Underwater pier column foot connecting structure
By using a combination of support, embedded components, outsourcing steel pipes, interposed steel pipe columns and boot beam components in the water pier foot connection structure, the problem of difficulty and high danger of removing temporary pier brackets in the water is solved, and a safe and convenient dismantling process is achieved.
Patent Information
- Application Number
- CN202410933048.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-12
- Publication Date
- 2025-05-02
- Estimated Expiration
- 2044-07-12
AI Technical Summary
In the prior art, the removal of temporary pier next to the water is difficult, dangerous and economically damaged. Especially in the later demolition, the cutting and removal of the pier pillar foot needs to be carried out underwater.
A water-based pier foot connection structure is provided, including a support platform, an embedded component, an outsourcing steel pipe, an interposed steel pipe column and a shoe beam assembly. Through the combination of these components, stable connection and convenient removal of pier foot are achieved.
This structure does not require sludge removal during later demolition, and does not involve underwater cutting. It can directly remove the interpolated steel pipe columns through mechanical equipment, which is safe and convenient, simple in construction, and economical and reasonable.
Smart Images

Figure CN119913821A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of bridge construction, and in particular to an underwater pier foot connection structure. Background Art
[0002] When the steel truss is erected, a temporary pier bracket is usually set up on the side of the corresponding pier. The pier column foot connection method of the traditional pier bracket adopts the first reinforced concrete column foot to be welded or bolted to the foundation. The temporary pier bracket will be removed after the steel truss is erected. At this time, the temporary pier bracket located in the water faces problems such as difficulty in removal, high risk and large economic losses. During the later removal, professionals are usually required to cut and remove the pier column feet underwater. There are great risks in underwater operations. Due to the particularity of river geology, the column feet are covered with silt in the river. The silt is thick and difficult to clean, which makes the operation difficult and causes great economic losses. Summary of the invention
[0003] In view of this, the purpose of the present application is to provide an underwater pier foot connection structure to solve the problem that the pier foot needs to be cut and removed underwater during the later stage of demolition in the prior art, and the underwater operation is high-risk and difficult.
[0004] The technical solution adopted by this application to solve the above technical problems is: The present application provides an underwater pier foot connection structure, comprising: A capping platform, wherein a pre-embedded component is disposed in the capping platform, and the upper surface of the pre-embedded component is flush with the upper surface of the capping platform; The outer steel pipe is fixed to the upper surface of the embedded component; The inner-inserted steel pipe column is obliquely inserted into the outer-wrapped steel pipe, and the outer-wrapped steel pipe and the inner-inserted steel pipe column are fixed by a shoe beam assembly.
[0005] In some embodiments, the outer steel pipe is fixed obliquely to the upper surface of the embedded component, and the outer steel pipe has the same inclination angle as the inner steel pipe column.
[0006] In some embodiments, the inclination angle of the outer steel pipe is 1°~20°.
[0007] In some embodiments, the central axis of the inner inserted steel pipe column and the outer wrapped steel pipe are on the same straight line.
[0008] In some embodiments, a gap is provided between a portion of the inner steel pipe column located inside the outer steel pipe and the outer steel pipe, and the gap is filled with sand and gravel.
[0009] In some embodiments, the particle size of the sand and gravel is 0.5 mm to 2 mm.
[0010] In some embodiments, the inserted steel pipe column is filled with a first concrete; and / or The boot beam assembly includes a first ring plate that is sleeved and fixed on the outer periphery of the inner inserted steel pipe column, the first ring plate is located on the upper part of the outer steel pipe, a second ring plate that is sleeved and fixed on the outer periphery of the inner inserted steel pipe column is provided on the side of the first ring plate away from the outer steel pipe, and a plurality of stiffening plates are provided between the first ring plate and the second ring plate, and each of the stiffening plates is fixed on the outer periphery of the inner inserted steel pipe column.
[0011] In some embodiments, a plurality of gripping plates are evenly arranged at the bottom of the first ring plate, and each of the gripping plates is in contact with the outer periphery of the outer steel pipe; and / or An inner ring plate is arranged inside the inner-inserted steel pipe column, and the inner ring plate and the first ring plate are located on the same horizontal plane.
