Method for erecting cross-track temporary transfer bridge for entering of business line construction equipment

By obtaining multi-dimensional structure data and stress analysis, and formulating a crossing bridge erection plan and conducting experiments, the problems of inefficiency and insufficient safety in traditional methods are solved, and efficient, safe and stable crossing bridge erection are achieved.

CN120277749AActive Publication Date: 2025-07-08ZHONGTIE ELECTRIZATION BUREAU GRP BEIJING CONSTR ENG
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202510135581.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-02-07
Publication Date
2025-07-08
Estimated Expiration
2045-02-07

AI Technical Summary

Technical Problem

During the construction of railway business lines, the traditional method of erecting temporary crossing bridges lacks scientific data support, resulting in inefficient efficiency and insufficient safety and stability, making it difficult to adapt to complex on-site environments and track state changes.

Method used

By obtaining multi-dimensional structure data, conducting feasibility analysis and stress analysis, formulating a crossing bridge erecting plan, and setting up a test crossing bridge off-site for load-bearing tests, optimizing the crossing bridge design to ensure safety and stability.

Benefits of technology

The safety, stability and efficiency of the mount of the crossing bridge are improved, and can adapt to changes in different site environments and track conditions, ensuring the smooth passage of construction equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120277749A_ABST
    Figure CN120277749A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of transfer bridge building, in particular to a method for building a cross-track temporary transfer bridge for entering business line construction equipment, and the safety, the stability and the efficiency of building the cross-track temporary transfer bridge are improved. The method comprises the following steps: acquiring multi-dimensional structure data and construction equipment basic parameters of a business line construction site; carrying out feasibility analysis on the multi-dimensional structure data to obtain a transfer bridge erection supporting point position set; carrying out stress analysis on the basic parameters of the construction equipment to obtain a load-bearing lower limit index of the transfer bridge; according to the transfer bridge erecting supporting point position set and the transfer bridge bearing lower limit index, a station track-crossing temporary transfer bridge erecting scheme is formulated; building a test transfer bridge outside the yard according to the cross-track temporary transfer bridge building scheme, carrying out a load-bearing test on the test transfer bridge, and obtaining a transfer bridge building optimization scheme according to the building process and the load-bearing test result; and the transfer bridge erecting optimization scheme is applied, construction materials and personnel are arranged, and erecting operation of the station track-crossing temporary transfer bridge is carried out.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of bridge erection, and particularly to a method for erecting a temporary cross-track bridge for the entry of construction equipment on an operating line. Background Art

[0002] During the construction process of a railway operating line, it is often necessary for large construction equipment to enter the site for operation. However, due to the continuity of the railway track and the uninterrupted operation, the entry of construction equipment is often restricted. Especially when it is necessary to cross tracks, how to safely and efficiently erect a temporary bridge for the smooth passage of construction equipment has become an urgent problem to be solved.

[0003] Traditional methods for erecting a temporary cross-track bridge often rely on empirical judgment, lacking scientific data support and systematic analysis methods. This method is not only inefficient but also difficult to ensure the safety and stability of the bridge. In the complex construction site of an operating line, due to the diversity of the site environment, track conditions, and operating line operation conditions, the traditional erection method is not only less efficient but also has great potential safety hazards in terms of safety and accuracy, and is easily affected by external environmental changes, resulting in delays or safety problems during the construction process. Summary of the Invention

[0004] To solve the above technical problems, the present invention provides a method for erecting a temporary cross-track bridge for the entry of construction equipment on an operating line, which improves the safety, stability, and efficiency of the erection of the temporary cross-track bridge.

[0005] In a first aspect, the present invention provides a method for erecting a temporary cross-track bridge for the entry of construction equipment on an operating line, the method comprising:

[0006] Obtaining multi-dimensional structural data of the construction site on the operating line and basic parameters of the construction equipment;

[0007] Performing a feasibility analysis on the multi-dimensional structural data to obtain a set of support points for bridge erection;

[0008] Performing a force analysis on the basic parameters of the construction equipment to obtain a lower limit index of the bridge load-bearing capacity;

[0009] Formulating a construction plan for the temporary cross-track bridge according to the set of support points for bridge erection and the lower limit index of the bridge load-bearing capacity;

[0010] Erecting a test bridge off-site according to the construction plan for the temporary cross-track bridge and performing a load-bearing test on the test bridge, and obtaining an optimized construction plan for the bridge erection according to the erection process and the results of the load-bearing test;

[0011] Applying the optimized construction plan for the bridge erection, arranging construction materials and personnel to perform the erection operation of the temporary cross-track bridge.

[0012] Furthermore, the multi-dimensional structure data includes on-site three-dimensional data, track status change data, and operating line operation data.

[0013] Furthermore, the method for obtaining the set of support points for the temporary bridge across tracks includes:

[0014] Clean and preprocess the multi-dimensional structure data;

[0015] Based on the on-site three-dimensional data, evaluate the environmental and geological conditions to obtain the on-site environmental impact analysis results;

[0016] According to the track status change data, evaluate the impact of the temporary bridge construction on the track;

[0017] Combined with the operating line operation data, evaluate the impact on railway operation during the construction and use of the temporary bridge;

[0018] Comprehensively evaluate the on-site environmental impact analysis results, the impact of the temporary bridge construction on the track, and the impact of the temporary bridge construction on railway operation to obtain the set of support points for the temporary bridge across tracks.

