Self-peristaltic inclined shaft full-process integrated construction equipment and construction method

Through the integrated construction equipment of the entire process of self-perpetitive inclined shafts, the safety risks and slow progress of sliding form construction in high-steep slope inclined shafts are solved, and the efficient connection between concrete pouring and grouting is achieved, and construction efficiency and safety are improved.

CN120465963AActive Publication Date: 2025-08-12SINOHYDRO BUREAU 14 CO LTD +2
View PDF 14 Cites 0 Cited by

Patent Information

Application Number
CN202510658875.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-05-21
Publication Date
2025-08-12
Estimated Expiration
2045-05-21

AI Technical Summary

Technical Problem

In the construction of high steep slope inclined shafts, sliding form construction has problems such as high safety risks, slow construction progress, and inability to efficiently connect the processes, especially in short-distance high steep slope inclined shafts, the advantages of sliding form are not obvious.

Method used

The self-perpetual inclined shaft is integrated with the entire process, including needle beams, beam frames, formwork and walking system. Through the combination of needle beams, inner and outer frame structures, formwork and walking system connected in series, the entire process of concrete pouring and grouting is achieved. The inner and outer frames are coordinated to deform under the drive of the oil cylinder, and the position of the components is accurately adjusted.

Benefits of technology

Efficient construction of two-lined concrete pouring and grouting of high-steep slope inclined shafts has been achieved, and various processes are efficiently connected, which improves construction safety and progress and reduces safety risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120465963A_ABST
    Figure CN120465963A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of inclined shaft lining and grouting construction, and provides self-wriggling type inclined shaft full-process integrated construction equipment and a construction method.The self-wriggling type inclined shaft full-process integrated construction equipment comprises a needle beam, a beam frame, a formwork and a walking system, and the needle beam is composed of a front-section needle beam unit, a middle-section needle beam unit and a rear-section needle beam unit; the beam frame is composed of an inner frame and an outer frame. The template consists of a top die, a left side die, a right side die, a bottom die, a screw rod seat and a template hinge lug; the walking system is composed of a driven walking mechanism device, a locking claw, a walking support and a hydraulic oil cylinder. The formwork trolley has the composite function of a formwork trolley and a grouting trolley, full-process efficient construction of concrete pouring and grouting is achieved, and structurally, the inner frame and the outer frame can be driven by the oil cylinder to deform in a coordinated mode so that the positions of components can be accurately adjusted. The device is not only suitable for high abrupt slope inclined shaft second lining concrete pouring, but also suitable for high abrupt slope inclined shaft grouting and inclined shaft upward bending section concrete and grouting construction, and all procedures can be efficiently connected.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of inclined shaft lining and grouting construction, in particular to self-propelled creeping inclined shaft full-process integrated construction equipment and a construction method. Background Art

[0002] During inclined shaft construction, lining trolleys are essential equipment for secondary lining operations, primarily used to apply concrete to the shaft's interior walls. Currently, concrete for high- and steep-slope inclined shafts is typically poured in sections using full-frame support frames or using slipforms. Full-frame support frame pouring has been largely eliminated in recent years due to slow construction progress, significant safety hazards, and the high volume and difficulty of recyclable materials. While slipform construction significantly outperforms full-frame support frame pouring in terms of construction progress and safety, it also presents challenges such as large over-excavation and backfill in the upper bend of the inclined shaft, high safety risks associated with slipform installation and lowering, a failure to adequately consider concrete pouring in the upper bend, high risks associated with installing and removing the sealing platform for the upper bend, and the need for a separate grouting platform after concrete construction is completed. Furthermore, slipform construction for inclined shafts cannot be efficiently integrated with other processes. While the advantages of the slipform system can be realized for long inclined shafts, the advantages of slipform technology are less pronounced for shorter, steeply sloped inclined shafts.

[0003] Therefore, the present invention proposes a self-propelled creeping inclined shaft full-process integrated construction equipment and construction method. Summary of the Invention

[0004] The purpose of the present invention is to provide a self-propelled creeping inclined shaft full-process integrated construction equipment and construction method to solve the problems raised in the above background technology.

[0005] In order to achieve the above object, the present invention adopts the following technical solutions: A self-propelled creeping inclined shaft full-process integrated construction equipment, comprising: a needle beam, a beam frame, a template, and a walking system; the needle beam comprises: a front needle beam, a middle needle beam, and a rear needle beam, the three needle beams being connected in series via bolts, and the top and bottom of the middle needle beam being provided with a plurality of beam frame support members; The beam frame is arranged on the periphery of the middle needle beam, and the beam frame includes: an inner frame and an outer frame. The inner frame is sleeved with the middle needle beam, and a plurality of outer frame support members are provided at the bottom of both sides of the inner frame, and the outer frame passes through the outer frame support members; the top and bottom of the middle needle beam are respectively connected to the top and bottom of the inner frame through translation cylinders; a plurality of lifting cylinders are provided between the inner frame and the outer frame; The template is arranged on the periphery of the outer frame, and the template includes: a top mold, a left mold, a right mold and a bottom mold; The walking system is arranged under the needle beam, and the walking system includes: a front driven walking mechanism, a rear driven walking mechanism, a locking claw and a box-type track; the front driven walking mechanism is arranged under the front section of the needle beam; the rear driven walking mechanism and the locking claw are arranged under the rear section of the needle beam; the rear driven walking mechanism and the locking claw are connected by a driving cylinder; the locking claw is engaged with the box-type track.