[0012] In some embodiments, the embedded part includes an anchor plate and a plurality of anchor bars located at the bottom of the anchor plate, the upper surface of the anchor plate is flush with the upper surface of the cap, and each of the anchor bars is located inside the cap.
[0013] In some embodiments, a plurality of stiffening ribs are evenly arranged on the outer periphery of the bottom of the outer steel pipe, and each stiffening rib is fixed to the top of the anchor plate; and / or The cap comprises multiple layers of steel mesh distributed in the vertical direction, multiple main reinforcement bars are vertically distributed in the steel mesh, and the space between the steel mesh and the main reinforcement bars and the upper part of the uppermost steel mesh are filled with second concrete; and / or A sealing plate is provided at the bottom of the inner-inserted steel pipe column. The sealing plate is circular, and the diameter of the sealing plate is greater than or equal to the inner diameter of the inner-inserted steel pipe column, and the diameter of the sealing plate is smaller than the inner diameter of the outer-wrapped steel pipe.
[0014] The pedestal and embedded components of the present application provide the required stability for the underwater pier foot connection structure. The upper part of the embedded component is connected to the outer steel pipe, so that the outer steel pipe is stable and firm. A socket-type connection structure is adopted between the inner steel pipe column and the outer steel pipe, and the inner steel pipe column and the outer steel pipe are fastened by the boot beam component. Specifically, the boot beam component is fixed to the outer periphery of the inner steel pipe column, and the boot beam component only plays a role of fastening and limiting the outer steel pipe, that is, there is no absolute fixation between the boot beam component and the outer steel pipe. When dismantling at the later stage, there is no need to remove the silt covering the pier foot, and it does not involve underwater cutting. The inner steel pipe column can be directly removed by mechanical equipment. It is safe and convenient, simple to construct, and economical and reasonable. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings of the embodiments are briefly introduced below. Obviously, the drawings described below only relate to some embodiments of the present application, but are not intended to limit the present application, wherein: Figure 1 This is a schematic diagram of the underwater pier foot connection structure of an embodiment of the present application; Figure 2 For the embodiment of this application Figure 1 Sectional view of AA in the middle; Figure 3 For the embodiment of this application Figure 1 Cross-sectional view of the middle BB; Figure 4 For the embodiment of this application Figure 1 Cross-sectional view of CC; Figure 5 This is a schematic diagram of the structure of the steel pipe column inserted in the embodiment of the present application; Figure 6 This is a schematic diagram of the structure of the inner ring plate in an embodiment of the present application; Figure 7 This is a schematic diagram of the structure of the cap and embedded components of the embodiment of the present application; Figure 8 It is a top view of the foundation and embedded components of the embodiment of the present application.
[0016] Description of reference numerals: 1-cap, 2-first ring plate, 3-inserted steel pipe column, 4-second ring plate, 5-stiffening plate, 6-outer steel pipe, 7-gap, 8-grab plate, 9-anchor bar, 10-anchor plate, 11-sealing plate, 12-grouting hole, 13-inner ring plate, 14-steel mesh. DETAILED DESCRIPTION
[0017] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of them. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of this application.
[0018] In the description of the present application, it should be understood that the terms "length", "width", "thickness", "up", "down", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicating the orientation or positional relationship are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a unique orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present application. In addition, the terms "first" and "second" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance or indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more features. In the description of the present application, "multiple" means two or more, unless otherwise clearly and specifically defined.
[0019] In the application, the word "exemplary" is used to mean "serving as an example, illustration, or description". Any embodiment described in the present application as "exemplary" is not necessarily to be construed as preferred or advantageous over other embodiments. The following description is given to enable any technician in the field to implement and use the present application. In the following description, details are listed for the purpose of explanation. It should be understood that a person of ordinary skill in the art can recognize that the present application can be implemented without using these specific details. In other instances, known structures and processes are not described in detail to avoid obscuring the description of the present application with unnecessary details. Therefore, the present application is not intended to be limited to the embodiments shown, but is consistent with the widest scope consistent with the principles disclosed in the present application.
[0020] To facilitate understanding of the scheme of the present application, the spline curves and arrows used in the drawings are explained here: the components indicated by the spline curves without arrows are solid components, that is, components with solid structures; the components indicated by the spline curves with arrows are virtual components, that is, components without solid structures.
