Leakage blocking construction method for injecting oil soluble polyurethane into inclined hole of upstream face of deformation joint
Patent Information
- Application Number
- CN202510671722.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-05-23
- Publication Date
- 2025-06-24
AI Technical Summary
The traditional deformation joint sealing method is difficult to achieve long-term and stable waterproofing effects when facing complex leakage situations in subway tunnels, especially in special working conditions such as high-pressure water seepage, vibration loads and periodic deformation.
The leakage sealing construction method of oil-filled soluble polyurethane in the deformed joint surface inverted holes is adopted, including pretreatment, inclined hole positioning and drilling, interval jumping hole grouting, epoxy resin reinforcement, water stop installation and waterproof coil reinforcement, etc., to form a composite waterproof layer to enhance the sealing effect.
This method uses inclined hole grouting technology and epoxy resin to form a high-strength and flexible composite waterproof layer, which effectively adapts to special working conditions such as high-pressure water seepage, vibration loads and periodic deformation, and significantly improves the waterproof performance and service life of the deformation joints of the subway tunnel.
Smart Images

Figure CN120193864A_ABST
Abstract
Citation Information
Cited By
A structure and construction method for grading repair of leakage of deformation joint of existing tunnel
CN122812672A