Temporary operation transfer implementation releasing method and system and storage medium
During the temporary operation and handover process of nuclear power plants, a unique transaction code is set for boundary change needs and relevant operating processes are executed, and the problems of insufficient information interoperability and lagging information synchronization are solved, and the satisfaction of boundary change needs and information synchronization are achieved.
Patent Information
- Application Number
- CN202510107673.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-23
- Publication Date
- 2025-05-06
AI Technical Summary
During the temporary operation and handover of nuclear power plants, there are problems of insufficient information exchange and lag in information synchronization between the on-site live situation and the management system.
By collecting the boundary change requirements for temporary operation handover, setting a unique transaction code for each boundary change requirements, and executing relevant operation processes in the boundary management system, determining the operation steps for implementing the cancellation.
It realizes the satisfaction of boundary changes during the temporary operation handover process, ensuring information interconnection and synchronization between the on-site live situation and the boundary management system.
Smart Images

Figure CN119941185A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of nuclear power plant operation management, and in particular to a temporary operation handover implementation release method, system and storage medium. Background Art
[0002] As a systematic project, the systems and equipment of a nuclear power plant can be divided into several important links, such as installation, commissioning, and operation. Temporary operation handover is the process of handing over systems and equipment from the commissioning party to the operator. A set of isolation equipment is used to completely separate a temporary operation area from the outside world to demarcate a temporary operation area to prevent the operation activities in the area from affecting the safety of activities in adjacent areas.
[0003] When conducting a temporary operation handover, in order to achieve the boundary integrity of the area where the system and equipment are located, it is necessary to ensure that the boundary is complete and the boundary equipment can be isolated. Its boundary is complete means that the setting of the boundary can disconnect all connections between the temporary operation handover area and the non-temporary operation handover area outside, including the connection of all fluids and electrical circuits in the system and equipment. Boundary equipment can be isolated means that it has the ability to isolate; it can judge the status, can be operated, can be locked and has correct identification.
[0004] During the process of the nuclear power system entering the operation state, since the data between the management systems used by the commissioning party and the operating party cannot be connected, and corresponding physical signs are still required to divide the boundaries at the site of the nuclear power system equipment, there will be insufficient information exchange and information synchronization lag between the on-site actual situation and the management system for boundary changes and debugging progress in the temporary operation handover state. Therefore, it is necessary to determine the process of connecting the on-site actual situation boundaries and information management during the temporary operation handover process.
[0005] It should be noted that the information disclosed in the above background technology section is only used to enhance the understanding of the background of the present invention and does not constitute any limitation to the present invention. Summary of the invention
[0006] In view of the shortcomings of the prior art mentioned above, the present invention provides a method, system and storage medium for releasing the implementation of temporary operation handover. By collecting the boundary change requirements of temporary operation handover, a unique transaction code is set for each boundary change requirement, and the relevant operation process is executed in the boundary management system. The operation steps for implementing the release are determined according to the executed operation process, so as to solve the problems of insufficient information exchange and delayed information synchronization between the on-site actual situation and the management system.
[0007] The present invention provides a method for releasing temporary operation handover implementation, comprising:
[0008] Obtain boundary change requirements for temporary operation transfer and execute corresponding transaction codes;
[0009] Determine the review process based on the work flow corresponding to the transaction code;
[0010] Determine the temporary operation transfer conditions that the transaction code meets, and confirm the operation steps that require changes to the operation process boundary.
[0011] In one embodiment of the present invention, obtaining a boundary change requirement for temporary operation handover includes: obtaining boundary differences in the boundary change requirements by comparison, and determining whether the boundary change requirements are boundary expansion requirements or boundary fusion requirements based on the boundary differences.
[0012] In one embodiment of the present invention, executing the corresponding transaction code includes: executing the application expansion code according to the boundary expansion requirement, or executing the fusion check code according to the boundary fusion requirement.
[0013] In one embodiment of the present invention, the review process is determined based on the work process corresponding to the transaction code, including: creating an isolation application instruction according to the executed transaction code, then generating a corresponding debugging application form based on the isolation application instruction, and then approving the debugging application form, and generating an isolation operation form corresponding to the debugging application form after approval.
[0014] In one embodiment of the present invention, an isolation application instruction is created according to an executed transaction code, including: executing an application creation code and using a conversion tool to fill in the content of the isolation application instruction to complete the creation; wherein the conversion tool is used to input the boundary information filled in the isolation application instruction in the isolation handover step into the boundary information of the temporary operation handover step.