[0021] The traditional connection method of pier column bases is to weld or bolt the reinforced concrete column base to the foundation. However, when the column base is located in water and under the silt, this connection method has problems such as difficult welding and long construction period.
[0022] See also Figure 1-4 The embodiment of the present application provides an underwater pier foot connection structure, comprising: A cap 1, wherein the cap 1 is provided with an embedded component, and the upper surface of the embedded component is flush with the upper surface of the cap 1; An outer steel pipe 6 is fixed to the upper surface of the embedded component; The inner-inserted steel pipe column 3 is obliquely inserted into the outer-wrapped steel pipe 6, and the outer-wrapped steel pipe 6 and the inner-inserted steel pipe column 3 are fixed by a shoe beam assembly.
[0023] It can be understood that the embedded component of the present application is fixed to the base 1 to provide the required stability for the underwater pier foot connection structure, and the upper part of the embedded component is connected to the outer steel pipe 6 to make the outer steel pipe 6 stable and firm.
[0024] In some embodiments, the outer steel pipe 6 and the inner steel pipe column 3 are both vertically arranged, that is, the outer steel pipe 6 and the inner steel pipe are both perpendicular to the base 1.
[0025] In some embodiments, the outer steel pipe 6 and the embedded component are fixed by double-sided fillet welds. It can be understood that the weld leg size is not less than half of the minimum butt plate thickness. In this application, the weld leg size is not less than half of the minimum anchor plate 10 thickness.
[0026] In some embodiments, the bottom midpoint of the outer steel pipe 6 coincides with the upper midpoint of the embedded component.
[0027] Exemplarily, the material of the outer steel pipe 6 is Q355B.
[0028] In some embodiments, the inner diameter of the inner steel pipe column 3 is 80 mm to 120 mm smaller than the inner diameter of the outer steel pipe 6, such as 80 mm, 85 mm, 90 mm, 95 mm, 100 mm, 105 mm, 110 mm, 115 mm, 120 mm, etc. Within the range, a gap 7 can be formed between the inner steel pipe column 3 and the outer steel pipe 6 in contact with it, so as to facilitate filling of sand and gravel.
[0029] It can be understood that the boot beam assembly is fixed to the outer periphery of the inner inserted steel pipe column 3, and the boot beam assembly only plays a role in tightening and limiting the outer steel pipe 6, that is, there is no absolute fixation between the boot beam assembly and the outer steel pipe 6. The boot beam assembly strengthens the connection ability between the inner inserted steel pipe column 3 and the outer steel pipe 6, and at the same time strengthens the local shear resistance of the inner inserted steel pipe column 3.
[0030] In the present application, the pedestal 1 and the embedded components provide the required stability for the underwater pier foot connection structure. The upper part of the embedded components is connected to the outer steel pipe 6, so that the outer steel pipe 6 is stable and firm. A socket-type connection structure is adopted between the inner steel pipe column 3 and the outer steel pipe 6, and the inner steel pipe column 3 and the outer steel pipe 6 are fastened by the boot beam component. Specifically, the boot beam component is fixed to the outer periphery of the inner steel pipe column 3, and the boot beam component only plays a role in fastening and limiting the outer steel pipe 6, that is, there is no absolute fixation between the boot beam component and the outer steel pipe 6. When dismantling in the later stage, there is no need to remove the silt covering the pier foot, and it does not involve underwater cutting. The inner steel pipe column 3 can be directly removed by mechanical equipment, which is safe and convenient, simple to construct, and economical and reasonable.
[0031] It can be understood that during the later dismantling, the inner-inserted steel pipe column 3 can be directly removed by mechanical equipment, and the outer-wrapped steel pipe 6 in the water can be used multiple times.
[0032] See also Figure 1 In some embodiments, the outer steel pipe 6 is fixed obliquely to the upper surface of the embedded component, and the outer steel pipe 6 has the same inclination angle as the inner steel pipe column 3. In this way, the outer steel pipe 6 and the inner steel pipe column 3 are structurally stable and easy to install.