[0006] Preferably, the front needle beam includes a front main truss, and the front main truss includes a horizontal beam arranged in the horizontal direction, a longitudinal beam extending longitudinally along the needle beam, a plumb column distributed in the vertical direction and arranged at the intersection of the horizontal beam and the longitudinal beam, and connecting diagonal braces staggered between the horizontal beam and the longitudinal beam.

[0007] Preferably, the middle needle beam includes a middle main truss and a beam frame support, and the beam frame support includes two I-beams connected by welding, wherein the web of one I-beam is connected to the bottom plate of the other I-beam into one piece, and the upper and lower cross beams of the inner frame are butted against one end of the beam frame support.

[0008] Preferably, the rear section needle beam includes a rear section main truss and diagonal brace connection hinge ears arranged at the upper and bottom parts of the rear section vertical columns, and the diagonal brace connection hinge ears are used to achieve flexible connection and force transmission between the rear section needle beam and other components.

[0009] Preferably, the top and bottom of the middle needle beam are respectively connected to the top and bottom of the inner frame through several symmetrically arranged translation cylinders, and the upper and lower sides of the middle needle beam are connected to the inner frame through several symmetrically arranged horizontal hydraulic jacks. The translation cylinders and horizontal hydraulic jacks are used for adjusting the horizontal displacement between the inner frame and the needle beam, so as to achieve precise docking of various components during assembly and construction; several lifting cylinders and several vertical hydraulic jacks are provided between the inner frame and the outer frame, and the lifting cylinders and vertical hydraulic jacks are used for vertical height adjustment between the inner frame and the outer frame.

[0010] Preferably, the top mold, left mold, right mold and bottom mold in the template are all arc-shaped templates, one end of the arc-shaped template is provided with a template hinge ear, and the other end is provided with an oblique cut, the top mold, left mold, right mold and bottom mold are connected end to end to form a ring, and a grouting device is provided on the inside of the top mold; the inside of the top mold, left mold and right mold are provided with a working window and a screw seat; the inside of the bottom mold is provided with a working window; the screw seat is connected to the screw jack and one end of the demoulding cylinder, and the other end of the screw jack and the demoulding cylinder is connected to the outer frame; the bottom mold is connected to the bottom of the outer frame through the hanger base.

[0011] Preferably, the front driven walking mechanism and the rear driven walking mechanism include: walking wheels, a walking frame, an upper support, a lower support, and a walking support; the walking wheels are rotatably connected to the walking frame through a clamping plate and a bolt assembly; the lower support is connected to the top of the walking frame, the lower support is hinged to the upper support via a distribution shaft, the lower support is connected to the bottom of the walking support, and the top of the walking support is connected to the bottom of the needle beam; The locking claw comprises: a guide mechanism seat, rollers provided at both ends of the guide mechanism seat, and positive and negative triangular claws provided on the inner side of the guide mechanism seat; the positive and negative triangular claws are rotatably connected to the guide mechanism seat via a clamping plate pin; a lifting lug is provided on one side of the locking claw; a lifting lug is provided on one end of the rear driven traveling mechanism traveling frame; the driving cylinder is connected to the locking claw and the rear driven traveling mechanism via the lifting lug; The box-shaped track has equidistantly spaced bayonet holes on both sides of its top. A rectangular track is located in the center of the top of the box-shaped track, with grooves on both sides. The ends of the positive and negative triangular claws engage with the bayonet holes on the upper surface of the box-shaped track. When the equipment stops, the claws automatically lock into a predetermined position to clamp the equipment and the track or other components on the equipment to prevent the equipment from moving. Preferably, the locking claws and the rear driven walking mechanisms are each provided with three groups, the three groups of locking claws and the rear driven walking mechanisms are arranged along the box-shaped track, and the corresponding driving cylinders are also provided with three groups.

[0012] Preferably, the anti-overturning device is further included, and the anti-overturning device includes: an oblique support, a front stabilizing mechanism, and a rear stabilizing mechanism; the oblique support includes: a short oblique support and a large rear oblique support, the short oblique support includes: a main body screw connected to the needle beam through a connecting piece, an adjustment component provided at the control end of the main body screw, and the adjustment component is connected to the box-type track through a connecting piece; the large rear oblique support includes: two parallel main body screws and a transverse connecting piece; the main body screws are connected through the transverse connecting piece to form a stable triangular support structure, the large rear oblique support is installed at the tail of the needle beam, one on each side, and the end of the large rear oblique support is anchored to the ground; The short diagonal brace includes a main screw rod, an adjustment assembly, and a connecting end. The short diagonal brace is installed from the plumb bob column of the rear needle beam to the bottom longitudinal beam of the rear needle beam and is finally fixed to the track; The front stabilizing mechanism includes: a top end supporting frame and a side end supporting frame; the rear stabilizing mechanism includes: a top end stabilizing frame and a side end stabilizing frame.

