A method for calculating the settlement of adjacent high-rise buildings during canal foundation pit excavation
Through the improved settlement calculation method, combined with the building load and groundwater level changes, the inclination measurement data and floor settlement data of high-rise buildings are analyzed, and the problem of groundwater level changes and complex parameters in the existing technology is solved, and accurate prediction and safety guarantee of settlement of high-rise buildings is achieved.
Patent Information
- Application Number
- CN202510033546.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-09
- Publication Date
- 2025-08-29
- Estimated Expiration
- 2045-01-09
AI Technical Summary
The existing technology fails to effectively consider the impact of groundwater level changes on the settlement of adjacent buildings during the excavation of foundation pits, and lacks analysis of the inclined side data of the building and the settlement data of the bottom building. The calculations are complex and there are many parameters, resulting in large errors in the calculation results.
The improved settlement calculation method is adopted, combining the building load, groundwater level changes and soil permeability coefficient, and the settlement curve is drawn by superimposing the settlement values, and the inclination measurement data and floor settlement data of high-rise buildings are analyzed, and the calculation model is dynamically adjusted to reduce errors.
It improves the accuracy and simplicity of settlement calculations, can timely monitor building deformation, formulate scientific excavation plans, reduce settlement risks, and ensure building structure safety.
Smart Images

Figure CN119939732B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of settlement calculation, in particular to a method for calculating the settlement of adjacent high-rise buildings during a canal foundation pit excavation process. Background Art
[0002] With the rapid development of urbanization, the development of underground space has been increasing. It is a common phenomenon to excavate foundation pits in areas near buildings in cities. The loss of soil caused by foundation pit excavation will lead to surface subsidence. Buildings within the settlement trough will be affected by surface subsidence, plus the subsidence caused by the building's own gravity. Finally, the total subsidence reflected by the building is the total subsidence.
[0003] Existing technologies basically consider the building's own load and settlement calculations under different soil conditions, but lack consideration of settlement caused by changes in groundwater levels. During the foundation pit excavation process based on the canal background, considering that there was a lot of rainfall during the excavation process, the water level around the river also rose sharply, causing the groundwater level to increase. The settlement caused by changes in the groundwater level cannot be ignored.
[0004] The defects of the existing settlement calculation method are:
[0005] 1. Patent document CN106777974B discloses a method for calculating the settlement of surrounding buildings caused by foundation pit excavation. However, this settlement calculation method does not consider the impact of changes in groundwater levels on the settlement of nearby buildings.
[0006] 2. The existing method for calculating the settlement of buildings near foundation pits does not consider the analysis of the inclined side data of the building and the settlement data of the bottom of the building close to the ground, and does not take into account the analysis of the deformation of the building;
[0007] 3. The existing building settlement calculation methods do not consider the spatial distribution of soil deformation outside the pit, that is, they do not consider the relationship between the distance between the settlement point and the foundation pit and the actual settlement;
[0008] 4. Patent document CN108647474B discloses a method for calculating the settlement of soil at the edge of a foundation pit of a pile-supported retaining structure. However, the settlement calculation method in this patent document is relatively complex, requires many parameters, and the workload of measuring parameters and calculation is large. Summary of the Invention
[0009] The purpose of the present invention is to provide a method for calculating the settlement of adjacent high-rise buildings during the excavation of a canal foundation pit, so as to solve the problems raised in the above-mentioned background technology.
