Spray cooling device temporarily arranged on construction site

By designing a temporary spray cooling device for construction sites with convenient movement and flexible adjustment, the problem that existing devices are difficult to adapt to actual construction sites is solved, and the convenient handling and efficient cooling effect of the devices is achieved.

CN119879307APending Publication Date: 2025-04-25济南一建集团有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510286908.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-03-12
Publication Date
2025-04-25

AI Technical Summary

Technical Problem

The existing temporary spray cooling device for construction sites is difficult to adapt to the adjustment of the actual construction site, the parts are inconvenient to be transported, and it cannot be flexibly adjusted after assembly, and the adaptability is poor.

Method used

A spray cooling device including a mobile rack, a water storage tank, a water pipe limiting assembly and a telescopic roller-skating assembly are designed. The mobile frame is conveniently moved through the universal wheel, the water storage tank adjusts the height by a fixed rope, and the water pipe adjusts the height of the nozzle through a telescopic roller-skating assembly and a wire-controlled roller-skating group.

Benefits of technology

It realizes convenient handling and flexible assembly of the device, improves the applicability and use efficiency of the device, and can adjust the spray height according to actual needs to improve the cooling effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119879307A_ABST
    Figure CN119879307A_ABST
Patent Text Reader

Abstract

The invention particularly relates to a spraying cooling device temporarily arranged on a construction site. The movable frame is of a structure that the stand column is fixed to the cavity base. The stand column is provided with a water pipe limiting assembly, a drive-by-wire pulley set and a water storage tank fixing assembly. Different moving frames are connected based on a connecting rod, and a plurality of telescopic roller skating assemblies are arranged at the bottom end of the connecting rod; the water storage tank in the cavity base is connected to the bottom of the stand column based on a first telescopic assembly. The water storage tank is provided with a fixing rope; the height of the water storage tank is adjusted by adjusting the gears, connected to the water storage tank fixing assembly, of the fixing rope; the two ends of the water pipe are fixed to the movable frame based on the water pipe limiting assembly. The middle of the water pipe is limited in the annular groove of the telescopic roller skating assembly. The drive-by-wire roller skating group adjusts the telescopic degree of the telescopic roller skating assembly based on the connecting line so as to adjust the height of the nozzle arranged in the middle of the water pipe. According to the device, the carrying convenience degree of the device components is improved, and meanwhile adaptive and adjustable assembly and flexible adjustment of the components are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of engineering construction, and in particular to a spray cooling device for temporary facilities at a construction site. Background Art

[0002] In order to prevent construction workers from suffering from heat stroke during construction in summer, it is necessary to temporarily set up a spray cooling device at the construction site. The existing temporary spray cooling devices for construction sites are usually preset fixed connection structures. The following problems usually exist during the use of the existing spray cooling devices. The first aspect is that it is difficult to adapt and adjust the spray cooling devices in combination with the actual construction site; the second aspect is that some assembly parts are large in size, and the transportation process is time-consuming and laborious; the third aspect is that the assembled spray cooling devices cannot be flexibly adjusted in combination with actual use conditions, and the adaptability is poor. In summary, there is an urgent need for a temporary spray cooling device for construction sites. Summary of the invention

[0003] In view of the above-mentioned shortcomings and deficiencies of the prior art, the present invention provides a spray cooling device for temporary facilities on construction sites, which solves the technical problem existing in the use of the existing spray cooling device for temporary facilities on construction sites, namely, "how to achieve "adaptive adjustable assembly of components" and "flexible adjustment of components" while "making the transportation of components more time-saving and labor-saving".