[0019] Furthermore, the method for obtaining the lower limit index of the temporary bridge load-bearing capacity includes:

[0020] Calculate the maximum static load exerted by the equipment on the temporary bridge according to the total weight of the construction equipment and its distribution on the temporary bridge;

[0021] Conduct dynamic analysis on the dynamic load generated when the construction equipment moves on the temporary bridge to obtain dynamic load data;

[0022] Based on the maximum static load and dynamic load data, determine the lower limit index of the temporary bridge load-bearing capacity.

[0023] Furthermore, the method for formulating the construction plan for the temporary bridge across tracks includes:

[0024] Select the temporary bridge structure form according to the set of support points and the lower limit index of the load-bearing capacity;

[0025] Select building materials according to the load-bearing requirements and durability requirements of the temporary bridge;

[0026] Determine the span, width, and height of the temporary bridge according to the size and weight distribution of the construction equipment;

[0027] Design the support structure based on the set of support points;

[0028] Formulate the construction process, including the erection sequence, construction time window, and personnel division of labor of the temporary bridge;

[0029] Formulate safety measures, including safety management at the construction site and response measures for emergencies.

[0030] Furthermore, the method for erecting the test temporary bridge includes:

[0031] Prepare the required building materials, construction equipment and personnel according to the temporary bridge erection plan across the tracks;

[0032] Select an off-site location for erecting the test temporary bridge;

[0033] Erect the temporary bridge on the off-site location according to the support point set and structural design in the plan;

[0034] After erection, conduct quality inspection on the test temporary bridge.

[0035] Furthermore, the method for conducting a bearing capacity test on the test temporary bridge includes:

[0036] Prepare a test load simulating the construction equipment to simulate the load effect of the actual construction equipment on the temporary bridge;

[0037] Install monitoring equipment, including strain gauges and displacement sensors, to monitor the strain and displacement of the temporary bridge under the load;

[0038] Gradually increase the test load to simulate different positions and action modes of the construction equipment on the temporary bridge;

[0039] Record the monitoring data in real time and observe the strain and displacement changes of the temporary bridge;

[0040] Organize and analyze the monitoring data to evaluate the structural performance of the temporary bridge under the test load and identify structural defects and potential safety hazards.

[0041] Furthermore, the method for obtaining an optimized erection plan for the temporary bridge includes:

[0042] Based on the results of the bearing capacity test, identify the problems existing in the temporary bridge and analyze the causes of the problems;

[0043] Propose optimization measures for the identified problems;

[0044] Calculate and analyze the optimized plan to verify its feasibility and effectiveness;

[0045] Determine the optimized erection plan for the temporary bridge according to the verification results.

[0046] In a third aspect, the present application provides an electronic device, including a bus, a transceiver, a memory, a processor, and a computer program stored on the memory and executable on the processor. The transceiver, the memory, and the processor are connected through the bus, and when the computer program is executed by the processor, the steps in any one of the above methods are implemented.

[0047] Fourthly, the present application also provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the steps in any of the above-mentioned methods are implemented.

[0048] Compared with the prior art, the beneficial effects of the present invention are as follows: By obtaining multi-dimensional structural data of the construction site on the operating line, a comprehensive and accurate information basis is provided for the erection of the temporary bridge; the feasibility analysis and force analysis based on the data can more accurately determine the support points and load-bearing capacity of the temporary bridge, thereby improving the accuracy and scientificity of the erection of the temporary bridge; the lower limit index of the load-bearing capacity of the temporary bridge obtained through the force analysis can ensure that the temporary bridge has sufficient safety margin when carrying construction equipment, avoiding safety accidents such as collapse or damage; the erection and load-bearing test of the test temporary bridge further verify the feasibility and safety of the erection plan, ensuring that the finally erected temporary bridge has high stability and reliability.

[0049] Through a systematic analysis and optimization process, the method can quickly formulate an erection plan for the temporary bridge that conforms to the actual situation on site, improving the construction efficiency; at the same time, the method also has high flexibility and can adapt to changes in different site environments, track conditions and operating line conditions, ensuring that construction equipment can pass smoothly.

[0050] Traditional erection methods are easily affected by changes in the external environment, resulting in delays or safety problems during the construction process; while this method can minimize the impact of changes in the external environment on the erection of the temporary bridge through scientific data analysis and optimization process, ensuring the smooth progress of the construction process.

[0051] In summary, the above method for erecting a temporary cross-track bridge for the entry of construction equipment on the operating line not only improves the safety, stability and efficiency of the erection of the temporary cross-track bridge, but also greatly enhances the ability to cope with complex construction environments. BRIEF DESCRIPTION OF THE DRAWINGS

[0052] Figure 1 is a flowchart of the present invention;

[0053] Figure 2 is a flowchart of the method for formulating an erection plan for a temporary cross-track bridge. DETAILED DESCRIPTION OF THE EMBODIMENTS

[0054] In the description of the present application, those skilled in the art should know that the present application can be implemented as a method, an apparatus, an electronic device, and a computer-readable storage medium. Therefore, the present application can be specifically implemented in the following forms: completely hardware, completely software (including firmware, resident software, microcode, etc.), and a combination of hardware and software. In addition, in some embodiments, the present application can also be implemented in the form of a computer program product in one or more computer-readable storage media, and the computer-readable storage media contain computer program code.

