Shield tunneling machine and rear matched trolley synchronous curve translation construction device and method
In the construction of the shield machine and the rear supporting trolley, a synchronous curve translation construction device of the battery car assembly head, slag bucket chassis and traveling tracks is solved, and the problem of large workload and low safety and reliability of the rail extension and triangular sleeper setting in the prior art is solved, achieving efficient and safe construction results.
Patent Information
- Application Number
- CN202510082467.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-20
- Publication Date
- 2025-04-25
AI Technical Summary
In the construction process of the shield machine and the rear supporting trolley, there are problems such as large workload and low safety and reliability of rail extension and triangular sleeper installation.
A shield machine and rear matching trolley are adopted to synchronous curve translation construction device, including the battery car assembly head, the slag bucket chassis and the traveling track, the battery car assembly head and the slag bucket chassis are articulatedly connected, and an H-shaped steel frame is installed on the slag bucket chassis to fix the trolley, and the battery car assembly is used for horizontal transportation in the hole.
It has achieved the maximization of mechanical operations, reduced labor intensity for personnel, improved construction efficiency, reduced safety hazards, and used less materials and fewer welding operations, which has the advantages of environmental protection and energy saving.
Smart Images

Figure CN119878212A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of tunnel construction, and in particular to a device and method for synchronous curved translation construction of a shield machine and a rear supporting trolley. Background Art
[0002] With the development of cities, the utilization rate of urban underground space has gradually increased, and urban transportation and pipeline corridors are increasingly developing underground. The shield method is a fully mechanized construction method in the dark excavation construction method. It is increasingly widely used because it does not affect ground transportation and facilities, is suitable for various strata, has safe construction, and has a fast excavation speed. It often has technical and economic advantages in the construction of tunnels with greater burial depths and longer intervals.
[0003] As a high-cost and high-efficiency mode of transportation, urban subways are usually built in densely populated areas in order to increase passenger flow during the operation period and reduce the pressure of principal and interest repayment. Subway stations are also often located on major traffic arteries where people gather. In order to reduce the impact on ground traffic, dark excavation or covered excavation construction is usually selected when conditions permit. There are often no hoisting shafts or only small hoisting shafts on the ground, which cannot meet the hoisting conditions of the subsequent supporting trolleys. This results in the need for the subsequent supporting trolleys to be horizontally transported in the tunnel to the large-sized hoisting shaft near the station and then hoisted to the ground.
[0004] In addition, in order to save the cost of temporary construction sites and facilities, temporary facilities such as shield construction slag pits, circulating water pools, dormitories, canteens, etc. are usually set up at the same site. For double-track tunnel construction in the same section, after one tunnel is completed, the shield machine and the supporting trolley need to be re-transferred to the starting station for re-assembly and debugging before the second start of construction of another tunnel or adjacent section tunnel. In order to save the cost of hoisting and transfer of shield equipment, the supporting trolley is usually returned to the starting station by horizontal transportation in the tunnel.
[0005] The existing technology mainly uses the method of continuously extending the trolley moving track to move horizontally to the tunnel entrance and then lifting it out. This method has the following disadvantages: (1) It is necessary to continuously extend the rails and place triangular sleepers, which is labor-intensive and inefficient. (2) The safety and reliability are low. The longitudinal slope of the tunnel is usually 5‰ to 30‰, which is prone to dangerous situations such as slipping. Summary of the invention
[0006] The purpose of the present invention is to solve the defects in the prior art and to propose a construction device and method for synchronous curved translation of a shield machine and a subsequent matching trolley.
[0007] In order to achieve the above object, the present invention adopts the following technical solutions:
[0008] A shield machine and a rear supporting trolley synchronous curve translation construction device, comprising a battery car marshaling machine head, a slag bucket chassis and a travel track; the travel track is arranged in a tunnel;
[0009] The battery car marshaling machine head and the slag bucket chassis are hingedly arranged through a connecting beam, and the battery car marshaling machine head and the slag bucket chassis are both arranged on a travel track; an H-shaped steel frame is arranged on the slag bucket chassis, and a shield machine rear supporting trolley is arranged on the H-shaped steel frame.