[0013] Another object of the present invention is to provide a construction method for an underground cavern group during the construction period, which is applied to the above-mentioned self-propelled creeping inclined shaft full-process integrated construction equipment, comprising the following steps: Step 1) Casting of the straight section of the inclined shaft: Install self-propelled peristaltic inclined shaft full-process integrated construction equipment and anti-overturning device at the bottom of the inclined shaft. After installation, when the equipment is in a stationary state, the three sets of locking claws are locked, and the ends of the positive and negative triangular claws engage with the bayonet on the upper surface of the box-type track, and the pouring state is entered; the template is connected to the bottom of the outer frame through the screw jack, demoulding cylinder, and hanger base, and the template is moved to the predetermined position through the screw jack and demoulding cylinder. After the assembly, positioning and debugging of the template are completed, concrete is poured. After the pouring is completed, the template is removed in turn, and the screw jack, demoulding cylinder, hanger base and anti-overturning device are recovered; Step 2) Equipment promotion: After pouring is completed, the first set of locking claws are released, the second and third sets of locking claws are locked, and the equipment is driven along the box track to the next working section by two sets of driving cylinders; after reaching the new position, the first set of locking claws are locked, the second and third sets of locking claws are unlocked, and the hydraulic cylinders are retracted. After the hydraulic cylinders are retracted, the second and third sets of locking claws are locked, and the equipment enters the pouring state again and enters the next construction cycle until the construction of the straight section of the inclined shaft is completed; Step 3) Casting construction of the upper curved section of the inclined shaft: When the equipment reaches the upper bend section, the front needle beam, middle needle beam and beam frame are removed, leaving only the rear needle beam and walking system; a scaffolding is set up between the rear needle beam and the inclined shaft wall as a working platform, with one end of the scaffolding main beam simply supported on the reserved concrete groove of the inclined shaft wall, and the other end fixed on the rear needle beam. After the main beam is built, the secondary beam and the full-floor support frame are built to form a formwork support frame. After the working platform and formwork support frame are built, the upper bend section is poured; Step 4) Grouting construction of the straight section of the inclined shaft: After the pouring of the upper bend section is completed, the scaffolding is removed, and the equipment returns to the grouting starting position of the straight section of the inclined shaft. The front needle beam and the middle needle beam are reconnected, the three sets of locking claws are locked, and the equipment enters the grouting state. The operating personnel carry out grouting and hole making, grouting and post-grouting inspection on the platform built on the middle needle beam; after completing a section of grouting, the first set of locking claws are released, the second and third sets of locking claws are locked, and the equipment is driven forward along the box track to the next grouting section by two sets of driving cylinders; after reaching the new grouting section, the first set of locking claws are locked, the second and third sets of locking claws are unlocked, and the hydraulic cylinder is retracted. After the hydraulic cylinder is retracted, the second and third sets of locking claws are locked, and the equipment enters the grouting state again and enters the next construction cycle until the construction of the straight section of the inclined shaft is completed.

[0014] The present invention discloses a self-propelled creeping inclined shaft full-process integrated construction device and a construction method having the following beneficial effects.

[0015] The present invention includes a needle beam, a beam frame, a template, and a walking system. The needle beam is composed of a front needle beam unit, a middle needle beam unit, and a rear needle beam unit; the beam frame is composed of an inner frame and an outer frame; the template is composed of a top template, a left template, a right template, a bottom template, a screw seat, and a template hinge ear; and the walking system is composed of a driven walking mechanism, a locking claw, a walking support, and a hydraulic cylinder component. The present invention has the combined functions of a template trolley and a grouting trolley, and realizes efficient construction of the entire process of concrete pouring and grouting. Structurally, the inner frame and the outer frame can coordinate deformation under the drive of the cylinder to accurately adjust the position of the components, and due to the existence of the walking system, it can be walked from the bottom. The present invention is not only suitable for pouring secondary lining concrete for high-steep slope inclined shafts, but also suitable for grouting of high-steep slope inclined shafts, and concrete and grouting construction of the upper bend section of the inclined shaft, and can enable efficient connection of each process. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 This is a cross-sectional diagram of the integrated construction equipment for the entire process; Figure 2 This is a side view of the integrated construction equipment for the entire process; Figure 3 is a schematic side view of the needle beam; Figure 4 Three views of the beam frame-needle beam assembly; (a) side view; (b) front view; (c) top view; Figure 5 Three views of the inner frame; (a) side view; (b) main view; (c) top view; Figure 6 Three views of the outer frame; (a) side view; (b) main view; (c) top view; Figure 7 It is the schematic diagram of the top mold and its expansion diagram; Figure 8 The left side is a schematic diagram of the mold and its expansion diagram; Figure 9 The right side is the schematic diagram of the mold and its expansion diagram; Figure 10 The bottom mold schematic diagram and its expansion diagram; Figure 11 Schematic diagram of the driven walking mechanism; Figure 12 This is a schematic diagram for locking and grabbing; Figure 13 It is a cross-sectional view of the front stabilizing mechanism; Figure 14 It is the cross-sectional view of the rear stabilizing mechanism; Figure 15 for Figure 2 A partial enlarged schematic diagram in the middle; In the accompanying drawings: 1, needle beam; 11, front needle beam; 111, front main truss; 12, middle needle beam; 121, middle main truss; 122, beam frame support; 13, rear needle beam; 131, rear main truss; 2. Beam frame; 21. Inner frame; 211. Inner upper crossbeam; 212. Inner lower crossbeam; 213. Inner column; 214. Inner upper longitudinal beam; 215. Inner middle longitudinal beam; 216. Inner lower longitudinal beam; 217. Outer frame support; 218. Inner diagonal support rod; 22. Outer frame; 221. Outer upper crossbeam; 222. Outer lower crossbeam; 223. Outer column; 224. Outer upper longitudinal beam; 225. Outer middle longitudinal beam; 226. Outer lower longitudinal beam; 227. Outer diagonal support rod; 228. Walkway support; 3. Formwork; 31. Top formwork; 311. Grouting device; 32. Left formwork; 33. Right formwork; 34. Bottom formwork; 341. Hanger base; 35. Screw seat; 36. Formwork hinge; 37. Working window; 4. Travel system; 41. Front driven travel mechanism; 411. Travel wheels; 412. Travel frame; 413. Upper support; 414. Lower support; 42. Locking claw; 421. Front and rear rollers; 422. Guide mechanism seat; 423. Positive and negative triangular claws; 424. Pallet pin; 43. Travel support; 44. Box track; 45. Rear driven travel mechanism; 5. Anti-overturning; 51. Diagonal brace; 511. Short diagonal brace; 512. Large rear diagonal brace; 52. Front stabilizing mechanism; 521. Top support frame; 522. Side support frame; 53. Rear stabilizing mechanism; 531. Top stabilizing frame; 532. Side stabilizing frame; 6. Accessory components; 61. Screw jack; 62. Demoulding cylinder; 63. Lifting cylinder; 64. Translation cylinder; 65. Horizontal hydraulic jack; 66. Vertical hydraulic jack; 67. Hydraulic cylinder; 68. Bottom mould hanger. DETAILED DESCRIPTION

[0017] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.