[0015] In one embodiment of the present invention, a corresponding debugging application form is generated based on the isolation application instruction, including: determining the operation content of generating the debugging application form according to the created isolation application instruction, and executing a conflict check code to determine the boundary conflict conditions satisfied by the debugging application form.
[0016] In one embodiment of the present invention, the debugging application form is approved, including: querying the operation process of the debugging application form by executing the application display code, and reviewing and confirming according to the query result; and judging whether the debugging application form meets the boundary fusion condition by executing the fusion check code.
[0017] In one embodiment of the present invention, the temporary operation handover conditions satisfied by the transaction code are determined, and the operation steps of the operation process execution boundary change requirements are confirmed, including: judging whether the boundary change requirements meet the boundary conflict conditions and boundary fusion conditions during the temporary operation handover according to the debugging application form generated by the transaction code; wherein, determining whether the operation steps are approved according to the satisfied boundary conflict conditions, and determining whether the operation steps are fused according to the satisfied boundary fusion conditions.
[0018] The present invention also provides a temporary operation handover implementation release system, comprising a plurality of transaction code modules, wherein the plurality of transaction code modules are used to respectively execute different operation steps in the temporary operation handover implementation release process; wherein the transaction code module comprises an application creation code, an application display code, an application expansion code, a fusion check code and a conflict check code; and the operation steps comprise a boundary expansion step, a boundary fusion step and a boundary release step.
[0019] The present invention also provides a computer-readable storage medium on which a computer program is stored, and the computer program is used to execute the above method.
[0020] The beneficial effects of the present invention are as follows: by collecting the boundary change requirements of temporary operation handover, a unique transaction code is set for each boundary change requirement, and the relevant operation process is executed in the boundary management system. According to the approved transaction code, the specific conditions to be met in the temporary operation handover process are evaluated and determined, and then the operation steps for implementation of release are determined according to the operation process to meet the boundary change requirements in the temporary operation handover process. In this way, the implementation of the release steps realizes the temporary operation handover, ensuring that the on-site actual situation in the temporary operation handover process and the boundary management system maintain information exchange and synchronization.
[0021] It is to be understood that the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] The drawings herein are incorporated into the specification and constitute a part of the specification, showing embodiments consistent with the present invention, and together with the specification, are used to explain the principles of the present invention. Obviously, the drawings described below are only some embodiments of the present invention, and for those of ordinary skill in the art, other drawings can be obtained based on these drawings without creative work. In the drawings:
[0023] Figure 1 A flowchart of the method for releasing the temporary operation handover implementation of the present invention;
[0024] Figure 2 A schematic diagram of boundary changes in the method for releasing temporary operation handover implementation of the present invention;
[0025] Figure 3 The architecture diagram of the temporary operation handover implementation release system of the present invention;
[0026] Figure 4 A flow chart of a method for releasing temporary operation handover implementation of the present invention;
[0027] Figure 5 It is a schematic diagram of the review process in the temporary operation transfer implementation release method of the present invention. DETAILED DESCRIPTION
[0028] The following describes the embodiments of the present invention by specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied by other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention. It should be noted that the features in the following embodiments and embodiments can be combined with each other without conflict. It should also be understood that the terms used in the embodiments of the present invention are to describe specific specific embodiments, rather than to limit the scope of protection of the present invention.
[0029] See also Figures 1 to 5 . It should be noted that the structures, proportions, sizes, etc. illustrated in the drawings in this specification are only used to match the contents disclosed in the specification for people familiar with this technology to understand and read, and are not used to limit the limiting conditions for the implementation of the present invention, so they have no substantial technical significance. Any structural modification, change in proportional relationship, or adjustment of size, without affecting the effects and purposes that can be achieved by the present invention, should still fall within the scope of the technical content disclosed by the present invention. At the same time, the terms such as position and quantitative relationship cited in this specification are only for the convenience of description, and are not used to limit the scope of the implementation of the present invention. Changes or adjustments in their relative relationships should also be regarded as the scope of the implementation of the present invention without substantially changing the technical content.