[0010] Furthermore, the hopper chassis are provided with at least two groups, the first hopper chassis is connected to the battery vehicle marshaling machine head, the second hopper chassis is connected to the second hopper chassis, and the H-shaped steel frame is provided on the second hopper chassis.
[0011] Furthermore, a positioning groove is provided on the hopper chassis, a positioning hole is provided on the H-shaped steel frame, a pin shaft passes through the positioning hole, and is embedded in the positioning groove.
[0012] Furthermore, the travel track includes a channel steel sleeper, a travel groove is opened on the channel steel sleeper, and the hopper chassis and the bottom of the battery car marshaling machine head are both provided with rollers, and the rollers are arranged in the travel groove.
[0013] Furthermore, reset springs are symmetrically arranged on both sides of the connection beam, and both ends of the reset springs are respectively fixedly connected to the battery car marshaling machine head and the slag bucket chassis.
[0014] Furthermore, it also includes auxiliary support, which includes triangular sleepers, lower pads, jacks and upper pads. The triangular sleepers are arranged on both sides of the travel track. The lower pads, jacks and upper pads are arranged on the triangular sleepers in sequence, and an H-shaped steel frame is arranged above the upper pad.
[0015] A shield machine and a rear supporting trolley synchronous curve translation construction method, comprising the following steps:
[0016] S1: Arrange the slag bucket chassis of the original battery car marshaling and the battery car marshaling locomotive into a group and place them on the travel track;
[0017] S2: Use steel pipes to connect the two separated parts at the bottom of the trolley to prevent them from opening during jacking, transportation and lifting;
[0018] S3: Place the vertical hydraulic jack at the foot of the trolley and adjust the height with H-shaped steel and steel plate, so that the piston rod of the jack is extended synchronously to lift the trolley and make the wheels of the trolley fall off the track;
[0019] S4: Place an H-shaped steel frame between the hopper chassis and the bottom plate of the trolley and fix the H-shaped steel frame and the hopper chassis with a pin;
[0020] S5: Simultaneously release the pressure from the jacks on the trolley feet, let the trolley fall onto the H-shaped steel frame, and fix the H-shaped steel frame and the trolley with pins;
[0021] S6: Finally, start the battery car group to transport the trolley horizontally in the tunnel and hoist it to the wellhead for reassembly.
[0022] Beneficial Effects
[0023] Compared with the prior art, the present invention has the following beneficial effects:
[0024] 1. During the construction, only steel pipes, H-shaped steel, pins and steel plates were used as steel structure materials; only a small amount of welding was used to connect the steel pipes with the two separate platforms at the bottom of the trolley. Less steel structure materials and welding operations are used, and all materials can be recycled, which has the advantages of environmental protection and energy saving.
[0025] 2. This device uses battery cars to transport the trolleys horizontally in the tunnel. There is no need to lay sleepers and tracks separately, which realizes the maximization of mechanical operation and long-distance horizontal transportation in the tunnel. During transportation, the battery car locomotive can brake the tunnel slope and obstacles to stop, accelerate and decelerate at any time, reducing the labor intensity of personnel, improving construction efficiency, avoiding safety hazards and ensuring the safety of construction.
[0026] 3. The device is easy to operate, does not require additional power, has good maneuverability, can stop midway to handle obstacles, is highly practical, and can be used as a reference in the horizontal transportation of various large-size track components.
[0027] 4. This device has the characteristics of simple operation, high efficiency, novel structure, economic rationality, safety and reliability. It realizes the maximization of mechanical operation in the horizontal transportation operation of the shield machine trolley in the tunnel, improves the construction efficiency of the horizontal transportation operation of the shield machine rear trolley in the tunnel, and reduces construction costs and risks. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] The accompanying drawings are used to provide further understanding of the present invention and constitute a part of the specification. They are used to explain the present invention together with the embodiments of the present invention and do not constitute a limitation of the present invention.
[0029] Figure 1 Schematic diagram of the placement of the shield machine and the supporting trolley in the tunnel for synchronous curved translation construction equipment
[0030] Figure 2 This is a top view of the shield machine and the rear supporting trolley's synchronous curved translation construction device.
[0031] Figure 3 This is a structural diagram of the coordination between the battery car marshaling locomotive head and the slag hopper chassis.
[0032] Figure 4 It is a structural schematic diagram of the jack-lifting trolley.