[0033] It can be understood that the purpose of the inclined setting of the outer steel pipe 6 and the inner steel pipe column 3 is to enable the outer steel pipe 6 and the inner steel pipe column 3 to be located on the existing base 1. At the same time, the inclined setting of the outer steel pipe 6 and the inner steel pipe column 3 can increase the support distance of the upper part of the inner steel pipe column 3, thereby achieving a better support effect.
[0034] It can be understood that the size of the bottom of the outer steel pipe 6 is corrected. It can be understood that the correction refers to the strict control and slight size modification of the size of the outer steel pipe 6 to ensure that the slope of the outer steel pipe 6 is consistent with the design, and the bottom is flat, and the bottom of the outer steel pipe 6 is ensured to fit the embedded components tightly. The upper part of the outer steel pipe 6 is simultaneously corrected in slope to ensure that the slope of the upper opening and the lower opening of the outer steel pipe 6 are consistent. It can also be understood that the outer steel pipe 6 provides support and fixation for the inner steel pipe column 3.
[0035] It can be understood that the size of the bottom of the inserted steel pipe column 3 is corrected. It can be understood that the correction refers to cutting, grinding, etc. of the inserted steel pipe column 3 to ensure that the size is correct. In addition, it is necessary to ensure that the bottom of the inserted steel pipe column 3 can fit tightly with the top of the embedded component, but is not welded and fixed to the embedded component.
[0036] In some embodiments, the inclination angle of the outer steel pipe 6 is 1° to 20°, such as 1°, 2°, 3°, 4°, 5°, 6°, 7°, 8°, 9°, 10°, 11°, 12°, 13°, 14°, 15°, 16°, 17°, 18°, 19°, 20°, etc. Within the angle range, the force requirements can be met while increasing the support distance of the upper part of the inserted steel pipe column 3, and the support effect is better.
[0037] In some embodiments, the central axis of the inner-inserted steel pipe column 3 and the outer-wrapped steel pipe 6 are on the same straight line. In this way, the entire structure is stable and firm, and is easy to install.
[0038] See also Figure 1 In some embodiments, the midpoint of the inner steel pipe column 3, the midpoint of the outer steel pipe 6, the midpoint of the pedestal 1 and the midpoint of the embedded component coincide with each other, so that the pedestal 1 and the embedded component support the outer steel pipe 6 and the inner steel pipe column 3 stably, and the overall structure is stable.
[0039] In some embodiments, a gap 7 is provided between the portion of the inner-inserted steel pipe column 3 located inside the outer-enclosed steel pipe 6 and the outer-enclosed steel pipe 6 , and the gap 7 is filled with sand and gravel.
[0040] It can be understood that the sand and gravel are of moderate coarseness and excellent quality; in the process of filling with sand and gravel, tools are used to continuously and appropriately knock on the outer steel pipe 6 to ensure that the sand and gravel can be completely densely and tightly filled in the gap 7 between the outer steel pipe 6 and the inner steel pipe column 3, which plays a role in limiting the displacement movement of the inner steel pipe column 3 in the outer steel pipe 6, restricts the position of the inner steel pipe column 3, and enhances the stability of the inner steel pipe column 3.
[0041] In some embodiments, the particle size of sand and gravel is 0.5 mm ~ 2 mm, for example 0.5 mm, 0.8 mm, 1 mm, 1.2 mm, 1.5 mm, 1.6 mm, 1.8 mm, 2 mm, etc. Within the particle size range, it is beneficial to fill the gap 7 between the inserted steel pipe column 3 and the outer steel pipe 6 firmly with good density.
[0042] In some embodiments, the inserted steel pipe column 3 is filled with a first concrete.
[0043] It can be understood that the inserted steel pipe column 3 is located in the outer steel pipe 6, and the contact part between the inserted steel pipe column 3 and the top of the outer steel pipe 6 is subjected to a large shear force. Concrete with a strength grade of C30 is filled in the inserted steel pipe column 3 to enhance the shear force requirements of this part and enhance the stability of this part.