[0018] In the description of the present invention, it should be understood that the terms "upper", "lower", "front", "back", "left", "right", "top", "bottom", "inside", "outside", etc., indicating directions or positional relationships, are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as limiting the present invention. Example 1

[0019] like Figures 1-14 As shown, a self-propelled creeping inclined shaft full-process integrated construction equipment includes: a needle beam 1, a beam frame 2, a template 3 and a walking system 4; the needle beam 1 includes: a front needle beam 11, a middle needle beam 12 and a rear needle beam 13, the three needle beams are connected in series by bolts, and a plurality of beam frame support members 122 are provided at the top and bottom of the middle needle beam 12; An auxiliary component 6 is provided between the beam frame 2 and the needle beam 1, and the auxiliary component 6 includes a screw jack 61, a demoulding cylinder 62, a lifting cylinder 63, a translation cylinder 64, a horizontal hydraulic jack 65, a vertical hydraulic jack 66, a hydraulic cylinder 67, and a bottom mold 34 hanger; the beam frame 2 is provided on the periphery of the middle needle beam 12, and the beam frame 2 includes: an inner frame 21 and an outer frame 22, the inner frame 21 is sleeved with the middle needle beam 12, and a number of outer frame support members are provided on the bottom of both sides of the inner frame 21 217, the outer frame 22 passes through the outer frame support 217, and a rectangular channel is provided in the middle of the outer frame support 217. The outer frame 22 passes through the rectangular channel of the outer frame support 217. The outer frame support 217 limits the outer frame 22 so that it can only move vertically relative to the inner frame 21; the top and bottom of the middle needle beam 12 are respectively connected to the top and bottom of the inner frame 21 through the translation cylinder 64; a plurality of lifting cylinders 63 are provided between the inner frame 21 and the outer frame 22; The template 3 is arranged outside the outer frame 22, and the template 3 includes: a top mold 31, a left mold 32, a right mold 33 and a bottom mold 34; The walking system 4 is arranged under the needle beam 1, and the walking system 4 includes: a front driven walking mechanism 41, a rear driven walking mechanism 45, a locking claw 42 and a box-type track 44; the front driven walking mechanism 41 is arranged under the front section of the needle beam 11; the rear driven walking mechanism 45 and the locking claw 42 are arranged under the rear section of the needle beam 13; the rear driven walking mechanism 45 and the locking claw 42 are connected by a driving cylinder; the locking claw 42 is engaged with the box-type track 44.

[0020] like Figures 3 to 6 As shown, preferably, in this embodiment, the front needle beam 11 includes a front main truss 111, and the front main truss 111 includes a horizontal beam arranged in the horizontal direction, a longitudinal beam extending longitudinally along the needle beam 1, a plumb column distributed in the vertical direction and arranged at the intersection of the horizontal beam and the longitudinal beam, and connecting diagonal braces staggered between the horizontal beam and the longitudinal beam.

[0021] Preferably, in this embodiment, the middle needle beam 12 includes a middle main truss 121 and a beam frame support 122. The beam frame support 122 includes two I-beams connected by welding, wherein the web of one I-beam is connected to the bottom plate of the other I-beam as a whole, and the upper and lower beams of the inner frame 21 are abutted against one end of the beam frame support 122. The beam frame support 122 prevents the inner frame 21 and the middle needle beam 12 from sliding along the tunnel direction.

[0022] Preferably, in this embodiment, the rear section needle beam 13 includes a rear section main truss 131 and diagonal brace connecting hinge ears arranged at the upper and bottom parts of the rear section vertical columns. The diagonal brace connecting hinge ears are used to achieve flexible connection and force transmission between the rear section needle beam 13 and other components. It should be noted that the rear section main truss 131 and the middle section main truss 121 have the same structure as the front section main truss 111, and only the size is different.

[0023] Preferably, in this embodiment, the inner frame 21 includes: an inner upper crossbeam 211, an inner lower crossbeam 212, an inner column 213; an inner upper longitudinal beam 214, an inner middle longitudinal beam 215, an inner lower longitudinal beam 216, and an inner support diagonal rod 218. The inner upper crossbeam 211 and the inner lower crossbeam 212 of the inner frame 21 abut against one end of the beam frame support member 122; Preferably, in this embodiment, the outer frame 22 includes: an outer upper crossbeam 221, an outer lower crossbeam 222, an outer column 223, an outer upper longitudinal beam 224, an outer middle longitudinal beam 225, an outer lower longitudinal beam 226, an outer supporting diagonal rod 227, and a walkway bracket 228; the outer column 223 passes through the rectangular channel of the outer frame support 217.