[0033] Figure 5 Schematic diagram of the structure when the jack trolley is removed and dropped to the upper section of the H-beam.
[0034] Figure 6 This is a schematic diagram of the structure of the slag bucket chassis of the lifting trolley.
[0035] Figure 7 It is a schematic diagram of the structure of the reset tension spring.
[0036] In the figure: 1. Trolley behind the shield machine; 2. H-shaped steel frame; 3. Tunnel; 4. Steel pipe; 5. Slag bucket chassis; 6. Battery car marshaling machine head; 7. Travel track; 8. Triangular sleeper; 9. Channel steel sleeper; 10. Upper pad; 11. Jack; 12. Lower pad. DETAILED DESCRIPTION
[0037] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present application, and should not be construed as limiting the present application. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present application.
[0038] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0039] In this application, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0040] Reference Figure 1-Figure 6 A shield machine and a rear supporting trolley synchronous curve translation construction device, comprising a battery car marshaling machine head 6, a slag bucket chassis 5 and a travel track 7; the travel track 7 is arranged in a tunnel 3;
[0041] The battery car marshaling machine head 6 and the slag bucket chassis 5 are hingedly arranged through a connecting beam, and the battery car marshaling machine head 6 and the slag bucket chassis 5 are both arranged on a travel track 7; an H-shaped steel frame 2 is arranged on the slag bucket chassis 5, and a shield machine rear supporting trolley 1 is arranged on the H-shaped steel frame 2.
[0042] During the construction, only steel pipes, H-shaped steel, pins and steel plates were used as steel structure materials; only a small amount of welding was used to connect the steel pipes to the two separate platforms at the bottom of the trolley. Less steel structure materials and welding work are used, and all materials can be recycled, which has the advantages of environmental protection and energy saving.
[0043] In other preferred embodiments, at least two groups of hopper chassis 5 are provided, the first hopper chassis is connected to the battery vehicle marshaling machine head 6, the second hopper chassis is connected to the second hopper chassis, and the H-shaped steel frame 2 is provided on the second hopper chassis 5.
[0044] In other preferred embodiments, a positioning groove is provided on the hopper chassis 5, a positioning hole is provided on the H-shaped steel frame 2, and a pin passes through the positioning hole and is embedded in the positioning groove.
[0045] In other preferred embodiments, the travel track 7 includes a channel steel sleeper 9, a travel groove is opened on the channel steel sleeper 9, and rollers are provided at the bottom of the hopper chassis 5 and the battery car marshaling machine head 6, and the rollers are arranged in the travel groove.
[0046] In other preferred embodiments, reset springs are symmetrically arranged on both sides of the connecting beam, and the two ends of the reset springs are respectively fixedly connected to the battery car marshaling machine head 6 and the slag bucket chassis 5. Through the reset springs, the tension state can be maintained during the turning process of the machine set, so that the rollers at the bottom of the battery car marshaling machine head 6 and the slag bucket chassis 5 are closely attached to the grooves of the travel track, ensuring its stability during operation.
[0047] In other preferred embodiments, auxiliary supports are further included, and the auxiliary supports include triangular sleepers 8, lower pads 12, jacks 11 and upper pads 10. The triangular sleepers 8 are arranged on both sides of the travel track 7. The lower pads 12, jacks 11 and upper pads 10 are arranged on the triangular sleepers 8 in sequence, and an H-shaped steel frame 2 is arranged above the upper pad 10. The lower pad 12 and the upper pad 10 are steel plates with a thickness of about 20 mm.