[0010] To achieve the above-mentioned object, the present invention provides the following technical solution: The present invention provides a method for calculating the settlement of adjacent high-rise buildings during the excavation of a canal foundation pit, the specific steps of which are as follows:
[0011] Step S1: Considering the building, calculate the surface settlement caused by the foundation pit excavation, and calculate the displacement of the area where the building is located. The calculation formula for the surface settlement caused by the foundation pit excavation is:
[0012]
[0013] Where: S is the settlement, F is the building load, v is the Poisson's ratio, E is the elastic modulus of the soil, h is the depth of the foundation pit, α is the attenuation factor, and x is the distance from the calculated settlement point to the foundation pit;
[0014] Step S2: Considering the groundwater level changes caused by the canal excavation approaching the original river channel and the water level changes around the canal due to rainfall, the settlement caused by groundwater changes is calculated using the following formula:
[0015]
[0016] Where: S w is the settlement caused by water level change (m), K is the soil permeability coefficient, h1 and h2 are the water level heights before and after the change (m), L is the length of the water flow path (m), and β is the correction coefficient;
[0017] Step S3: superimposing the settlement values of the surface settlement and the groundwater level change, and drawing settlement curves for layered excavation at different periods with or without groundwater level change;
[0018] Step S4: analyzing the inclinometric data of the high-rise building and the settlement data of the bottom of the building close to the ground, and drawing a settlement curve of the high-rise building when the deep foundation pit is excavated under the condition of canal water level changes;
[0019] Step S5: The calculated building settlement cannot be completely consistent with the measured settlement value. Therefore, by comparing the difference between the calculated value and the measured value and performing error analysis, it is determined that the result obtained by this calculation method can be controlled within a certain range with the actual error, and can more accurately predict the settlement value of adjacent high-rise buildings caused by the excavation of the canal foundation pit.
[0020] Preferably, the attenuation factor α describes the attenuation degree of the settlement caused by the load in the depth direction, and the attenuation factor α is related to the characteristics of the soil and the load position.
[0021] Preferably, in step S3, the superimposed sedimentation value is S 总 , the specific formula is:
[0022] S 总=S+S w
[0023] Among them, S 总 is the total settlement of the building taking groundwater into account.
[0024] Preferably, in step S4, the specific analysis method for analyzing the inclinometer data of the high-rise building and the settlement data of the bottom of the building close to the ground is: comparing and analyzing whether there is a deviation in the settlement of the high-rise building, and whether the relationship between the settlement of the ground and the settlement of the top of the building is consistent.
[0025] Preferably, in step S4, the oblique side data of the high-rise building includes tilt observation data and displacement observation data.
[0026] Preferably, the oblique side data of the high-rise building in step S4 is obtained and updated by staff through regular measurements.
[0027] Preferably, the tilt observation data is obtained by measuring with a digital display inclinometer.
[0028] Preferably, the displacement observation data includes X-axis horizontal displacement data and Y-axis horizontal displacement data.
[0029] Preferably, the X-axis horizontal displacement data and the Y-axis horizontal displacement data are both obtained by measuring with a fully automatic total station.
[0030] Compared with the prior art, the present invention has the following beneficial effects:
[0031] 1. The calculation formula of the present invention not only considers the load of the building itself, but also takes into account the impact of groundwater level changes caused by conditions such as rainfall on building settlement caused by foundation pit excavation, so that the calculation formula can adapt to the process of canal foundation pit excavation. Considering the changes in groundwater levels makes the application range of the calculation formula wider, and the higher the degree of groundwater level change, the more accurate the settlement calculated by this calculation method is and the smaller the error is.
[0032] 2. The present invention evaluates whether there is any deviation in the settlement of a high-rise building and whether the relationship between the ground settlement and the top settlement is consistent by comparative analysis of the inclinometric data of the high-rise building and the settlement data of the bottom of the building close to the ground; the comparative analysis of the data can help to timely monitor the deformation of the building, evaluate the impact of foundation pit excavation on the stability of the building, correct the settlement calculation model, formulate a scientific excavation plan, and make dynamic adjustments based on real-time data, thereby minimizing the risk of settlement and ensuring the structural safety of the building.
[0033] 3. The calculation formula of the present invention includes the distance x between the position of the calculated settlement point and the foundation pit, so that the calculation result of the calculation formula can change according to the change of the distance between the specific foundation pit and the calculated settlement point, indicating that the calculation formula takes into account the distribution of soil deformation caused by the foundation pit in space, further improving the accuracy of the calculation formula.