[0030] When conducting a temporary operation handover, in order to achieve the boundary integrity of the area where the system and equipment are located, it is necessary to ensure that the boundaries are complete and the boundary equipment can be isolated. Its complete boundaries mean that the boundary of the temporary operation handover may not be a completely closed area, that is, the boundaries between adjacent temporary operation handover areas disappear naturally, which is equivalent to forming a large temporary operation handover area, but the areas determined in the form of a temporary operation handover certificate still exist separately. Boundary equipment can be isolated means that the drain and exhaust valves of the system and equipment are no longer selected as boundaries, and their status is set according to the operating procedures or temporary operation instructions. For the boundary changes and debugging progress of the system and equipment during the temporary operation handover process, there will be insufficient information exchange and information synchronization lag between the on-site actual situation and the management system. Therefore, it is necessary to determine the process of connecting the on-site actual situation boundary and information management during the temporary operation handover process.
[0031] See also Figure 1 The present invention provides a method for releasing temporary operation handover implementation, comprising:
[0032] Obtain boundary change requirements for temporary operation transfer and execute corresponding transaction codes;
[0033] Determine the review process based on the work flow corresponding to the transaction code;
[0034] Determine the temporary operation transfer conditions that the transaction code meets, and confirm the operation steps that require changes to the operation process boundary.
[0035] Specifically, in an embodiment of the present invention, when a temporary operation handover operation is required, the boundary change requirements of the temporary operation handover are collected by collecting information such as on-site inspection, equipment operation status inspection and confirmation of the temporary operation handover content. The corresponding transaction code is executed in the corresponding boundary management system, and the transaction code sets a unique transaction code for each boundary change requirement to facilitate subsequent tracking and management. The corresponding transaction code is input in the boundary management system to execute the relevant operation process. The corresponding audit process is set according to the operation process determined by the transaction code, and the auditor, audit steps and audit standards are clarified. The corresponding operation flow can also be executed in the boundary conversion system by means of the transaction code, and the audit process and related information are sent to the relevant personnel involved in the audit, and approved in the boundary conversion system. The auditor checks whether the transaction code meets the requirements of the temporary operation handover according to the set conditions, such as equipment status, personnel qualifications, etc. When all conditions are ensured to be met, the validity of the transaction code is confirmed, that is, the audit is passed. Then, based on the audited transaction code, the specific conditions met in the temporary operation handover process are evaluated and determined, and then the operation steps for implementation of the release are determined according to the operation process executed by it, so as to meet the boundary change requirements in the temporary operation handover process. Executing the release steps in this way achieves temporary operational handover, ensuring that the boundary change requirements are met while ensuring that the operation process complies with safety regulations.
[0036] See also Figure 1 and Figure 2 In one embodiment, obtaining a boundary change requirement for temporary operation handover includes: obtaining a boundary difference in the boundary change requirement by comparison, and determining the boundary change requirement as a boundary expansion requirement or a boundary fusion requirement based on the boundary difference.
[0037] Further, the corresponding transaction code is executed, including: executing the application expansion code according to the boundary expansion requirement, or executing the fusion check code according to the boundary fusion requirement.
[0038] Specifically, in an embodiment of the present invention, by collecting the current boundary information, including the boundary range of the equipment, area or system division, and comparing the boundary information after the boundary change demand is adjusted, the boundary setting and change situation is understood. The existing boundary data is compared with the adjusted expected boundary to identify the difference. And the specific difference content of the boundary is recorded, including the location, size and function of the boundary. Then the boundary change demand type to which it belongs is determined according to the boundary change situation. For example, when the new boundary exceeds the original boundary, it means that the boundary range of the operation or the system equipment resources within the boundary need to be increased, and the reason for the boundary expansion is confirmed, such as adding equipment, expanding the use area, etc., and it is divided into a boundary expansion demand. When the new boundary overlaps or merges with the existing boundary, it means that the system equipment resources or functions need to be integrated, and the reason for the fusion is confirmed, such as reducing redundancy and improving efficiency, etc., and it is divided into a boundary fusion demand: In this way, the boundary change demand of the temporary operation transfer can be clearly obtained, and its type can be accurately determined as a boundary expansion demand or a boundary fusion demand. It is also possible to analyze the impact of the identified boundary change demand differences on operation, management and resource allocation. It is also convenient to communicate with relevant operating departments or operators to confirm the necessity and rationality of boundary change requirements.
