survey result; S3: Before drilling and surveying, the first driving member 201 and the second driving member 303 are started, the first driving member 201 drives the first moving frame 3 to move through the first screw 202, the second driving member 303 drives the second moving frame 305 to move through the second screw 304, and the second moving frame 305 drives the drilling assembly 4 to move, and the position of the drilling assembly 4 is adjusted; S4: When the drilling assembly 4 moves to a position where drilling and investigation is required, the first driving member 201 and the second driving member 303 are closed, and the third driving member 401 is started. The third driving member 401 drives the drill rod 403 through the coupling 402, and the drill rod 403 drives the drill bit 404 to rotate; S5: At the same time, the hydraulic cylinder 102 is started, and the hydraulic cylinder 102 drives the first mobile frame 3 through the connecting frame 2, and the first mobile frame 3 drives the drilling assembly 4 to move downward, and the rotating drill bit 404 performs drilling and exploration; S6: When there are many potholes at the location to be drilled and surveyed, two different anchoring nails 510 on the same fixing assembly 5 are respectively inserted into different locations on the ground. Since the potholes on the ground are not evenly distributed, the ground levels at the locations where the different anchoring nails 510 are located are not the same; S7: After the limit plate 508 on the anchor nail 510 at a relatively high position contacts the ground, the limit plate 508 pushes the connecting ball 505 upward through the connecting column 507, and the connecting ball 505 pushes the connecting ball 505 corresponding to the relatively low position downward through the first sliding member 504; S8: The connecting ball 505 corresponding to the position with a relatively low horizontal height pushes the connecting column 507 corresponding to the position with a relatively low horizontal height, and the connecting column 507 corresponding to the position with a relatively low horizontal height drives the anchor nail 510 corresponding to the position with a relatively low horizontal height to move downward through the limiting plate 508 and insert it into the ground at the position with a relatively low horizontal height, ensuring that the anchor nails 510 at different positions can be inserted into the ground to fix the device, thereby avoiding shaking or tilting of the device when used in a place with many potholes, ensuring the stability of the device during drilling and investigation, and thus ensuring the effect of drilling and investigation.

[0031] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments, and the above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, and these changes and improvements all fall within the scope of the present invention to be protected.

Claims

1. A drilling device for geotechnical construction investigation, characterized in that: It comprises a support frame, a connecting frame is arranged on the top of the support frame, a first moving frame is arranged on the connecting frame, a drilling assembly is arranged on the bottom of the first moving frame, and a fixing assembly is arranged on the support frame; The fixing assembly includes a third screw, one end of the third screw is provided with an adjusting head, the end of the third screw away from the adjusting head is rotatably connected to a connecting shell, a first sliding member is provided inside the connecting shell, connecting balls are provided on both sides of the first sliding member, a second sliding member is provided on the side of the connecting shell away from the third screw, a connecting column is slidably connected to the second sliding member, one end of the connecting column located inside the connecting shell is in contact with the connecting ball, a limiting plate is provided on the end of the connecting column located outside the connecting shell, an elastic member is provided on the limiting plate, and an anchor nail is provided on the side of the limiting plate away from the connecting column.

2. A drilling device for geotechnical construction and investigation according to claim 1, characterized in that: A rotating frame is arranged on the support frame, and a hydraulic cylinder, a first limiting sliding rod and a fixing bolt are arranged on the rotating frame. A limiting block is arranged at one end of the first limiting sliding rod away from the rotating frame.

3. A drilling device for geotechnical construction survey according to claim 2, characterized in that: The connecting frame is arranged at the output end of the hydraulic cylinder, and a first driving member is arranged on the connecting frame. A first screw is arranged at the output end of the first driving member, and the first screw is rotatably connected to the connecting frame. A sliding groove is provided on the connecting frame, and the position of the sliding groove corresponds to the position of the first screw. A second limiting sliding rod is provided at the bottom of the connecting frame, and a first connecting hole is provided on the connecting frame. The connecting frame is slidably connected to the first limiting sliding rod through the first connecting hole.