[0055] The above-mentioned computer-readable storage media can adopt any combination of one or more computer-readable storage media. Computer-readable storage media include: electrical, magnetic, optical, electromagnetic, infrared, or semiconductor systems, devices, or components, or any combination of the above. More specific examples of computer-readable storage media include: portable computer disks, hard disks, random access memories, read-only memories, erasable programmable read-only memories, flash memories, optical fibers, compact discs read-only memories, optical storage devices, magnetic storage devices, or any combination of the above. In the present application, the computer-readable storage media can be any tangible medium that contains or stores a program, and the program can be used by or in combination with an instruction execution system, device, or component.

[0056] In the technical solution of the present application, the acquisition, storage, use, processing, etc. of data all comply with the relevant provisions of national laws.

[0057] The present application describes the provided method, apparatus, and electronic device through flowcharts and / or block diagrams.

[0058] It should be understood that each block of the flowchart and / or block diagram, as well as the combination of blocks in the flowchart and / or block diagram, can be implemented by computer-readable program instructions. These computer-readable program instructions can be provided to the processor of a general-purpose computer, a special-purpose computer, or other programmable data processing devices, thereby producing a machine. These computer-readable program instructions are executed by a computer or other programmable data processing devices, generating an apparatus that implements the functions / operations specified in the blocks of the flowchart and / or block diagram.

[0059] These computer-readable program instructions can also be stored in a computer-readable storage medium that enables a computer or other programmable data processing device to work in a specific manner. In this way, the instructions stored in the computer-readable storage medium produce an instruction device product that includes instructions for implementing the functions / operations specified in the blocks of the flowchart and / or block diagram.

[0060] Computer-readable program instructions may also be loaded onto a computer, other programmable data processing apparatus, or other devices, causing a series of operational steps to be performed on the computer, other programmable data processing apparatus, or other devices to generate a computer-implemented process, so that the instructions executed on the computer or other programmable data processing apparatus can provide a process for implementing the functions / operations specified in the blocks of the flowchart and / or block diagram.

[0061] The present application will be described below with reference to the accompanying drawings in the present application.

[0062] Embodiment 1: As Figures 1 to 2 shown, the method for erecting a temporary cross-track bridge for the entry of construction equipment on an operating line of the present invention specifically includes the following steps:

[0063] S1. Obtain multi-dimensional structure data of the operating line construction site and basic parameters of construction equipment; the multi-dimensional structure data includes on-site three-dimensional data, track state change data, and operating line operation data;

[0064] The on-site three-dimensional data can reflect the actual spatial layout of the construction site, and the on-site three-dimensional data includes:

[0065] Topography and geomorphology: By means of technical means such as laser scanners, UAV aerial photography, or satellite remote sensing, obtain the topographic map and elevation information of the construction site to understand natural features such as the undulations and gullies of the ground;

[0066] Building layout: Record the positions, heights, and structural types of existing buildings and structures on the site, as well as the directions, spacings, and intersections of railway tracks;

[0067] Underground pipeline information: Through geological exploration and pipeline detection, understand the directions, burial depths, and materials of underground pipelines under the construction site to avoid damage to the pipelines during the erection of the bridge;

[0068] The track state change data reflects the current condition and future change trend of the railway track, and the track state change data includes:

[0069] Track geometric dimensions: Measure geometric dimensions such as gauge, level, alignment, and cross-level of the track to ensure good docking with the track after the bridge is erected and guarantee the smooth passage of construction equipment;

[0070] Track material and wear condition: Understand the material and wear degree of the track, evaluate the bearing capacity and stability of the track, and provide a basis for bridge design;

[0071] Track maintenance records: Consult the maintenance history of the track to understand recent maintenance projects, maintenance times, and maintenance effects, so as to conduct necessary inspections and adjustments on the track before the bridge is erected;

[0072] The operation line operation data reflects the actual situation and future plans of railway operation. The operation line operation data includes:

[0073] Train operation diagram: Obtain the train operation plan for the current and a period of time in the future, understand information such as the departure time, arrival time, running speed, and train number of the train, so as to determine the time window for the erection and demolition of the crossover bridge;

[0074] Train type: Understand the train type and load capacity of the trains passing through the construction site;

[0075] Emergency braking distance: Calculate the emergency braking distance according to the train type and speed to ensure that there is enough safety margin between the erection position of the crossover bridge and the emergency braking distance of the train;

[0076] The basic parameters of construction equipment include:

[0077] Equipment type and size: Understand the type, size, and weight of the construction equipment to ensure that the crossover bridge can meet the passage requirements of the equipment;

[0078] Equipment movement method: Understand the movement method of the construction equipment and its dynamic characteristics during the movement process, providing a basis for dynamic load analysis in the design of the crossover bridge;

[0079] Equipment operation requirements: Understand the special requirements of the construction equipment during the operation process to ensure that the design of the crossover bridge can meet the operation requirements of the equipment.