[0048] A shield machine and a rear supporting trolley synchronous curve translation construction method, comprising the following steps:
[0049] S1: Arrange the slag bucket chassis 5 and the battery car marshaling locomotive 6 of the original battery car marshaling into a group and place them on the travel track 7; wherein two slag bucket chassis 5 and one battery car marshaling locomotive 6 are required;
[0050] S2: Use a steel pipe 4 to connect the two separated parts at the bottom of the trolley to prevent them from opening during jacking, transportation, and lifting; two steel pipes 4 are required for connection, and the specifications of the steel pipes 4 are 1830 mm in length and 48 mm in outer diameter;
[0051] S3: Place four vertical hydraulic jacks 11 on the four feet of the trolley and adjust the height with steel and steel plates, so that the piston rods of the four jacks 11 extend synchronously to lift the trolley, so that the wheels of the trolley fall off the track to a certain height; two sets of H-shaped steel are required to form an H-shaped steel frame 2, and the specifications of one H-shaped steel are: 300*300H-shaped steel with a length of 500mm and 3700mm;
[0052] S4: Place the H-shaped steel frame 2 between the hopper chassis 5 and the bottom plate of the trolley and fix the H-shaped steel frame 2 and the hopper chassis 5 with a pin;
[0053] S5: Slowly release the pressure of the four jacks 11 at the same time, let the trolley fall steadily on the H-shaped steel and fix the H-shaped steel and the trolley with pins; the number of pins required is eight, with specifications of: length 80mm, diameter 20mm,
[0054] S6: Finally, start the battery car group to transport the trolley horizontally in the tunnel and hoist it to the wellhead for reassembly.
[0055] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A shield machine and a rear supporting trolley synchronous curve translation construction device, characterized in that: It includes a battery car marshaling machine head, a slag bucket chassis and a travel track; the travel track is arranged in a tunnel; The battery car marshaling machine head and the slag bucket chassis are hingedly arranged through a connecting beam, and the battery car marshaling machine head and the slag bucket chassis are both arranged on a travel track; an H-shaped steel frame is arranged on the slag bucket chassis, and a shield machine rear supporting trolley is arranged on the H-shaped steel frame.
2. According to claim 1, a shield machine and a rear supporting trolley synchronous curve translation construction device is characterized in that: The hopper chassis are provided with at least two groups, the first hopper chassis is connected to the battery vehicle marshaling machine head, the second hopper chassis is connected to the second hopper chassis, and the H-shaped steel frame is provided on the second hopper chassis.
3. The shield machine and the rear supporting trolley synchronous curve translation construction device according to claim 1 is characterized in that: A positioning groove is provided on the bottom plate of the hopper, a positioning hole is provided on the H-shaped steel frame, a pin shaft passes through the positioning hole, and is embedded in the positioning groove.
4. The shield machine and the rear supporting trolley synchronous curve translation construction device according to claim 1 is characterized in that: The travel track comprises a channel steel sleeper, a travel groove is opened on the channel steel sleeper, and rollers are arranged at the bottom of the slag bucket chassis and the battery car marshaling machine head, and the rollers are arranged in the travel groove.
5. The shield machine and the rear supporting trolley synchronous curve translation construction device according to claim 1 is characterized in that: Reset springs are symmetrically arranged on both sides of the connection beam, and both ends of the reset springs are respectively fixedly connected to the battery car marshaling machine head and the slag bucket chassis.
6. The shield machine and the rear supporting trolley synchronous curve translation construction device according to claim 1 is characterized in that: It also includes auxiliary supports, which include triangular sleepers, lower pads, jacks and upper pads. The triangular sleepers are arranged on both sides of the travel track. The lower pads, jacks and upper pads are arranged on the triangular sleepers in sequence, and an H-shaped steel frame is arranged above the upper pad.
7. A construction method for synchronous curved translation of a shield machine and a rear supporting trolley, characterized in that: The following steps are involved: S1: Arrange the slag bucket chassis of the original battery car marshaling and the battery car marshaling locomotive into a group and place them on the travel track; S2: Use steel pipes to connect the two separated parts at the bottom of the trolley to prevent them from opening during jacking, transportation and lifting; S3: Place the vertical hydraulic jack at the foot of the trolley and adjust the height with H-shaped steel and steel plate, so that the piston rod of the jack is extended synchronously to lift the trolley and make the wheels of the trolley fall off the track; S4: Place an H-shaped steel frame between the hopper chassis and the bottom plate of the trolley and fix the H-shaped steel frame and the hopper chassis with a pin; S5: Simultaneously release the pressure from the jacks on the trolley feet, let the trolley fall onto the H-shaped steel frame, and fix the H-shaped steel frame and the trolley with pins; S6: Finally, start the battery car group to transport the trolley horizontally in the tunnel and hoist it to the wellhead for reassembly.
Citation Information
Cited By
Shield flight launching frame
CN121701213A
Shield flight launching stand
CN121701213B