[0004] In order to achieve the above object, the main technical solutions adopted by the present invention include: The present invention provides a spray cooling device for temporary installation at a construction site, specifically: The mobile frame is a structure in which a column is fixed to a cavity base; the column is provided with a water pipe limit assembly, a wire-controlled roller skating assembly and a water tank fixing assembly; different mobile frames are connected based on a connecting rod, and a plurality of telescopic roller skating assemblies are provided at the bottom of the connecting rod; The water tank in the cavity base is connected to the bottom of the column based on the first telescopic component; the water tank is provided with a fixing rope; the height of the water tank is adjusted by adjusting the gear position of the fixing rope connected to the water tank fixing component; The two ends of the water pipe are fixed to the mobile frame based on the water pipe limiting assembly, and the middle part of the water pipe is limited to the annular groove of the telescopic roller skating assembly; the wire-controlled roller skating group adjusts the telescopic degree of the telescopic roller skating assembly based on the connecting line to adjust the height of the nozzle arranged in the middle part of the water pipe.

[0005] Optionally, the structure of the column is a regular polygonal columnar structure; Each set of matching wire-controlled roller skating groups and water pipe limiter components are installed on each side of the column from top to bottom.

[0006] Optionally, a square through hole adapted to the water tank is provided on the bottom surface of the cavity base, and an operation window is provided on one side surface of the cavity base; The side of the water tank is provided with a water filling port and a water outlet port; the top surface of the water tank and the top surface of the cavity base are provided with circular through holes adapted to fit the water pipe; A water suction pump is arranged on the top of the cavity base, and one water suction pump corresponds to each set of wire-controlled roller skates.

[0007] Optionally, one end of the fixing rope is fixed to the side of the water tank, and the other end provided with a fixing hook penetrates the top surface of the cavity base; The water tank fixing component is a fixing ring fixed to the side of the column and adapted to the fixing hook.

[0008] Optionally, the water pipe limiting assembly includes a double annular groove steering wheel and a plurality of spring-type water pipe fixing clamps; The spring type water pipe fixing clamp ring is set at equal intervals from top to bottom, and the double annular groove type steering wheel is arranged on the upper side of the spring type water pipe fixing clamp ring.

[0009] Optionally, LED lighting strips are fixedly embedded on both sides of the connecting rod; The telescopic roller skating assembly is a structure in which a first roller skating member is vertically connected to a second roller skating member based on a second telescopic assembly; two connecting lines are simultaneously adapted to one telescopic roller skating assembly; The first wheel slide is provided with two annular grooves; the second wheel slide is provided with four annular grooves; One end of the connecting line is fixed to the first wheel slider, and the other end is passed around the second wheel slider and the first wheel slider in sequence and then horizontally connected to the wire-controlled roller skating group.

[0010] Optionally, the wire-controlled roller skating group is a structure in which a fixed annular member is nested in an electrically controlled rotating shaft; The fixed annular member and the electric control shaft form two annular grooves, and one end of the connecting wire matched on one side is respectively fixed in the corresponding annular groove.

[0011] Optionally, the two annular grooves of the double annular groove steering wheel and the two outermost annular grooves of the second wheel slide are respectively adapted to two water pipes.

[0012] Optionally, a plurality of universal wheels are provided at the bottom of the mobile frame; A hand-pushing handle is provided on the outside of the mobile frame, and buttons for adjusting and controlling the water suction pump, the LED lighting light strip, and the wire-controlled roller skating group are provided on the hand-pushing handle.

[0013] The beneficial effects of this application are: Compared with the existing devices, the column in this device is a regular polygonal column structure, and each set of matching wire-controlled roller skating groups and water pipe limit components are installed on each side of the column from top to bottom in sequence, so that a certain mobile rack can be connected to other preset mobile racks in multiple directions based on actual working conditions, realizing a simplified water supply of "centralized water supply and circulating flow". Through the aforementioned "simplification of the structural assembly process and the simplification of the water supply process", the efficiency of the device can be improved.