[0080] In this step, by obtaining multi-dimensional structural data such as on-site three-dimensional data, track status change data, and operating line operation data, as well as a detailed understanding of the basic parameters of construction equipment, the actual situation of the operating line construction site can be comprehensively and accurately grasped; it helps with subsequent construction planning, design, and execution, ensuring the smooth progress of construction activities; the measurement and analysis of track geometric dimensions, material properties, and wear conditions, as well as an understanding of train operation plans and types, help determine the optimal time window for the erection and demolition of the crossover bridge, avoiding unnecessary interference to railway operations; at the same time, based on information such as the type, size, and movement method of construction equipment, a crossover bridge that better meets actual requirements can be designed, improving construction safety and efficiency; by conducting geological exploration and pipeline detection to understand the underground pipeline information beneath the construction site, damage to pipelines during the erection of the crossover bridge can be avoided, protecting the safety of underground facilities; at the same time, recording the building layout also helps avoid damage to existing buildings during construction; a detailed understanding of the basic parameters of construction equipment helps to reasonably arrange the allocation and use of construction resources according to the type, size, and operation requirements of the equipment; it can not only improve construction efficiency but also reduce construction costs; the acquisition and analysis of multi-dimensional structural data and construction equipment basic parameters provide a scientific basis for construction decision-making; it helps formulate more reasonable and feasible construction plans, ensuring the smooth progress of construction activities and the safety and stability of railway operations.

[0081] S2. Conduct a feasibility analysis on the multi-dimensional structural data to obtain the set of support points for the erection of the crossover bridge;

[0082] The method for obtaining the set of support points for the erection of the crossover bridge includes:

[0083] Clean and preprocess the multi-dimensional structural data; remove noise data and unify the formats of data from different sources for subsequent analysis;

[0084] Based on the on-site three-dimensional data, conduct a detailed assessment of the environmental and geological conditions; analyze the characteristics such as terrain undulation and gully distribution at the construction site, and evaluate the impact of the terrain on the erection of the crossover bridge; analyze the locations, heights, and structural types of existing buildings and structures at the site to determine their limitations and potential impacts on the erection of the crossover bridge, and evaluate whether it is necessary to demolish or move some buildings during the erection of the crossover bridge, as well as the related costs and risks; based on the underground pipeline information obtained through geological exploration and pipeline detection, analyze the pipeline routes, burial depths, and materials, and evaluate the impact of the erection of the crossover bridge on the underground pipelines to ensure that the normal operation of the pipelines will not be damaged or affected during the erection of the crossover bridge;

[0085] Evaluate the impact of the ferry bridge erection on the track based on the track status change data; measure the geometric dimensions of the track such as gauge, level, alignment, and direction, and evaluate whether they meet the requirements for the erection of the ferry bridge; analyze the change trend of the track geometric dimensions and predict the change of the track status in the next period of time; understand the track material and wear degree, and evaluate its bearing capacity and stability; analyze the impact of track wear on the ferry bridge erection, such as whether it is necessary to reinforce the track or adjust the ferry bridge design; consult the track maintenance history to understand the recent maintenance projects, maintenance time, and maintenance effects; evaluate the impact of the track maintenance records on the ferry bridge erection;

[0086] Combined with the operation data of the operating line, evaluate the possible impact on railway operation during the erection and use of the ferry bridge; obtain the train operation plan for the current and next period of time, and analyze information such as the departure time, arrival time, running speed, and train number of the train; determine the time window for the erection and demolition of the ferry bridge to avoid unnecessary interference to railway operation; calculate the emergency braking distance according to the type and speed of the train; ensure that there is enough safety margin between the erection position of the ferry bridge and the train emergency braking distance to cope with emergencies;

[0087] Comprehensively evaluate the analysis results of the data in each dimension, determine the feasibility of the ferry bridge erection, and determine the set of the best support points for the ferry bridge erection.

[0088] In this step, by cleaning and preprocessing the multi-dimensional structure data, noise is removed and the data format is unified, providing an accurate and consistent data basis for subsequent analysis; ensuring the accuracy and reliability of the analysis results and avoiding misjudgment caused by inconsistent or incorrect data; based on the on-site three-dimensional data, a detailed evaluation of the terrain undulation, gully distribution, location and structural type of buildings and structures is carried out, and the information of geological exploration and pipeline detection is considered at the same time, which helps to identify potential risks and challenges; by analyzing the geometric dimensions, material, wear degree, and maintenance history of the track, the impact of the ferry bridge erection on the track is accurately evaluated; helping to ensure that the erection of the ferry bridge will not damage the stability and bearing capacity of the track, and at the same time avoiding potential safety hazards caused by track problems; combined with the operation data of the operating line, the impact on railway operation during the erection and use of the ferry bridge is evaluated, and a reasonable erection and demolition time window is determined; helping to ensure that the ferry bridge erection work will not cause unnecessary interference to railway operation and ensuring the smoothness and safety of the railway; comprehensively evaluate the analysis results of the data in each dimension, determine the feasibility of the ferry bridge erection and the set of the best support points; ensuring the scientificity and rationality of the decision-making and improving the success rate and efficiency of the ferry bridge erection.