[0024] Preferably, in this embodiment, the top and bottom of the middle needle beam 12 are respectively connected to the top and bottom of the inner frame 21 through several symmetrically arranged translation cylinders 64, and the upper and lower sides of the middle needle beam 12 are connected to the inner frame 21 through several symmetrically arranged horizontal hydraulic jacks 65. The translation cylinders 64 and the horizontal hydraulic jacks 65 are used for horizontal displacement adjustment between the inner frame 21 and the needle beam 1, so as to achieve precise docking of various components during assembly and construction; a number of lifting cylinders 63 and a number of vertical hydraulic jacks 66 are provided between the inner frame 21 and the outer frame 22, and the lifting cylinders 63 and the vertical hydraulic jacks 66 are used for vertical height adjustment between the inner frame 21 and the outer frame 22, so as to ensure the vertical alignment or spacing adjustment of the structure.

[0025] Through the translation cylinder 64, the horizontal hydraulic jack 65, the lifting cylinder 63 and the vertical hydraulic jack 66, the relative positions of the inner frame 21 and the outer frame 22, and the needle beam 1 and the inner frame 21 can be dynamically adjusted to meet the structural balance and functional requirements during system operation, facilitate the positioning of the template 3, reduce errors and stress concentration, and improve the stability and accuracy of the overall device.

[0026] like Figures 7 to 10Preferably, in this embodiment, the top mold 31, left mold 32, right mold 33, and bottom mold 34 in the template 3 are all curved molds, each having a template hinge ear 36 at one end and an oblique cut at the other. The top mold 31, left mold 32, right mold 33, and bottom mold 34 are connected end to end to form a ring. A grouting device 311 is provided on the inside of the top mold 31. After installation, the grouting device 311 is required to rotate and pull flexibly. A working window 37 and a screw seat 35 are provided on the inside of the top mold 31, left mold 32, and right mold 33. A working window 37 is provided on the inside of the bottom mold 34. The screw seat 35 is connected to one end of a screw jack 61 and a demolding cylinder 62. The other ends of the screw jack 61 and the demolding cylinder 62 are connected to the outer frame 22. The screw jack 61 is used to assist in positioning the template 3. The bottom mold 34 is connected to the bottom of the outer frame 22 via a hanger base 341 and a bottom mold hanger 68. The template 3 is 6 meters long in the longitudinal direction. The thickness of template 3 is 10mm, and No. 8 channel steel is used for longitudinal reinforcement inside template 3 to ensure the strength of template 3 and prevent local deformation.

[0027] like Figure 11 and 12 As shown, as a preference, in this embodiment, the front driven walking mechanism 41 and the rear driven walking mechanism 45 include: a walking wheel 411, a walking frame 412, an upper support 413, a lower support 414, and a walking support 43; the walking wheel 411 is rotatably connected to the walking frame 412 through a clamping plate and a bolt assembly; the lower support 414 is connected to the top of the walking frame 412, the lower support 414 is hinged to the upper support 413 via a pin shaft, the lower support 414 is connected to the bottom of the walking support 43, and the top of the walking support 43 is connected to the bottom of the needle beam 1; The locking claw 42 includes: a guide mechanism seat 422, rollers 421 provided at both ends of the guide mechanism seat 422, and positive and negative triangular claws 423 provided on the inner side of the guide mechanism seat 422; the positive and negative triangular claws 423 are rotatably connected to the guide mechanism seat 422 via a clamping plate pin 424; a lifting lug is provided on one side of the locking claw 42; a lifting lug is provided on one end of the traveling frame 412 of the rear driven traveling mechanism 45; and a driving cylinder connects the locking claw 42 and the rear driven traveling mechanism 45 via the lifting lug. like Figure 15 As shown, the top of the box-shaped track 44 is provided with equidistantly spaced bayonet holes on both sides. A rectangular track is provided at the center of the top of the box-shaped track 44, with grooves on both sides of the rectangular track. The ends of the positive and negative triangular claws 423 engage with the bayonet holes on the upper surface of the box-shaped track 44. The locking claws 42 are locked when the equipment is stopped to clamp the equipment and the track or other components on the equipment to prevent the equipment from moving. After the locking claws 42 reach the predetermined position, the positive and negative triangular claws 423 need to be manually moved to engage the ends of the positive and negative triangular claws 423 with the bayonet holes on the upper surface of the box-shaped track 44. In this embodiment, the positive and negative triangular claws 423 are provided with a column to facilitate the rotation of the positive and negative triangular claws 423.

[0028] Preferably, in this embodiment, three groups of locking claws 42 and rear driven walking mechanisms 45 are provided, and the three groups of locking claws 42 and rear driven walking mechanisms 45 are arranged along the box-type track 44, and three groups of corresponding driving cylinders are also provided.

[0029] When the self-propelled peristaltic inclined shaft full-process integrated construction equipment is moving, the positive and negative triangular claws 423 are in an unlocked state, ensuring that the self-propelled peristaltic inclined shaft full-process integrated construction equipment can move freely. At this time, the positive and negative triangular claws 423 are in a loose position and do not hinder the movement of the self-propelled peristaltic inclined shaft full-process integrated construction equipment. When the self-propelled peristaltic inclined shaft full-process integrated construction equipment stops moving, the ends of the positive and negative triangular claws 423 engage with the upper surface snap-on of the box-type track 44, ensuring that the self-propelled peristaltic inclined shaft full-process integrated construction equipment is fixed in the stopped state.

[0030] As a preference, in this embodiment, when the self-propelled peristaltic inclined shaft full-process integrated construction equipment works at a high and steep slope inclined shaft, the overturning problem of the full-process integrated construction equipment needs to be considered, and an anti-overturning system 5 needs to be installed.