[0014] In the device, the mobile frame is provided with universal wheels, the water tank in the cavity base is connected to the bottom of the column based on the first telescopic component, and the water tank is provided with a fixed rope; based on the above structure, the mobile frame can be easily and conveniently moved to a preset position based on the universal wheels; and, by adjusting the gear position of the fixed rope connected to the fixed component of the water tank, after the bottom of the water tank touches the ground, water is injected into the water tank to stabilize the overall structure of the mobile frame; ensuring that the stable assembly of the mobile frame structure is achieved by the water injection process, killing two birds with one stone and improving efficiency; In this device, both ends of the water pipe are fixed to the mobile frame based on the water pipe limiting assembly, and the middle part of the water pipe is limited to the annular groove of the telescopic roller skating assembly; based on the above structure, the telescopic degree of the telescopic roller skating assembly can be adjusted based on the connecting line through the wire-controlled roller skating group to adjust the height of the nozzle arranged in the middle part of the water pipe, thereby improving the applicability of the device by adjusting the spraying height.

[0015] In the device, buttons for adjusting and controlling the water suction pump, the LED lighting strip, and the wire-controlled roller skating group are provided at the hand-pushing handle of the mobile frame, so that the device can be easily and conveniently controlled. BRIEF DESCRIPTION OF THE DRAWINGS Figure 1 A schematic diagram of the structural assembly of a temporary spray cooling device for a construction site provided by an embodiment of the present invention; Figure 2 A schematic diagram of a mobile rack structure provided by an embodiment of the present invention; Figure 3 A schematic diagram of the structural assembly of a temporary spray cooling device for a construction site provided by an embodiment of the present invention; Figure 4 A schematic diagram of the installation of a telescopic roller skate assembly and a connecting rod structure provided by one embodiment of the present invention; Figure 5 A schematic diagram of the assembly of a telescopic roller skate assembly and a connecting rod structure provided by one embodiment of the present invention; Figure 6 A schematic diagram of the assembly of a telescopic roller skate assembly and a connecting wire structure provided by one embodiment of the present invention; Figure 7 A schematic diagram of the assembly of a wire-controlled roller skating group and a connecting wire structure provided by an embodiment of the present invention; Figure 8A simplified top view of a spray cooling device for temporary installation at a construction site provided by one embodiment of the present invention; Fig. 9 A simplified top view of a spray cooling device for temporary installation at a construction site provided by one embodiment of the present invention; Fig.10 A simplified top view of a spray cooling device for temporary installation at a construction site provided by one embodiment of the present invention; Fig.11 A simplified top view of a spray cooling device for temporary installation at a construction site provided by one embodiment of the present invention; Figures 1 to 11 The component numbers in correspondence are as follows: Mobile frame 1, column 1-1, cavity base 1-2, water storage tank 1-2-1, water injection port 1-2-1-1, water outlet port 1-2-1-2, fixed rope 1-2-1-3, fixed hook 1-2-1-4, first telescopic component 1-2-2, circular through hole 1-2-3, square through hole 1-2-4, operation window 1-2-5, universal wheel 1-3, hand push rod 1-4, button 1-4-1, water suction pump 1-5, wire-controlled roller skating group 1-6, fixed ring member 1-6 -1, electric control shaft 1-6-2, water pipe limit assembly 1-7, double annular groove steering wheel 1-7-1, spring-type water pipe fixing clamp 1-7-2, water tank fixing assembly 1-8, fixing collar 1-8-1, threaded fixing groove 1-9, connecting rod 2, LED lighting light strip 2-1, threaded fixing end 2-2, water pipe 3, telescopic wheel pulley assembly 4, threaded connection end 4-1, first wheel pulley 4-2, second telescopic assembly 4-3, second wheel pulley 4-4, nozzle 5, connecting line 6. DETAILED DESCRIPTION

[0017] In order to better explain the present invention and facilitate understanding, the present invention is described in detail below through specific implementation modes in conjunction with the accompanying drawings.

[0018] In order to better understand the above technical solution, exemplary embodiments of the present invention will be described in more detail below with reference to the accompanying drawings. Although exemplary embodiments of the present invention are shown in the accompanying drawings, it should be understood that the present invention can be implemented in various forms and should not be limited by the embodiments described herein. On the contrary, these embodiments are provided to enable a clearer and more thorough understanding of the present invention and to fully convey the scope of the present invention to those skilled in the art.