[0039] For more details, please see the attached Figure 2 As shown, during the temporary operation handover process, Figure 2 Figures (1) and (2) in the figure show different boundary change requirements. In the boundary change situation shown in Figure (1), there are still other system equipment terminals between the current temporary operation handover boundary and the adjusted temporary operation handover boundary, that is, there are no adjacent areas between the areas covered by the two boundaries. In the boundary change situation shown in Figure (2), there are no other system equipment terminals between the current temporary operation handover boundary and the adjusted temporary operation handover boundary, that is, the areas covered by the two boundaries are adjacent areas. In this way, the boundaries of the adjacent areas can be further cancelled to form a new fusion area, which is also a boundary change situation that meets the requirements of the fusion inspection conditions. In this way, through the boundary fusion operation, the number of boundaries in the temporary operation handover can be reduced, and then the number of boundaries in the temporary operation handover can be reduced, which is convenient for the statistics of the boundary areas to which the system equipment terminals belong when the boundary change operation is performed later, and the operation of placing the on-site isolation signs on the original adjacent boundaries is avoided, thereby improving the boundary management efficiency during the temporary operation handover process.
[0040] Furthermore, according to the previously determined boundary change requirements, confirm whether it is a boundary expansion requirement or a boundary fusion requirement, so as to execute the subsequent processing steps. At the same time, in the boundary management system, according to the boundary expansion requirements, generate a unique application expansion transaction code (make sure the transaction code complies with the organization's coding specifications and management processes), and fill in the relevant form information of the application expansion in the boundary conversion system, such as the applicant information and the specific expanded boundary information (such as location, range, etc.), and then submit the completed application form and transaction code to the corresponding audit department port for approval through the boundary management system. According to the boundary fusion requirements, generate a unique fusion check transaction code, and also fill in the relevant form information of the fusion check in the boundary conversion system, and submit it to the relevant audit department port for evaluation. Finally, according to the audit results, execute the specific operations of boundary expansion or fusion to ensure compliance with the organization's standards and processes. In this way, the transaction code related to the boundary change requirements is executed to ensure the standardization and compliance of the change process.
[0041] See also Figure 1 , Figure 4 and Figure 5 In one embodiment, the review process is determined based on the operation process corresponding to the transaction code, including: creating an isolation application instruction according to the executed transaction code, then generating a corresponding debugging application form based on the isolation application instruction, and then approving the debugging application form, and generating an isolation operation form corresponding to the debugging application form after approval.
[0042] Specifically, in an embodiment of the present invention, the form of the isolation application instruction is filled in by extracting information related to the current transaction code from the boundary conversion system, including, for example, the transaction code, the isolation reason, the specific isolation object (such as equipment, area, etc.) and the applicant information, and then the isolation application instruction is submitted to the review department. After the review is passed, a debugging application form is automatically generated in the boundary conversion system. The debugging application form should include, for example, the isolation application instruction number, the purpose and content of the debugging, the estimated debugging time and the participants, etc. The debugging application form is submitted and the reviewer is designated to review the debugging application form. It should be noted that the review of the isolation application instruction and the debugging application form is performed by different personnel of the relevant departments, for example, the isolation application instruction can be reviewed by the operation manager position of the operation department, and the debugging application form is reviewed by the operation duty officer or the operation manager position on duty. The review content may include, for example, the necessity and rationality of boundary debugging, safety assessment, and the availability of resources and personnel. After the review is passed, the review results are recorded and the debugging application form status is updated. At the same time, the boundary conversion system generates an isolation operation form according to the debugging application form. The isolation operation form should include information such as the debugging application form number, specific steps of the isolation operation, responsible person and execution time, and relevant safety precautions. After confirming that the content of the isolation operation form is correct, it will be officially released to ensure that the operation process corresponding to the transaction code is reviewed and executed efficiently and in a standardized manner.
[0043] Further, creating an isolation application instruction according to the executed transaction code includes: executing the application creation code and using a conversion tool to fill in the content of the isolation application instruction to complete the creation; wherein the conversion tool is used to input the boundary information filled in the isolation application instruction in the isolation transfer step into the boundary information of the temporary operation transfer step.
[0044] Generating a corresponding debugging application form based on the isolation application instruction includes: determining the job content of generating the debugging application form according to the created isolation application instruction, and executing a conflict check code to determine the boundary conflict conditions satisfied by the debugging application form.