[0031] The anti-overturning device 5 includes: a diagonal brace 51, a front stabilizing mechanism 52, and a rear stabilizing mechanism 53; the diagonal brace 51 includes: a short diagonal brace 511 and a large rear diagonal brace 512. The short diagonal brace 511 includes: a main body screw rod connected to the needle beam 1 through a connector, an adjustment component provided at the control end of the main body screw rod, and the adjustment component is connected to the box-shaped track 44 through a connector; the large rear diagonal brace 512 includes: two parallel main body screw rods and a transverse connector; the main body screw rods are connected by the transverse connector to form a stable triangular support structure. The large rear diagonal brace 512 is installed at the tail end of the needle beam 1, one on each side, and the ends of the large rear diagonal brace 512 are anchored to the ground. The short diagonal brace 511 includes a main screw rod, an adjustment assembly, and a connection end. The short diagonal brace 511 is installed from the plumb column of the rear needle beam 13 to the bottom longitudinal beam of the rear needle beam 13 and is finally fixed to the track. The front stabilizing mechanism 52 includes a top support frame 521 and a side support frame 522; the rear stabilizing mechanism 53 includes a top stabilizing frame 531 and a side stabilizing frame 532. This ensures that the fully integrated construction equipment remains stable during the pouring process and prevents tilting.

[0032] When the pouring operation is completed, the four short diagonal braces 511 are retracted and the large rear diagonal brace 512 is removed; and when the self-propelled peristaltic inclined shaft full-process integrated construction equipment moves to the next pouring position, the large rear diagonal brace 512 is re-anchored to ensure that it still has good stability in the new position.

[0033] like Figure 13As shown, the front stabilization mechanism 52 includes a top support frame 521 and a side support frame 522. The top support frame 521 includes vertical support columns, horizontal connecting rods, and vertical connecting rods. The vertical support columns are symmetrically arranged on both sides of the cross beam on the front needle beam 11 and are fixed by bottom connecting parts to ensure that the columns can withstand vertical loads and provide stable support. Between the vertical support columns, a number of horizontal and vertical connecting rods are installed. These connecting rods are arranged in parallel and evenly distributed in the horizontal and vertical directions to strengthen the connection between the left and right columns, forming a stable frame structure to effectively resist lateral deformation and shear force. The side support frame 522 has the same structure as the top support frame 521. The vertical support columns are horizontally arranged on both sides of the longitudinal beam on the front needle beam 11 and are fixed by bottom connecting parts to ensure that the columns can withstand horizontal loads and provide stable support. like Figure 14 As shown, the rear stabilizing mechanism 53 includes a top support frame 521 and a side support frame 522. The structure and connection method are the same as those of the front stabilizing mechanism 52. Example 2

[0034] Based on Example 1, this embodiment provides a construction method for an underground cavern group during the construction period, which is applied to the above-mentioned self-propelled peristaltic inclined shaft full-process integrated construction equipment, including the following steps: Step 1) Casting of the straight section of the inclined shaft: At the bottom of the inclined shaft, a self-propelled peristaltic inclined shaft full-process integrated construction equipment and an anti-overturning device 5 are installed. After installation, when the equipment is in a stationary state, the three sets of locking claws 42 are locked, and the ends of the positive and negative triangular claws 423 engage with the upper surface of the box track 44, entering the pouring state. The formwork 3 is connected to the bottom of the outer frame 22 through the screw jack 61, the demoulding cylinder 62, the hanger base 341 and the bottom form hanger 68. The formwork 3 is moved to the predetermined position through the screw jack 61 and the demoulding cylinder 62. After the assembly, positioning and debugging of the formwork 3 are completed, concrete pouring is carried out. Specifically, when the pouring position is reached, the lateral position of the inner frame 21 is adjusted by the translation cylinder 64. After the lateral position of the inner frame 21 is adjusted to the right position, the lifting cylinder 63 is used to adjust the position of the outer frame 22 along the height direction of the tunnel. After the position of the outer frame 22 along the height direction of the tunnel is adjusted to the right position, the horizontal hydraulic jack 65 is used to slightly adjust the inner frame 21 to adjust the lateral position of the outer frame 22. Finally, when the horizontal and vertical positions of the outer frame 22 are adjusted, the vertical hydraulic jack 66 starts working to bear part of the force of the outer frame 22; after the pouring is completed, the formwork 3 is removed in sequence. First, the screw jack 61 is removed, and the demoulding cylinders 62 of the top form 31, the left form 32, and the right form 33 are recovered. The demoulding cylinder 62, the bottom form hanger 68, and the anti-overturning device 5 are removed; Step 2) Equipment promotion: After pouring is completed, the first set of locking claws 42 are released, the second and third sets of locking claws 42 are locked, and the equipment is driven by two sets of driving cylinders to move forward along the box track 44 to the next working section; after reaching the new position, the first set of locking claws 42 are locked, the second and third sets of locking claws 42 are unlocked, and the hydraulic cylinder 67 is retracted. After the hydraulic cylinder 67 is retracted, the second and third sets of locking claws 42 are locked, and the equipment enters the pouring state again and enters the next construction cycle until the construction of the straight section of the inclined shaft is completed; Step 3) Casting construction of the upper curved section of the inclined shaft: When the equipment reaches the upper bend section, the front needle beam 11, the middle needle beam 12 and the beam frame 2 are removed, leaving only the rear needle beam 13 and the walking system 4; a scaffolding is set up between the rear needle beam 13 and the inclined shaft wall as a working platform, one end of the scaffolding main beam is simply supported on the reserved concrete groove of the inclined shaft wall, and the other end is fixed on the rear needle beam 13. After the main beam is built, the secondary beam and the full-floor support frame are built to form a formwork support frame. After the working platform and the formwork support frame are built, the upper bend section is poured; Step 4) Grouting construction of the straight section of the inclined shaft: After the pouring of the upper bend section is completed, the scaffolding is removed, and the equipment returns to the grouting starting position of the straight section of the inclined shaft, the front needle beam 11 and the middle needle beam 12 are reconnected, the three groups of locking claws 42 are locked, and the equipment enters the grouting state. The operating personnel carry out grouting and hole making, grouting and post-grouting inspection on the platform built on the middle needle beam 12; after completing a section of grouting, the first group of locking claws 42 are released, the second and third groups of locking claws 42 are locked, and the equipment is driven by two groups of driving cylinders to move forward along the box track 44 to the next grouting section; after reaching the new grouting section, the front first group of locking claws 42 are locked, the second and third groups of locking claws 42 are unlocked, and the hydraulic cylinder 67 is retracted. After the hydraulic cylinder 67 is retracted, the second and third groups of locking claws 42 are locked, and the equipment enters the grouting state again and enters the next construction cycle until the construction of the straight section of the inclined shaft is completed.