[0019] Embodiment 1 This embodiment provides a temporary spray cooling device for construction sites. Figure 1 As shown, the spray cooling device includes a mobile frame 1, a connecting rod 2, and a water pipe 3 with a plurality of spray heads 5 arranged at equal intervals; In this embodiment, the structure of the mobile frame 1 needs to be explained as follows: Figure 2 As shown, the mobile frame 1 is a structure in which a column 1-1 is fixed to a cavity base 1-2; like Figure 2 As shown, the bottom of the mobile frame 1 is provided with a plurality of universal wheels 1-3; a push handle 1-4 is provided on the outside of the mobile frame 1, and a button 1-4-1 for correspondingly adjusting and controlling the water suction pump 1-5, the LED lighting strip 2-1, and the wire-controlled roller skating group 1-6 is provided on the push handle 1-4. Based on the push handle 1-4 and the universal wheel 1-3, the mobile frame 1 can be conveniently driven to move to a preset position; based on the button 1-4-1 on the push handle 1-4, the function of the spray cooling device can be conveniently adjusted.

[0020] Regarding the structure of the cavity base 1-2, it should be noted that: like Figure 2 As shown, a water tank 1-2-1 is provided in the cavity base 1-2; the top of the water tank 1-2-1 is connected to the bottom of the column 1-1 based on the first telescopic component 1-2-2; A water filling port 1-2-1-1 and a water outlet port 1-2-1-2 are provided on the side of the water storage tank 1-2-1, and a circular through hole 1-2-3 adapted to the water pipe 3 is provided on the top surface of the water storage tank 1-2-1 and the top surface of the cavity base 1-2; One end of the two fixing ropes 1-2-1-3 is symmetrically fixed to the side of the water tank 1-2-1, and the other end with a fixing hook 1-2-1-4 passes through the top surface of the cavity base 1-2; A square through hole 1-2-4 adapted to the water tank 1-2-1 is provided on the bottom surface of the cavity base 1-2, and the square through hole 1-2-4 ensures that the bottom end of the water tank 1-2-1 can smoothly enter and exit the inside and outside of the cavity base 1-2; an operation window 1-2-5 is provided on one side of the cavity base 1-2, and the operation window 1-2-5 is used to facilitate the filling and drainage of the water tank 1-2-1 based on the water filling port 1-2-1-1 and the water outlet port 1-2-1-2; A plurality of water suction pumps 1-5 are fixedly arranged on the top of the cavity base 1-2.

[0021] In this embodiment, for the aforementioned water storage tank 1-2-1, it should be noted that: A high water level monitoring and alarm device and a low water level monitoring and alarm device are provided at a preset height inside the water tank 1-2-1; the high water level monitoring and alarm device and the low water level monitoring and alarm device are used to monitor the water level height inside the water tank 1-2-1. When the water level inside the water tank 1-2-1 is lower than a first preset height, the low water level monitoring and alarm device starts an early warning to remind the operator to start the pump to inject water into the water tank 1-2-1 based on the water pipe connected to the water injection port 1-2-1-1, so as to prevent the structure of the mobile frame 1 from being unstable due to insufficient water in the water tank 1-2-1; when the water level inside the water tank 1-2-1 is higher than a second preset height, the high water level monitoring and alarm device starts an early warning to remind the operator to turn off the pump; when the operation is completed, the operator starts the pump to drain the water inside the water tank 1-2-1 based on the water pipe connected to the water outlet port 1-2-1-2, so as to facilitate the structural movement of the mobile frame 1.