4. A drilling device for geotechnical construction and investigation according to claim 3, characterized in that: The first movable frame is provided with a connecting screw hole and a second connecting hole, the first movable frame is threadedly connected to the first screw rod through the connecting screw hole, the first movable frame is slidably connected to the second limiting sliding rod through the second connecting hole, a second driving member is provided on one side of the first movable frame, a second screw rod is provided on the output end of the second driving member, the second screw rod is rotatably connected to the first movable frame, the axis of the second screw rod is perpendicular to the axis of the first screw rod, the second movable frame is threadedly connected to the second screw rod, and the second movable frame is slidably connected to the first movable frame.

5. A drilling device for geotechnical construction and investigation according to claim 4, characterized in that: The drilling assembly includes a third driving member, which is fixedly mounted on the second movable frame. A coupling is provided at the output end of the third driving member. The output end of the third driving member is connected to a drill rod through the coupling. A drill bit is provided at one end of the drill rod away from the coupling.

6. A drilling device for geotechnical construction and investigation according to claim 1, characterized in that: The third screw is threadedly connected to the support frame.

7. A drilling device for geotechnical construction and investigation according to claim 1, characterized in that: The cross section of the first sliding member is an inverted triangle, and the two connecting balls are in contact with two surfaces of the bottom of the first sliding member respectively.

8. The drilling device for geotechnical construction and investigation according to claim 1, characterized in that: The elastic member is arranged between the limiting plate and the second sliding member.

9. A drilling device for geotechnical construction and investigation according to claim 1, characterized in that: The number of the connecting ball, the second sliding member, the connecting column, the limiting plate, the elastic member and the anchoring nail are all two.

10. A method for using a drilling device for geotechnical construction investigation according to any one of claims 1 to 9, characterized in that: It includes the following steps: S1: When the location to be drilled and surveyed is located on a slope, the third screw is rotated by the adjusting head, the third screw drives the connecting shell to move, the connecting shell drives the connecting column through the second sliding member, the connecting column drives the anchor nail to move through the limit plate, and the anchor nail is inserted into the ground to fix the device; S2: Adjust different fixing components according to the inclination angle of the slope to ensure the level of the support frame, thereby avoiding the situation where the drill rod is skewed when the drilling component is drilling and surveying, ensuring the quality of the survey borehole, and thus ensuring the accuracy of the drilling and survey results; S3: before drilling and surveying, start the first driving member and the second driving member, the first driving member drives the first moving frame to move through the first screw, the second driving member drives the second moving frame to move through the second screw, and the second moving frame drives the drilling assembly to move, so as to adjust the position of the drilling assembly; S4: When the drilling assembly moves to a position where drilling and investigation is required, the first driving member and the second driving member are turned off, and the third driving member is started. The third driving member drives the drill rod through the coupling, and the drill rod drives the drill bit to rotate; S5: At the same time, the hydraulic cylinder is started, and the hydraulic cylinder drives the first moving frame through the connecting frame, and the first moving frame drives the drilling assembly to move downward, and the rotating drill bit performs drilling and exploration; S6: When there are many potholes in the location to be drilled for investigation, two different anchoring nails on the same fixing assembly are respectively inserted into different locations on the ground. Since the potholes on the ground are not evenly distributed, the ground levels at the locations where the different anchoring nails are located are not the same; S7: After the limit plate on the anchor nail at a relatively high level contacts the ground, the limit plate pushes the connecting ball upward through the connecting column, and the connecting ball pushes the connecting ball corresponding to the relatively low level position downward through the first sliding member; S8: The connecting ball corresponding to the position with a relatively low horizontal height pushes the connecting column corresponding to the position with a relatively low horizontal height, and the connecting column corresponding to the position with a relatively low horizontal height drives the anchor nail corresponding to the position with a relatively low horizontal height to move downward through the limit plate, and is inserted into the ground at the position with a relatively low horizontal height, ensuring that the anchor nails at different positions can be inserted into the ground to fix the device, thereby avoiding shaking or tilting of the device when used in places with many potholes, ensuring the stability of the device during drilling and investigation, and thus ensuring the effect of drilling and investigation.

Citation Information

Patent Citations

  • Geological survey equipment

    CN109540226A

  • Drilling rig and drilling process for geotechnical engineering investigation

    CN112324355A

  • Drilling and coring equipment for geological exploration

    CN116255140A

  • Exploration device for geological survey of geological mineral products

    CN117888895A

  • Reamer for geological exploration

    CN118728269A