[0045] Further, in an embodiment of the present invention, a new isolation application is created by extracting an execution application creation code related to the current transaction code from the boundary conversion system. In the creation process, the isolation application instruction content is quickly filled in by using a conversion tool. After all boundary instructions of the isolation transfer are debugged, and when creating a boundary application for temporary operation transfer, the boundary application number of the isolation transfer is entered into the boundary conversion system to quickly query the application content of the isolation transfer boundary. And by using the application number of the isolation transfer boundary, it is possible to quickly adjust the application number when the temporary operation transfer boundary is created, so as to realize the application content of the isolation transfer boundary directly obtained by using the modified application number of the temporary operation transfer boundary to enter the application content of the temporary operation transfer boundary. And further, according to the relevant requirements of the temporary operation transfer boundary, it is possible to modify the application content of the isolation transfer boundary, quickly create the application content of the temporary operation transfer boundary, thereby reducing the difficulty of creating the temporary operation transfer boundary, saving the labor cost of repeatedly entering the application content when creating the temporary operation transfer boundary, and improving the efficiency of boundary transfer management. Moreover, by checking the boundary conflicts at the temporary operation transfer boundary, the validity of the boundary instructions after the boundary conversion can be guaranteed.
[0046] In one embodiment, by obtaining the created isolation application instruction from the system, the key information in the instruction, such as the isolation object and the relevant time node, is parsed. The specific operation content of the debugging application form is clarified, including but not limited to the debugging purpose, debugging method or steps and the required resources (personnel, tools, etc.). By extracting the conflict verification rules and conditions related to the debugging application form, the boundary conflict conditions that need to be detected, such as time overlap, resource occupation and security restrictions, are confirmed. The conflict rules corresponding to the conflict verification code are used to detect the currently generated debugging application form. For example, by making corresponding modifications according to the relevant modification requirements of the debugging application form before and after the review submission, the conflict between the review of the operation isolation manager platform and the boundary change is resolved, and then the management of the isolation instruction modification before and after the submission of the review is realized separately, so as to ensure the applicability of the modification of the isolation instruction in different scenarios. Further, after the isolation instruction is newly added, when the boundary is submitted, the boundary conflict check is performed on the submitted boundary, so as to ensure the availability and conflict-free of the created temporary operation transfer boundary in the entire boundary management system.
[0047] Furthermore, the debugging application form is approved, including: querying the operation process of the debugging application form by executing the application display code, and reviewing and confirming according to the query result; and judging whether the debugging application form meets the boundary fusion condition by executing the fusion check code.
[0048] Specifically, in an embodiment of the present invention, the debugging application form to be reviewed is queried by using the application display code. Obtaining detailed information of the debugging application form includes: Querying the pending confirmation list: The isolation manager enters the planned plant, unit, system name, isolation operation form number, administrative isolation / operation isolation form number, submission date, application type and other conditions to query the pending confirmation list. Query the returned list: When the isolation manager reviews and returns, the status of the temporary operation transfer or isolation transfer application form is "isolation manager returned", and it is queried through the returned list. Query the confirmed list. When the isolation manager has created isolation and the status of the isolation operation form is in the pending confirmation state, the status of the temporary operation transfer or isolation transfer application form is "confirmed", and it is queried through the implemented list. Query the approved list. When the isolation manager creates isolation, the isolation operation form status is approved / pending approval but has not reached the pending status. The status of the temporary operation transfer or isolation transfer application form is "approved", and it is queried through the approved list. Query the implemented list. The quarantine manager has implemented the quarantine, and the quarantine operation form is in the confirmed quarantine status. The status of the temporary operation transfer or quarantine transfer application form is "Implemented", which can be queried through the implemented list. Query the closed list. When the quarantine manager releases the quarantine, the quarantine operation form is set to the completed / closed status, and the status of the temporary operation transfer or quarantine transfer application form is "Closed", which can be queried through the closed list. Query the unassigned list. When the quarantine manager clicks [Cancel Assignment] on the quarantine operation form, the association between the debugging application form and the quarantine operation form is cut off, and the status of the temporary operation transfer or quarantine transfer application form is "Cancel Assignment", which can be queried through the unassigned list. Confirm the pending confirmation list. Double-click the application number to penetrate to the detail interface, and display the approval or rejection button.