[0089] S3. Conduct a force analysis on the basic parameters of the construction equipment to obtain the lower limit index of the ferry bridge load-bearing capacity;

[0090] Methods for obtaining the lower limit index of the bridge load-bearing capacity include:

[0091] Based on the total weight of the construction equipment and its distribution on the bridge, calculate the maximum static load imposed by the equipment on the bridge. This process needs to take into account the differences in weight distribution of the equipment under different working conditions.

[0092] Consider the dynamic loads generated when construction equipment moves on the bridge, and conduct dynamic analysis, including evaluating the impact effect, vibration frequency and amplitude of the equipment movement on the bridge;

[0093] Consider the impact of environmental factors on equipment and bridges, including additional loads caused by wind, temperature changes, etc.;

[0094] Analyze the overall stability of the bridge when it is subjected to the load of construction equipment to ensure that the bridge will not overturn or slide under the load;

[0095] Based on the analysis results, determine the type of material used for the bridge and verify the bridge structure based on its mechanical properties. If the preliminary analysis shows that the existing design cannot meet the load-bearing requirements, the structural design of the bridge needs to be adjusted, such as adding support points, changing the cross-sectional shape or thickness of the beam, etc., until the best design solution that ensures both safety and economy is found.

[0096] Based on all the analysis results, the lower limit index of the ferry bridge's load-bearing capacity is determined. The lower limit index of the ferry bridge's load-bearing capacity is used to indicate the minimum load-bearing capacity that the ferry bridge must have to ensure that it can safely support the passage of the scheduled construction equipment. It not only reflects the structural strength of the ferry bridge itself, but also indirectly reflects the safety redundancy of the entire system.

[0097] In this step, by conducting a detailed force analysis of the basic parameters of the construction equipment, the lower limit index of the bridge load can be accurately calculated, thereby ensuring that the bridge has sufficient minimum load-bearing capacity to safely support the passage of the scheduled construction equipment; greatly reducing the safety risks caused by insufficient load-bearing; in the analysis process, the weight distribution differences of the equipment under different working conditions, the dynamic loads generated during movement, and the impact of environmental factors on the equipment and the bridge are considered, so that the design of the bridge is more in line with the actual situation and the accuracy and reliability of the design are improved; based on the analysis results, the structural design of the bridge can be adjusted and optimized to achieve the best design solution that can ensure safety and achieve economy; it helps to reduce construction costs and improve the economic benefits of the project; the determination of the lower limit index of the bridge load not only reflects the structural strength of the bridge itself, but also indirectly reflects the safety redundancy of the entire system; through the analysis of this step, it can provide a strong basis for construction decisions; this step not only ensures the safety of construction activities through detailed force analysis and structural design optimization, but also improves the accuracy and economy of the bridge design.

[0098] S4. Develop a construction plan for the temporary cross-track bridge according to the set of support points for the bridge erection and the lower limit index of the bridge's load-bearing capacity.

[0099] The method for developing a construction plan for the temporary cross-track bridge includes:

[0100] Select the bridge structure form according to the set of support points and the lower limit index of the load-bearing capacity; the bridge structure forms include beam bridges, arch bridges, suspension bridges, etc.

[0101] Select building materials according to the load-bearing requirements and durability requirements of the bridge; the building materials include steel, concrete, wood, etc.

[0102] Determine the span, width, and height of the bridge according to the size and weight distribution of the construction equipment; ensure that the bridge can accommodate the smooth passage of the construction equipment, while considering a certain safety margin.

[0103] Design the support structure based on the set of support points; this includes support columns, cross beams, connectors, etc., to ensure that the bridge has sufficient stability and stiffness when bearing loads.

[0104] Develop a detailed construction process, including the erection sequence of the bridge, construction time window, personnel division of labor, etc.; ensure that the construction activities can be carried out efficiently and orderly, while reducing the impact on railway operations.

[0105] Develop comprehensive safety measures, including safety management at the construction site, response measures for emergencies, etc.; ensure the safety of construction personnel and the safety of the bridge erection process.

[0106] The construction plan for the temporary cross-track bridge includes:

[0107] Use disk buckle scaffolds for erection; the longitudinal spacing of the vertical poles is 600 mm, locally 900 mm and 300 mm, and the transverse spacing is 600 mm; the step distance of the horizontal bars is 500 mm, and a full set of steel pipe horizontal scissors braces is arranged at the top layer of the horizontal bars; the main keel is erected with channel steel, and the secondary keel is laid flat with channel steel, and the secondary keel is the finished surface.

[0108] First lay the first channel steel longitudinally between the sleepers, then lay the second channel steel transversely, place the inverted top supports on the second channel steel according to the designed spacing, and then install the vertical poles.

[0109] Erect from both platforms towards the middle at the same time. When the vertical pole spacing and the horizontal bar length modulus do not match during the closure in the middle, use steel pipes for tying. Four are arranged horizontally and two are arranged vertically along the height direction. The tying rods are connected to the vertical poles of the scaffold through fasteners, and two connection points are set at each end.