[0034] 4. The calculation method of the present invention is simple, requires fewer parameters to be known, and considers more comprehensive influencing factors, so that the final calculation result of the present invention has a smaller error, the result is more accurate, and has broad application prospects. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] Figure 1 A diagram of surface subsidence in the case of groundwater in an embodiment of the present invention;
[0036] Figure 2 This is a diagram of surface subsidence in the absence of groundwater in an embodiment of the present invention;
[0037] Figure 3 This is a horizontal displacement diagram of the X-axis of a building without groundwater according to an embodiment of the present invention;
[0038] Figure 4 This is a diagram of the horizontal displacement of the Y axis of a building without groundwater according to an embodiment of the present invention;
[0039] Figure 5 For the embodiment of the present invention, there is a horizontal displacement diagram of the X-axis of the groundwater structure;
[0040] Figure 6 An embodiment of the present invention includes a diagram of the horizontal displacement of a groundwater structure along the Y axis. DETAILED DESCRIPTION
[0041] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the present invention.
[0042] The technical solution of the present invention will be further described below in conjunction with the accompanying drawings:
[0043] See also Figures 1 to 6 The present invention proposes a specific embodiment of a method for calculating the settlement of adjacent high-rise buildings during canal foundation pit excavation, comprising the following steps:
[0044] Step S1: Considering the building, calculate the surface settlement caused by the foundation pit excavation, and calculate the displacement of the area where the building is located. The calculation formula for the surface settlement caused by the foundation pit excavation is:
[0045]
[0046] Where: S is the settlement, F is the building load, v is the Poisson's ratio, E is the elastic modulus of the soil, h is the depth of the foundation pit, α is the attenuation factor, and x is the distance from the settlement point to the foundation pit;
[0047] Specifically, this calculation method is based on the Boussinesq theory, establishes a surface settlement model caused by foundation pit excavation, and improves the existing calculation method using existing empirical relationships, where S is the surface settlement caused by foundation pit excavation, in meters, the building load F, v Poisson's ratio refers to the ratio of the lateral normal strain to the axial normal strain when the material is subjected to unidirectional tension or compression, also called the lateral deformation coefficient, which is an elastic constant reflecting the lateral deformation of the material, E is the elastic modulus of the soil where the foundation pit is located, which refers to the ratio between the strain of the soil and the external force when the soil is subjected to an external force, h is the depth of the foundation pit to be excavated, in meters, the attenuation factor α describes the attenuation degree of the settlement caused by the load in the depth direction, which is usually related to the characteristics of the soil and the load position, and x is the distance from the location of the settlement calculation point to the foundation pit;
[0048] Specifically, before calculating the ground settlement caused by foundation pit excavation, the building is considered.
[0049] Step S2: Considering the groundwater level changes caused by the canal excavation approaching the original river channel and the water level changes around the canal due to rainfall, the settlement caused by groundwater changes is calculated using the following formula:
[0050]
[0051] Where: S w is the settlement caused by water level change (m), K is the soil permeability coefficient, h1 and h2 are the water level heights before and after the change (m), L is the length of the water flow path (m), and β is the correction coefficient;
[0052] Specifically, h1 is the water level height after the change (m), h2 is the water level height before the change (m), h1-h2 is the water level change height, and L is the length of the groundwater flow path (m);
[0053] Step S3: superimposing the settlement values of the surface settlement and the groundwater level change, and drawing settlement curves for layered excavation at different periods with or without groundwater level change;
[0054] Among them, S 总 =S+S w ;
[0055] Specifically, without considering groundwater, the surface subsidence curve is as follows: Figure 1 As shown, considering the groundwater, the surface settlement curve is as follows Figure 2 As shown;
[0056] Step S4: analyzing the inclinometric data of the high-rise building and the settlement data of the bottom of the building close to the ground, and drawing a settlement curve of the high-rise building when the deep foundation pit is excavated under the condition of canal water level changes;
[0057] Specifically, the analysis method for inclinometer data installed on high-rise buildings and settlement data close to the ground at the bottom of the building is to compare and analyze whether there is any deviation in the settlement of the high-rise building and whether the relationship between the settlement of the ground and the settlement of the top is consistent. This comparative analysis of data can help to timely monitor the deformation of the building, evaluate the impact of foundation pit excavation on the building stability, revise the settlement calculation model, formulate a scientific excavation plan, and make dynamic adjustments based on real-time data, thereby minimizing the risk of settlement and ensuring the structural safety of the building.