[0044] See also Figure 1-4In some embodiments, the boot beam assembly includes a first ring plate 2 which is sleeved and fixed on the outer periphery of the inner steel pipe column 3, the first ring plate 2 is located on the upper part of the outer steel pipe 6, and a second ring plate 4 which is sleeved and fixed on the outer periphery of the inner steel pipe column 3 is provided on the side of the first ring plate 2 away from the outer steel pipe 6, and a plurality of stiffening plates 5 are provided between the first ring plate 2 and the second ring plate 4, and each of the stiffening plates 5 is fixed on the outer periphery of the inner steel pipe column 3.
[0045] During installation, the gap 7 between the inner steel pipe column 3 and the outer steel pipe 6 is filled with sand and gravel to be compacted. The first ring plate 2 and the second ring plate 4 are respectively divided into two half ring plates. After the two half ring plates of the first ring plate 2 are aligned with the outer wall of the inner steel pipe column 3, they are welded into a whole by butt welding; after the two half ring plates of the second ring plate 4 are aligned with the outer wall of the inner steel pipe column 3, they are welded into a whole by butt welding; then the stiffening plate 5 is welded between the first ring plate 2 and the second ring plate 4. It can be understood that each stiffening plate 5 can be welded to the outer wall of the inner steel pipe column 3, or it can be welded to the outer wall of the inner steel pipe column 3. The boot beam assembly enhances the local shear resistance of the inner steel pipe column 3.
[0046] Another installation method is that during installation, the first ring plate 2, the second ring plate 4 and the stiffening plate 5 between the first ring plate 2 and the second ring plate 4 are first welded as a whole, that is, multiple stiffening plates 5 are uniformly welded between the first ring plate 2 and the second ring plate 4, and then the side of the first ring plate 2 is placed on the upper part of the outer steel pipe 6, and then the inserted steel pipe column 3 is passed through the boot beam assembly and placed in the outer steel pipe 6, and then the boot beam assembly is lifted, and the gap 7 between the inserted steel pipe column 3 and the outer steel pipe 6 is filled with sand and gravel to be compacted, and then the boot beam assembly is dropped to place the first ring plate 2 on the upper part of the outer steel pipe 6, and finally the first ring plate 2 and the second ring plate 4 are welded to the outer periphery of the inserted steel pipe column 3. It can be understood that each stiffening plate 5 can be welded to the outer wall of the inserted steel pipe column 3, or it can be welded to the outer wall of the inserted steel pipe column 3.
[0047] It can be understood that the inner diameter of the first ring plate 2 is smaller than the inner diameter of the outer steel pipe 6 .
[0048] See also Figure 1 In some embodiments, a plurality of grab plates 8 are evenly arranged at the bottom of the first ring plate 2 , and each of the grab plates 8 is in contact with the outer periphery of the outer steel pipe 6 .
[0049] It can be understood that multiple grab plates 8 are evenly welded to the bottom of the first ring plate 2, and the grab plates 8 are tightly fastened to the outer wall of the outer steel pipe 6. The grab plates 8 only play a gripping and limiting role on the outer steel pipe 6. The grab plates 8 and the outer wall of the outer steel pipe 6 are not welded and fixed, that is, the grab plates 8 and the outer steel pipe 6 are not absolutely fixed. The boot beam assembly strengthens the connection ability between the inner steel pipe column 3 and the outer steel pipe 6, and at the same time strengthens the local shear resistance of the inner steel pipe column 3.
[0050] In some embodiments, the inner steel pipe column 3 is filled with first concrete, and the first concrete is filled at least to the position of the second ring plate 4. The filling of the inner steel pipe column 3 with the first concrete enhances the connection stability between the inner steel pipe column 3 and the outer steel pipe 6.
[0051] See also Figure 5 and Figure 6 In some embodiments, an inner ring plate 13 is provided inside the inner inserted steel pipe column 3 , and the inner ring plate 13 and the first ring plate 2 are located on the same horizontal plane.
[0052] It can be understood that the inner ring plate 13 is welded to the inner inserted steel pipe column 3, the inner diameter of the inner ring plate 13 is slightly smaller than the inner diameter of the inner inserted steel pipe column 3, and the welding between the inner ring plate 13 and the inner inserted steel pipe column 3 adopts full penetration welding. The inner ring plate 13 is located at the height where the first ring plate 2 is connected to the outer steel pipe 6. The inner ring plate 13 is welded inside the inner inserted steel pipe column 3, which enhances the local stability of the steel pipe column.