[0049] More specifically, the debugging application form is analyzed by using the fusion check code. To check the boundary fusion conditions, which may include: Overlap within the time period: Ensure that the debugging time does not conflict with other activities or tasks. Resource sharing: Verify whether the required resources are already occupied by other tasks. Security and compliance requirements: Ensure that the debugging activities comply with corporate security standards and compliance regulations. Audit confirmation when the conditions are met: If the debugging application form meets all boundary fusion conditions, it will be marked as "approved" and the temporary operation handover implementation work steps under the boundary fusion conditions will be executed. If not, the temporary operation handover implementation work steps under the non-fusion conditions will be executed.
[0050] In one embodiment, determining whether the temporary operation handover conditions satisfied by the transaction code and confirming the operation steps of the operation process execution boundary change requirements include: determining whether the boundary change requirements satisfy the boundary conflict conditions and boundary fusion conditions during the temporary operation handover according to the debugging application form generated by the transaction code; wherein, determining whether the operation steps are approved according to the satisfied boundary conflict conditions, and determining whether the operation steps are fused according to the satisfied boundary fusion conditions.
[0051] Specifically, in an embodiment of the present invention, by using a transaction code to create a debugging application form and recording relevant information, the scheduled tasks are queried: whether there are other scheduled work contents within the application debugging time period. If there is a conflict, it is recorded as not approved; if there is no conflict, it is marked as approved. That is to say, the necessary information during the isolation transfer is input by the debugging person responsible for inputting, and a new boundary instruction is added based on the application form, thereby realizing the creation and management of the temporary operation transfer boundary. After the isolation application instruction, that is, the debugging application form, is created, since corresponding boundary changes may be involved, corresponding modifications are made according to the relevant modification requirements before and after the boundary review is submitted to resolve the conflict between the operation isolation manager platform review and the boundary change, thereby realizing the separate management of the isolation instruction modification before and after the submission review, so as to ensure the applicability of the isolation instruction modification in different scenarios. Further, after the isolation instruction is added, when the boundary is submitted, the availability and conflict-free nature of the created temporary operation transfer boundary can be ensured by performing a boundary conflict check on the submitted boundary.
[0052] More specifically, by conducting a fusion check on the work content of the isolation operation sheet, the rationality and feasibility of all measures are ensured. After confirming that there are no safety hazards, the decision is made to perform basic isolation without fusion (such as disconnecting the power supply, closing the valve, etc.) or to adjust the area identification and warning (such as adjusting the coverage area of warning signs, fences, etc.) in the case of fusion, that is, to fuse the identification or warning areas with different initial boundaries according to the fusion situation.
[0053] See also Figure 3 The present invention also provides a temporary operation handover implementation release system, including multiple transaction code modules, which are used to respectively execute different operation steps in the temporary operation handover implementation release process; wherein the transaction code module includes an application creation code, an application display code, an application expansion code, a fusion check code and a conflict check code; the operation steps include a boundary expansion step, a boundary fusion step and a boundary release step.
[0054] Specifically, in an embodiment of the present invention, the temporary operation transfer implementation release system may include multiple transaction code modules, each module is used to execute different operation steps in the temporary operation transfer implementation release process. Its core is to manage the boundary conditions in the three main steps of expansion, fusion and release involved in the temporary operation transfer process. In the transaction code module, the application creation code is used to create a new debugging application and record basic information (applicant, operation content, time, etc.). Its input is application information and its output is the generated debugging application form. The application display code is used to query and display the status and detailed information of the current application. Its input is the debugging application form and its output is the current status of the debugging application form information. The application expansion code is used to expand the existing application to increase the debugging scope or time. Its input is the debugging application form and its related content parameters for executing the expansion step, and its output is the updated debugging application form information. The fusion check code is used to check whether the operation content executed by the current debugging application form can share resources with other tasks, that is, to perform boundary fusion on adjacent systems and devices. Its input is the isolation operation form and its output is the fusion feasibility report to determine whether the boundary fusion step can be executed. The conflict check code is used to check the time and resource conflicts between the current application and other scheduled tasks. The input is also the isolation operation sheet, and the output is the conflict check result.
[0055] More specifically, the boundary expansion step realizes boundary status modification of the initial edition boundary based on boundary upgrade instructions according to the created initial edition boundary and the boundary change requirements for the initial edition boundary, that is, the isolation application instructions, during the temporary operation handover stage. When it involves direct modification of the initial edition boundary, or merging and modifying the current initial edition boundary with other initial edition boundaries, the upgrade processing of the initial edition boundary to the upgraded edition boundary can be completed by performing direct modification of the initial edition boundary, or merging and modifying the current initial edition boundary with other initial edition boundaries according to the boundary upgrade instructions.