[0058] The oblique side data of high-rise buildings includes tilt observation data and displacement observation data. The oblique side data of high-rise buildings is obtained and updated through regular measurements by staff. Staff can go to the observation point for measurement every other day. The tilt observation data is obtained by measuring with a digital display inclinometer, such as the CX-03 digital display tester. The displacement observation data includes X-axis horizontal displacement data and Y-axis horizontal displacement data, and both the X-axis horizontal displacement data and the Y-axis horizontal displacement data are obtained by measuring with a fully automatic total station.
[0059] Without considering the influence of groundwater on building settlement, the settlement curve of the building is as follows: Figure 3 and Figure 4 , Figure 3 and Figure 4 These are the displacement diagrams of the building in the horizontal direction of the X axis and the horizontal direction of the Y axis;
[0060] Considering the influence of groundwater on building settlement, the settlement curve of the building is as follows: Figure 5 and Figure 6 , Figure 5 and Figure 6 These are the displacement diagrams of the building in the horizontal direction of the X axis and the horizontal direction of the Y axis respectively;
[0061] The displacement of the building in the horizontal direction of the X axis represents the offset distance of the building in the horizontal direction, and the unit symbol is m;
[0062] The horizontal displacement of the building's Y axis is the vertical displacement of the building, which is positive from the ground upwards and the unit symbol is m;
[0063] Step S5: The calculated building settlement cannot be completely consistent with the measured settlement value. Therefore, by comparing the difference between the calculated value and the measured value and performing error analysis, it is determined that the result obtained by this calculation method can be controlled within a certain range with the actual error, and can more accurately predict the settlement value of adjacent high-rise buildings caused by the excavation of the canal foundation pit.
[0064] The calculation formula of the present invention includes the distance between the location of the calculated settlement point and the foundation pit as x, and x can vary according to the distance between the specific foundation pit and the calculated settlement point. This takes into account the spatial distribution of soil deformation caused by the foundation pit, thereby being able to explain the different degrees of soil deformation at the building settlement calculation points at different distances outside the pit.
[0065] The calculation formula of the present invention includes the building's own load parameter F, which means that the calculation method of the present invention takes into account the influence of the building's own rigidity on the settlement;
[0066] The calculation formula of the present invention takes into account the influence of the groundwater level on the settlement, so that the calculation formula can adapt to the process of canal foundation pit excavation. Taking into account the changes in the groundwater level makes the application range of the calculation formula wider, and the higher the degree of change in the groundwater level, the more accurate the settlement calculated by this calculation method is and the smaller the error is.
[0067] It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above and that the invention can be embodied in other specific forms without departing from the spirit or essential characteristics of the invention. Therefore, the embodiments should be considered in all respects as illustrative and non-restrictive, and the scope of the invention is defined by the appended claims, not the foregoing description, and all variations within the meaning and range of equivalents of the claims are intended to be included therein. Any reference sign in a claim should not be construed as limiting the claim to which it relates.