[0035] The above are merely preferred embodiments of the present invention, but the scope of protection of the present invention is not limited thereto. Replacement may be partial structure, device, or method step replacement, or it may be a complete technical solution. Equivalent replacements or modifications based on the technical solution and inventive concept of the present invention are all within the scope of protection of the present invention.

Claims

1. A self-propelled creeping inclined shaft full-process integrated construction equipment, characterized in that: include: Needle beam, beam frame, template and walking system; the needle beam includes: front needle beam, middle needle beam and rear needle beam, the three needle beams are connected in series by bolts, and the top and bottom of the middle needle beam are provided with several beam frame support members; The beam frame is arranged on the periphery of the middle needle beam, and the beam frame includes: an inner frame and an outer frame. The inner frame is sleeved with the middle needle beam, and a plurality of outer frame support members are provided at the bottom of both sides of the inner frame, and the outer frame passes through the outer frame support members; the top and bottom of the middle needle beam are respectively connected to the top and bottom of the inner frame through translation cylinders; a plurality of lifting cylinders are provided between the inner frame and the outer frame; The template is arranged on the periphery of the outer frame, and the template includes: a top mold, a left mold, a right mold and a bottom mold; The walking system is arranged under the needle beam, and the walking system includes: a front driven walking mechanism, a rear driven walking mechanism, a locking claw and a box-type track; the front driven walking mechanism is arranged under the front section of the needle beam; the rear driven walking mechanism and the locking claw are arranged under the rear section of the needle beam; the rear driven walking mechanism and the locking claw are connected by a driving cylinder; the locking claw is engaged with the box-type track.

2. The self-propelled creeping inclined shaft full-process integrated construction equipment according to claim 1 is characterized in that: The front needle beam includes a front main truss, which includes a horizontal beam arranged in the horizontal direction, a longitudinal beam extending longitudinally along the needle beam, a plumb column distributed in the vertical direction and arranged at the intersection of the horizontal beam and the longitudinal beam, and connecting diagonal braces staggered between the horizontal beam and the longitudinal beam.

3. The self-propelled creeping inclined shaft full-process integrated construction equipment according to claim 1 is characterized in that: The middle needle beam includes a middle main truss and a beam frame support. The beam frame support includes two I-beams connected by welding, wherein the web of one I-beam is connected to the bottom plate of the other I-beam into one piece, and the upper and lower cross beams of the inner frame are against one end of the beam frame support.

4. The self-propelled creeping inclined shaft full-process integrated construction equipment according to claim 1 is characterized in that: The rear section needle beam includes a rear section main truss and diagonal brace connection hinge ears arranged at the upper and bottom parts of the rear section vertical columns. The diagonal brace connection hinge ears are used to achieve flexible connection and force transmission between the rear section needle beam and other components.

5. The self-propelled creeping inclined shaft full-process integrated construction equipment according to claim 1 is characterized in that: The top and bottom of the middle needle beam are respectively connected to the top and bottom of the inner frame through several symmetrically arranged translation cylinders, and the upper and lower sides of the middle needle beam are connected to the inner frame through several symmetrically arranged horizontal hydraulic jacks. The translation cylinders and horizontal hydraulic jacks are used for adjusting the horizontal displacement between the inner frame and the needle beam, so as to achieve precise docking of various components during assembly and construction; several lifting cylinders and several vertical hydraulic jacks are provided between the inner frame and the outer frame, and the lifting cylinders and vertical hydraulic jacks are used for vertical height adjustment between the inner frame and the outer frame.

6. The self-propelled creeping inclined shaft full-process integrated construction equipment according to claim 1 is characterized in that: The top mold, left mold, right mold and bottom mold in the template are all arc-shaped templates, one end of the arc-shaped template is provided with a template hinge ear, the other end is provided with an oblique cut, the top mold, left mold, right mold and bottom mold are connected end to end to form a ring, and a grouting device is provided on the inside of the top mold; the inside of the top mold, left mold and right mold are provided with a working window and a screw seat; the inside of the bottom mold is provided with a working window; the screw seat is connected to the screw jack and one end of the demoulding cylinder, and the other end of the screw jack and the demoulding cylinder is connected to the outer frame; the bottom mold is connected to the bottom of the outer frame through the hanger base.