[0053] See also Figure 1 and Figure 7 In some embodiments, the embedded part includes an anchor plate 10 and a plurality of anchor bars 9 located at the bottom of the anchor plate 10 , the upper surface of the anchor plate 10 is flush with the upper surface of the pedestal 1 , and each of the anchor bars 9 is located inside the pedestal 1 .
[0054] It can be understood that multiple anchor bars 9 are fixed to the second concrete in the pedestal 1. The anchor bars 9 are made of HRB400 material. The anchor plate 10 is also embedded in the second concrete. The anchor plate 10 is level with the surface of the second concrete. The anchor plate 10 is made of Q355B steel. The anchor plate 10 and the anchor bars 9 are fixed by perforated plug welding. The pedestal 1 and the embedded components provide a guarantee for the overall structural force.
[0055] See also Figure 1 In some embodiments, a plurality of stiffening ribs are evenly arranged on the outer periphery of the bottom of the outer steel pipe 6 , and each stiffening rib is fixed to the top of the anchor plate 10 .
[0056] It can be understood that the stiffening ribs are first welded to the outer steel pipe 6 using double-sided fillet welds. The stiffening ribs are distributed on the bottom periphery of the outer steel pipe 6 at uniform angle intervals. The inclination angle value of the stiffening ribs of the outer steel pipe 6 changes accordingly with the slope of the steel pipe. The stiffening ribs are then welded to the anchor plate 10 using double-sided fillet welds. The stiffening ribs are made of Q355B. The stiffening ribs connect the outer steel pipe 6 to the base 1 and the embedded components to form a whole, further improving the stability of the overall structure.
[0057] See also Figure 8 In some embodiments, the anchor plate 10 is an annular plate, and the inner diameter of the annular plate is smaller than the inner diameter of the inserted steel pipe column 3. The setting of the anchor plate 10 as an annular plate saves materials.
[0058] In some embodiments, the anchor plate 10 is a circular plate, which can provide stable support for the overall structure.
[0059] See also Figure 7 In some embodiments, the foundation 1 includes a plurality of layers of steel mesh 14 distributed along the vertical direction, a plurality of main steel bars are vertically distributed in the steel mesh 14, and the space between the steel mesh 14 and the main steel bars and the upper part of the uppermost layer of the steel mesh 14 are filled with a second concrete.
[0060] It is understood that the second concrete is conventional concrete in the art, and the second concrete can be the same as or different from the first concrete. If the anchor bar 9 collides with the main reinforcement bars and the steel mesh 14 of the cap 1, the position of the anchor bar 9 can be appropriately moved, and the second concrete at the anchor bar 9 should be vibrated and compacted.
[0061] See also Figure 5 In some embodiments, a sealing plate 11 is provided at the bottom of the inserted steel pipe column 3. The sealing plate 11 is circular, and the diameter of the sealing plate 11 is greater than or equal to the inner diameter of the inserted steel pipe column 3, and the diameter of the sealing plate 11 is smaller than the inner diameter of the outer steel pipe 6.
[0062] In some embodiments, the sealing plate 11 is welded to the bottom of the inserted steel pipe column 3 , and the sealing plate 11 plays a role in supporting and sealing the bottom of the inserted steel pipe column 3 .
[0063] It can be understood that when removing, the sealing plate 11 and the inserted steel pipe column 3 are removed together.
[0064] In some embodiments, grouting holes 12 are provided on the inserted steel pipe column 3 above the second ring plate 4 .
[0065] It can be understood that the grouting hole 12 is sealed by welding after the first concrete is added.
[0066] The basic concepts have been described above. Obviously, for those skilled in the art, the above detailed disclosure is only for example and does not constitute a limitation of the present application. Although not explicitly stated herein, those skilled in the art may make various modifications, improvements and amendments to the present application. Such modifications, improvements and amendments are suggested in the present application, so such modifications, improvements and amendments still belong to the spirit and scope of the exemplary embodiments of the present application.