[0022] Regarding the structure of column 1-1, it should be noted that: like Figure 2 As shown, the column 1-1 in the figure is a regular quadrangular prism structure; the structure of the column 1-1 in the present application is a regular polygonal columnar structure, and is not limited to the regular quadrangular prism structure in the figure; The column 1-1 is provided with a water pipe limiting assembly 1-7, a wire-controlled roller skating assembly 1-6, a water tank fixing assembly 1-8, and a threaded fixing groove 1-9 adapted to the threaded fixing ends 2-2 at both ends of the connecting rod 2; wherein the water pipe limiting assembly 1-7, the wire-controlled roller skating assembly 1-6 and the threaded fixing groove 1-9 are fixedly arranged on each side surface corresponding to the column 1-1 from bottom to top; the water tank fixing assembly 1-8 is fixedly arranged on two opposite sides of the column 1-1; Specifically, "the number of sides of the regular polygonal columnar structure corresponding to the column 1-1" is the same as "the number of water suction pumps 1-5", "the number of circular through holes 1-2-3", "the number of water pipe limiter assemblies 1-7", "the number of wire-controlled roller skating assemblies 1-6" and "the number of threaded fixing grooves 1-9". A group of circular through holes 1-2-3 includes two circular through holes 1-2-3, and a group of water pipe limiter assemblies 1-7 includes a double annular groove steering wheel 1-7-1 and two rows of symmetrically arranged spring-type water pipe fixing clamps 1-7-2. The water pipe limiting assembly 1-7 is used to fix and limit the two ends of the water pipe 3; the spring-type water pipe fixing clamps 1-7-2 are set at equal intervals from top to bottom, and the double-annular groove steering wheel 1-7-1 is arranged on the upper side of the top spring-type water pipe fixing clamp 1-7-2; a row of spring-type water pipe fixing clamps 1-7-2 are combined with an annular groove of the double-annular groove steering wheel 1-7-1 to fix and limit the two ends of a water pipe 3, specifically: manually adjust the spring-type water pipe fixing clamp 1-7-2, place the water pipe 3 in the spring-type water pipe fixing clamp 1-7-2, and based on the rebound effect, the spring-type water pipe fixing clamp 1-7-2 clamps the corresponding water pipe 3; the water pipe 3 bypasses the double-annular groove steering wheel 1-7-1 clockwise, so that the water pipe 3 is limited and clamped in the annular groove of the double-annular groove steering wheel 1-7-1 to achieve structural fixed limiting.

[0023] The water tank fixing component 1-8 is used to fix the water tank 1-2-1 at a preset height in combination with the fixing hook 1-2-1-4; the water tank fixing component 1-8 is a plurality of fixing rings 1-8-1 fixed to the side of the column 1-1, adapted to the fixing hooks 1-2-1-4, and arranged vertically at equal intervals; one fixing ring 1-8-1 corresponds to one gear; by adjusting the fixing rope 1-2-1-3 and hanging the fixing hook 1-2-1-4 on the fixing ring 1-8-1, the height of the water tank 1-2-1 can be adjusted.

[0024] In this embodiment, Figure 1 and Figure 3 As shown, different mobile racks 1 are connected based on connecting rods 2; Figure 4 As shown, two LED lighting strips 2-1 are fixedly embedded in the two sides of the connecting rod 2, and the threaded fixed ends 2-2 are fixedly arranged at both ends of the connecting rod 2; the aforementioned LED lighting strips 2-1 are used for nighttime lighting; Figure 1 and Figure 3 , based on the threaded connection and fixation between the threaded fixing end 2-2 and the threaded fixing groove 1-9, the mobile frame 1 is fixedly connected to the connecting rod 2; It should be noted that: the bottom surface of the connecting rod 2 is provided with a plurality of threaded connection holes at equal intervals; Figure 4 and Figure 5 , the telescopic roller skating assembly 4 is fixed to the bottom of the connecting rod 2 at equal intervals based on the threaded connection end 4-1 and the aforementioned threaded connection hole; Regarding the structure of the telescopic roller skating assembly 4, it should be noted that: like Figure 6 As shown, the telescopic wheel skating assembly 4 is a structure in which the first wheel skating member 4-2 is vertically connected to the second wheel skating member 4-4 based on the second telescopic assembly 4-3; the first wheel skating member 4-2 is provided with two annular grooves; the second wheel skating member 4-4 is provided with four annular grooves; Two connecting wires 6 are simultaneously adapted to a telescopic roller skating assembly 4; one end of the connecting wire 6 is fixed to the first roller skating member 4-2, and the other end passes through the second roller skating member 4-4 and the first roller skating member 4-2 in sequence and is horizontally connected to the aforementioned wire-controlled roller skating group 1-6.