7. The self-propelled creeping inclined shaft full-process integrated construction equipment according to claim 1 is characterized in that: The front driven walking mechanism and the rear driven walking mechanism include: walking wheels, a walking frame, an upper support, a lower support, and a walking support; the walking wheels are rotatably connected to the walking frame through a clamping plate and a bolt assembly; the lower support is connected to the top of the walking frame, the lower support is hinged to the upper support via a distribution shaft, the lower support is connected to the bottom of the walking support, and the top of the walking support is connected to the bottom of the needle beam; The locking claw comprises: a guide mechanism seat, rollers provided at both ends of the guide mechanism seat, and positive and negative triangular claws provided on the inner side of the guide mechanism seat; the positive and negative triangular claws are rotatably connected to the guide mechanism seat via a clamping plate pin; a lifting lug is provided on one side of the locking claw; a lifting lug is provided on one end of the rear driven traveling mechanism traveling frame; the driving cylinder is connected to the locking claw and the rear driven traveling mechanism via the lifting lug; The top of the box-shaped track is provided with equidistantly arranged bayonet holes on both sides, the top center of the box-shaped track is provided with a rectangular track, and both sides of the rectangular track are provided with grooves; the ends of the positive and negative triangular claws are engaged with the bayonet holes on the upper surface of the box-shaped track.

8. The self-propelled creeping inclined shaft full-process integrated construction equipment according to claim 1 is characterized in that: The locking claws and the rear driven walking mechanism are each provided with three groups, and the three groups of locking claws and the rear driven walking mechanism are arranged along the box-shaped track, and the corresponding driving cylinders are also provided with three groups.

9. The self-propelled creeping inclined shaft full-process integrated construction equipment according to claim 1 is characterized in that: The anti-overturning device also includes: an oblique support, a front stabilizing mechanism, and a rear stabilizing mechanism; the oblique support includes: a short oblique support and a large rear oblique support, the short oblique support includes: a main body screw connected to the needle beam through a connector, an adjustment component provided at the control end of the main body screw, and the adjustment component is connected to the box-type track through a connector; the large rear oblique support includes: two parallel main body screws and a transverse connector; the main body screws are connected by the transverse connector to form a stable triangular support structure, the large rear oblique support is installed at the tail of the needle beam, one on each side, and the end of the large rear oblique support is anchored to the ground; The short diagonal brace includes a main screw rod, an adjustment assembly, and a connecting end. The short diagonal brace is installed from the plumb bob column of the rear needle beam to the bottom longitudinal beam of the rear needle beam and is finally fixed to the track; The front stabilizing mechanism includes: a top end supporting frame and a side end supporting frame; the rear stabilizing mechanism includes: a top end stabilizing frame and a side end stabilizing frame.

10. A self-propelled peristaltic inclined shaft full-process integrated construction method, using the self-propelled peristaltic inclined shaft full-process integrated construction equipment of claims 1-9, characterized in that: The following steps are involved: Step 1) Casting of the straight section of the inclined shaft: Install self-propelled peristaltic inclined shaft full-process integrated construction equipment and anti-overturning device at the bottom of the inclined shaft. After installation, when the equipment is in a stationary state, the three sets of locking claws are locked, and the ends of the positive and negative triangular claws engage with the bayonet on the upper surface of the box-type track, and the pouring state is entered; the template is connected to the bottom of the outer frame through the screw jack, demoulding cylinder, and hanger base, and the template is moved to the predetermined position through the screw jack and demoulding cylinder. After the assembly, positioning and debugging of the template are completed, concrete is poured. After the pouring is completed, the template is removed in turn, and the screw jack, demoulding cylinder, hanger base and anti-overturning device are recovered; Step 2) Equipment promotion: After pouring is completed, the first set of locking claws are released, the second and third sets of locking claws are locked, and the equipment is driven along the box track to the next working section by two sets of driving cylinders; after reaching the new position, the first set of locking claws are locked, the second and third sets of locking claws are unlocked, and the hydraulic cylinders are retracted. After the hydraulic cylinders are retracted, the second and third sets of locking claws are locked, and the equipment enters the pouring state again and enters the next construction cycle until the construction of the straight section of the inclined shaft is completed; Step 3) Casting construction of the upper curved section of the inclined shaft: When the equipment reaches the upper bend section, the front needle beam, middle needle beam and beam frame are removed, leaving only the rear needle beam and walking system; a scaffolding is set up between the rear needle beam and the inclined shaft wall as a working platform, with one end of the scaffolding main beam simply supported on the reserved concrete groove of the inclined shaft wall, and the other end fixed on the rear needle beam. After the main beam is built, the secondary beam and the full-floor support frame are built to form a formwork support frame. After the working platform and formwork support frame are built, the upper bend section is poured; Step 4) Grouting construction of the straight section of the inclined shaft: After the pouring of the upper bend section is completed, the scaffolding is removed, and the equipment returns to the grouting starting position of the straight section of the inclined shaft. The front needle beam and the middle needle beam are reconnected, the three sets of locking claws are locked, and the equipment enters the grouting state. The operating personnel carry out grouting and hole making, grouting and post-grouting inspection on the platform built on the middle needle beam; after completing a section of grouting, the first set of locking claws are released, the second and third sets of locking claws are locked, and the equipment is driven forward along the box track to the next grouting section by two sets of driving cylinders; after reaching the new grouting section, the first set of locking claws are locked, the second and third sets of locking claws are unlocked, and the hydraulic cylinder is retracted. After the hydraulic cylinder is retracted, the second and third sets of locking claws are locked, and the equipment enters the grouting state again and enters the next construction cycle until the construction of the straight section of the inclined shaft is completed.

Citation Information

Patent Citations

  • Diversion tunnel slope and flat full-section universal steel mould trolley

    CN106223983A

  • Circular tunnel full-face concrete pouring system

    CN110185476A

  • Hydropower station diversion tunnel inclined shaft upper and lower bent section concrete lining device

    CN113279784A

  • Shield small-radius tunnel lining construction method

    CN113309541A

  • Shield small-radius tunnel needle beam type formwork-rotating full-circle lining trolley and formwork rotating method thereof

    CN113309542A