[0067] At the same time, the present application uses specific words to describe the embodiments of the present application. For example, "one embodiment", "an embodiment", and / or "some embodiments" refer to a certain feature, structure or characteristic related to at least one embodiment of the present application. Therefore, it should be emphasized and noted that "one embodiment" or "an embodiment" or "an alternative embodiment" mentioned twice or more in different positions in this specification does not necessarily refer to the same embodiment. In addition, some features, structures or characteristics in one or more embodiments of the present application can be appropriately combined.
Claims
1. An underwater pier foot connection structure, characterized in that: include: A capping platform, wherein a pre-embedded component is disposed in the capping platform, and the upper surface of the pre-embedded component is flush with the upper surface of the capping platform; The outer steel pipe is fixed to the upper surface of the embedded component; The inner-inserted steel pipe column is obliquely inserted into the outer-wrapped steel pipe, and the outer-wrapped steel pipe and the inner-inserted steel pipe column are fixed by a shoe beam assembly.
2. The underwater pier foot connection structure according to claim 1, characterized in that: The outer steel pipe is fixed obliquely on the upper surface of the embedded component, and the outer steel pipe has the same inclination angle as the inner steel pipe column.
3. The underwater pier foot connection structure according to claim 2, characterized in that: The inclination angle of the outer steel pipe is 1°~20°.
4. The underwater pier foot connection structure according to claim 1 or 2, characterized in that: The central axis of the inner-inserted steel pipe column and the outer-wrapped steel pipe are on the same straight line.
5. The underwater pier foot connection structure according to claim 4, characterized in that: A gap is provided between the portion of the inner-inserted steel pipe column located inside the outer-clad steel pipe and the outer-clad steel pipe, and the gap is filled with sand and gravel.
6. The underwater pier foot connection structure according to claim 4, characterized in that: The particle size of the sand and gravel is 0.5 mm to 2 mm.
7. The underwater pier foot connection structure according to claim 1, characterized in that: The inner-inserted steel pipe column is filled with a first concrete; and / or The boot beam assembly includes a first ring plate that is sleeved and fixed on the outer periphery of the inner inserted steel pipe column, the first ring plate is located on the upper part of the outer steel pipe, a second ring plate that is sleeved and fixed on the outer periphery of the inner inserted steel pipe column is provided on the side of the first ring plate away from the outer steel pipe, and a plurality of stiffening plates are provided between the first ring plate and the second ring plate, and each of the stiffening plates is fixed on the outer periphery of the inner inserted steel pipe column.
8. The underwater pier foot connection structure according to claim 7, characterized in that: A plurality of gripping plates are evenly arranged at the bottom of the first ring plate, and each of the gripping plates is in contact with the outer periphery of the outer steel pipe; and / or An inner ring plate is arranged inside the inner-inserted steel pipe column, and the inner ring plate and the first ring plate are located on the same horizontal plane.
9. The underwater pier foot connection structure according to claim 1, characterized in that: The embedded part includes an anchor plate and a plurality of anchor bars located at the bottom of the anchor plate. The upper surface of the anchor plate is flush with the upper surface of the cap, and each of the anchor bars is located inside the cap.
10. The underwater pier foot connection structure according to claim 11, characterized in that: A plurality of stiffening ribs are evenly arranged on the outer periphery of the bottom of the outer steel pipe, and each stiffening rib is fixed to the top of the anchor plate; and / or The cap comprises multiple layers of steel mesh distributed in the vertical direction, multiple main reinforcement bars are vertically distributed in the steel mesh, and the space between the steel mesh and the main reinforcement bars and the upper part of the uppermost steel mesh are filled with second concrete; and / or A sealing plate is provided at the bottom of the inner-inserted steel pipe column. The sealing plate is circular, and the diameter of the sealing plate is greater than or equal to the inner diameter of the inner-inserted steel pipe column, and the diameter of the sealing plate is smaller than the inner diameter of the outer-wrapped steel pipe.
Citation Information
Patent Citations
Bracket used for overlong water pier pre-stress cover beam construction support system
CN104404884A
Construction method for water pier super-long pre-stressed cap beam construction supporting system
CN104452598A
Whole body embedded type rigid pedestal and construction method thereof
CN104963354A
Socket and spigot joint type connecting structure based on T-shaped groove and construction method of socket and spigot joint type connecting structure
CN116607400A
Bracket bracket
CN213625251U