[0025] Regarding the structure of the aforementioned wire-controlled roller skating group 1-6, it should be noted that: like Figure 7 As shown, the wire-controlled roller skating group 1-6 is a structure in which a fixed annular member 1-6-1 is nested in an electrically controlled rotating shaft 1-6-2; the fixed annular member 1-6-1 and the electrically controlled rotating shaft 1-6-2 form two annular grooves, and one end of the two connecting wires 6 is respectively fixed to the corresponding annular grooves; furthermore, based on the rotation of the electrically controlled rotating shaft 1-6-2, the stretching degree of the two connecting wires 6 is adjusted, and the telescopic degree of the telescopic roller skating assembly 4 is adjusted; In this embodiment, the two annular grooves of the double annular groove steering wheel 1-7-1 and the two outermost annular grooves of the second wheel slider 4-4 are respectively adapted to the two water pipes, that is, the two water pipes can be fixed by the limited clamping structure based on the above-mentioned two annular grooves; therefore, by adjusting the telescopic degree of the telescopic wheel slider assembly 4, the height of the two water pipes can be adjusted to achieve the adjustment of the height of the nozzle 5 on the water pipe 3.

[0026] In this embodiment, it should be noted that: a plurality of nozzles 5 are provided at equal intervals in the middle section of the water pipe 3, so that after assembly, a nozzle 5 is provided between every two adjacent telescopic roller skating assemblies 4.

[0027] In this embodiment, the design of the telescopic roller skating assembly 4 and the wire-controlled roller skating group 1-6 is mainly based on the idea of ​​"adjusting the water spray height of the nozzle 5 by adjusting the tension of the connecting line 6". The water spray height of the nozzle 5 can be adjusted according to the temperature and smoke conditions at the construction site. Specifically, when the weather is hot, while "increasing the pump power to increase the water spray density", the water spray height is appropriately increased, and the cooling effect of the construction site is improved by expanding the coverage of the water spray; when the smoke and dust at the construction site is large, while "increasing the pump power to increase the water spray density", the water spray height is appropriately adjusted based on the smoke and dust flying height, and the smoke and dust are covered to the maximum extent to improve the dust reduction effect of the construction site; When assembling the water pipe 3 based on the aforementioned telescopic wheel skating assembly 4 and the double annular groove steering wheel 1-7-1, ensure that the "sprinklers 5 located at the left and right ends of the water pipe 3" are lower than the corresponding preset height of the adjacent double annular groove steering wheel 1-7-1, so as to ensure that when "the water spray height of the sprinkler 5 is adjusted by stretching the connecting line 6", there is room for adjustment of the overall structure of the water pipe 3, and there will be no problem of tension in the water pipe 3 structure.

[0028] For the temporary construction site spray cooling device described in the first embodiment, compared with the existing device, the column in this device is a regular polygonal columnar structure, and each set of matching wire-controlled roller skating groups and water pipe limit assemblies are installed on each side of the column from top to bottom in sequence, so that a certain mobile frame can be connected to other preset mobile frames in multiple directions based on actual working conditions, realizing a simplified water supply of "centralized water supply and circulating flow". Through the aforementioned "simplification of the structural assembly process and the simplification of the water supply process", the use efficiency of the device can be improved.