[0056] The difference between the boundary fusion steps is that the rationality and feasibility of all measures are ensured by fusion checking the work content of the isolation operation sheet. The basic isolation without fusion is performed according to whether there is fusion; or the regional identification and warning adjustment is performed in the case of fusion, that is, the identification or warning areas of different initial boundaries are merged according to the fusion situation.
[0057] The boundary release step is to release the temporary operation transfer boundary by revoking the isolation application instruction created by the application creation code when it is determined that the boundary conditions no longer need to be divided. It includes necessary system checks to ensure that the equipment and system are in a safe state after release, perform recovery operations (such as restoring power, opening valves, etc.), and simultaneously close the isolation operation sheet on the system to record the release situation, ensuring that all relevant personnel are aware of the release status, that is, restoring the relevant boundaries to the initial situation.
[0058] See also Figure 4 and Figure 5 In one embodiment, when the implementation steps are executed in the main control panel module of the boundary management system, for example, the SAP system is used to build the implementation step, the temporary operation transfer, i.e., the application creation of TOTO, is represented according to the executed transaction code, such as "Z32PMTS001", and the isolation application instruction of TOTO is applied for by the debugging person in charge of the debugging branch (the "TOB to TOTO tool" in the attached figure can be understood as the tool of the boundary management system itself, which is not repeated here), that is, the preparation of the TOTO certificate; it also includes the day shift isolation manager of the operation day shift signing and confirming the work permit corresponding to the isolation application instruction, i.e., signing the TOTO certificate, and creating a TOTO class work permit, i.e., WCA (Work Control Authorization), with the debugging information of the isolation application; then, by calling the boundary instruction created by the debugging, i.e., the isolation application instruction, a TOTO class isolation operation sheet, i.e., WCD (Work Clearance Document) is created; similarly, the TOB to TOTO tool is used to compare the isolation operation sheet with the content list of the isolation application; and the WCA / WCD can be set to pending approval / approved, i.e., DEVD / REVD (Development Status / Recovery Status) The WCA / WCD can also be submitted to the operation shift supervisor of the delivery liaison office for review and approval before the TOTO certificate is signed, that is, the review and confirmation certificate; then the on-duty isolation manager on duty will conduct a fusion check on the work content of the WCA / WCD, and select different work steps according to the results of the fusion check, that is, implement the corresponding TOTO isolation measures.
[0059] After confirming that there is no fusion boundary in the work content, the WCA / WCD can be placed in the pending / processed BTG / PTAG (Pending to Go / Processed Tag) status; based on this, the TOTO type isolation operation sheet and isolation sign can be printed; and handed over to the on-site operator for on-site sign hanging; then the on-duty isolation manager can put the temporary operation transfer boundary in the confirmed isolation, that is, ETG (Execution To Go) status; at the same time, the work permit applied for isolation in this status can be approved and set to the executable green light status; finally, the isolation certificate can be printed for record.
[0060] When it is confirmed that there is a fusion boundary in the work content, the isolation of the relevant temporary operation transfer, i.e., TOTO boundary, is lifted according to the fusion inspection prompt; and the approval status of the work permit, i.e., WCA, in the isolation manager is revoked; then the corresponding isolation release operation sheet is printed based on this; and then it is handed over to the on-site operator for on-site card collection; then the on-duty isolation manager can lift the isolation instruction and set the execution completed, i.e., EUG (Execution Undergone) status and put it in an inactive state (putting it in an inactive state ensures that potential safety risks are avoided before all necessary inspections and preparations are completed); finally, the relevant work permit, i.e., WCA, is put back in the issuance status (existing safety risks can be avoided by re-evaluating the issuance of WCA).
[0061] After the implementation steps are completed, when executing the release steps, the on-duty isolation manager will revoke the approval status of the work permit, namely WCA, in the isolation manager; thereby, the temporary operation transfer, namely TOTO's isolation application instruction, is released and can be set to the unable to execute, namely BUG status; accordingly, the TOTO isolation release operation sheet is printed; the on-site delisting is carried out; then the isolation instruction can be released and can be set to the execution completed, namely EUG status; at the same time, all the instructions of the isolation operation sheet, namely WCD, are also in the execution completed, namely EUG status, and the isolation operation sheet WCD is closed; finally, the isolation application WCA is closed.