[0110] To ensure that the coping stones are not damaged, thick formwork is laid on the platform surface, thick wooden planks are laid at the coping stones, thick formwork is nailed to the side to protect the side of the coping stones, and three sets of backstays are arranged at the bottom of the coping stones; three horizontal braces are arranged horizontally on the platform side wall and two horizontal braces are arranged vertically along the height direction. The horizontal braces are made of steel pipes sleeved with bottom supports. The steel pipes are connected to the vertical poles of the scaffold, and three connection points are set to protect the side wall and prevent the scaffold from tilting forward.

[0111] Since the carrying capacity of the trench cover plate is weak, it is prohibited to directly install the vertical poles on the trench cover plate. The vertical poles are supported by setting channel steel on the concrete surfaces on both sides of the trench cover plate; to avoid installing the vertical poles at the edge of the steps or conflicting with the communication pipeline positions, the vertical poles are supported by setting channel steel supporting beams.

[0112] The width of the overpass is expanded outwards on both sides. First, the rails are covered with quilts to prevent the generation of red light bands, and thick plywood hard protection is covered to prevent the materials from bumping against the rails during the erection process.

[0113] In this step, by comprehensively considering factors such as the set of support points, the minimum load-bearing index, the size and weight distribution of construction equipment, etc., the structural form and building materials of the overpass can be scientifically selected, and the span, width and height of the overpass can be accurately determined; it ensures that the overpass not only meets the construction requirements but also has sufficient safety margins; the support structure designed based on the set of support points, including support columns, cross beams, connectors, etc., ensures that the overpass has sufficient stability and stiffness when bearing loads; at the same time, the comprehensive safety measures formulated effectively guarantee the safety of construction personnel and the safety of the overpass erection process; by formulating a detailed construction process, including the erection sequence of the overpass, the construction time window, personnel division of labor, etc., it can ensure that the construction activities are carried out efficiently and orderly; it not only improves work efficiency but also reduces the impact on railway operations; the specific settings such as the use of disc buckle scaffolds for erection, the spacing of vertical poles and the step distance of horizontal poles mentioned in the plan show the adaptability and flexibility of the plan to different site conditions; during the erection of the overpass, protective measures are taken for key parts such as the platform surface, coping stones and side walls to avoid damage during the construction process; in addition, the plan also considers the reusability and environmental protection of materials, which helps to achieve sustainable development; the overpass erection plan for crossing tracks formulated in this step has multiple beneficial effects such as scientificity and accuracy, stability and safety, efficiency and orderliness, adaptability and flexibility, and protection and sustainability, providing a strong guarantee for the construction safety of the railway operating line.

[0114] S5. Erect a test overpass off-site according to the overpass erection plan for crossing tracks, and conduct a load-bearing test on the test overpass. Based on the erection process and the results of the load-bearing test, obtain an optimized overpass erection plan.

[0115] The erection method of the test overpass includes:

[0116] According to the construction plan for the temporary cross-track bridge, prepare the required construction materials, construction equipment and personnel;

[0117] Select an off-site location similar to the construction site environment of the operating line for building the test bridge;

[0118] Build the bridge on the off-site location according to the support point sets and structural design in the plan;

[0119] After completion of the construction, conduct a comprehensive quality inspection of the test bridge, including aspects such as dimensions, shape, material strength, etc.;

[0120] Ensure that the test bridge meets the requirements of the design plan and has the conditions for carrying out the load-bearing test;

[0121] Methods for conducting the load-bearing test on the test bridge include:

[0122] Prepare test loads similar to the weight and dimensions of the construction equipment to simulate the load effect of the actual construction equipment on the bridge;

[0123] Install monitoring equipment, including strain gauges and displacement sensors, to monitor the strain and displacement of the bridge under the action of the load;

[0124] Gradually increase the test load to simulate different positions and action modes of the construction equipment on the bridge;

[0125] Record the monitoring data in real time and observe the changes in the strain and displacement of the bridge;

[0126] Sort out and analyze the monitoring data to evaluate the structural performance of the bridge when bearing the test load;

[0127] Compare the test results with the expected values in the design plan to identify possible structural defects or safety hazards;

[0128] Methods for obtaining the optimized construction plan for the bridge include:

[0129] According to the results of the load-bearing test, identify the problems existing in the structural performance, stability or safety of the bridge;

[0130] Analyze the causes of the problems, which may be unreasonable design, insufficient material strength or errors in the construction process, etc.;

[0131] For the identified problems, propose corresponding optimization measures; including adjusting the support points, strengthening the structural connections, replacing high-strength materials, etc.;

[0132] Calculate and analyze the optimized plan to verify its feasibility and effectiveness;

[0133] Based on the verification results, determine the final optimized plan for the erection of the temporary bridge; ensure that the optimized plan not only meets the requirements for the passage of construction equipment but also has sufficient safety and stability.