[0029] In the device, the mobile frame is provided with universal wheels, the water tank in the cavity base is connected to the bottom of the column based on the first telescopic component, and the water tank is provided with a fixing rope; based on the above structure, the mobile frame can be moved to a preset position, and the gear position of the fixing rope connected to the water tank fixing component is adjusted so that after the bottom of the water tank touches the ground, water is injected into the water tank to stabilize the overall structure of the mobile frame; ensuring that the stable assembly of the mobile frame structure is achieved by the water injection process, killing two birds with one stone and improving efficiency; In this device, both ends of the water pipe are fixed to the mobile frame based on the water pipe limiting assembly, and the middle part of the water pipe is limited to the annular groove of the telescopic roller skating assembly; based on the above structure, the telescopic degree of the telescopic roller skating assembly can be adjusted based on the connecting line through the wire-controlled roller skating group to adjust the height of the nozzle arranged in the middle part of the water pipe, thereby improving the applicability of the device by adjusting the spraying height.

[0030] In the device, buttons for adjusting and controlling the water suction pump, the LED lighting strip, and the wire-controlled roller skating group are provided at the hand-pushing handle of the mobile frame, so that the device can be easily and conveniently controlled.

[0031] Embodiment 2 This embodiment proposes an operation method of the temporary construction site spray cooling device based on the aforementioned embodiment 1, specifically: Based on the actual needs of the construction site, a preset number of mobile racks 1 are moved to a preset position; By adjusting the gear position of the fixing rope 1-2-1-3 connected to the water tank fixing component 1-8, after the bottom of the water tank 1-2-1 touches the ground, water is injected into the water tank 1-2-1 to stabilize the overall structure of the mobile frame, and the stable assembly of the mobile frame 1 structure is achieved through the water injection process; The multiple mobile frames 1 are structurally connected based on the connecting rod 2; the telescopic roller skating assembly 4 is correspondingly installed on the connecting rod 2, and the wiring operation is performed based on the connecting wire 6, the telescopic roller skating assembly 4 and the wire-controlled roller skating group 1-6; Insert both ends of the water pipe 3 into the corresponding water storage tank 1-2-1 based on the circular through hole 1-2-3, and attach a counterweight to the end of the water pipe 3; assemble the water suction pump 1-5 to the water pipe 3, and limit the two ends of the water pipe 3 based on the water pipe limit assembly 1-7; The middle part of the water pipe 3 is assembled onto the telescopic roller skating assembly 4 , ensuring that a nozzle 5 is correspondingly provided between every two adjacent telescopic roller skating assemblies 4 .

[0032] The functions of the spray cooling device are controlled by pressing the button 1-4-1 installed at the hand push handle 1-4 for correspondingly adjusting and controlling the water suction pump 1-5, the LED lighting light strip 2-1, and the wire-controlled roller skating group 1-6.

[0033] In addition, it should be noted that the column 1-1 of the temporary spray cooling device for the construction site described in the first embodiment is a regular quadrangular prism structure, and its corresponding simplified top view structure is shown in FIG. Figure 8 and Fig. 9 As shown; When the column 1-1 of the temporary spray cooling device at the construction site is a regular triangular prism structure, the corresponding simplified top view structure is as follows: Fig.10 As shown; When the column 1-1 of the temporary spray cooling device at the construction site is a regular pentagonal prism structure, the corresponding simplified top view structure is as follows: Fig.11 shown.

[0034] It should be noted that in the claims, any reference numerals placed between brackets shall not be construed as limiting the claims. The word "comprising" does not exclude the presence of components or steps not listed in the claims. The word "a" or "an" preceding a component does not exclude the presence of a plurality of such components. The use of the words first, second, third, etc., is only for convenience of expression and does not indicate any order. These words may be understood as part of the component name.

[0035] In addition, it should be noted that, in the description of this specification, the description of the terms "one embodiment", "some embodiments", "embodiment", "example", "specific example" or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, unless they are contradictory.