[0062] The present invention also provides a computer-readable storage medium on which a computer program is stored, and the computer program is used to execute the above method.
[0063] In summary, the present invention provides a method, system and storage medium for implementing the release of temporary operation handover, which collects the boundary change requirements of temporary operation handover and sets a unique transaction code for each boundary change requirement to execute the relevant operation process in the boundary management system. The corresponding review process is set according to the operation process determined by the transaction code, and the reviewers, review steps and review standards are clarified. Then, based on the transaction code that has passed the review, the specific conditions that are met during the temporary operation handover process are evaluated and determined, and then the operation steps for implementing the release are determined according to the operation process that is executed to meet the boundary change requirements during the temporary operation handover process. The release steps are executed in this way to realize the temporary operation handover, ensuring that information is exchanged and synchronized between the on-site actual situation and the boundary management system during the temporary operation handover process.
[0064] The above embodiments are merely illustrative of the principles and effects of the present invention, and are not intended to limit the present invention. Anyone familiar with the art may modify or alter the above embodiments without departing from the spirit and scope of the present invention. Therefore, all equivalent modifications or alterations made by a person of ordinary skill in the art without departing from the spirit and technical concept disclosed by the present invention shall still be covered by the claims of the present invention.
Claims
1. A method for releasing temporary operation handover, characterized in that: include: Obtain boundary change requirements for temporary operation transfer and execute corresponding transaction codes; Determine the review process based on the work process corresponding to the transaction code; Determine the temporary operation handover conditions satisfied by the transaction code, and confirm that the operation process executes the operation steps required by the boundary change.
2. The release method according to claim 1, characterized in that: Obtaining the boundary change requirement of the temporary operation handover includes: obtaining the boundary difference in the boundary change requirement by comparison, and determining that the boundary change requirement is a boundary expansion requirement or a boundary fusion requirement based on the boundary difference.
3. The method for releasing the implementation according to claim 2, characterized in that: Executing corresponding transaction codes includes: executing application expansion codes according to the boundary expansion requirements, or executing fusion check codes according to the boundary fusion requirements.
4. The release method according to claim 1, characterized in that: The audit process is determined based on the work process corresponding to the transaction code, including: creating an isolation application instruction according to the executed transaction code, then generating a corresponding debugging application form based on the isolation application instruction, and then approving the debugging application form, and generating an isolation operation form corresponding to the debugging application form after approval.
5. The release method according to claim 4, characterized in that: Creating an isolation application instruction according to the executed transaction code includes: executing the application creation code and using a conversion tool to fill in the content of the isolation application instruction to complete the creation; wherein the conversion tool is used to input the boundary information filled in the isolation application instruction in the isolation handover step into the boundary information of the temporary operation handover step.
6. The release method according to claim 5, characterized in that: Generating a corresponding debugging application form based on the isolation application instruction includes: determining the job content of generating the debugging application form according to the created isolation application instruction, and executing a conflict check code to determine the boundary conflict conditions satisfied by the debugging application form.
7. The release method according to claim 6, characterized in that: The debugging application form is examined and approved, including: querying the operation flow of the debugging application form by executing the application display code, and reviewing and confirming according to the query result; and judging whether the debugging application form meets the boundary fusion condition by executing the fusion check code.
8. The release method according to claim 1, characterized in that: Determining the temporary operation transfer conditions satisfied by the transaction code and confirming the operation steps of the operation flow to execute the boundary change requirements, including: According to the debugging application form generated by the transaction code, it is determined whether the boundary change requirement meets the boundary conflict condition and boundary fusion condition during temporary operation handover; wherein, it is determined whether the operation step is approved based on the satisfied boundary conflict condition, and it is determined whether the operation step is fused based on the satisfied boundary fusion condition.
9. A temporary operation transfer implementation release system, comprising a plurality of transaction code modules, wherein the plurality of transaction code modules are used to respectively execute different operation steps in the temporary operation transfer implementation release process; wherein: The transaction code module includes an application creation code, an application display code, an application expansion code, a fusion check code and a conflict check code; the operation steps include a boundary expansion step, a boundary fusion step and a boundary release step.
10. A computer-readable storage medium having a computer program stored thereon, wherein the computer program is used to execute the method according to any one of claims 1 to 8.