[0134] In this step, by erecting a test temporary bridge off-site and conducting a load-bearing test, the feasibility and effectiveness of the erection plan for the temporary bridge across multiple tracks can be visually inspected; this practical process not only verifies the rationality of the design plan but also discovers existing structural defects or safety hazards through the feedback of real-time monitoring data, providing an important basis for subsequent optimization; during the load-bearing test, by gradually increasing the test load and monitoring the strain and displacement of the temporary bridge in real time, the structural performance of the temporary bridge under the actual load of construction equipment can be accurately evaluated; it helps to timely discover and solve potential safety problems, thus ensuring that the finally erected temporary bridge not only meets the construction requirements but also has sufficient safety and stability; through the erection and load-bearing test of the test temporary bridge, the quantity and specifications of the required building materials, construction equipment, and personnel can be determined more precisely, avoiding resource waste; at the same time, through the design and implementation of the optimized plan, the cost of erecting the temporary bridge can be effectively reduced and the construction efficiency can be improved; during the implementation of this step, multidisciplinary knowledge such as structural mechanics, materials science, and construction technology needs to be comprehensively applied for plan design and optimization; it not only improves the professional level of technical personnel but also stimulates innovative thinking, providing impetus for the continuous improvement and innovation of the erection technology of the temporary bridge across multiple tracks; ensure the quality and safety of the erection of the temporary bridge, thus effectively guaranteeing the continuity and safety of railway operation.

[0135] S6. Apply the optimized plan for the erection of the temporary bridge, arrange construction materials and personnel, and carry out the erection operation of the temporary bridge across multiple tracks.

[0136] According to the material list in the optimized plan, prepare the required structural materials, connectors, support devices, etc., and ensure that all materials meet the quality standards.

[0137] Prepare construction equipment and safety inspection instruments to ensure that the equipment performance is good and meets the construction requirements.

[0138] According to the construction plan, form a professional construction team, including structural engineers, safety supervisors, operators, etc., clarify the job responsibilities of each person, and conduct safety education and skills training.

[0139] Re-inspect the construction site of the operating line, confirm the support points, evaluate the impact of the on-site environment on the erection operation, and formulate an emergency plan.

[0140] According to the set of support points in the optimized plan, carry out the foundation construction to ensure the stability and durability of the support structure.

[0141] According to the design plan, assemble the prefabricated bridge crossing components in sequence, firmly connect the bridge crossing components together to ensure the integrity and stability of the structure; conduct quality inspections on key connection parts to ensure reliable connections;

[0142] During the erection process, set up safety warning signs and equip safety protection facilities to ensure the safety of construction workers and passing trains;

[0143] During the erection process, use monitoring equipment to monitor the stress, deformation, etc. of the bridge crossing structure in real time, and promptly discover and handle abnormal situations;

[0144] After the erection is completed, conduct a comprehensive quality inspection on the bridge crossing, including aspects such as dimensions, shape, material strength, connection quality, etc., to ensure compliance with the design requirements.

[0145] In this step, by strictly following the optimized plan for construction preparation and erection operations, the efficiency and accuracy of the bridge crossing erection are ensured; the material list, construction equipment selection, construction team formation, and on-site investigation in the optimized plan have all been carefully designed and scientifically analyzed, avoiding the empiricism and randomness in traditional erection methods, thereby improving the erection efficiency and accuracy; by preparing safety protection facilities, setting up safety warning signs, conducting safety education and skills training, etc., the safety of construction workers during the erection process is ensured; at the same time, the stress, deformation, etc. of the bridge crossing structure are monitored in real time, and abnormal situations are promptly discovered and handled, further ensuring the stability and safety of the bridge crossing; it can effectively reduce potential safety hazards during the construction process and improve the overall construction safety; the comprehensive quality inspection of the bridge crossing ensures that the bridge crossing meets the design requirements; it helps to improve the overall performance and service life of the bridge crossing, while meeting the requirements of relevant regulations and standards and enhancing compliance; measures such as formulating emergency plans and evaluating the on-site environment reflect the flexibility and adaptability of this method in the face of complex and changeable on-site environments; by promptly adjusting the construction plan and taking corresponding measures, the smooth progress of the bridge crossing erection operation can be ensured, and various emergencies can be effectively dealt with.

[0146] In addition, the present application also provides an electronic device, including a bus, a transceiver, a memory, a processor, and a computer program stored on the memory and executable on the processor. The transceiver, the memory, and the processor are respectively connected by the bus. When the computer program is executed by the processor, it realizes each process of the method embodiment for controlling the output data above, and can achieve the same technical effects. To avoid repetition, it will not be elaborated here.

[0147] The above are only the preferred embodiments of the present invention. It should be noted that for those of ordinary skill in the art in this technical field, without departing from the technical principle of the present invention, several improvements and modifications can be made, and these improvements and modifications should also be regarded as the protection scope of the present invention.

Claims

1. Method for erecting temporary cross-track ferry bridge for construction equipment entering operating line, characterized in that, The method includes: Obtaining multi-dimensional structural data and basic parameters of construction equipment at the construction site of the operating line; Conducting a feasibility analysis on the multi-dimensional structural data to obtain a set of support points for the erection of the temporary bridge; Conducting a force analysis on the basic parameters of the construction equipment to obtain the lower limit index of the load-bearing capacity of the temporary bridge; Formulating a construction plan for the temporary bridge across the track based on the set of support points for the erection of the temporary bridge and the lower limit index of the load-bearing capacity of the temporary bridge; Erecting a test temporary bridge off-site according to the construction plan for the temporary bridge across the track, conducting a load-bearing test on the test temporary bridge, and obtaining an optimized construction plan for the temporary bridge based on the erection process and the results of the load-bearing test; Applying the optimized construction plan for the temporary bridge, arranging construction materials and personnel, and carrying out the erection operation of the temporary bridge across the track.