[0036] Although the preferred embodiments of the present invention have been described, those skilled in the art may make other changes and modifications to these embodiments after knowing the basic creative concept. Therefore, the claims should be interpreted as including the preferred embodiments and all changes and modifications falling within the scope of the present invention.

[0037] Obviously, those skilled in the art can make various modifications and variations to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention should also include these modifications and variations.

Claims

1. A temporary spray cooling device for construction sites, characterized in that: The mobile frame is a structure in which a column is fixed to a cavity base; the column is provided with a water pipe limit assembly, a wire-controlled roller skating assembly and a water tank fixing assembly; different mobile frames are connected based on a connecting rod, and a plurality of telescopic roller skating assemblies are provided at the bottom of the connecting rod; The water tank in the cavity base is connected to the bottom of the column based on the first telescopic component; the water tank is provided with a fixing rope; the height of the water tank is adjusted by adjusting the gear position of the fixing rope connected to the water tank fixing component; The two ends of the water pipe are fixed to the mobile frame based on the water pipe limiting assembly, and the middle part of the water pipe is limited to the annular groove of the telescopic roller skating assembly; the wire-controlled roller skating group adjusts the telescopic degree of the telescopic roller skating assembly based on the connecting line to adjust the height of the nozzle arranged in the middle part of the water pipe.

2. The spray cooling device according to claim 1, characterized in that: The structure of the column is a regular polygonal columnar structure; Each set of matching wire-controlled roller skating groups and water pipe limiter components are installed on each side of the column from top to bottom.

3. The spray cooling device according to claim 1, characterized in that: The bottom surface of the cavity base is provided with a square through hole adapted to the water tank, and one side surface of the cavity base is provided with an operation window; The side of the water tank is provided with a water filling port and a water outlet port; the top surface of the water tank and the top surface of the cavity base are provided with circular through holes adapted to fit the water pipe; A water suction pump is arranged on the top of the cavity base, and one water suction pump corresponds to each set of wire-controlled roller skates.

4. The spray cooling device according to claim 1, characterized in that: One end of the fixing rope is fixed to the side of the water tank, and the other end provided with a fixing hook penetrates the top surface of the cavity base; The water tank fixing component is a fixing ring fixed to the side of the column and adapted to the fixing hook.

5. The spray cooling device according to claim 1, characterized in that: The water pipe limiting assembly includes a double annular groove type steering wheel and a plurality of spring type water pipe fixing clamps; The spring type water pipe fixing clamp ring is set at equal intervals from top to bottom, and the double annular groove type steering wheel is arranged on the upper side of the spring type water pipe fixing clamp ring.

6. The spray cooling device according to claim 5, characterized in that: LED lighting strips are fixedly embedded on both sides of the connecting rod; The telescopic roller skating assembly is a structure in which a first roller skating member is vertically connected to a second roller skating member based on a second telescopic assembly; two connecting lines are simultaneously adapted to one telescopic roller skating assembly; The first wheel slide is provided with two annular grooves; the second wheel slide is provided with four annular grooves; One end of the connecting line is fixed to the first wheel slider, and the other end is passed around the second wheel slider and the first wheel slider in sequence and then horizontally connected to the wire-controlled roller skating group.

7. The spray cooling device according to claim 6, characterized in that: The wire-controlled roller skating group is a structure in which a fixed annular part is nested in an electrically controlled rotating shaft; The fixed annular member and the electric control shaft form two annular grooves, and one end of the connecting wire matched on one side is respectively fixed in the corresponding annular groove.

8. The spray cooling device according to claim 6, characterized in that: The two annular grooves of the double annular groove type steering wheel and the two outermost annular grooves of the second wheel sliding member are respectively adapted to the two water pipes.

9. The spray cooling device according to any one of claims 3 or 7, characterized in that: A plurality of universal wheels are arranged at the bottom of the mobile frame; A hand-pushing handle is provided on the outside of the mobile frame, and buttons for adjusting and controlling the water suction pump, the LED lighting light strip, and the wire-controlled roller skating group are provided on the hand-pushing handle.