Claims
1. A method for calculating the settlement of adjacent high-rise buildings during canal foundation pit excavation, the specific steps are as follows: Step S1: Considering the building, calculate the surface settlement caused by the foundation pit excavation, and calculate the displacement of the area where the building is located. The calculation formula for the surface settlement caused by the foundation pit excavation is: Where: S is the settlement, F is the building load, v is the Poisson's ratio, E is the elastic modulus of the soil, h is the depth of the foundation pit, α is the attenuation factor, and x is the distance from the calculated settlement point to the foundation pit; Step S2: Considering the groundwater level changes caused by the canal excavation approaching the original river channel and the water level changes around the canal due to rainfall, the settlement caused by groundwater changes is calculated using the following formula: Where: S w is the settlement caused by water level change, K is the soil permeability coefficient, h1 and h2 are the water level heights before and after the change, L is the length of the water flow path, and β is the correction coefficient; Step S3: superimposing the settlement values of the surface settlement and the groundwater level change, and drawing settlement curves for layered excavation at different periods with or without groundwater level change; Step S4: analyzing the inclinometric data of the high-rise building and the settlement data of the bottom of the building close to the ground, and drawing a settlement curve of the high-rise building when the deep foundation pit is excavated under the condition of canal water level changes; Step S5: The calculated building settlement cannot be completely consistent with the measured settlement value. Therefore, by comparing the difference between the calculated value and the measured value and performing error analysis, it is determined that the result obtained by this calculation method can be controlled within a certain range with the actual error, and can more accurately predict the settlement value of adjacent high-rise buildings caused by the excavation of the canal foundation pit.
2. The method for calculating the settlement of adjacent high-rise buildings during canal foundation pit excavation according to claim 1, characterized in that: The attenuation factor α describes the attenuation degree of the settlement caused by the load in the depth direction. The attenuation factor α is related to the characteristics of the soil and the load position.
3. The method for calculating the settlement of adjacent high-rise buildings during canal foundation pit excavation according to claim 1, characterized in that: In step S3, the superimposed sedimentation value is S 总 , the specific formula is: S 总 =S+S w Among them, S 总 is the total settlement of the building taking groundwater into account.
4. The method for calculating the settlement of adjacent high-rise buildings during canal foundation pit excavation according to claim 1, characterized in that: In step S4, the specific analysis method for analyzing the inclinometric data of the high-rise building and the settlement data of the bottom of the building close to the ground is: comparing and analyzing whether there is a deviation in the settlement of the high-rise building and whether the relationship between the settlement of the ground and the settlement of the building top is consistent.
5. The method for calculating the settlement of adjacent high-rise buildings during canal foundation pit excavation according to claim 1, characterized in that: In step S4, the oblique side data of the high-rise building includes tilt observation data and displacement observation data.
6. The method for calculating the settlement of adjacent high-rise buildings during canal foundation pit excavation according to claim 1, characterized in that: In step S4, the oblique side data of the high-rise building is obtained and updated through regular measurements by staff.
7. The method for calculating the settlement of adjacent high-rise buildings during canal foundation pit excavation according to claim 5, characterized in that: The tilt observation data is obtained by measuring with a digital display inclinometer.
8. The method for calculating the settlement of adjacent high-rise buildings during canal foundation pit excavation according to claim 5, characterized in that: The displacement observation data includes X-axis horizontal direction displacement data and Y-axis horizontal direction displacement data.
9. The method for calculating the settlement of adjacent high-rise buildings during canal foundation pit excavation according to claim 8, characterized in that: The X-axis horizontal displacement data and the Y-axis horizontal displacement data are both obtained by measuring with a fully automatic total station.
Citation Information
Patent Citations
A method for calculating the settlement of surrounding buildings caused by foundation pit excavation.
CN106777974B
A method for calculating the settlement of soil at the edge of a pile-supported retaining structure foundation pit
CN108647474B
Settlement calculation method for surrounding nearby buildings during excavation of foundation pits
CN106777974A
Deformation foundation settlement calculation method based on building inherent settlement
CN112160354A