2. The method for erecting a temporary cross-track bridge for the entry of construction equipment on the operating line according to claim 1, characterized in that, The multi-dimensional structural data includes on-site three-dimensional data, track status change data, and operating line operation data.

3. The method for erecting a temporary cross-track bridge for the entry of construction equipment on the operating line according to claim 2, characterized in that, The method for obtaining the set of support points for the erection of the temporary bridge includes: Cleaning and preprocessing the multi-dimensional structural data; Based on the on-site three-dimensional data, evaluating the environmental and geological conditions to obtain the analysis results of the impact of the on-site environment; Evaluating the impact of the erection of the temporary bridge on the track according to the track status change data; Combining the operating line operation data to evaluate the impact on railway operation during the erection and use of the temporary bridge; Comprehensively evaluating the analysis results of the impact of the on-site environment, the impact of the erection of the temporary bridge on the track, and the impact of the erection of the temporary bridge on railway operation to obtain the set of support points for the erection of the temporary bridge.

4. The method for erecting a temporary cross-track bridge for the entry of construction equipment on the operating line according to claim 1, characterized in that The method for obtaining the lower limit index of the load-bearing capacity of the temporary bridge includes: Calculating the maximum static load exerted by the equipment on the temporary bridge according to the total weight of the construction equipment and its distribution on the temporary bridge; Conducting a dynamic analysis on the dynamic load generated when the construction equipment moves on the temporary bridge to obtain dynamic load data; Determining the lower limit index of the load-bearing capacity of the temporary bridge based on the maximum static load and the dynamic load data.

5. The method for erecting a temporary cross-track bridge for the entry of construction equipment on the operating line according to claim 1, characterized in that, The method for formulating a construction plan for the temporary bridge across the track includes: Selecting the structural form of the temporary bridge according to the set of support points and the lower limit index of the load-bearing capacity; Selecting building materials according to the load-bearing requirements and durability requirements of the temporary bridge; Determining the span, width, and height of the temporary bridge according to the size and weight distribution of the construction equipment; Designing the support structure based on the set of support points; Formulating a construction process, including the erection sequence of the temporary bridge, the construction time window, and the personnel division of labor; Formulating safety measures, including safety management at the construction site and response measures for emergencies.

6. The method for erecting a temporary cross-track bridge for the entry of construction equipment on the operating line as described in claim 1, characterized in that, The method for erecting the test temporary bridge includes: Preparing the required building materials, construction equipment, and personnel according to the construction plan for the temporary bridge across the track; Selecting an off-site location for erecting the test temporary bridge; Erecting the temporary bridge off-site according to the set of support points and the structural design in the plan; After the erection is completed, conducting a quality inspection on the test temporary bridge.

7. The method for erecting a temporary cross-track bridge for the entry of construction equipment on the operating line as described in claim 1, characterized in that, The method for conducting a load-bearing test on the test temporary bridge includes: Preparing a test load simulating the construction equipment to simulate the load effect of the actual construction equipment on the temporary bridge; Installing monitoring equipment, including strain gauges and displacement sensors, to monitor the strain and displacement of the temporary bridge under the load; Gradually increasing the test load to simulate different positions and action modes of the construction equipment on the temporary bridge; Record the monitoring data in real time and observe the strain and displacement changes of the ferry bridge; Sort out and analyze the monitoring data, evaluate the structural performance of the ferry bridge under the test load, and identify structural defects and potential safety hazards.

8. The method for erecting a temporary cross-track bridge for the entry of construction equipment on the operating line as claimed in claim 1, wherein Methods for obtaining an optimized erection plan for the ferry bridge, including: Based on the results of the bearing test, identify the problems existing in the ferry bridge and analyze the causes of the problems; Propose optimization measures for the identified problems; Calculate and analyze the optimized plan to verify its feasibility and effectiveness; Determine the optimized erection plan for the ferry bridge according to the verification results.

9. Electronic equipment for erecting a temporary cross-track bridge for the entry of construction equipment on an operating line, comprising a bus, a transceiver, a memory, a processor, and a computer program stored on the memory and operable on the processor, wherein the transceiver, the memory, and the processor are connected by the bus, and characterized in that, When the computer program is executed by the processor, it implements the steps in the method described in any one of claims 1-7.

10. A computer-readable storage medium having a computer program stored thereon, characterized in that, When the computer program is executed by the processor, it implements the steps in the method described in any one of claims 1-7.

Citation Information

Patent Citations

  • Engineering construction simulation method and system based on BIM

    CN117786802A

  • Temporary support construction technology for building butterfly arch bridge

    CN118166662A

  • Bridge construction management method and system based on multiple factors

    CN118608017A

  • Structure analyzing method, device, and non-transitory computer-readable medium

    US20200401745A1

  • Bridge renewal method and assistance system

    WO2023248918A1